Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 10

The Power Supply industry in Tripura was under the control of the Department of Power, Government of Tripura till

31st December 2004. The Department of Power, Government of Tripura was entrusted with Generation, Transmission, and Distribution including Rural Electrification since inception. The Department of Power had remained a beneficiary constituent of North Eastern Regional Electricity Board. Tripura State Electricity Corporation Limited had started functioning w.e.f 1st January 2005. Subsequently TSECL has taken over the entire existing network along with asset of erstwhile Department of Power for operating and maintaining the power supply industry in the State of Tripura. The State has a Population of 31.91 Lakhs as per 2001 census and spread over 10,486 sq. km. in 4 districts comprising of 4 major towns and 870 villages. The state is predominantly agrarian with few small scale industries. In line with the provision of the MOU between Ministry of Power, Govt. of India and Government of Tripura, the State Government decided to introduce reforms in the power sector in the state and restructure the sector with objectives of creating the conditions for the sustainable development of the power sector in the state and improving the efficiency of services to the people of Tripura. So, in 2002, the Government of Tripura entrusted the Administrative Staff College of India (ASCI), Hyderabad to provide consultancy services to assess restructuring options and recommend suitable organisation structure for the power sector. The assignment also included inter-alia the financial restructuring plan and formulation of implementation programme. As per the ASCI recommendations, Tripura Electricity Regulatory Commission (TERC) was set up on 31st May 2004 and subsequently, Tripura State Electricity Corporation Limited (TSECL), Agartala was incorporated under the Indian Companies Act-56 on 9th June 2004 as a State owned Company with authorised equity share capital of Rs.10 crores. It has been made functional under, section 131 & 133 of the IE Act 2003, w.e.f 1st January 2005 with the operational control of all assets related to Generation, Transmission, Distribution & its allied activities related to power sector of Tripura and with objective of creating conditions for the sustainable development of the power sector along with improvement in efficiency of services to the consumer in particular and the State at large. Existing Power System Generation

Name of Project Gumti H.E Project Baramura Gas

Installed Capacity 5x3=15.00 MW 21x1=21.00 MW

Effective Capacity 8.5 MW 21.00 MW

Thermal Project Rokhia Gas Thermal Project Total 8x4+21x2=74.00 MW 110.00 MW 50.00 MW 79.50 MW

Transmission and Distribution Network Particulars 132 KV 66 KV 33 KV 11 KV LT HT:LT Ratio Line 387.63 CKM 380.20 CKM 504.52 CKM 7687.18 CKM 13849.05 CKM 1 : 1.80 Sub-Station Capacity 10 Nos. 13 Nos. 35 Nos. 5915 Nos. 200.00 MVA 165.50 MVA 217.95 MVA 484.81 MVA

Interconnection The state power systems in the North Eastern Region are integrated with 400/220 kV network of Power Grid Corporation of India Ltd. The power system of Tripura is connected to these power systems of the neighbouring states in the North Eastern region at 132 kV. This provides the stable operation for the state power system. Consumer Profile

Category DOMESTIC COMMERCIAL

No. of Consumer 348551 36760

% of Total 88.26% 9.31%

INDUSTRIAL BULK SUPPLY IRRIGATION & WATER WORKS OTHERS

3780 376 4692 739

0.96% 0.10% 1.19% 0.19%

Commercial Overview

Total Consumers 394898 No % coverage of Households 59.44% 100% Metering up to 11 KV Level 100% Computerized Energy Billing to be
Achieved by 2009

Average Cost of Supply Rs. 2.74 /kWh Average Rate of Realization Rs. 2.58 /kWh Annual Per Capita Consumption 192.48 kWh

Current Status TSECL has a total capacity of 110 MW from 3 generating stations viz. Gomuti Hydroelectric Project, Baramura Gas Thermal Power Station and Rokhia Gas Thermal Power Station. In addition to this, it has diesel based generating units of 5.85MW, which are also operational since pre-independence. The unit-wise capacity of all generating stations is mentioned below.

Name of Project Gumti H.E Project

Unit Unit-I Unit-II Unit-III

Installed Capacity 5.00 MW 5.00 MW 5.00 MW 5.00 MW 5.00 MW 6.50 MW

Year of Installation

Phase Phase-I Phase-II Not in Operation and already Surveyed

Baramura Gas Thermal Project

Unit-I Unit-II Unit-III

1976 1976 1984 1986 1986 1990

off. Unit-IV Rokhia Gas Thermal Project Unit-I Unit-II Unit-III Unit-IV Unit-V Unit-VI Unit-VII Unit-VIII Total Less: 3 units of Baramura station Less: 2 units of Rokhia station Installed (Hy+Th) Total 21.00 MW 8.00 MW 8.00 MW 8.00 MW 8.00 MW 8.00 MW 8.00 MW 21.00 MW 21.00 MW 142.50 MW 16.50 MW 16.00 MW 110.00 MW Unit I/II/III Unit I/II

2002 1990 1990 1995 1995 1997 1997 2002 2006

Not in operation Phase-III

Phase-II

Out of these stations, first three units of Baramura gas station (French Make) and first two nos. unit (Phase-I) of Rokhia Project are not working because of obsolesce. Therefore effective Installed Capacity is 110.00 MW. Hydel power There is a small Hydel power station in south Tripura named Gumti Hydel project having only 3 x 5 MW capacities.The yearly energy content in the reservoir of Gumti project is only 60 Million units. Normally 2 units of 5MW each run at a continuous load of 8 MW and the 3rd one is kept as stand by. It has been observed during last few years that with this arrangement 100% generation is achieved, i.e. 60 MU which fulfils the annual target. Theoretically the PLF is about 53 .33% with one unit as stand by. But there is hardly any water available at the end of the year and before next monsoon to increase the generation for achieving higher PLF. Gas Thermal Project at Rokhia The project has 6 no. of Gas Turbine sets of 8 MW each. Unit-VII of 21 MW capacity was commissioned during August 2002 and is now in operation. Another 21MW capacity (Unit-VIII) was come into bus on March 2006. Unit I has outlived its life. Further, unit II has been unstable since commissioning. The cost of reconditioning these units are found to be beyond economical viability. Therefore survey reports have been proposed for these units.Similar to Unit IV of Baramura, 50% capacity share of Units V and VI of this project is to be given to neighbouring states i.e. Manipur and Mizoram. Appropriate share of energy has to be transferred to these states at net generation cost. Unit-VII (21MW) was out of bus from 11th January 2006 due to major defect developed in the generator. The major maintenance work has been taken up including replacement of generator which is likely to be available for generation in the month of

June-06. Unit VIII (21 MW) has been commissioned on May 31, 2006. Along with rest of the units, the project is generating 40-MW of power from Unit- III, IV, V, VI and VIII. This will reach 50 MW by June-06 after re-commissioning of Unit#VII. Additional generation would depend on availability of additional gas at the power stations. The Diesel power house is operated intermittently, on emergency basis, mainly due to very high cost of fuel for the same. Out of 110 MW installed capacity in the state comprising of Baramura-21 MW, Rokhia74 MW and Gumti Hydel project-15 MW the over all generation is 70 MW round the clock as such the PLF works out at 63.63% for installed effective capacity the State. 1X21 MW Gas Thermal Project at Baramura The first three units have been out lived their normal life due to prolonged use and further life extension seems uneconomical because of non-availability of spares from market and huge funds would be required for this purpose. Preparation for assessment of book value of the machine & other codal formalities to be observed is under consideration of TSECL. A unit of 21 MW was commissioned on 27th November 2002 and is running at PLF is almost 95%. The Baramura project has been synchronized with NE Grid in the ABT regime. Being funded by NEC, this unit is considered as Inter-state station and hence 50% capacity share has to be given to neighbouring states of Manipur and Mizoram. With finalisation of power purchase agreement and issuance of satisfactory payment mechanism expected to be completed this year, appropriate share of energy is to be transferred to these states at net generation cost. Calorific Value of Natural Gas The rate of Gas consumption in a gas based Thermal plant depends upon the Heat Rate of the Turbine as well as Calorific value of the gas. At Rokhia Gas Thermal Power Station it is observed that Calorific value of Gas varies from month to month in the range of 8200 to 8300 Kcal/Cum. Union Ministry of Petroleum fixes the gas price considering Calorific Value of Gas at 10000 Kcal/Cum. Rebate/Premium on the gas price is applicable if the actual Calorific value of gas differs from the 10000 Kcal/Cum. GAIL indicates the average calorific value of gas for the particular month in their monthly gas bills to calculate the quantum of Rebate/Premium applicable.

Half Yearly Compliance Report on environmental stipulations for Baramura Gas Thermal Project Ongoing Capacity Addition in Generation

21 MW Unit V at Baramura GT
Project.

Proposed Capacity Addition in Generation

105 MW CCGT Project at


Chakmaghat.

104 MW TGBPP at Manarchwak by


NEEPCO.

740 MW CCGT at Palatana by OTPC.

Tranmission
The transmission network of the TSECL spans over 10486 sq. km. with 4 districts comprising of 4 major town and 870 villages. In addition to state level network, it is interconnected with other states with the transmission network of Power Grid Corporation of India Limited. List of Transmission Assets (Voltage Class Wise)

SUB-STATION a. 132KV Grid Sub-Station, 79 Tilla, Agartala. i. ii. iii. iv. b. 132/66 KV, 1x15MVA Auto Tr. with associated switch gear and control panels. 132/33 KV, 4x15MVA Trans. with associated switch gear and control panels. 132/33 KV, 2x20MVA Trans. with associated switch gear and control panels. 132/11 KV, 1x15MVA Trans. with associated switch gear and control panels. 132/33/11 KV, 3x7.5 MVA Trans. with associated switch gear and control panels. 132/33/11 KV, 1x7.5 MVA Trans. with associated switch gear and control panels. 132/33KV, 1x15 MVA Trans. with associated switch gear and control panels. 132/11KV, 1x10 MVA Trans. with associated switch gear and control panels. 132/11 KV, 1x15 MVA Trans. with associated switch gear and control panels.

132KV Grid Sub-Station, Mission Tilla, Dharmanagar. i.

c.

132KV Grid Sub-Station, Gournagar, Kailasahar. i.

d.

132KV Grid Sub-Station, PURBA KANCHANBARI i. ii.

e.

132KV Sub-Station, Kamalpur i.

f.

132KV Sub-Station, Dhalabil, Khowai 132/33 KV, 1x7.5 MVA Trans. With associated switch gear and control panels.

g.

132KV Sub-Station, Banduar, Udaipur i. ii. iii. iv. 132/11 KV, 1x15 MVA Trans. With associated switch gear and control panels. 132/66 KV, 1x15 MVA Trans. with associated switch gear and control panels. 66/11 KV, 1x6.3 MVA Trans. with associated switch gear and control panels. 66/33/11 KV, 1x5/2/5 MVA Trans. with associated switch gear and control panels. 66/33 KV, 1x6.3 MVA Trans. with associated switch gear and control panels. 66/33 KV, 1x4 MVA Trans. with associated switch gear and control panels. 66/11 KV, 1x6.3 MVA Trans. with associated switch gear and control panels. 66/33 KV , 1x15 MVA Trans. with associated switch gear and control panels. 66/11 KV , 2x10 MVA Trans. with associated switch gear and control panels. 66/11KV, 1x15MVA Trans. with associated switch gear and control panels. 66/11 KV, 1x6.3 MVA Trans. with associated switch gear and control panels. 66/33 KV, 2x5 MVA Trans. with associated switch gear and control panels. 66/11 KV, 1x10 MVA Trans. with associated switch gear and control panels. 66/33 KV, 1x4 MVA Trans. with associated switch gear and control panels. 66/11 KV, 1x6.3 MVA Trans. with associated switch gear and control panels. 66/33 KV, 1x10 MVA Trans. with associated switch gear and control panels.

h.

66KV Sub-Station, Gamai Tilla, Taliamura i. ii.

i.

66KV Sub-Station, Amarpur i.

j.

66KV Sub-Station, Badarghat i. ii.

k.

66KV Sub-Station, Gakulnagar, Bishalgarh i.

l.

66KV Sub-Station, Rabindranagar, Sonamura i. ii.

m. 66KV Sub-Station, Bagafa i. ii. n.

66KV Sub-Station, Belonia i. ii.

o.

66KV Sub-Station, Satchand i. 66/11 KV, 1x4 MVA Trans. with associated switch gear and control panels. 66/11 KV, 1x10 MVA Trans. with associated switch gear and control panels.

p.

66KV Sub-Station, Sabroom i.

TRANSMISSION LINES q. 132KV DC Transmission Line i. r. 132KV DC trans. Line on steel tower with 30/7/3/2.15mm ACSR conductor (Panther) from Rokhia to Agartala.

132KV SC Transmission Line i. 132KV SC trans. Line on steel tower with 30/7/3/2.15mm ACSR conductor (Panther) from Dharmanagar to Agartala via Purbakanchanbari & Ambassa 132KV S/S. (Teliamura to Champaknagar section has been renovated by AASC of size 37/3.15mm renovated) 132KV SC trans. Line on steel tower with 30/7/3/2.15mm ACSR conductor (Panther) from Agartala to Purbakanchanbari via Khowai & Kamalpur 132KV S/S 132KV SC trans. Line on steel tower with 30/7/3/2.15mm ACSR conductor (Panther) from Purbakanchanbari to Kailasahar 132KV S/S. 132KV SC trans. Line on steel tower with 30/7/3/2.15mm ACSR conductor (Panther) from Agartala to Udaipur 132KV S/S. 66KV SC trans. Line on steel tower with 6/7/4.72/1.57mm ACSR conductor (Dog) from Gumti H.E. Project to Agartala via Amarpur, Teliamura & Baramura 66KV S/S. 66KV SC trans. Line on steel tower with 6/7/4.72/1.57mm ACSR conductor (Dog) from Gumti H.E. Project to Agartala via Udaipur, Bishalgarh & Badarghat 66KV S/S. 66KV SC trans. Line on steel tower with 6/7/4.72/1.57mm ACSR conductor (Dog) from Udaipur to Satchand via Bagafa 66KV S/S. 66KV SC trans. Line on steel tower with 6/7/4.72/1.57mm ACSR conductor (Dog) from Badarghat to Bagafa via Rokhia, Sonamura & Belonia 66KV S/S. 66KV SC trans. Line on steel Pole with 6/7/4.72/1.57mm ACSR conductor (Dog) from Satchand to Sabroom 66KV S/S.

ii.

iii.

iv. s.

66KV SC Transmission Line i.

ii.

iii. iv.

v.

Distribution
The current load factor of Tripura system is 47% and the same is adopted over the period of next year as the demand is mostly domestic, commercial, public lighting etc. which occurs only few hours a day. The peak demand may get reduced if the load

factor improves. TSECL has undertaken various schemes for strengthening and extending its T&D network. Progress of New Works

Accelerated Power Development Reform Programme (APDRP) Sl. Name of scheme No. 100% metering of the feeders in the entire State, metering of Distribution Transformers, Consumer metering & augmentation of sub-transmission & distribution system in West Tripura District. Metering, computerisation, subtransmission & distribution scheme for Agartala Town. Sub-transmission and distribution improvement for Outer Agartala. Sub-transmission and distribution improvement for South Tripura District. Sub-transmission and distribution improvement for North Tripura District. Sub-transmission and distribution improvement for Dhalai District. SCADA / DMS scheme for Agartala town. TOTAL: Sanctioned Project Cost

1.

13.27

2.

14.27

3. 4. 5.

20.57 31.11 28.7

6. 7.

18.99 23.65 150.56

APDRP Scheme was launched in Tripura during 2001-2002. Since then total 7 nos. APDRP Schemes have been sanctioned for a total project cost of Rs.150.56 Crores. Out of these two schemes of 100% metering of the entire State and strengthening of sub-transmission and distribution network of West District for project cost of Rs.27.54 Crores were under implementation upto FY 2004-05. During FY 2005-06 programme for implementation of balance work of the first two schemes and the newly sanctioned 4 schemes for North Tripura District, Dhalai District, South Tripura District & Outer Agartala including SCADA/DMS Project at Agartala Circle has been taken up.

DOMESTIC

Average cost of Supply Average rate of realization Average cost of Supply Average rate of realization

Rs.2.74/kwh Rs.2.38/kwh Rs.2.74/kwh Rs.2.58/kwh

OVERALL

AVARAGE COST OF POWER PURCHASE Rs.2.30/kwh AVARAGE COST OF OWN GENERATION Rs.1.57/kwh

You might also like