Professional Documents
Culture Documents
Earned Schedule
Earned Schedule
- 10 Symposium
May 17-20, 2005 London, England
Earned Schedule
an extension to EVM theory
Kym Henderson
Education Director PMI Sydney, Australia Chapter kym.henderson@froggy.com.au 61 414 428 537
Walt Lipke
Software Division Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341
Purpose
To discuss and encourage the application of a new method of schedule analysis derived from Earned Value Management, termed Earned Schedule.
Overview
The Problem with EVM Earned Schedule Concept Applications Status & Future Summary
The Problem
BCWS
SPI =
BCWP BCWS
$
ACWP
CV SV
BCWP
Time
Earned Value
Cost and Schedule Variances
CV = BCWP - ACWP CV = BCWP - ACWP SV = BCWP - BCWS SV = BCWP - BCWS
+$
0
J F M A M J J A S O N
01
D J
02
F M A
-$
CV SV Note: Project completion was scheduled for Jan 02, but completed Apr 02. 7
Earned Value
2.0
INDEX VALUE
1.5
1.0
0.5
CPI SPI
0.0 J F M A M J J A S O
01
02
Note: Project completion was scheduled for Jan 02, but completed Apr 02. 8
BCWS
SPI(t) =
ES AT
SV(t) = ES AT
$
BCWP
ES = All of May + Portion of June ES = 5 + AT = 7 BCWP($) - BCWS(May) BCWS(June) - BCWS(May)
Time
10
60
0.6
Mo
40
0.4
20
0.2
SV($)
0
SV(t)
0
Mo
-400
-3
11
SPI($)
F M A M J J A S O N D J F
SPI(t)
M
12
13
SV Earned Earnedschedule schedulemetrics metricsrelate relate work performed to actual time, work performed to actual time,not not work workscheduled scheduled Retain Retainutility utilityover overtime time Only Onlyreturn returnto to0 0or or1.00 1.00where where on time completion achieved on time completion achieved
14
BCWP
SV(t)
Applications
D o llars (,000)
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Elapsed Weeks
W eeks
16
Sched wk 25
4.0 3.0
Dollars ($,000)
Stop wk 16
Re-start wk 19
-2.0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Elapsed Weeks
W eeks
2.0
17
IEAC(t) Predictions using ES Techniques: Weekly Plots of IEAC(t) Late Finish Project Example
Commercial IT Infrastructure Expansion Project Phase 1
Earned Schedule, Independent Estimate At Completion (time) - IEAC(t)
as at Project Completion: Week Starting 15th July xx
Planned Schedule Earned Schedule cum IEAC(t) PD/SPI(t)
40 35 30 Duration (Weeks) 25 20 15 10 5 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Plan Dur wk 20
Stop wk 19
Re-start wk 26
18
IECD Predictions using ES Techniques: Weekly Plots of Independent Estimate of Completion Date
Commercial IT Infrastructure Expansion Project Phase 1
Earned Schedule, Independent Estimates of Completion Date (IECD)
as at Project Completion: Week Starting 15th July xx
Planned Schedule Earned Schedule cum Planned Com pletion Date Independent Estim ate of Com pletion Date
25
Stop wk 19
20 Duration (Weeks)
15
19 May 90
Re-start wk 26
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
27 Jan 90
19
ES vs EVM Comparison
Earned Schedule Earned Value
SV(t) and SPI(t) valid for SV($) and SPI($) validity entire project, including early limited to early finish projects and late finish Limited prediction capability Duration based predictive No predictive capability after capability analogous to EVMs cost based indicators planned completion date exceeded Facilitates Cost Schedule Management (using EVM and ES) EVM Management focused to Cost
20
22
Early Adopters
Incorporation of ES into EVM Instruction
Several instruction sources now offer ES as part of EVM
23
24
Summary
Summary
Derived from EVM data only Provides time-based schedule indicators Indicators do not fail for late finish projects Application is scalable up/down, just as is EVM Schedule prediction is better than any other EVM method presently used
SPI(t) behaves similarly to CPI IEAC(t) = PD / SPI(t) behaves similarly to IEAC = BAC / CPI
References
1. Schedule is Different, The Measurable News, March & Summer 2003 [Walt Lipke] 2. Earned Schedule: A Breakthrough Extension to Earned Value Theory? A Retrospective Analysis of Real Project Data, The Measurable News, Summer 2003 [Kym Henderson] 3. Further Developments in Earned Schedule, The Measurable News, Spring 2004 [Kym Henderson] 4. Connecting Earned Value to the Schedule, The Measurable News, Winter 2004 [Walt Lipke] 5. Forecasting Project Schedule Completion by Using Earned Value Metrics Presentation by Ing. Stephan Vandevoorde, Senior Project Manager, Fabricom Airport Systems, Belgium 6. Earned Schedule in Action, Publication pending, [Kym Henderson]
http://sydney.pmichapters-australia.org.au/ Click Education, then Presentations and Papers for .pdf copies, except (6)
27