Capital Construction Cost Tracking

Anacostia Neighborhood Library


Budget Authority $ 13,656,169
planned v. 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY
actual in 2007 2008 2008 2008 2008 2009 2009 2009 2009 2010 2010
Project Phase Budget Balance 000's July Aug Sept Oct Nov Dec Jan Feb Mar April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May Jun July Aug Sept Oct Nov Dec Jan Feb Mar
1 Demolition $ 266,997 $ 228,632 Planned 150 26 25
Change Orders $ 26,982 Actual 61 4
2 Programming $ 75,000 $ 75,000 Planned 25 25 25
Actual
3 Design $ 1,565,852 $ 844,627 Planned 157 225 200 185 320 20 20 20 20 20 32 27 27 27 27 27 27 27 27 27 27 27 27 27
Actual 79 81 52 81 99 93 93 144
4 Construction $ 9,100,000 $ 9,100,000 Planned 66 980 875 2576 1206 800 525 498 687 132 126 126 126 126 126 126
Actual
5 Construction Mgt $ 1,092,785 $ 1,092,785 Planned 60 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52
Actual
6 Equipment $ 365,509 $ 365,509 Planned 366
Actual
Contingency $ 1,194,966
Budget $ 13,688,091

Benning Neighborhood Library


Budget Authority $ 14,057,112
planned v. 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY
actual in 2007 2008 2008 2008 2008 2009 2009 2009 2009 2010 2010
Project Phase Budget Balance 000's July Aug Sept Oct Nov Dec Jan Feb Mar April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May Jun July Aug Sept Oct Nov Dec Jan Feb Mar
1 Demolition $ 261,997 $ 180 Planned 36 36 36 Benning Demolition is Complete:
Change Orders $ 4,350 Actual 101 4 54 71 36 Payments have been made in full
2 Programming $ 50,000 $ 50,000 Planned 25 25 25
Actual
3 Design $ 1,561,199 $ 660,687 Planned 225 157 320 185 100 105 18 18 18 18 18 32 27 27 27 27 27 27 27 27 27 27 27 27 27
Actual 79 79 79 26 180 90 195 172
4 Construction $ 9,400,000 $ 9,400,000 Planned 166 980 875 2576 1206 800 625 498 687 232 126 126 126 126 126 126
Actual
5 Construction Mgt $ 1,122,320 $ 1,122,320 Planned 53 53 53 53 53 53 53 53 53 53 53 53 53 53 53 53 53 53 53 53 53
Actual
6 Equipment $ 365,509 $ 365,509 Planned 366
Actual
Contingency $ 1,296,087
Budget $ 14,061,462

Document #8C.4
Board of Library Trustees Meeting
May 28, 2008
Capital Construction Cost Tracking

Tenley-Friendship Neighborhood Library


Budget Authority $ 14,503,897
planned v. 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY
actual in 2007 2008 2008 2008 2008 2009 2009 2009 2009 2010 2010
Project Phase Budget Balance 000's July Aug Sept Oct Nov Dec Jan Feb Mar April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May Jun July Aug Sept Oct Nov Dec Jan Feb Mar
1 Demolition $ 314,580 $ 2,148 Planned 110 100 62 Demolition is Complete: Payments
Change Orders $ 128,043 Actual 169 3 6 129 26 10 14 83 have been made in full
2 Programming $ 35,000 $ 35,000 Planned 15 10 10
Actual
3 Design $ 1,642,899 $ 874,430 Planned 225 157 300 200 175 110 20 18 18 18 18 32 32 27 27 27 27 27 27 27 27 27 27 27 27
Actual 83 85 54 85 105 100 98 157
4 Construction $ 9,620,500 $ 9,620,500 Planned 215 1000 975 2576 1206 852 625 498 687 232 126 126 126 126 126 126
Actual
5 Construction Mgt $ 1,126,340 $ 1,126,340 Planned 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54
Actual
6 Equipment $ 365,509 $ 365,509 Planned 366
Actual
Contingency $ 1,339,583
Budget $ 14,572,454

Watha T. Daniel/Shaw Neighborhood Library


Budget Authority $ 13,281,104
planned v. 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY
actual in 2007 2008 2008 2008 2008 2009 2009 2009 2009 2010 2010
Project Phase Budget 000's July Aug Sept Oct Nov Dec Jan Feb Mar April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May Jun July Aug Sept Oct Nov Dec Jan Feb Mar
1 Demolition $ 306,000 $ 3,350 Planned 125 101 35 Demolition is Complete: Payments
Change Orders $ 47,634 Actual 122 3 18 18 164 25 have been made in full
2 Programming $ 25,000 Planned 12 13
Actual
3 Design $ 1,527,432 $ 844,427 Planned 212 157 253 185 155 110 20 15 12 12 12 32 32 27 27 27 27 27 27 27 27 27 27 27 27
Actual 78 78 104 52 52 178 124 18
4 Construction $ 8,830,000 $ 8,830,000 Planned 200 875 975 2166 1116 767 625 432 687 232 126 126 126 126 126 126
Actual
5 Construction Mgt $ 1,035,743 $ 1,035,743 Planned 49 49 49 49 49 49 49 49 49 49 49 49 49 49 49 49 49 49 49 49 49
Actual
6 Equipment $ 365,509 $ 365,509 Planned 366
Actual
Contingency $ 1,156,524
Budget $ 13,293,842

Document #8C.4
Board of Library Trustees Meeting
May 28, 2008
Capital Construction Cost Tracking

Georgetown Neighborhood Library*


Budget Authority $ 13,281,104
planned v. 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY
actual in 2008 2008 2009 2009 2009 2009 2010 2010 2010 2010 2011
Project Phase Budget Balance 000's April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May Jun July Aug Sept Oct Nov Dec Jan Feb Mar April May Jun July Aug Sept Oct Nov Dec
1 Building Stabilzation $ 955,509 $ - Planned
Actual 956
2 Programming $ 8,000 $ 2,606 Planned 8
Actual 5
3 Design $ 1,660,958 $ 1,660,958 Planned 111 111 111 166 166 133 133 133 133 133 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18
Actual
4 Construction $ 14,428,000 $ 14,428,000 Planned 450 850 1500 250 3750 650 1800 2456 485 874 409 257 190 115 86 76 72 59 43 56
Actual
5 Construction Mgt $ 1,930,675 $ 1,930,675 Planned 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64
Actual
6 Equipment $ 1,000,000 $ 1,000,000 Planned 550 450
Actual
Contingency $ 1,608,896
Budget $ 21,592,038

Mt. Pleasant Neighborhood Library*


Budget Authority $ 7,750,000
planned v. 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY 2nd Quarter FY 3rd Quarter FY 4th Quarter FY 1st Quarter FY
actual in 2008 2008 2009 2009 2009 2009 2010 2010 2010 2010 2011
Project Phase Budget Balance 000's April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May Jun July Aug Sept Oct Nov Dec Jan Feb Mar April May Jun July Aug Sept Oct Nov Dec
1 Programming $ 8,000 $ 4,505 Planned 8
Actual 3
2 Design $ 1,720,000 $ 1,705,577 Planned 111 111 111 166 166 133 133 133 133 133 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18
Actual 14
3 Construction $ 5,580,000 $ 5,580,000 Planned 450 850 1500 250 3750 650 1800 2456 485 874 409 257 190 115 86 76 72 59 43 56
Actual
4 Construction Mgt $ 450,000 $ 450,000 Planned 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64 64
Actual
5 Equipment $ 365,509 $ 365,509 Planned 550 450
Actual
Contingency $ 1,608,896
Budget $ 9,732,405

Document #8C.4
Board of Library Trustees Meeting
May 28, 2008