C/Hands Utility Men Comments
Operatives
Job Location
Operatives Names
Area/Fire Zone.
Job Card No: 8LW3-061 Workpack No: 8LW3 Date Work Started: 24th May 2013 RH % Dew Point Steel Temp. C C
RECORD 3 TIMES DAILY (INCLUDE DAY & NIGHTSHIFT ON SAME REPORT. ENSURE UPDATED BEFORE END OF YOUR SHIFT
CREATE NEW WORKSHEET IF YOU RUN OUT OF SPACE BY RIGHT CLICK ON WORKSHEET TAB SELECT MOVE/COPY, SELECT CREATE A COPY BOX, SELECT OK. RENAME I.E. DAILY REPORT 1, 2, 3 ETC BY RIGHT CLICK ON WORKSHEET & SELECT RENAME
Drawing Number
Line Number
Date
Drawing Number
Line Number
Pre-wash Complete: Yes Surface Preparation Method: Dry Grit Blast Date 5/12/2013 Blast Surface Profile (m) Dust Level Max 85m Max 2 Mill Scale Clear Y/N Yes Soluble Salt Level
MAX 30mg/m
Surface Degreased: IF APPLICABLE Abrasive Used: Garnet or Aquagrit Date Blast Surface Profile (m) Dust Level Cleaning Grade: SA 2 Mill Scale Clear Y/N Soluble Salt Level
Coating Manufacturer: Carboline Stripe Coating Performed: Yes Date Time 12/5 1015 13/5 0850 15/5 0830 Area/Item Coated Structure Structure Structure System Code P01 P01 P01 Coat Number 1 2 3 Coating 18FC 18FC 2000 TC
Coating Used: Carbomastic 18FC & Carboxane 2000TC Paint Application Method: Either Airless Spray or Brush Batch No. Base Batch No. Hardner Colour Grey Grey Yellow DFT (Average) 150m 300m 400m 5 Mpa Minimum Adhesion (Pull off Force)
Location:
Put JC Number
Location:
Put JC Number
Location:
Put JC Number
Location:
Put JC Number
Location:
Put JC Number
Location:
Inspection Equipment Used: Testex Tape and Micrometer Calibration Date: Put Calibration Due Date
Spray applied C750V2 Test panel done in-situ Photo of completed job as per JC
Adhesion Test - Photo value recorded on adhesion test beside test plate
Statement: All work has been completed to the current Total approved specifications. Work orders have been updated and closed out in SAP Inspection records have recorded the environmental conditions, surface preparation, coating application, trace heating, Insulation and cladding (where applicable), all of which have been measured with inspection equipment traceable to national standards.
FINAL ACCEPTANCE