Professional Documents
Culture Documents
Good Practices in Tunnelling: The Experience of Norway
Good Practices in Tunnelling: The Experience of Norway
Introduction
Underground excavation is often a key factor in the cost and time for opening production in a mining projects. Mining in Chile is in general world class. Nevertheless, tunnelling performance is still very poor. Norway has a long tradition in tunnelling and excavation rates commonly reach 70 m/week though working less hours (100 vs. 168 h/week) and with less people. This study aims to summarize the good practices of tunnelling in Norway, trying to identify some of the reasons behind the differences in the tunnelling rates and costs between Chile and Norway.
Road tunnels Sub sea road tunnels Railroad tunnels Hydropower tunnels Other tunnels Caverns Total tunnel projects
1891 - Eidfjordvatn
Source: NTNU
Source: NTNU
risk-sharing inthe tunnel contracts is The Themain groundprinciple condition is of always uncertain when contract is sign. toIf the contractor has to assume all the risk he will ask a each very high price in give to the parties a tool for converting unit order to be safe. work into time-equivalents and cost-equivalents Courtactivity proceedings regarding change ground conditions may be very costly and time consuming, the only winners are the lawyers.
Such How the allows risk can be shared? tool to meet any contingency arising from
All types and activities possibly needed during tunneling are estimated in discussions over regulation of the construction time the BoQ. where A unit price is offered by the costs contractor for each unit activity. needed, or over incurred. An equivalent time is offered by the contractor for each unit activity. For rock support elements, different time is defined for primary support and support behind the face. Thus, the contractor is paid by unit of work done and the contractual construction time is adjusted to the actual ground conditions by mean of the equivalent time system.
Rock Support
The support is decided at face based on the observed conditions, without predefined classes, this requires to have: Flexible Contract. Contractor compensated by unit (not by rock class!). Flexible Support Elements. Main elements are shotcrete with fiber and bolts. Expertise. Experienced geologist in the tunnel for defining the support. Support is installed in two stages:
Initial support. Installed at face to ensure safe working conditions during construction. Permanent support. Installed behind face to ensure project requirements during operation. Initial elements are recommended to be part of permanent support system. i.e. all elements have to reach long term standards.
Rock Support
The main support elements in Norway are rock bolts and shotcrete (with and without fiber). Most typical rock bolt types are rock bolts end-anchored by resin capsules and CT-Bolts. Fully grouted rebar bolts is considered to be optimal for hard rock applications. Combi-coat corrosion protection and hot-dip galvanized steel have shown to be very effective for harsh environments. Shotcrete is normally improved by the use of fiber and accelerators. The use of Reinforced Ribs of Shotcrete (RRS or Norwegian arches) can usually replace the more expensive and time-consuming cast in place concrete lining. CT-Bolts: Expansion Shell for instant support plus arrangement for grouting injection for permanent support. Spilling Bolts: XXX RRS is Double a very flexible method in which the thickness and spacing of the ribs corrosion protection. can vary as required. When required, support may be installed ahead the face.
The Contractor
Rather small and self sufficient teams
State of the art equipment and methodology Managers with hands on experience (former tunnel workers and supervisors etc) Flat structure in the organization (mutual respect and thrust) Knowledge, responsibility and decision making power at the face Culture of responsibility at all levels (internally and towards the client and side contractors) Strong focus on logistics and optimization of processes Dynamic payment based on production and KPI (bono system) Problem solving focus rather than focus on short term gains
-Top down approach -Only following instructions -Little communication -Low knowledge transfer -Static system -Punishment
-Bottom up approach -Procedures only basis -Safe Job Analysis -Running communication -Positive focus on registered unwanted events -Dynamic system - Bono systems
Dalvatnet
Snn HPP
Raundalen Kraftstasjon
GRANITIC GNEIS
VULCANITES
Sagelva
Maldal
Tengesdalselva
10 km
VULCANITES
Lingvangselva
GRANITIC GNEIS
Adit Raundalen
Final Comments Dynamic rock support incl. Inital (at face) and permanent support (additional behind face) High competence at face De-sentraliced decition making Benefit sharing with tunnel workers
(KPI dependant salary = Production, HSE, Teamwork) (ventilation, water control, road surface, light)
Maintain optimal working conditions at all times Good logistics is essential Running maintainance and supply of critical spare parts