Professional Documents
Culture Documents
Construction Schedule For Sewege Treatment Plant
Construction Schedule For Sewege Treatment Plant
Construction Schedule For Sewege Treatment Plant
Remarks
677 m
Interconnection of Ponds
i) ii) Arrangement of Material / Labour Supply of R.C.C pipes 21"i/d = 63 Nos,18" i/d = 36 Nos. 21" i/d 18" i/d iii) iv) v) vi) Excavation / Lean Concrete Steel Fabrication of Inlet / outlet slides Concrete laying of inlet / outlet slides Laying of pipes and concrete pouring
01 Structure / day
36 Nos.
63 Nos. 15 pipes/day 36 Nos. 15 pipes/day 2 Structures/day 1 Structure/day 2 Structures/day 2 Structures/day 100 m / day
4035 m3
Distribution Chamber
i) ii) iii) iv) v) Arrangement of material Excavation / Lean concrete Steel Fabrication for Base Slab Concrete Laying in Base Slab Steel Fabrication of Walls
Sr No.
Description / Scope
Balance Qty.
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
Jun,11
Remarks
Inlet Channel
i) ii) iii) iv) v) vi) Arrangement of material and labour Excavation / Lean concrete Steel Fabrication in Base Slab Concrete laying in base Slab Steel Fabrication for walls Concrete pouring in walls
15 m / day
(535/15 = 53 days)
535 m
Outlet channel
i) ii) iii) iv) v) vi) Arrangement of material and labour Excavation / Lean concrete Steel Fabrication in Base Slab Concrete laying in base Slab Steel Fabrication for walls Concrete pouring in walls
15 m / day
(610/15 = 40 days)
610 m
Area Lighting
i) ii) Arrangement of poles Installation of poles with laying of wires (8 nos. x 3 days = 24 days)
1 pole/ 3 days
1 Job
Plantation
i) ii) iii) Laying of Sweet soil Arrangement of plants Plantation 3421/60 = 57 /day
3421 Nos.
1 Job
vii) Concrete laying in Roof slab viii) Fixing of Windows / Ventilators / Door Shutter ix) x) Plaster Electrification
Sr No. 2
Description / Scope
Balance Qty.
1 Job
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
Jun,11
Remarks
Pluging
i) ii) iii) iv) v) Arrangement of material /labour / machinery First layer Second layer Third layer Final Layer / Finishing
4 Jobs
Dry Well
i) ii) iii) iv) v) v) Civil Work Intermediate Slab Stairs / Railing Brick Work Fixing of Girder / Chain Pully Roof Slab
1 Job
Electrical works
i) ii) iii) Manual Change Over Control pannel Motor control centre
1 Job
1 Job
Sr No. 7
Description / Scope
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
Jun,11
Remarks
C 1
vii) Concrete laying in Roof slab viii) Fixing of Windows / Ventilators / Door Shutter ix) x) 2 Plaster Electrification
1 Job
Staff Quarter
i) ii) iii) iv) v) vi) Arrangement of material and labour Excavation and Lean Concrete Brick Work / Flooring / Plaster Fixing of Door / Window / Ventilators Electrification Sanitary Works
Sinking
i) ii) iii) Arangement of machinery Dewatering set etc. Excavation under SSWL
4 Jobs
Sr No. 4
Description / Scope
Balance Qty.
4 Jobs
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
Jun,11
Remarks
Dry Well
i) ii) iii) iv) v) v) Civil Work Intermediate Slab Stairs / Railing Brick Work Fixing of Girder / Chain Pully Roof Slab
1 Job
Electrical works
i) ii) iii) Manual Change Over Control pannel Motor control centre
1 Job
Installation of Machinery
i) ii) ii) iii) Construction of Foundatio for Pumps M.S Sheet Installation under pumps Fixing of Machinery Yard Piping (suction, delivery with specials)
1 Job
Screening Chamber
i) ii) iii) iv) Arrangement of Material (Screen / Pen Stock, etc) Intermediate Slab (Shttering / Steel Fabrication / Concrete Pouring Fixing of Screen Fixing of Pen Stock
1 Job
Boundary wall
i) ii) iii) iv) North Side South Side East Side West Side
(182 / 40 = 05 m/ day)
5 m / day
180 m
Sr No. D 1 2 3 4 5 E 1 2
Description / Scope
Balance Qty.
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
Jun,11
Remarks
Other works
Ittefaq colony disposal Missing link to old disposal Line S -T 27" dia i) ii) Manufacturing of pipe Laying of pipe
G - I sewer line
i) ii) Manufacturing of pipe Laying of pipe
48" dia
543 m/ 223 Nos. 543 m/ 223 Nos.
4 5
192 m /
79 Nos.
Sr No. 9
Description / Scope
Balance Qty.
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
Jun,11
Remarks
10
15",18" dia
791 m/ 324 Nos.
11 12 13 14
Collection Chamber Dari sangi "Q" Point Q-J Crossing of Fauji Chowk 24" dia
Collection Cahmber Ittefaq Town "U" Point Q-J Zarai College (additional)
i) ii) Manufacturing of pipe Laying of pipe
18" dia
65 m / 65 m / 27 Nos. 27 Nos.
15
72" dia
1 Job
vii) Concrete Pouring viii) Construction of Manholes ix) x) xi) Laying of pipe 72"i/d Steel Fabrication & Shuttering for R.C.C Conduit Concrete Pouring
Ventilating Shaft
i) ii) Arrangement of material (Poles, etc) / labour Fixing of Poles
35 Nos.
Sr No. 17
Description / Scope
Balance Qty.
10 m
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
Jun,11
Remarks
33" dia
18
U-V Crossing
i) ii) Manufacturing of pipe Laying of pipe
18" dia
24 m / 9 Nos. 24 m / 9 Nos.
19 20 21
D-E-F-H Missing link/M.H Line I-R Missing Manhole A.C Force main Dari Sangi
i) ii) iii) Arrangement of A.C pipe Laying of pipe Testing of Pipe
44 m 1 No.
715 m 715 m
22 23 F 1
Fixing of machinery Lift Station Dari Sangi Fixing of machinery Lift Station chak 111/P Gharbi. G.R.P PIPE (Forcemain)
Ittefaq colony Arrangement of pipe Laying of pipe 20" 20" 20" 20" 36" 36" 36" 36" 36" 36"
1 Job 1 Job
176 m
285 m
Basti Kahur
560 m
253 m
Pattan Minara
120 m
SEWERAGE SCHEME OF RAHIM YAR KHAN CITY WITH TREATMENT PLANT ZONE II Targets of Balance Work
Sr. No. Description Balance Qty.
Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11
A Lift station Moye Mubark P.IV 1 Sinking of well i) ii) iii) i) ii) iii) iv) v) i) ii) iii) iv) v) vi) i) ii) iii) iv) v) vi) vii) viii) ix) x) i) ii) iii) iv) Arangement of machinery Dewatering set etc. Excavation under SSWL
4 Jobs
2 Pluging Arrangement of material / labour / machinery First layer Second layer Third layer Finishing
4 Jobs
3 Dry well Civil Work Intermediate Slab Stairs / Railing Brick work Fixing of Girder/ Chain Pully Roof Slab
1 Job
4 Generator room Arrangement of material / labour / machinery Excavation and lean concrete Steel fabrication for columns and beams Concrete pouring in columns and beams Brick work / Foundation / cable trench / flooring Fabricatio for Roof Slab Concrete laying in Roof Slab Fixing of Windows/ Ventilators/ Door Shutters Plaster Electrification
1 Job
5 Installation of Machinery & Yard Piping Constructio of foundations for pumps M.S Sheet Installation under pumps Fixing of machinery Yard piping (suction / delivery with specials)
1 Job
Sr. No.
Description
Balance Qty.
1 Job
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
200 m
iv) South 8 GRP Pipe 40" dia i) ii) iii) i) ii) Arrangement of GRP Pipe Laying of Pipe Testing of pipe
290 m
1 Job
iii) Motor control Centre 10 Ventilating Shaft i) ii) Arrangement of material (Poles, etc) Fixing of Poles
4 Nos
B Package III,V 1 LAW6-b 18" i/d i) ii) i) ii) i) ii) i) Manufacturing of pipes Laying of pipes Arrangement of material / labour / machinery Laying of pipe
2 MH 219 m / 90 Nos. 15 m/ (4 MH)
112 Mtr
Sr. No.
Description
Balance Qty.
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
60 Mtr
10 Remaining connections in Package III,V i) ii) Arrangement of material/ labour/ machinery Laying of pipe
50 Mtr
C Package IX Part I
Sr. No.
Description
Balance Qty.
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
3 Installation of Machinery i) ii) iii) iv) Construction of foundation for pumps M.S Sheet Installation under pumps Fixing of machinery Yar piping (Suction / Delivery with specials)
4 Electrical works i) ii) iii) Manual Change Over Control pannel Motor control centre
1 Job
Sr. No.
Description
Balance Qty.
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
Lift station Moye Mubark P.IV iv) South Side Lift station Basti Nayian 1 Forcemain(C.I)
i) ii) Arrangement of Pipe / Labour / machinery Laying of pipe
157805 Cum 32 Mtr
E STP,Moye Mubarak P.VIII 1 Earth Work i) Excavation / Filling for Ponds 1520 cu.m/day
220 Sq.m / Day 3521 Cum.
2 Lining of Anaerobic ponds i) ii) Arrangement of material / labour Lining (daily consumption of bricks 2537159 / 215 = 11800 Nos/ day)
3 Lining of Facultative Ponds i) ii) Arrangement of material / labour Lining (daily consumption of bricks 1893929 / 205 = 9240 Nos/ day)
3972 Cum
4 Lining of Maturation ponds i) ii) Arrangement of material / labour Lining (daily consumption of bricks 648952 / 200 = 3245 Nos/ day)
61 Sq.m / Day
1361 Cum
5 Distribution Chamber i) ii) iii) iv) v) vi) Arrangement of material Excavation / Lean concrete Steel Fabrication for Base Slab Concrete Laying in Base Slab Steel Fabrication of Walls Concrete pouring in walls 7 m/ day
1 Job
6 Inlet Channel i) ii) iii) iv) Arrangement of material and labour Excavation / Lean concrete Steel Fabrication in Base Slab Concrete laying in base Slab
497 Mtr
Sr. No.
Description
Balance Qty.
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
7 Interconnection i) Arrangement of Material / Labour Casting of R.C.C pipes ii) 21"i/d = 56 Nos,18" i/d = 32 Nos. iii) Excavation / Lean Concrete iv) Steel Fabrication of Inlet / outlet slides Concrete laying of inlet / outlet slides v) vi) Laying of pipes and concrete pouring 8 Outlet Channel i) ii) iii) iv) v) vi) Arrangement of material and labour Excavation / Lean concrete Steel Fabrication in Base Slab Concrete laying in base Slab Steel Fabrication for walls Concrete pouring in walls
549 Mtr
9 Soling / Brick Pavement ( 1204 m) i) Arrangement of Material / Labour ii) Levelling / Dressing / Compaction of bed Pavement (Cosumption of bricks iii) 2431148/75 = 32415 Nos./ day) 10 Area Lighting i) Arrangement of poles Installation of poles with laying of wires (8 nos. x 3 days = 24 days)
16 m / day 50 m / day
5098.67 Cu.m
1 pole/ 3 days
1 Job
ii) 11 Plantation i) Laying of Sweet soil ii) Arrangement of plants iii) Plantation 3090/30 = 103 Plants /day 12 Barbed Wire Fence i) Arrangement of Material / Labour / Moulds for casting of R.C.C Posts ii) Casting of Concrete Poles (1051/15 = 70 days) iii) Arangement of barbed wire (13 gauge) and eye bolts (10 mm) iv) Installation of Concrete Poles 1051 /20 = 53 days
3090 Nos
20 Poles / day
Sr. No.
Description Installation of Barbed Wire P.IV v) Lift station Moye Mubark (2575 / 150 = 18 days)
Balance Qty.
Nov,10
Dec,10
Jan,11
Feb,11
Mar,11
Apr,11
May,11
150 m / day
Jun,11
Remarks
Jun,11
Remarks
Nadeem Construction
Jun,11
Remarks
Sadaqat Builders
work is in progress
Jun,11
Remarks
Jun,11
Remarks
Jun,11
Remarks