Professional Documents
Culture Documents
Mechanical Engineering Faculty (Mef), Sarajevo (Building Envelope and Heating System Reconstruction)
Mechanical Engineering Faculty (Mef), Sarajevo (Building Envelope and Heating System Reconstruction)
The MEF owns 2 buildings, one built in 1960 and the other in the late 1980s. There are three main goals of the project: 1. To reduce heat loss through the building envelope 2. To increase the efficiency of energy transformation of natural gas in the boiler house 3. To conduct monitoring of parameters necessary to establish an efficient and effective energy management TECHNICAL ANALYSIS and CONCEPTUAL ENGINEERING DESIGN showed that the heating systems for the west and east building should be separated and a NEW BOILER FOR THE WEST BUILDING
INSTALLED.
The systems will be connected manually when needed, as in the case of gas supply disruption or if the east building needs exceed the capabilities of the two remaining boilers. It was also shown that significant energy savings can be achieved BY REPLACING THE WINDOWS, since they are 50 years old, poorly maintained and in bad condition, and by THERMALLY INSULATING THE FASADE. The project also included a SYSTEM FOR MONITORING ENERGY CONSUMPTION AND VERIFICATION OF ENERGY SAVINGS (M&V SYSTEM), which will serve to introduce energy management. The project started in fall 2010 with the installation of the M&V system, and it was completed in December 2011.
1. BUILDING DESCRIPTION
Type of building: Year of construction: Number of occupants: Permanent Temporary Occupancy schedule: Net floor area (basement and 6 floors) Net heating area School (University) 1960 100 150 8 am - 4 pm (Monday to Friday) 8 am - 12 pm (Saturday) Closed - Sunday 5819 m2 4119 m2
22
Outside temperature
12000
18
10000
8000
10
6000 Natural Gas 4000 Electricty 2000 Water 0 Jan Feb Mar Apr May Jun Jul Avg Sep Oct Nov Dec
-2
-6
Month
Temperature [ C]
EEM#1-2: Installation of radiator thermostatic valves Since the load is frequently changed in rooms because of different numbers of occupants in a room, thermostatic valves will accomplish the necessary regulation of temperature in the room. Otherwise, the flow and return temperature of water is controlled automatically in the boiler house according to the outside temperature.
Figure 3. View on the west MEF building after Figure 2. View on the west MEF building before
mounting the new boiler, the connection to natural gas and electricity was then prepared. Instead of the existing chimney, a new chimney was placed and connected with the boiler. An underground flow-return pipeline was constructed of pre-insulated pipes and connected to the existing distribution pipes in the west MEF building. This pipeline was connected directly to the boiler. A circulating pump, three-way valve and expansion vessel were installed in the boiler house.
Figure 4. View on the old boiler Figure 5. View on the new condensing boiler
4. ENVIRONMENTAL IMPACT
Expected energy (natural gas) savings after implementation of all proposed ECMs are: NG: (309,206.0 1.2) = 371,047.2 kWh/a
Reduction of CO2 emission is (see attachment 3): CO2(NG) = 0.1836 NG = 68,124 kgCO2e/a
4. Outside air temperature (1 measuring point) 5. Electrical energy consumption (6 measuring points) 6. Heat energy consumption (for radiator system of the west building , for radiator system of the east building and for air heating of the east building)
Energy Management Information System
Internet
M-bus
5000 4500
Before implementation of EE measures
-4,0
-2,0
0,0
2,0
4,0
6,0
8,0
10,0
12,0
Figure 7. Energy Consumption versus Average outside Temperature Before and After the EE Measures Implementation for the period from Dec 13, 2011, to Jan 12, 2012 From category E, the building has moved into category C, according to the criteria for building certification. After a month of monitoring the average inside temperature in rooms of the building, the increase of temperature has been recorded from an insufficient 19 to a comfortable 21 oC. Thermostatic valves on heating bodies have not yet been installed and fine temperature control is still not possible. The medium efficiency degree of boilers in the boiler house was around 73%. It is expected that the installed condensing boiler will reach a middle efficiency close to 100% (calculated according to the lower heating capacity). The installed M&V system enables complete the energy management of heating, electricity and water consumption. In 2012, the energy management system was put into practice. CO2 emissions have been reduced by about 20 tons per year only through savings in the heating system. The measurement control conducted for a duration of 12 days in January 2011 and 2012, shows that electrical energy consumption fell by 24% in January 2012, in relation to the electric energy consumption in the same period in 2011. Electricity consumption in mentioned periods is presented in Figure 8.
700
600
500
2011
400
300 2012 200 1-12 January 2011: 6285.6 kWh 1-12 January 2012: 4757.9 kWh
100
0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Day in January
8. CONCLUSIONS
1. By applying proposed and implemented measures for energy efficiency increase, annual aggregate savings of about 40% of heat energy are accomplished. 2. The saving of electricity is around 24%. 3. It is very important to emphasize that comfort conditions are significantly improved which is confirmed in many conversations with students and teaching staff. This is also proved by temperature measurements in several typical rooms within the M&V Program. 4. Installation of such a boiler at the Mechanical Engineering Faculty will certainly contribute in the education of students and in the promotion of this highly efficient boiler. 5. The establishment of modern M&V systems has created conditions for essential improvement of energy management however, for achieving that, it is necessary to train staff in charge of such matters.