Site ID (Near end): 0078 Site ID (Opposite end): 0390 Site Name: Kamran chowrangi Region: Karachi Project: MW South Submission Date: 26-09-2013

About This cument:


This document is intended to regulate the site installation documents at each step of a microwave project, specify the quantity and format of output documents at each phase and provide guide lines on the integrity and specification of output documents.

Table of Contents
Link Budget.......................................................................................................................... 4 Board Plan ........................................................................................................................... 5 Media Plan .......................................................................................................................... 5 SW Commissioning ............................................................................................................. 6 HW Installation Pictures ................................................................................................... 08 MW Installation Check list ................................................................................................ 11 Confirmation Check List ...15

1- Link Budget
Designed RSL: -39.24(dBm) Achieved RSL: -41.2(dBm)
3

Tx Power: 20.0(dBm) Tx Frequency:15047.0/ 14557.0(MHz)

S-KHI-0078 Elevation (m) Latitude Longitude True azimuth () Vertical angle () Antenna model Antenna height (m) Antenna gain (dBi) Circ. branching loss (dB) Frequency (MHz) Polarization Path length (km) Free space loss (dB) Atmospheric absorption loss (dB) Field margin (dB) Net path loss (dB) Radio model TX power (watts) TX power (dBm) EIRP (dBm) Emission designator TX Channels RX threshold criteria RX threshold level (dBm) RX signal (dBm) Thermal fade margin (dB) XPD fade margin - multipath (dB) Flat fade margin - multipath (dB) Geoclimatic factor Path inclination (mr) Fade occurrence factor (Po) Average annual temperature (C) Worst month - multipath (%) (sec) Annual - multipath (%) (sec) (% - sec) Rain region 0.01% rain rate (mm/hr) XPD fade margin - rain (dB) Flat fade margin - rain (dB) Rain rate (mm/hr) Rain attenuation (dB) Annual rain (%-sec) Annual multipath + rain (%-sec) Tue, Jun 04 2013 S-KHI-0078-S-KHI-0390.pl4 4 Method - ITU-R P.530-12 Reliability Ran - ITU-R P530-7 63.67 24 55 39.10 N 067 07 50.40 E 76.69 -0.16 A15D12HS 25.00 42.60 3.60 15000.00 Vertical 7.12 133.04 0.20 1.00 56.24

S-KHI-0390 46.31 24 56 32.30 N 067 11 57.30 E 256.72 0.12 A15D12HS 25.00 42.60 3.60

56.24

15G_HP_128Q_28M_159M 15G_HP_128Q_28M_159M 0.10 0.10 20.00 20.00 59.00 59.00 28M0D7W 28M0D7W 24B28H 15047.0000H 24B28L 14557.0000H 24B28H 15047.0000V 24B28L 14557.0000V BER 10-6 BER 10-6 -70.00 -70.00 -39.24 33.76 29.07 27.80 1.53E-03 2.44 6.49E-03 26.00 99.99892 28.35 99.99960 127.58 99.99919 - 255.16 ITU Region K 42.00 41.10 33.03 128.25 33.03 99.99964 - 112.06 99.99884 - 367.22 99.99892 28.35 99.99960 127.58 -39.24 33.76 29.07 27.80

41.10

2- Board Plan
Site ID: 0078
PIU10 PIU9 7 CSH FAN11 5IFX2->0390-V 3IFX2->0390-V 18 6IFX2->0390-H 4IFX2->0390-H 2SL1D

3- Media Plan
Route Site ID Rout Site-1 Rout Site-2 Rout Site-3 Warid Tie

E1

4. SW Commissioning pictures
After completion of Hardware installation and Software commissioning following pictures will be required.

1. Software Commissioning (Pictures).


Main Window (Select NE from NE Explorer >> Click Slot Layout from main Window) TX Frequency (Select ODU from NE Explorer >> Click ODU Interface>> Radio Frequency Attribute)

IF Attributes (Select IF1A from NE Explorer >> Click IF Attribute>> Radio Working Mode)

TX Power & RSL (Select ODU from NE Explorer >> Click ODU Interface>> Power Attribute)

N/A

Node Name & Node ID 6

(Select NE from NE Explorer >> Expend NE Configuration >> Click NE Attribute)

Cross Connections (Please capture after expanding cross connections)

Protection (If applicable) (Select NE from NE Explorer >>ExpendNE Configuration >> Click Cross connect Configuration)

N/A

5. MW Installation pictures
Antenna Fixing (Must Cover antenna assembly while capturing) ODU Fixing and waterproof (Must cover both IF Connectors in case of 1+0)

ODU Grounding (Show Grounding termination)

IF Cable grounding (Show IF End)

IF Cable Grounding (Show Bus Bar end)

IF Cable Grounding (If Bus Bar installed)

MW Rack& DDF& DCDB (Cover all Three in one frame)

IF cableloop (Near to ODU)

10

Cable Routing on Vertical Ladder (Identify Recently Installed cable)

IDU Grounding (Cover termination end)

Near to tower brases use the mounting bracket bolts in revarce path

Use Of the labels for DC power breakers

11

DDF (Identify Recently Installed cable with proper labeling)

DCDB (Cover your Cable connection at Breaker in right sequence)

N/A

N/A

12

Grounding cable should be routed & printed labeled

Power cable should be routed & printed labeled

IF connector of ODU should be waterproofed and face downward.

Mention the Faceing ID at both end

13

6- Microwave Installation Check List


Site Supervisor Name: Adnan Cell Number:03003672767

Signature: ____________________________ Date:_________26-09-2013___________________

nformation
Site ID (A) 0078 Site ID (B) 0390 Subcon Symbia

MW Design Detail Checklist


Link Type (PDH/SDH) PDH OK N/A N/A N/A N/A N/A Not OK Remarks

1.Indoor Installations 1- 19 inch Rack Installation


Stability of 19" Rack mounting and alignment as per drawing. Proper Leveling and Drilling works Proper tightening of all nuts and bolts and No nuts and bolts missing Grounding Bus Bar Mounting & DCDB installation.

2.IDU Check List

14

Firmly installed (Best suitable place) Software Check (using WEB LCT) RSL Check & Snapshots (using WEB LCT) Attenuation Values & TX Power Check & Snapshots as per Link Budget Check Far end Visibility (NMS) Proper IF Cable Connector & tightness Circuit Breakers of proper rating installed

OK OK OK OK OK OK OK

3- Grounding
Proper thimbles used at Grounding Bus Bar Surge Arrestors properly installed & grounded (If applicable) OK N/A

List
IDU properly grounded 19'' rack properly grounded DDF properly grounded

OK
OK N/A N/A

Not OK

Remarks

4- Cable Laying/ Labeling


All cables properly cut, laced and terminated Proper Routing of IF Cables, PCM Cables and Power Cables IF Cables and Power Cables laid separately IDUs properly labeled Tie Tags used at IDU end for labeling PDB and Circuit Breakers labeled IF/ PCM/ Power Cables labeled Labeling of E1 terminations done on DDFs OK OK OK OK OK OK OK N/A

Outdoor Installations

15

5- Antenna/Mounting Works
Microwave Dish and Mounting Bracket installed properly Extra IF cable should be twisted to 2 or 3 circles near ODU/Antenna Proper weather proof taping at ODU/ Antenna side Antenna Water drain hole detaches rubber cap and drain hole must be at bottom Antenna height as per the link budget All Nuts and Bolts properly tightened MW Antenna Side Support properly mounted Antenna Pole Fixed Properly Antenna Bracket Fixed in Pole Properly Connectors properly made and securely tightened Rostec properly sealed

OK OK OK OK OK OK OK OK OK OK OK N/A OK OK OK OK OK

NOK

Remarks

6- Grounding
Proper thimbles used ODU properly grounded with scratched paint tower IF Cables grounded with all outdoor bus bars available Not more than one grounding termination on a single point on bus bars

NOK

Remarks

7- Cable Laying/ Labeling


Proper Routing of IF Cables Aluminum tags used for labeling at ODU side for IF Cables All grounding wires/ cables in downward direction from ODU/ IF Cables on tower IF cables properly tied on tower Waveguide/IF cable termination (antenna to ODU/equipment side) Labeling for each PCM cable and for each E1 OK N/A OK OK OK N/A

16

8- Tests Performed
Switch over function success Tx/ Rx Mute function success IF loopback success Near-End loop back success Far-End loop back success EOW function success Alarm Generation and Reporting success Hop visible on NMS 24 hours BERT Test Patching of all E1s checked N/A OK OK OK OK N/A OK OK N/A N/A

9- Items to be attached with Pre-PAT document


24 Hours BERT Test Report Link Performance Report

OK N/A OK OK OK OK OK

NOK

Remarks

Commissioning Documents
Installation Pictures (Indoor/Outdoor) RSL & Configuration Snapshots (tx power, attenuation etc.) Board Inventory Information

10- House Keeping


Site properly cleaned OK

17

Equipment Serial #
IDU Site A Site B ODU HYBRID DISH

REMARKS

ATP done

7. Confirmation Check List


Item Description
Combine PR Received (BTS+MW)

Yes
NO

No

Remarks

Site RFI checked and confirmed to Project Team for equipment delivery, NO DN received before equipment delivery,
Yes

18

Combine Equipment received at site (BTS+MW),

YES

Link Budget, Board plan & Media plan was shared before team movement, YES Missing Equipment reported timely
YES