UNDERGROUND CONSTRUCTION MANUAL

TRENCHING
Back to MAIN INDEX Go to SECTION INDEX

DESCRIPTION Conduit ducting arrangement Conduit ducting arrangement Conduit ducting arrangement FN REGION Joint electricity, gas and Telstra Joint electricity, gas and multiple Telstra Conduit bend at pillar - sections 16mm 4 core cross road cable Conduit bend details at pillar 16mm 4 core cross road cable Conduit bend at pillar - sections 240mm 4 core cross road cable Conduit bend details at pillar 240mm 4 core cross road cable Allow bends for HV conduit road crossing Pillar base installation

DWG 5168/1 5168/2 5168/3

DESCRIPTION MK REGION Joint electricity and Telstra Joint electricity, Telstra and gas Conduit bend at pillar - sections 16mm 4 core cross road cable Conduit bend details at pillar 16mm 4 core cross road cable

DWG

5164/1 5164/2 5164/3 5164/4 5164/5 5164/6 5164/7 5164/8 5164/9 5164/10 5164/11

5162/1 5162/2 5162/3 5162/4 5162/5 5162/6 5162/7 5162/8

Conduit bend at pillar - sections 240mm 4 core cross road cable Conduit bend details at pillar 240mm 4 core cross road cable With Gas - Conduit bends at pillar - sections 16mm 4 core cross road cable With Gas - Conduit bend details at pillar 16mm 4 core cross road cable With Gas - Conduit bends at pillar - sections 240mm 4 core cross road cable With Gas - Conduit bend details at pillar 240mm 4 core cross road cable

NQ REGION URD areas URD areas joint electricity and Telstra City and urban areas Joint electricity - Telstra URD areas general layout Conduit bend at pillar - sections 16mm 4 core cross road cable Conduit bend details at pillar 16mm 4 core cross road cable Conduit bend at pillar - sections 240mm 4 core cross road cable Conduit bend details at pillar 240mm 4 core cross road cable Pillar base installation 5163/1 5163/2 5163/3 5163/4 5163/5 5163/6 5163/7 5163/8 5163/9

Pillar base installation

A B

ORIGINAL ISSUE 15.03.05

APPROVED

J. Brooks 11.08.10

UNDERGROUND DISTRIBUTION
TRENCHING INDEX

HARD COPY UNCONTROLLED


Ergon Energy Corporation Ltd ABN 50 087 646 062

DATE

PASSED

c D. McKeown
T.Borg FILE: 5 54 5012 1

DRAWN

Dwg

Sh

DESCRIPTION CA REGION Conduit, trench and pillar alignment schedule Trench detail electricity and Telstra Trench detail electricity and Telstra Gladstone electricity and Telstra Conduit bends at pillar - sections 16mm 4 core cross road cable Conduit bend details at pillar 16mm 4 core cross road cable

DWG

DESCRIPTION SW REGION

DWG

5165/1 5165/2 5165/3 5165/4 5165/5 5165/6

Electricity and Telstra Conduit bends at pillar - sections 16mm 4 core cross road cable Conduit bend details at pillar 16mm 4 core cross road cable

5167/1 5167/2 5167/3

Conduit bends at pillar - sections 240mm 4 core cross road cable 5167/4 Conduit bend details at pillar 240mm 4 core cross road cable 5167/5 Pillar base installation 5167/6

Conduit bends at pillar - sections 240mm 4 core cross road cable 5165/7 Conduit bend details at pillar 240mm 4 core cross road cable 5165/8 Pillar base installation 5165/9 TELECOMMUNICATION Joint electricity & Telecommunication WB REGION Electricity and Telstra Conduit bends at pillar - sections 16mm 4 core cross road cable Conduit bend details at pillar 16mm 4 core cross road cable 5166/1 5166/2 5166/3 Cable protection footpaths concrete slab detail Cable protection roadways concrete encasement detail Exclusion zone an LV pillars Pillar installation at easement or road reserve boundary Detail at pillar for future extension Underground service from overhead system service conduit bend location at pillar 5016 5017 5196/1 5196/2 5197 5187 ALL REGIONS Joing electricity - Telecommunication URD areas - General layout 5228 5249

Conduit bends at pillar - sections 240mm 4 core cross road cable 5166/4 Conduit bend details at pillar 240mm 4 core cross road cable 5166/5 Pillar base installation 5166/6

A B C D E

ORIGINAL ISSUE 15.3.05 11.8.10

APPROVED

C.Noel 11/8/10 A. Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING INDEX

DATE

PASSED
2.6.11
Ergon Energy Corporation Ltd

17.07.12

ABN 50 087 646 062

DRAWN

FILE: 5 54 5012 2

Dwg

Sh

DESCRIPTION 11kV PADMOUNTED SUBSTATIONS

DWG

DESCRIPTION Rectangular 22kV padmounted substation To suit RM6 switchgear - HV conduit location Rectangular 22kV padmounted substation 500kVA - Schneider Electric LV conduit location Rectangular 22kV padmounted substation 1000kVA - Schneider Electric LV conduit location

DWG 5142/8 5278/1 5278/2

Front entry type conduit location & cross section 5115/1 Front entry type conduit location - ABB RMU 5115/2 Front entry type conduit location - ABB RMU 5115/3 Front entry type conduit location insect prot. cable - ABB RMU5115/4 Front entry type conduit location insect prot. cable - ABB RMU5115/5 Front entry type conduit location - FBX RMU 5115/6 Front entry type conduit location - FBX RMU 5115/7 Front entry type conduit location insect prot. cable - FBX RMU5115/8 Front entry type conduit location insect prot. cable - FBX RMU5115/9 Front entry type LV cable location - ABB RMU 5128 Front entry type HV cable location ABB SDAF3 RMU 5129 Front entry type HV cable location Magnefix RMU + T 5130 Front entry type HV cable location Magnefix RMU & SFU 5131 Front entry type HV cable location no switchgear 5160 Front entry type LV cable location - FBX RMU Front entry type HV cable location - FBX RMU 22kV PADMOUNTED SUBSTATIONS Rectangular 22kV padmounted substation conduit location and cross section Rectangular 22kV padmounted substation conduit location Rectangular 22kV padmounted substation conduit location Rectangular 22kV padmounted substation 500kVA - LV conduit location Rectangular 22kV padmounted substation 1000kVA - LV conduit location Rectangular 22kV padmounted substation 3.7m padmount length - HV conduit location Rectangular 22kV padmounted substation To suit F & G HV switchgear 5142/1 5142/2 5142/3 5142/4 5142/5 5142/6 5142/7 5268 5269

HV SWITCHGEAR ABB free standing RMU conduit location and cross section ABB free standing RMU conduit location ABB free standing RMU conduit location Insect protected 5227/1 5227/2 5227/3

HV / LV Pole termination conduit and trench detail Pole termination conduit and trench detail Pole termination conduit bend detail Pole termination conduit bend detail Distribution cabinet 6 module conduit location and cross section Distribution cabinet 6 module conduit bend details Distribution cabinet 6 module conduit location Distribution cabinet 6 module conduit location Insect protected cable Distribution cabinet 6 module LV cable location 5144/1 5144/2 5173/1 5173/2 5143/1 5143/2 5143/3 5143/4 5141

A B C D E

ORIGINAL ISSUE 15.3.05 2.6.11

APPROVED

C. Noel 2/6/11 A. Bletchly L. Burton

UNDERGROUND DISTRIBUTION
TRENCHING INDEX

DATE

PASSED
10.01.12
Ergon Energy Corporation Ltd

17.07.12

ABN 50 087 646 062

DRAWN

FILE: 5 54 5012 3

Dwg

Sh

NOTES: 1. Conduit and cable nearest R.P. Street Alignment only, shown. 2. Locations and depths shown to conduit ends allow minimum bending radius of cables to be achieved for connection to switchgear. Refer MATERIAL DATA drawings No. 5108 to 5111 for minimum bending radius of cables. 3. Conduit depths shown are minimum and are dimensioned from finished ground line to top of conduit. Ramp down as required. Where conduits are normally laid at a depth greater than shown, that depth should be maintained. 4. Terminate LV and HV cable conduit in line, each end of pit. 5. Provide polymeric cable protection cover (and orange caution tape) over all cable not enclosed in conduit . 6. Backfill cable pit with bedding sand. 7. LV and HV cable locations shown at Padmounted Substation are illustrative only. Refer drawings No. 5128 to 5131 & 5160. Preferred sequence of construction is to install Padmounted Substation prior to cables. R.P. Street Alignment
F

Finished Ground Line


F

(refer sheets 2 to 9)

LV & HV cables
F

Uniculvert Foundation

Depth

Cable Pit

Base Slab
F

45
F

Max. from front edge of uniculvert, or base slab where provided.

Conduit

CROSS SECTION AT CABLE PIT UNICULVERT FOUNDATION ONLY A B


ORIGINAL ISSUE 13.12.11 APPROVED

UNDERGROUND DISTRIBUTION
20/11/01

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

c D. M K.
C.Lindsay

TRENCHING FRONT ENTRY 11kV PADMOUNTED SUBSTATION CONDUIT LOCATION AND CROSS SECTION
FILE: 5 54 5115 1

DRAWN

Dwg

5115

Sh

3000

Site Boundary

Retaining Wall (where reqd)

F
F

Side of trench / cable pit 200 Min.


F
F

HV

LV
F

H.V. Conduit L.V. Conduit not shown this end of Cable Pit

11kV CABLE SIZE TRIPLEX 400mm TRIPLEX 185mm TRIPLEX 35mm DEPTH 1000 1000 Normal DIM A 400 400 0 4C 240mm SIZE

A B

ORIGINAL ISSUE 13.12.11

HARD COPY UNCONTROLLED

Cable Pit FOOTPATH

End of conduit Seal around cable

PLAN VIEW

H.V. CABLE ENTERING / EXITING FROM LEFT OR LEFT & RIGHT HAND SIDE OF PADMOUNT
APPROVED

UNDERGROUND DISTRIBUTION
21/01/03

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

c D. M K.
C.Lindsay

TRENCHING - ABB RMU FRONT ENTRY 11kV PADMOUNTED SUBSTATION CONDUIT LOCATION
FILE: 5 54 5115 2

DRAWN

Dwg

F
F

Outline of concrete plinth Cables as required

300
F

R.P. Street Alignment

L.V. Conduit H.V. Conduit not shown this end of Cable Pit

LV CABLE DEPTH Normal DIM A To suit 11kV cable

5115

Sh

3000

Site Boundary

Retaining Wall (where reqd)

F
F

Side of trench / cable pit


F

HV

LV
F

L.V. Conduit

Cable Pit End of conduit Seal around cable

LV CABLE SIZE 4C 240mm


2

11kV CABLE FOOTPATH SIZE TRIPLEX 400mm TRIPLEX 185mm DEPTH 1000 1000 Normal

DEPTH Normal

PLAN VIEW H.V. CABLE ENTERING / EXITING RIGHT HAND SIDE OF PADMOUNT ONLY A B
ORIGINAL ISSUE 13.12.11 APPROVED

TRIPLEX 35mm

UNDERGROUND DISTRIBUTION
21/01/03

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

c D. M K.
C.Lindsay

TRENCHING - ABB RMU FRONT ENTRY 11kV PADMOUNTED SUBSTATION CONDUIT LOCATION
FILE: 5 54 5115 3

DRAWN

Outline of concrete plinth Cables as required

600
F

300
F

R.P. Street Alignment

H.V. Conduit L.V. Conduit not shown this end of Cable Pit

Dwg

5115

Sh

3000

Site Boundary

Retaining Wall (where reqd)

F
F

Side of trench / cable pit 200 Min.


F
F

HV

LV
F

H.V. Conduit L.V. Conduit not shown this end of Cable Pit

11kV INSECT PROTECTED CABLE SIZE TRIPLEX 400mm TRIPLEX 185mm TRIPLEX 35mm 1250 1250 500 0 DEPTH DIM A

A B

ORIGINAL ISSUE 13.12.11

HARD COPY UNCONTROLLED

Cable pit End of conduit Seal around cable FOOTPATH L.V. Conduit H.V. Conduit not shown this end of Cable Pit LV INSECT PROTECTED CABLE SIZE 4C 240mm DEPTH 1100 DIM A To suit 11kV cable

PLAN VIEW H.V. CABLE ENTERING / EXITING FROM LEFT OR LEFT & RIGHT HAND SIDE OF PADMOUNT
APPROVED

UNDERGROUND DISTRIBUTION
21/01/03

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

c D. M K.
C.Lindsay

TRENCHING - ABB RMU FRONT ENTRY 11kV PADMOUNTED SUBSTATION CONDUIT LOCATION INSECT PROTECTED CABLE
FILE: 5 54 5115 4

DRAWN

Dwg

5115

F
F

Outline of concrete plinth

Cables as required

400
F

R.P. Street Alignment

200 Min.

Sh

3000

Site Boundary

Retaining Wall (where reqd)

F
F

Side of trench / cable pit


F

HV

LV
F

L.V. Conduit FOOTPATH End of conduit Seal around cable 11kV INSECT PROTECTED CABLE SIZE TRIPLEX 400mm TRIPLEX 185mm TRIPLEX 35mm 1250 1250 DEPTH

H.V. Conduit L.V. Conduit not shown this end of Cable Pit

LV INSECT PROTECTED CABLE

PLAN VIEW H.V. CABLE ENTERING / EXITING RIGHT HAND SIDE OF PADMOUNT ONLY
APPROVED

SIZE 4C 240mm

A B

ORIGINAL ISSUE 13.12.11

UNDERGROUND DISTRIBUTION
21/01/03

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

c D. M K.
C.Lindsay

TRENCHING - ABB RMU FRONT ENTRY 11kV PADMOUNTED SUBSTATION CONDUIT LOCATION INSECT PROTECTED CABLE
FILE: 5 54 5115 5

DRAWN

Dwg

5115

Cable pit

Outline of concrete plinth

Cables as required

600

400 F R.P. Street Alignment

200 Min.

DEPTH 1100

Sh

3000

Site Boundary

Retaining Wall (where reqd)

F
F

Side of trench / cable pit 200 Min.


F
F

HV

LV
F

H.V. Conduit L.V. Conduit not shown this end of Cable Pit

11kV CABLE SIZE TRIPLEX 400mm TRIPLEX 185mm TRIPLEX 35mm DEPTH 1000 1000 Normal DIM A 400 400 0 4C 240mm SIZE

ORIGINAL ISSUE

HARD COPY UNCONTROLLED

Cable Pit FOOTPATH

End of conduit Seal around cable

PLAN VIEW

H.V. CABLE ENTERING / EXITING FROM LEFT OR LEFT & RIGHT HAND SIDE OF PADMOUNT
APPROVED

C.Noel 13.12.11 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING - FBX RMU FRONT ENTRY 11kV PADMOUNTED SUBSTATION CONDUIT LOCATION
FILE: 5 54 5115 6

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

F
F

Outline of concrete plinth Cables as required

300
F

R.P. Street Alignment

L.V. Conduit H.V. Conduit not shown this end of Cable Pit

LV CABLE DEPTH Normal DIM A To suit 11kV cable

5115

Sh

3000

Site Boundary

Retaining Wall (where reqd)

F
F

Side of trench / cable pit


F

HV

LV
F

L.V. Conduit

Cable Pit End of conduit Seal around cable

LV CABLE SIZE 4C 240mm


2

11kV CABLE FOOTPATH SIZE TRIPLEX 400mm TRIPLEX 185mm DEPTH 1000 1000 Normal

DEPTH Normal

PLAN VIEW H.V. CABLE ENTERING / EXITING RIGHT HAND SIDE OF PADMOUNT ONLY A
ORIGINAL ISSUE APPROVED

TRIPLEX 35mm

C.Noel 29.12.11 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING - FBX RMU FRONT ENTRY 11kV PADMOUNTED SUBSTATION CONDUIT LOCATION
FILE: 5 54 5115 7

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Outline of concrete plinth Cables as required

600
F

300
F

R.P. Street Alignment

H.V. Conduit L.V. Conduit not shown this end of Cable Pit

Dwg

5115

Sh

3000

Site Boundary

Retaining Wall (where reqd)

F
F

Side of trench / cable pit 200 Min.


F
F

HV
F

LV 200 Min.
F

H.V. Conduit L.V. Conduit not shown this end of Cable Pit

11kV INSECT PROTECTED CABLE SIZE TRIPLEX 400mm TRIPLEX 185mm TRIPLEX 35mm 1250 1250 500 0 DEPTH DIM A

ORIGINAL ISSUE

HARD COPY UNCONTROLLED

Cable pit End of conduit Seal around cable FOOTPATH L.V. Conduit H.V. Conduit not shown this end of Cable Pit LV INSECT PROTECTED CABLE SIZE 4C 240mm DEPTH 1100 DIM A To suit 11kV cable

PLAN VIEW H.V. CABLE ENTERING / EXITING FROM LEFT OR LEFT & RIGHT HAND SIDE OF PADMOUNT
APPROVED

C.Noel 29.12.11 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING - FBX RMU FRONT ENTRY 11kV PADMOUNTED SUBSTATION CONDUIT LOCATION INSECT PROTECTED CABLE
FILE: 5 54 5115 8

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

5115

F
F

Outline of concrete plinth Cables as required

400
F

R.P. Street Alignment


F

Sh

3000

Site Boundary

Retaining Wall (where reqd)

F
F

Side of trench / cable pit


F

HV

LV
F

L.V. Conduit FOOTPATH End of conduit Seal around cable 11kV INSECT PROTECTED CABLE SIZE TRIPLEX 400mm TRIPLEX 185mm TRIPLEX 35mm 1250 1250 DEPTH

H.V. Conduit L.V. Conduit not shown this end of Cable Pit

LV INSECT PROTECTED CABLE

PLAN VIEW H.V. CABLE ENTERING / EXITING RIGHT HAND SIDE OF PADMOUNT ONLY
APPROVED

SIZE 4C 240mm

ORIGINAL ISSUE

C.Noel 29.12.11 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING - FBX RMU FRONT ENTRY 11kV PADMOUNTED SUBSTATION CONDUIT LOCATION INSECT PROTECTED CABLE
FILE: 5 54 5115 9

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

5115

Cable pit

Outline of concrete plinth Cables as required

600

400 F R.P. Street Alignment

200 Min.

DEPTH 1100

Sh

R.P. Street Alignment

R.P. Street Alignment

FOOTPATH

3000

FOOTPATH

LV cable
F

LV cable 1st cable position 2nd cable position 3rd cable position 4th cable position Cables as reqd (Refer design)

100F

100 F

1230

1100

80

BACK of LV cable

Site Boundary 580 (ref)


F

Front of cable support

Position cables as close as possible to dimensions shown.

100kVA A B
ORIGINAL ISSUE 29.12.11 APPROVED

200kVA, 315kVA, 500kVA, 750kVA & 1000kVA UNDERGROUND DISTRIBUTION


29/3/01

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

c D. M K.
C.Lindsay

DRAWN

580 (ref)

560

560

BACK of LV cable Site Boundary

Front of cable support

TRENCHING - ABB SAFELINK RMU FRONT ENTRY 11kV PADMOUNTED SUBSTATION LV CABLE LOCATION
FILE: 5 54 5128 1

Dwg

5128

Cable position

Sh

3000
F

F
F F F

2800

2800

F
F
F F

6000
F

1st conduit position


F

550
F

2nd conduit position 3rd conduit position 4th conduit position 4000 H.V. 5th conduit position 6th conduit position

Cable Pit Cable exit direction as required.

320
F F

Site Boundary

R.P.Street Alignment

500kVA, 3.7m & 4.1m PADMOUNT LENGTH A B C D


ORIGINAL ISSUE 7.11.03 24.9.08 01.11.11 APPROVED

C.Noel 17/01/03 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING RECTANGULAR 22kV PADMOUNTED SUBSTATION 500kVA - LV CONDUIT LOCATION
FILE: 5 54 5142 4

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

5142

FOOTPATH

Sh

100 100 100 100 100

F
F

F F

100 Dia 1830 Radius, 90 vertical bends to 50mm Min. above concrete level.

6000
F

550

1st conduit position 2nd conduit position 3rd conduit position 4000 H.V.

Cable Pit

320
F F

Customer conduits as reqd

Cable exit direction as required.

Site Boundary

R.P.Street Alignment

1000kVA, 3.7m & 4.1m PADMOUNT LENGTH A B C D


ORIGINAL ISSUE 19.11.03 27.10.06 02.11.11 APPROVED

C.Noel 17/01/03 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING RECTANGULAR 22kV PADMOUNTED SUBSTATION 1000kVA - LV CONDUIT LOCATION
FILE: 5 54 5142 5

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

5142

FOOTPATH

Sh

100 100

F
F

F F

100 Dia 1830 Radius, 90 vertical bends to 50mm Min. above concrete level.

6000
F

H.V.
F

350 300 360

L.V.
F

4 0 0 0

Service Platform Foundations if required


F

5 0 0

1000 Radius 60 horizontal b

Cable Pit Cable exit direction as required. 450 max. wide cable trench where service platforms required. F
F
F

1000 Radius 90 vertical to 50mm above concrete level

1 0 0 0 F

1 0 0 0 F

150

NOTE: SECTION A SECTION A 3 conduits are required in all installations.

4.1m PADMOUNT LENGTH


Where no service platforms reqd Where service platforms reqd
APPROVED

A B C D

ORIGINAL ISSUE 19.11.03 10.10.08

C.Noel 17/01/03 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING RECTANGULAR 22kV PADMOUNTED SUBSTATION
F & G HV SWITCHGEAR - HV CONDUIT LOCATION

DATE

PASSED
11.07.12
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

FILE: 5 54 5142 7

Dwg

5142

F
F F

FOOTPATH

F Site Boundary
F
F
F

R.P.Street Alignment

Sh

6000
F

H.V.
F

360 365

700

4 0 0 0

1000 Radius 4 vertical bends to 50mm above concrete level

L.V.

F 4 0 0

Service Platform Foundations if required

1000 Radius 60 horizontal b

Cable Pit Cable exit direction as required. 450 max. wide cable trench where service platforms required. F
F
F

1000 Radius 90 vertical to 50mm above concrete level

1 0 0 0 F

1 0 0 0 F

150

NOTE: SECTION A SECTION A 3 conduits are required in all installations.

4.1m PADMOUNT LENGTH


Where no service platforms reqd Where service platforms reqd
APPROVED

ORIGINAL ISSUE

C.Noel 25.06.12 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING RECTANGULAR 22kV PADMOUNTED SUBSTATION SUIT RM6 SWITCHGEAR - HV CONDUIT LOCATION
FILE: 5 54 5142 8

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

5142

F
F F

FOOTPATH

F Site Boundary
F
F

R.P.Street Alignment

Sh

NOTES: LV CABLE 1. Locate cable on opposite side of pole to oncoming traffic where possible. 2. Excessive excavation at the pole base may disturb pole foundation. Avoid excavating in areas shown. 3. Location of conduit end and depth of excavation shown allow minimum bending radius of cable to be achieved. 4. Provide polymeric cable protection cover and orange caution tape to all conduit/cable outside Electricity Footpath Allocation. 5. Refer drawing No. 5173 for detail of allowable cables and bends at pole termination. 11kV CABLE CABLE DETAIL 35mm TRIPLEX 185mm TRIPLEX 35mm TRIPLEX Insect Protected 1.5m 185mm TRIPLEX Insect Protected 240mm Cu TRIPLEX Insect Protected 400mm Al TRIPLEX 400mm Cu TRIPLEX Insect Protected 2.0m 2.0m 2.0m 1.05m 1.2m 1.2m 1.2m DIMENSION A 1.5m 1.05m Normal trench depth DIMENSION B Normal trench depth CABLE DETAIL 240mm 4C 1.5m 16mm 4C 240mm 4C Insect Protected 50mm 4C Insect Protected 16mm 4C Insect Protected 2.5m 1.5m 1.5m 1.2m 1.05m Normal trench depth Normal trench depth DIMENSION A DIMENSION B

22kV CABLE CABLE DETAIL 185mm TRIPLEX 630mm 3 x 1C 35mm TRIPLEX Insect Protected DIMENSION A 1.5m 2.0m DIMENSION B 1.2m (CA) Normal trench depth (FN) 1.05m (CA) Normal trench depth (FN) Normal trench depth

1.5m

A B C

ORIGINAL ISSUE 24.9.08 23.3.11

APPROVED

C.Noel
14/01/03

UNDERGROUND DISTRIBUTION
TRENCHING POLE TERMINATION CONDUIT AND TRENCH DETAIL
FILE: 5 54 5144 1

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

A.Bletchly
C.Lindsay

DRAWN

Dwg

5144

Sh

Real Property Boundary


F

R.P. Street Alignment

45 1830mm radius bend


F

Kerb

Road crossing to diagonal property not straight across O A D


F

NOTE: Provide E Marker at all kerb crossings

Polymeric Cable Protection Cover

Electricity Footpath Allocation for FN Region and Telstra is from 0.3 to 1.2m from property FN Region to be property side of Telstra.

45 1830mm radius bend


F

F
F

A B

ORIGINAL ISSUE 1.06.09

APPROVED

UNDERGROUND DISTRIBUTION
20/12/01

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

c D. M K.
DJB

TRENCHING - FN REGION ALLOWABLE BENDS FOR HV CONDUIT ROAD CROSSING


FILE: 5 54 5162 7

DRAWN

Dwg

5162

Sh

NOTES: 1. Locate cable on opposite side of pole to oncoming traffic where possible. 2. Excessive excavation at the pole base may disturb pole foundation. Avoid excavating in areas shown. 3. Conduit bends shown allow minimum bending radius of cable to be achieved. 4. Provide polymeric cable protection cover and orange caution tape to all conduit/cable outside Electricity Footpath Allocation. 5. Cables not listed must be direct buried at pole. Refer drawing No. 5144. CABLE DETAIL 240mm 4C 16mm 4C 50mm 4C Insect Protected 16mm 4C Insect Protected 80 Dia. 90 1000 Radius LV CABLE BEND DETAIL 80 Dia. 90 750 Radius

80 Dia. 90 750 Radius

11kV CABLE CABLE DETAIL 35mm TRIPLEX BEND DETAIL 125 Dia. 90 1000 Radius

22kV CABLE CABLE DETAIL 35mm TRIPLEX Insect Protected BEND DETAIL 125 Dia. 90 1000 Radius

A B

ORIGINAL ISSUE 24.9.08

APPROVED

UNDERGROUND DISTRIBUTION
14/01/03

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

D. M K.

TRENCHING POLE TERMINATION CONDUIT BEND DETAIL


FILE: 5 54 5173 1

DRAWN

C.Lindsay

Dwg

5173

Sh

Real Property Boundary


F

Property Allotment

Survey peg

Property Allotment

400

400

Refer applicable regional TRENCHING detail for trench details and conduit positions.
F

F
FRONT

R.P. Street Alignment

c Pillar L

400 min LV Pillar Base 400 min c L

400 min
F

Exclusion Zone FOOTPATH No other service authorities pits or above ground plant to be located in this area.

A B C

ORIGINAL ISSUE 09.08.10 01.11.11

APPROVED

C.Noel 20/9/05 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING - ALL REGIONS EXCLUSION ZONE AT LV PILLARS

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

FILE: 5 54 5196 1

Dwg

5196

Sh

NOTES: Offset base to align with centre line of survey peg clear of Road Reserve or Easement area. 1. Pillars shall be located in areas remote from vehicular access. 2. Should the edge of the pillar base, at ground level, be located less than 1000mm from the kerb or the edge of trafficable areas, then the pillar shall be protected by two bollards. Refer to CONSTRUCTIONS PRACTICES for bollard details. 3. To gain access to a consumers property, remote from pillars, the lead in conduits shall be placed and run in the electricity footpath allocation. Locate to clear possible future fence corner post.
F
F

Easement or Road Reserve

Service Conduit 400

400 min 400 min LV Pillar Base

FOOTPATH

A B

ORIGINAL ISSUE 01.11.11

HARD COPY UNCONTROLLED

Ergon Energy Corporation Ltd ABN 50 087 646 062

F
F

Real Property Boundary

Survey peg

Property Allotment

R.P. Street Alignment

400

Refer applicable regional TRENCHING detail for trench details and conduit positions.
F

c Pillar L

FRONT

400 min Exclusion Zone No other service authorities pits or above ground plant to be located in this area.

APPROVED

C.Noel 23/9/08 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING - ALL REGIONS PILLAR INSTALLATION AT EASEMENT OR ROAD RESERVE BOUNDARY
FILE: 5 54 5196 2

DATE

PASSED

DRAWN

Dwg

5196

Sh

NOTES: 1. Conduit and cable nearest R.P. Street Alignment only, shown. 2. Locations and depths shown to conduit ends allow minimum bending radius of cables to be achieved for connection to switchgear. Refer MATERIAL DATA drawings No. 5108 to 5111 for minimum bending radius of cables. 3. Conduit depths shown are minimum and are dimensioned from finished ground line to top of conduit. Ramp down as required. Where conduits are normally laid at a depth greater than shown, that depth should be maintained. 4. Terminate HV cable conduit in line, each end of pit. 5. Provide polymeric cable protection cover (and orange caution tape) over all cable not enclosed in conduit . 6. Backfill cable pit with bedding sand. 7. HV cable locations shown at RMU site illustrative only. Preferred sequence of construction is to install Padmounted RMU prior to cables. R.P. Street Alignment
F

Finished Ground Line


F

(refer sheets 2 & 3)

LV & HV cables
F

RMU Foundation

Depth

Cable Pit
F

Base Slab
F

Conduit

45
F

Max. from front edge of uniculvert, or base slab where provided.

CROSS SECTION AT CABLE PIT UNICULVERT FOUNDATION ONLY A


ORIGINAL ISSUE APPROVED

C. Noel 28/2/11 A. Bletchly L. Burton

UNDERGROUND DISTRIBUTION
TRENCHING ABB FREE STANDING RMU CONDUIT LOCATION AND CROSS SECTION
FILE: 5 54 5227 1

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

5227

Sh

3000

Cables as required Outline of concrete plinth & foundation


F
F

Side of trench / cable pit

Cable Pit
F
F

H.V. Conduit FOOTPATH 11kV CABLE SIZE TRIPLEX 35mm TRIPLEX 185mm TRIPLEX 400mm 1000 DEPTH End of conduit Seal around cable

PLAN VIEW
HV cable entering / exiting from left or left & right hand side of RMU.
APPROVED

ORIGINAL ISSUE

C. Noel 24/2/11 A. Bletchly L. Burton

UNDERGROUND DISTRIBUTION
TRENCHING ABB FREE STANDING RMU CONDUIT LOCATION
FILE: 5 54 5227 2

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

5227

Site boundry

Side of trench / cable pit

R.P. Street Alignment


F

H.V. Conduit

Sh

3000

Cables as required Outline of concrete plinth & foundation


F
F

A
F F

Side of trench / cable pit


F

200 Min.
F

Cable Pit
F
F

H.V. Conduit 11kV INSECT PROTECTED CABLE SIZE TRIPLEX 35mm TRIPLEX 185mm TRIPLEX 240mm TRIPLEX 400mm DIM A 0 210 310 360 1250 DEPTH FOOTPATH End of conduit Seal around cable

PLAN VIEW
HV cable entering / exiting from left or left & right hand side of RMU.

ORIGINAL ISSUE

APPROVED

C. Noel 24/2/11 A. Bletchly L. Burton

UNDERGROUND DISTRIBUTION
TRENCHING ABB FREE STANDING RMU CONDUIT LOCATION INSECT PROTECTED CABLE
FILE: 5 54 5227 3

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

5227

Retaining Wall (where reqd)

F
F

Site boundry

R.P. Street Alignment Side of trench / cable pit


F

H.V. Conduit

Sh

As per region

Finished surface line


5 0 R o 5 0F o o

Re f e rn o t e2f o rAr t e r i a l Ro a d wa y s

9 0 0mi n Fo o t p a t h 1 0 5 0mi n Ro a d wa y -M i n o r

1 2 0 0mi n Ro a d wa y -Ar t e r i a l

7 5 0mi n Fo o t p a t h 9 0 0mi n Ro a d wa y -M i n o r

3 5 0

5 0 0

1 5 0ma x

7 5mi n

LV
F F

LV
F

25 min

25 min

25 min

A B

ORIGINAL ISSUE 09.07.12

Ergon Energy Corporation Ltd ABN 50 087 646 062

HV

HV

PL

F
F

Alignment

Trench width
F

NOTES: 1. Refer CONSTRUCTION PRACTICES drawing No. 5124 sheet 1 for locations. 2. For ARTERIAL (DMR) roads LV and HV cables may be laid at the same depth to avoid trench depth in excess of 1.5m. Telecommunication marker 3. Ergon cables are to occupy property tape to side conduits first. Telecommunication Authority requirements 4. Telecommunication conduit laid against roadside of trench to Telecommunication Authority requirements Telecommunication conduit (T) as required SEPARATION FROM TELECOMMUNICATION Polymeric cable protection cover where required Refer Note 1 Public Lighting Conduit CONDUITS CROSSING DIMENSION LV HV RADIAL 100 Min 100 Min

F
F

As per region

Caution tape orange, to cover entire width of conduits.

HV and LV conduit as Required Bedding Sand

SEPARATION FROM TELECOMMUNICATION CONDUITS PARALLEL DIMENSION LV HV VERTICAL 100 Min 300 Min

Clearance between Telecommunication Authority and Ergon conduits.

APPROVED

C. Noel 7/3/11 A. Bletchly L. Burton

UNDERGROUND DISTRIBUTION
TRENCHING - ALL REGIONS JOINT ELECTRICITY & TELECOMMUNICATION

DATE

PASSED

DRAWN

FILE: 5 54 5228 1

Dwg

5228

Sh

B
01.11.11

R. P. St r e e t Al i g n me n t F Note 1 T

Cr o s s r o a d Pi l l a r

C. Noel

23/3/11

Te l e c o mmu n i c a t i o np i t
F

Note 1

R. P. St r e e t Al i g n me n t T

LOT 2

Su p p l y Pi l l a r T Te l e c o mmu n i c a t i o n L e a d i nc o n d u i t Sh Pi l l a r Ex c l u s i o n Zo n e

UNDERGROUND DISTRIBUTION

TRENCHING - ALL REGIONS JOINT ELECTRICITY - TELECOMMUNICATION URD AREAS GENERAL LAYOUT

5249
C

Re a l Pr o p e r t y Bo u n d a r y

FILE: 5 54 5249 1

El e c t r i c i t y s e r v i c e s

Te l e c o mmu n i c a t i o n L e a d i nc o n d u i t

A. Bletchly

Ergon Energy Corporation Ltd

DATE

DRAWN PASSED

D T

ABN 50 087 646 062

Cr o s s Ro a d Te l e c o mmu n i c a t i o nc o n d u i t
APPROVED

c o n d u i t W A Y Po l y me r i c Ca b l e Pr o t e c t i o n Co v e r Ke r b Te l e c o mmu n i c a t i o n Co n d u i t 2 x1 0 0Ma x . HV/ L Vc o n d u i t s


F

T
F

Note 1. Refer applicable regional trenching detail for trench details and conduit positions.

LOT 4

El e c t r i c i t y s e r v i c e s

Pi l l a r Ex c l u s i o n Zo n e

Te l e c o mmu n i c a t i o np i t Ke r b

C
ORIGINAL ISSUE 09.07.12

Re a l Pr o p e r t y Bo u n d a r y

Te l e c o mmu n i c a t i o n L e a d i nc o n d u i t
F

Te l e c o mmu n i c a t i o n L e a d i nc o n d u i t

LOT 3

L. Burton

Sh a r e d Tr e n c ho n t h i s Fo o t p a t h Dwg

LOT 1

R.P. Street Alignment

R.P. Street Alignment

FOOTPATH

3000

FOOTPATH

LV cable 1st cable position

LV cable 1st cable position 2nd cable position 3rd cable position 4th cable position Cables as reqd (Refer design)

2nd cable position 3rd cable position 4th cable position Cables as reqd (Refer design)
F

110

110 F

110

110 F

1100

1000

110 F

110

Recess rear wall

Position cables as close as possible to dimensions shown.

315kVA & 500kVA A


ORIGINAL ISSUE APPROVED

C.Noel 29.12.11 A.Bletchly T.Borg

HARD COPY UNCONTROLLED

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

790 (ref)

Site Boundary

640

BACK of LV cable

640

BACK of LV cable Site Boundary

790 (ref)
F

Recess rear wall

750kVA & 1000kVA UNDERGROUND DISTRIBUTION


TRENCHING - FBX RMU FRONT ENTRY 11kV PADMOUNTED SUBSTATION LV CABLE LOCATION
FILE: 5 54 5268 1

Dwg

5268

Sh

3000
F

F
F

F
F F F F

2800

2800

F
F F F

790 (ref)
F F

Recess rear wall

Site Boundary

685

Centre of lug

320

Position cables as close as possible to dimensions shown.

750

FOOTPATH

R.P. Street Alignment

2800
F

FBX RMU A
ORIGINAL ISSUE APPROVED

C.Noel 30.12.11 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING FRONT ENTRY 11kV PADMOUNTED SUBSTATION HV CABLE LOCATION FBX RMU
FILE: 5 54 5269 1

HARD COPY UNCONTROLLED


Ergon Energy Corporation Ltd ABN 50 087 646 062

DATE

PASSED

DRAWN

Dwg

5269

3000
F

HV cable

F
F

F F F

Sh

6000
F

1st conduit position


F

450
F

2nd conduit position 3rd conduit position 4th conduit position 4 0 0 0 H.V. 5th conduit position 6th conduit position

100 100 200 100 100

Cable Pit Cable exit direction as required.

320
F

Site Boundary

R.P.Street Alignment

315kVA & 500kVA, 3.7m & 4.1m PADMOUNT LENGTH A


ORIGINAL ISSUE

APPROVED

C.Noel 20.04.12 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING RECTANGULAR 22kV PADMOUNTED SUBSTATION 500kVA - SCHNEIDER ELECTRIC LV CONDUIT LOCATION
FILE: 5 54 5278 1

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

5278

Sh

FOOTPATH

F
F

F
F

80 Dia 1000 Radius, 90 vertical bends to 50mm Min. above concrete level.

6000
F

450
F

1st conduit position 2nd conduit position 3rd conduit position 4 0 0 0 H.V.

Cable Pit

320
F

Customer conduits as reqd

Cable exit direction as required.

Site Boundary

R.P.Street Alignment

1000kVA, 3.7m & 4.1m PADMOUNT LENGTH A


ORIGINAL ISSUE

APPROVED

C.Noel 20.04.12 A.Bletchly T.Borg

UNDERGROUND DISTRIBUTION
TRENCHING RECTANGULAR 22kV PADMOUNTED SUBSTATION 1000kVA - SCHNEIDER ELECTRIC LV CONDUIT LOCATION
FILE: 5 54 5278 2

DATE

PASSED
Ergon Energy Corporation Ltd ABN 50 087 646 062

DRAWN

Dwg

5278

Sh

FOOTPATH

100 100

F
F

F
F

80 Dia 1000 Radius, 90 vertical bends to 50mm Min. above concrete level.