Project Control: Control of Work and Cost Versus Time +: S-Curve Gantt Chart
Project Control: Control of Work and Cost Versus Time +: S-Curve Gantt Chart
Edited by: Arch./Enp. Sylvester D. Seno, uap, piep, page, icomos, pgbi aa+adp, aaf, MArch-CTM
Purpose
Describe how to use the combined sets of SCurves to:
Control Cost (Budget) versus Schedule. Control Progress (Quantity and Quality of Work) versus Schedule. Use the combined curves to control Cost versus Work versus Schedule.
Learning Objectives
Given a set of S-Curves be able to determine:
Cost Variance over or under cost based solely upon Schedule Schedule Variance behind or ahead of schedule based upon planned and actual work. Budget Variance over or under budget based upon Schedule Variance
Work % Cost % Work % 4% 0% 4% 7% 1% 8% 14% 9% 15% 21% 17% 22% 29% 28% 32% 36% 35% 37% 43% 42% 50% 50% 55% 57% 57% 64% 71% 79% 86% 89% 93% 96% 100%
Actual
%Work
Planned
120%
200% 180% 160% 140% %Work 120% 100% 80% 60% 40% 20% 0%
40% 20% 0% 18
16
%Work
%Cost
120%
(4)
(3)
This is the budgeted cost of the actual work is equal to the cost incurred to date.
(2)
Planned
40% 20% 0%
16
18
%Work
This implies that the project is on budget and 1-day ahead of schedule.
3. Common
Under Budget Behind Schedule
2. Common
Over Budget Ahead of Schedule
4. Least Likely
Under Budget Ahead of Schedule
Work % 3% 6% 12% 18% 24% 32% 41% 49% 47% 63% 62% 67%
Answer to Case 1:
Cost Variance based upon schedule is 10% over budget. Schedule Variance based upon progress to date is (12 10.4 = 1.6 days) 10% behind schedule. Budget Variance based upon progress to date is (92% - 66%) 26% over budget, Since 70% of the schedule has elapsed at this point, you are in BIG trouble.
Work % 4% 8% 17% 25% 34% 39% 49% 60% 66% 75% 81% 91%
Answer to Case 2:
Cost Variance based upon schedule is 5% over budget. Schedule Variance based upon progress to date is (14 12) 2 days ahead of schedule at day 12. Budget Variance based upon progress to date is (98% - 88%) 10% under budget, Since 70% of the schedule has elapsed at this point, maintain momentum to finish early and close to budget.
Case 3: Under Budget, Behind Cost % Work % Cost % Work % Schedule Day 1 0% 4% 0% 4%
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 1% 9% 16% 24% 32% 40% 47% 55% 63% 71% 82% 92% 96% 100% 100% 100% 7% 14% 21% 29% 36% 43% 50% 57% 64% 71% 79% 86% 89% 93% 96% 100% 1% 8% 16% 22% 29% 39% 43% 55% 57% 68% 79% 7% 13% 20% 26% 36% 39% 47% 53% 59% 71% 72%
Answer to Case 3:
Budget Variance based upon schedule is 2% under budget. Schedule Variance based upon progress to date is (11 12) 1 days behind of schedule at day 12. Budget Variance based upon progress to date is (78% - 72%) 6% over budget, Since 70% of the schedule has elapsed at this point, increase momentum to finish on time and over budget OR
Case 4: Under Budget, Ahead Cost % Work % Cost % Work % of Schedule Day 1 0% 4% 0% 4%
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 1% 9% 16% 24% 32% 40% 47% 55% 63% 71% 82% 92% 96% 100% 100% 100% 7% 14% 21% 29% 36% 43% 50% 57% 64% 71% 79% 86% 89% 93% 96% 100% 1% 7% 13% 21% 30% 40% 41% 44% 54% 62% 67% 7% 17% 23% 34% 37% 44% 51% 68% 74% 76% 90%
200% 180% 160% 140% 120% 100% 80% 60% 40% 20% 0%
%Work
Case 4: Answer
Budget Variance based upon schedule is 15% under budget. Schedule Variance based upon progress to date is (12 14) 2 days ahead of schedule at day 12. Budget Variance based upon progress to date is (68% - 98%) 30% under budget, Since 70% of the schedule has elapsed at this point, maintain momentum to finish early and 30% under budget.