Professional Documents
Culture Documents
Oct10 - Past Year
Oct10 - Past Year
EC/OCT 2010/ECM527
COURSE
COURSE CODE
ECM527
EXAMINATION
OCTOBER 2010
TIME
3 HOURS
INSTRUCTIONS TO CANDIDATES
1.
2.
Answer ALL questions in the Answer Booklet. Start each answer on a new page.
3.
Do not bring any material into the examination room unless permission is given by the
invigilator.
4.
Please check to make sure that this examination pack consists of:
i) The question paper
ii) An answer booklet - provided by the faculty
CONFIDENTIAL
CONFIDENTIAL
EC/OCT2010/ECM527
QUESTION 1
a)
In performing project closure, several activities are essentially required. Point out and
explain in detail the project closure activities.
(10 marks)
QUESTION 2
a)
Prepare a Precedence Diagram for a renovation project, using the information given in
Table 2(a).
Activity
Predecessor
Duration
A
B
C
D
E
F
G
A
A
B
B
C
D, E, F
4
5
3
6
4
3
7
Constraints
Predecessor Relationship
-
SS4
FS3
Table 2(a)
(3 marks)
b)
Referring to the diagram drawn earlier, carry out calculations in order to obtain the
earliest and latest start and finish date for each activity. The project will begin on 1st
July 2010. The working days for this project will be from Mondays to Saturdays,
inclusive of public holidays. Therefore, only Sundays will be the non working days.
Calendar is provided in Table 2(b).
(14 marks)
CONFIDENTIAL
CONFIDENTIAL
EC/OCT 2010/ECM527
MONDAY
TUESDAY
WEDNESDAY
5
12
19
26
6
13
20
27
7
14
21
28
THURSDAY
1
8
15
22
29
FRIDAY
2
9
16
23
30
SATURDAY
3
10
17
24
31
SUNDAY
4
11
18
25
Table 2(b)
c) Differentiate the elements contained in pre tender planning and pre contract planning.
(8 marks)
QUESTION 3
a) Outline and describe the documents required in a project charter.
(12 marks)
b)
A construction firm is given a contract to complete a project in four months, which values
at RM 18, 000. A Gantt chart for the project was prepared and is shown in
Figure Q3(b), together with the budgeted cost for each activity.
JANUARY
FEBRUARY
Activity A (RM 3,
000)
Activity B ( RM 6, 000)
MARCH
APRIL
Activity C (RM 3,
000)
Activity D (RM 6, 000)
Figure Q3(b)
As of end of March, progresses of the activities on site are as follows:
Activity A - 100% completed
Activity B - 75% completed
Activity C - 50% completed
Activity D - 10% completed
Total cost spent = RM 16, 500
With the information given above, assess the status of the project at the end of March, by
providing answers for the following items:
i) The Earned Value (EV), Planned Value (PV) and Actual Cost (AC) for the project.
ii) Cost and schedule indices.
iii) Percentage of over/under budget and ahead/behind schedule
iv) Estimated at completion (EAC)
(13 marks)
CONFIDENTIAL
CONFIDENTIAL
EC/OCT 2010/ECM527
QUESTION 4
a)
b) Ahmad is considering three options to further develop his company next year.
Table 4(b) shows the option as opposed to its nature of demand, given the annual
payoff respectively.
Nature olF demand
Options
Unfavourable
Favourable
Expand
RM 3, 000
RM 15,000
Move to larger facility
RM - 1 , 000
RM 25, 000
Do nothing
RM 7, 000
RM 10, 000
Table 4(b)
Based on the given information, propose the decisions to be made by Ahmad using
these criterions:
')
ii)
Hi)
iv)
Maximax Criterion
Maximin Criterion
Laplace Criterion
Minimax Regret
(10 marks)
c)
CONFIDENTIAL
EC/OCT 2010/ECM527
Single Payment
Compound
N
I
i
Present
Amount.
Worth
.Factor
Factor
fF/p^VJ
i.(*in
(P/FW)
' . A m o u n t
'-
Sinking .
Fund
Factor
Factor -
(RCUNJ
' Present
Capital
Gradient
Gradient
' Worth
Recovery
Uniform
Present
Factor
Serf**
Worth
(AJGXN)
(PW*N)
Factor
8.0%
G r a d l e n it Scries
WFN}
tPtAW>
WW*>:
0.9259
1.0000
1.0000
0.9259
1.0800
o.ouun
0.0000
1.1664
1.1597
0.8573
20800
0.4808
1.7333
0.5608
0.4KOR
0.8573
0.7938
3.2464
0.3080
2.5771
0.3880
0.9487
l.3tf
4.5061
0.2219
3.3121
0.3019
1.4040
2.4450
4.6501
5.8666
0.1705
3.9927
0.2505
I.K465
7.3724
5
6
1
i
4
5
I.4S93
0.7350
0.6306
1.5869
0.6302
7.3359
0.1363
4.6229
0.2163
2.2763
10.5133
1.7138
0.5S35
B.9228
0.1121
5.2064
0.1921
2.6937
14.0242
R
9
1.8509
0.5403
10.6366
0.0940
5.7466
0.1740
3.U985
17.8061
1 9990
0.5002
12.4376
0.0801
6 2169
0.1601
3.49 iO
21.8081
8
1
ifl
2 1589
0.4632
14.4366
0.0690
6.7101
0.1490
3 8733
25.9768
10
2.3316
0.4289
7.1 yv.l
0.1401
4 2395
30.2657
II
2 ".182
0.3971
16.6455
18.9771
0.0601
i;
0.0527
7.5361
0.1327
4.5957
34.6339
12
13
i4
2 719s
0.3677
2I.4')53
0.0465
7.903 H
0.1265
39.0463
13
2.9372
0.3405
24.2149
0.0413
0.S213
43.4713
14
.5
3.1122
U.3J52
27.1521
0.0368
S2442
8 5595
4 9402
5 ^T-I;
0.1168
5.5945
47.8857
15
i6
3.41<9
0.29J9
30.3243
0.0330
8.8514
0 . ! 130
5 9046
52.2640
17
3.7000
0.2703
33.7502
0.0296
56.58*3
16
17
3.99S0
0.2502
37.4502
0.0267
0.1096
0.1067
6.2037
!K
9.1216
9.3719
6.4920
60.8426
13
19
4.3157
0.2317
41.4463
0.0241
9.6036
0.1041
6.7697
65.0134
19
3)
4.6610
0.2145
45.7620
0.0219
9.8 IS 1
0.1019
7.02*9
69.0898
20
21
5.033 S
0.19R7
50.4229
0.0998
7.2940
73.0629
21
5.4365
0.1839
55 4568
0.019s
0.01 HO
10 0168
I0.2IS07
0.0980
7.54 i 2
76.9257
i i
23
5.8715
0.1703
M i SIS'*
0.0164
10 3711
0.0964
7.7786
80.6726
23
-t
1
2+
Ci.3412
0.1577
66.7643
0.0150
10 5289
0.0950
24
6.8485
0.E460
73.1059
0.0137
10.6748
0.0937
8.0066
3.2254
S4.2997
25
87.8041
25
2ft
7 3964
0.1352
79.544
0.0125
10 3 1 0 0
0.0925
3.4 352
9!.1842
27
7 9HBI
0.1252
S7 3503
0.0114
10.9352
0.0914
X 6363
94.4390
26
27
78
K.<27|
0.1159
95.3338
0.0105
11.0511
0.090.5
8.K289
97.5>B7
28
29
9.3 r s
0.1073
[03.9659
0.0096
11.1534
0.0896
9 . 0 ! 33
100.5738
29
30
1(1 0627
0.0994
113.2832
n.ex%8
11.2578
0.0888
9.1K97
103.4558
30
31
fO ("")77
0.0920
111.3459
0.0081
11.3498
0.0881
9.35S4
106.2163
31
32
! l 7371
0.0K52
134.2135
0.0075
11.4350
0.0875
9.5197
I0S.8575
32
33
34
35
12.6760
0.0789
145.9506
axxm
11.5139
0.0869
9.67.17
111.3819
33
13.6901
0.073O
158 6267
0.0063
11 .5869
0X1863
9.R20K
113.7924
34
14.7853
0.0676
171 3Krt
0.0058
1 1.6546
0.0858
9.90 i l
116.0920
35
40
21.7245
0.0460
259.0565
O.CB39
11.9246
0.0839
111.5699
S26.0412
40
4?
31.92(4
0.0313
3Stv505&
0.0026
1 2 1034
0.0826
110447
133.7331
45
50
0.0213
573 7702
0.0017
12 2335
0.08 J 7
1 1.4107
539.5928
50
55
46.9016
68.9139
0.0145
K4N.y232
0.0012
12 3186
0.0812
1 1.6902
144.0065
.55
60
SO t. 257]
0.0099
1253 2133
coons
12.3761
0.0808
11.9015
147 .3000
6ft
dS
70
I4N779*
O.OD67
IS47.2481
0.0005
12.4160
0.0805
12.0602
149.7387
65
2is60&4
0.0046
2710.0301
0.00O4
12 4 4 2 *
0.0S04
12.1783
i 51.5316
70
75
321 2045
0.0031
401)2.5566
0.0002
12.4611
0.(1302
12.2658
152.8448
75
KO
47I.954H
0.002!
5886.9354
0.0002
12 4735
0.0802
12.3101
153.8001
SO
h5
693 4565
0.0014
8<i55.7l>61
U.0001
1 2.4320
0.0801
12.3772
! 54.4925
85
90
90
Ki;K9l5l
0.0010
12721.9336
0.0001
11.4377
0.0801
12.411"
154.9925
95
1497 1205
0.0007
O.OuOl
12.4917
0.0801
12.4165
155.3524
95
100
2199 7 6 1 '
0.0005
I S 7 0 I SCKi'i
27484 5157
O.OOiX)
1 2.4943
0.0800
12.4545
155.6107
HH>
Table 4(c)
CONFIDENTIAL