Labor Cost: Concrete
Labor Cost: Concrete
Labor Cost: Concrete
Concrete
Pier
3 x 37.5 x 48 = P 5, 400.00
4 x 22.5 x 48 = P 4, 320.00
Footing
3 x 37.5 x 38.56 = P 4,338.00
8 x 22.5 x 38.56 = P 6, 940.8.00
Piles
5 x 37.5 x 81.6 = P 15, 300.00
10 x 22.5 x 81.6 = P 18,360.00
Slab
5 x 37.5 x 27.2 = P 5,100.00
15 x 22.5 x 27.2 = P 9, 180.00
Interior Girder
5 x 37.5 x 25.6 = P 4,800.00
15 x 22.5 x 25.6 = P 8, 640.00
Exterior Girder
5 x 37.5 x 16.4 = P 3, 075.00
15 x 22.5 x 16.4 = P 5, 535.00
Trans. Beam
3 x 37.5 x 45.52 = P 5, 121.00
10 x 22.5 x 45.52 = P 10, 242.00
Railings
2 x 37.5 x 14.64 = P 1, 098.00
4 x 22.5 x 14.64 = P 1, 317.60
Shoulder
Wing Wall
1 x 37.5 x 4 = P 150.00
1 x 22.5 x 4 = P 90.00
Reinforcement
Pier
6 x 37.5 x 126 = P 28,350.00
4 x 37.5 x 126 = P 18, 900.00
6 x 22.5 x 126 = P17, 010.00
Footing
4 x 37.5 x 356 = P 53,400.00
2 x 37.5 x 356 = P 26, 700.00
4 x 22.5 x 356 = P32, 040.00
Piles
6 x 37.5 x 476 = P 107,100.00
4 x 37.5 x 476 = P 71, 400.00
6 x 22.5 x 476 = P 64, 260.00
Slab
4 x 37.5 x 668.8 = P 100,320.00
2 x 37.5 x 668.8 = P 50, 160.00
4 x 22.5 x 668.8 = P 60, 192.00
Interior Girder
4 x 37.5 x 356 = P 53,400.00
Exterior Girder
4 x 37.5 x 408 = P 61,200.00
2 x 37.5 x 408 = P 30, 600.00
6 x 22.5 x 408 = P 55, 080.00
Trans. Beam
2 x 37.5 x 29 = P 2,175.00
2 x 37.5 x 29 = P 2,175.00
4 x 22.5 x 29 = P2, 610.00
Railings
2 x 37.5 x 34.32 = P 2,574.00
1 x 37.5 x 34.32 = P 1,287.00
4 x 22.5 x 34.32 = P3, 089.00
Trans. Beam
2 x 37.5 x 121.12 = P 9,084.00
1 x 37.5 x 121.12 = P 4,542.00
4 x 22.5 x 121.12 = P10, 901.00
Railings
1 x 37.5 x 76.56 = P 2,871.00
1 x 37.5 x 76.56 = P 2,871.00
4 x 22.5 x 76.56 = P6, 890.00
Formworks
Pier
4 x 37.5 x 23.36 = P 3,504.00
8 x 22.5 x 23.36 = P4, 204.80
Footing
2 x 37.5 x 32 = P 2,400.00
4 x 22.5 x 32 = P 2, 880.00
Piles
4 x 37.5 x 290 = P 43, 500.00
Slab
4 x 37.5 x 120.8 = P 18,120.00
6 x 22.5 x 120.8 = P 16, 308.00
Interior Girder
4 x 37.5 x 103.2 = P 15,480.00
6 x 22.5 x 103.2 = P 13, 932.00
Exterior Girder
4 x 37.5 x 67.2 = P 10, 080.00
6 x 22.5 x 67.2 = P 9, 072.00
Trans. Beam
2 x 37.5 x 94.64 = P 7, 098.00
4 x 22.5 x 94.64 = P 8, 517.60
Railings
2 x 37.5 x 66.64 = P 4, 998.00
4 x 22.5 x 66.64 = P 5, 997.60
Shoulder
2 x 37.5 x 80 = P 6, 000.00
4 x 22.5 x 80 = P 7, 200.00
Wing Wall
2 x 37.5 x 4 = P 300.00
2 x 22.5 x 4 = P 360.00
B. Footing
28mm 288 x 43.5 = 12, 528
C. Pile
12mm 1,508 x 7.99 = 12, 049
F. Exterior Girder
12mm 606 x 7.99 = 4, 842
G. Transverse Beam
20mm 117 x 22.19 = 2, 596
H. Railings
J. Wing Wall
16mm 288 x 14.21 = 4,093
I. Shoulder
10mm 202 x 5.54 = 1, 119
Formworks
A. Form for Pier
a. Total Length
( )
= 2.51 x 6
= 15.06 x 8
= 120.48 x 0.347
= 41.8 or 42 pcs metal form
.: 42 pcs metal form 1.20 x 2.40 m
metal shed
120.48 x 25 =
= 502 pcs vert. supp.
Steel bars
E. Form for Interior Girder
120.48 x 9.52 =
= 192 pcs circum
ties
= 120 x 22
=2640 bd. ft 2x3 lumber
F. Form for Exterior Girder
P= 0.757 (2) + .46 + 0.1
= 2.074 x 54 x 2
=
= 78 pcs plywood
= 78 x 22
=1716 bd. ft 2x3 lumber
I. Form of Shoulder
A = 54 x 1.78
= 192.24 m2
=
= 66.75 or 67 pcs plywood
= 79 pcs plywood
=67 x 22
=1474 bd. ft 2x3 lumber
= 79 x 22
=1738 bd. ft 2x3 lumber
A=3x3
=9x4
= 36 m2
=
= 12.5 or 13 pcs plywood
=
= 17.78 or18 pcs plywood
= 18 x 22
=396 bd. ft 2x3 lumber
Horizontal Railings
A = 54 x 1 x 2
= 108 m2
=
= 37.5 or38 pcs plywood
=38 x 22
=836 bd. ft 2x3 lumber
=13 x 22
=286 bd. ft 2x3 lumber