CLK-2014!03!31 - Presentation To Council - Sewage
CLK-2014!03!31 - Presentation To Council - Sewage
PresentationOutline
WeWereGENIVARWeAreNowWSP ProjectUpdate ConstructionSchedule ProjectBudgetReview QuestionsandAnswers
WeWereGENIVARWeAreNowWSP
AsofJanuary1,2014,GENIVAR,haschangedournametoWSP CanadaInc. WSPwasacquiredbyGENIVARin2013andadds approximately10, 000staffoperatingin35countriestoourstaffof approximately5, 000people.
3, 400
2, 500
UK
Northern Europe
4, 750
Canada
1, 050
USA
750
Asia
South America
600
1, 450
Africa,India
MiddleEast
Australia
500
ProjectUpdate
ConstructionwasinitiatedinAugust2012. InOctober2012, itwasdeterminedthatbedrockwas notlocatedatthedepthwhichitwaspresumedinthe GeotechnicalReportpreparedduringthedesign. WSP( formerlyGENIVAR) workingwithCity AdministrationandNACstaff, exploredseveral alternativesforchangesthatwererequiredto addressthegeotechnicalissuesthatwerepresented atthesite. InDecember2012, itwasdeterminedthatdynamic compaction,amethodforcompactingthenativesoils tosupportthestructure, wasthepreferredmethodto addressthegeotechnicalissues. ByMay2013,thedynamiccompactionofthesiteand theinstallationofthefoundationpilingsystemwas completedonsite. Progresscontinuesonthesitewithatargettoachieve substantialcompletionbySeptember2015.
ProjectUpdate
Mattagami River
AirportRoad
ProjectUpdate
July10,2013
ProjectUpdate
October23,2013
ProjectUpdate
January16,2014
ProjectUpdate
March27,2014
10
ProjectUpdate
CONVERSIONOFGRIT REMOVALSYSTEM
11
ProjectUpdate
NEWGRIT CLASSIFIER INOLD SCREEN ROOM
January16,2014
12
ProjectUpdate
PIPINGGALLERYOUTSIDE OFNEWRAWSEWAGE PUMPINGSTATION
13
ConstructionSchedule
BasedonMarch2014 sProgressPayment,theconstructionproject is51%complete ( basedontheworkbilledtodate). MajorWorksCompleted Allfoundationworkcomplete,95%ofConcreteworkforAerationTanks andClarifiers,Headworks40%complete,TrunkSewerinstalledatRaw SewagePumpingStation MajorWorksRemaining ProcessMechanicalandElectricalthroughout,Digesterand IntermediatePumpingStationBuildings,YardPiping,andBuilding MechanicalSystemsareremainingtocomplete TheContractorhasindicatedthattheirintentionistocompletethe projectontheoriginalconstructioncompletiondate ( September16, 2015). AnticipatedProjectCompletion September2015
Consultation
No. DateDescription
14
1April27,2009
2Feb.8,2010 3July26,2010
4Sept.13,2010
5March30,2011
ApprovalbyCouncilofconsultingfirmaward
PublicInformationCentreNo.1
PublicInformationCentreNo.2
PresentationtoCouncilofproposedsewerrates
ApprovalbyCouncilofBCFFundingAgreement
8July30,2012 9
ApprovalbyCouncilofconstructiontenderaward
FoundationReDesign/SitePlanReOctober2012 GeotechnicalBedrockIssues/ Design March2013 PublicInformationCentreNo.3 SoilImprovement/ Dynamic 10March26,2013 CompactionforTankFoundations PresentedupdateandsolutionstoCouncilforGeotechnical BedrockIssues/ Foundationredesign/ SiteplanRedesignand 11Sept.25,2013 subsequentlitigationasrelated.
12March31,2014
ProjectUpdateandProjectBudgetApproval
15
BudgetProgression
DateDescriptionTotalProjectCostContingency July30,2012TenderEvaluation$
1 ( 73. 9M5. 4% incl.)
CurrentSpentToDate$
March31,2014
ProjectedTotalProjectCost$
41. 5M
80. 6M10% i ( ncl.)
16
ProjectBudget
ItemComponentofWorkValue
1NACContract TenderedPrice
ExcludingContingency)
61, 899, 504 6, 404, 793 5, 326, 297 400, 000 3, 597, 905
125, 000 2, 807, 467 80, 560, 966
17
SewerRateOutlookand10yearCapitalForecast
DateDescription
DebtFree TotalAnnual SewerRate 12 ProjectionRateIncreaseincrease
50$
30
50$
50$
45
45
50$ 30$
45 15
18
February2012MinisterBradley submission)
OGRAEqualshareon $ 73. 9M
February2013MinisterMurray August2013MinisterMurray
submission) submission)
meeting) meeting)
October2013MinisterMurray February2014MinisterMurray
19
QUESTIONSANDANSWERPERIOD