CONSTRUCTION OF 160 VILLAS - DSOA

WEEKLY PROGRESS UPDATE 160V AS ON 24-Mar-14


CLUSTER P - 14 VILLAS
BASED ON EARLY START/EARLY FINISH (REV. 01, DATED 29.08.2013)

TOTAL

WTG.

NO OF VILLAS

ACHIEVED %

STATUS

REMARKS

SCOPE

PLANN

ACTUAL

PLANN

ACTUAL

PLANN

ACTUAL

LAST
WEEK

THIS
WEEK

1.00 Excavation

1.76%

14

1.76%

1.76%

14

14

100%

100%

2.00 Foundation

6.31%

6.31%

6.31%

2.01 Blinding

1.65%

14

1.65%

1.65%

14

14

100%

100%

2.02 Footing

4.66%

14

4.66%

4.66%

14

14

100%

100%

3.00 Slab on Grade

6.60%

6.60%

6.60%

3.01 Stub Wall

2.10%

14

2.10%

2.10%

14

14

100%

100%

3.02 Backfilling

1.80%

14

1.80%

1.80%

14

14

100%

100%

3.03 Ground Slab

2.70%

14

2.70%

2.70%

14

14

100%

100%

4.00 G. Floor Tunnel (F.F. Slab)

8.00%

14

8.00%

8.00%

14

14

100%

100%

5.00 F. Floor Tunnel (Roof Slab)

8.00%

14

8.00%

8.00%

14

14

100%

100%

6.00 Parapets & Staircase

4.12%

4.12%

4.12%

6.01 Parapet & Upstands

2.06%

14

2.06%

2.06%

14

14

100%

100%

6.02 Staircase

2.06%

14

2.06%

2.06%

14

14

100%

100%

7.00 Blockwork

3.50%

14

3.50%

3.50%

14

14

100%

100%

8.00 Int. Plaster

2.96%

14

2.96%

2.96%

14

14

100%

100%

9.00 Wall & Floor Tiles

4.54%

4.54%

4.54%

9.01 Kitchen Wall Tiles

0.60%

14

0.60%

0.60%

14

14

100%

100%

9.02 Bathroom Wall Tiles

0.80%

14

0.80%

0.80%

14

14

100%

100%

9.03 Wet Area Waterproofing

0.19%

14

0.19%

0.19%

14

14

100%

100%

9.04 Bathroom Floor Tiles

1.20%

14

1.20%

1.20%

14

14

100%

100%

9.05 Int. Flooring

0.70%

14

0.70%

0.70%

14

14

100%

100%

9.06 Marble/Granite Steps

0.45%

14

0.45%

0.45%

14

14

100%

100%

9.07 External Floor Tiles

0.60%

14

0.60%

0.60%

14

14

100%

100%

7.76%

7.76%

Sl. No.s

Activities

10.00 Joinery Works

7.76%

10.01 Int. Door Frame

0.75%

14

0.75%

0.75%

14

14

100%

100%

10.02 Int. Door shutter & Ironmongery

1.10%

14

1.10%

1.10%

14

14

100%

100%

10.03 External Door Frame

0.35%

14

0.35%

0.35%

14

14

100%

100%

0.60%

14

0.60%

0.60%

14

14

100%

100%

10.05 Wardrobe Carcass

0.70%

14

0.70%

0.70%

14

14

100%

100%

10.06 Wardrobe Shutters

0.85%

14

0.85%

0.85%

14

14

100%

100%

10.07 Kitchen Cabinet Carcass

0.60%

14

0.60%

0.60%

14

14

100%

100%

10.08 Kitchen Work Top

0.30%

14

0.30%

0.30%

14

14

100%

100%

10.09 Kitchen Cabinet Shutters

0.85%

14

0.85%

0.85%

14

14

100%

100%

10.04

External Door shutter &


Ironmongery

Page 1 of 4

U-SI-P-(14)

CONSTRUCTION OF 160 VILLAS - DSOA


WEEKLY PROGRESS UPDATE 160V AS ON 24-Mar-14
CLUSTER P - 14 VILLAS
BASED ON EARLY START/EARLY FINISH (REV. 01, DATED 29.08.2013)

TOTAL

WTG.

NO OF VILLAS

ACHIEVED %

STATUS

REMARKS

SCOPE

PLANN

ACTUAL

PLANN

ACTUAL

PLANN

ACTUAL

LAST
WEEK

THIS
WEEK

0.60%

14

0.60%

0.60%

14

14

100%

100%

10.11 Vanity Metal Frame

0.16%

14

0.16%

0.16%

14

14

100%

100%

10.12 Vanity Work Top

0.20%

14

0.20%

0.20%

14

14

100%

100%

10.13 Vanity Shutters

0.70%

14

0.70%

0.70%

14

14

100%

100%

11.00 Miscellaneous

0.95%

0.95%

0.95%

11.01 Kitchen Exhaust Hood

0.15%

14

0.15%

0.15%

14

14

100%

100%

11.02 Mirrors

0.18%

14

0.18%

0.18%

14

14

100%

100%

11.03 Fixing Cat Ladder

0.21%

14

0.21%

0.21%

14

14

100%

100%

11.04 Shower Enclosure

0.19%

14

0.19%

0.19%

14

14

100%

100%

11.05 Sky Light

0.11%

14

0.11%

0.11%

14

14

100%

100%

11.06 Sun Pipe

0.11%

14

0.11%

0.11%

14

14

100%

100%

12.00 UPVC Doors & Windows.

4.10%

4.10%

4.10%

12.01 Aluminium Doors

1.60%

14

1.60%

1.60%

14

14

100%

100%

12.02 Aluminium Window Frames

1.80%

14

1.80%

1.80%

14

14

100%

100%

12.03 Glass for windows

0.70%

14

0.70%

0.70%

14

14

100%

100%

13.00 False Ceiling Works

1.95%

1.95%

1.95%

13.01 False Ceiling Suspension

0.70%

14

0.70%

0.70%

14

14

100%

100%

13.02 Gypsum Board

0.80%

14

0.80%

0.80%

14

14

100%

100%

13.03 False Ceiling Tiles

0.45%

14

0.45%

0.45%

14

14

100%

100%

14.00 Handrails

1.50%

1.50%

1.50%

14.01 Balcony Handrails

0.65%

14

0.65%

0.65%

14

14

100%

100%

14.02 Staircase Handrails

0.85%

14

0.85%

0.85%

14

14

100%

100%

15.00 Internal Painting Works

1.01%

1.01%

1.01%

Int. Paint Under Coat & First Coat /


15.01
Spray Plaster

0.46%

14

0.46%

0.46%

14

14

100%

100%

15.02 Int. Paint Final Coat

0.55%

14

0.55%

0.55%

14

14

100%

100%

16.00 External Plaster

3.10%

14

3.10%

3.10%

14

14

100%

100%

17.00 External Paint

2.66%

2.66%

2.66%

17.01 External Cladding Works

1.20%

14

1.20%

1.20%

14

14

100%

100%

17.02 External Painting Undercoat

0.90%

14

0.90%

0.90%

14

14

100%

100%

17.03 External Painting Final Coat

0.56%

14

0.56%

0.56%

14

14

100%

100%

18.00 Roofing & Water Proofing

2.47%

2.47%

2.47%

18.01 Light Weight Concrete

0.70%

14

0.70%

0.70%

14

14

100%

100%

18.02 Waterproofing Memberane

0.80%

14

0.80%

0.80%

14

14

100%

100%

Sl. No.s

Activities

10.1 Vanity Carcass

Page 2 of 4

U-SI-P-(14)

CONSTRUCTION OF 160 VILLAS - DSOA


WEEKLY PROGRESS UPDATE 160V AS ON 24-Mar-14
CLUSTER P - 14 VILLAS
BASED ON EARLY START/EARLY FINISH (REV. 01, DATED 29.08.2013)

TOTAL

WTG.

NO OF VILLAS

ACHIEVED %

STATUS

REMARKS

SCOPE

PLANN

ACTUAL

PLANN

ACTUAL

PLANN

ACTUAL

LAST
WEEK

THIS
WEEK

18.03 Protection Board

0.60%

14

0.60%

0.60%

14

14

100%

100%

Aggregate Filling & Roof Paving


18.04
Tiles

0.37%

14

0.37%

0.37%

14

14

100%

100%

19.00 External Works

2.56%

2.56%

2.56%

19.01 GRC Works

0.36%

14

0.36%

0.36%

14

14

100%

100%

19.02 Under Ground Water Tank

0.35%

14

0.35%

0.35%

14

14

100%

100%

19.03 Heel Kerb

0.30%

14

0.30%

0.30%

14

14

100%

100%

19.04 Shaded Structure : Pergola

0.20%

14

0.20%

0.20%

14

14

100%

100%

19.05 Interlock Tiles

0.60%

14

0.60%

0.60%

14

14

100%

100%

19.06 Pump & Gas Enclosures

0.35%

14

0.35%

0.35%

14

14

100%

100%

19.07 Sweet Soil

0.40%

14

0.40%

0.40%

14

14

100%

100%

20.00 Boundary Wall

3.77%

3.77%

3.77%

Sl. No.s

20.01

Activities

Precast Boundary Wall (Other


Sides)

2.35%

14

2.35%

2.35%

14

14

100%

100%

20.02 Boundary Wall Railing

0.77%

14

0.77%

0.77%

14

14

100%

100%

20.03 Manhole Works

0.65%

14

0.65%

0.65%

14

14

100%

100%

21.00 MEP 1st Fix

4.62%

4.62%

4.62%

Condu. for Drainage Piping in


21.01a
SubStr

0.20%

14

0.20%

0.20%

14

14

100%

100%

21.01b Condu. in Structure (Grade Slab)

0.20%

14

0.20%

0.20%

14

14

100%

100%

21.02a Condu. in Structure (GF Tunnels)

0.40%

14

0.40%

0.40%

14

14

100%

100%

21.02b Condu. in Structure (FF Tunnels)

0.40%

14

0.40%

0.40%

14

14

100%

100%

1.21%

14

1.21%

1.21%

14

14

100%

100%

1.21%

14

1.21%

1.21%

14

14

100%

100%

21.05 High Level Drainage

1.00%

14

1.00%

1.00%

14

14

100%

100%

22.00 MEP 2nd Fix

9.46%

9.46%

9.46%

22.01 Inst.of FCU's

2.00%

14

2.00%

2.00%

14

14

100%

100%

22.02 Wiring Works

1.85%

14

1.85%

1.85%

14

14

100%

100%

22.03 Inst.of AC Duct

2.00%

14

2.00%

2.00%

14

14

100%

100%

22.04 Refrigrant Pipes

0.80%

14

0.80%

0.80%

14

14

100%

100%

22.05 Inst.of Water Heaters

0.78%

14

0.78%

0.78%

14

14

100%

100%

22.06 Inst.of CU's

2.03%

14

2.03%

2.03%

14

14

100%

100%

23.00 MEP Final Fix

6.60%

6.60%

6.60%

23.01 Inst.of Exhaust Fan

0.30%

14

0.30%

0.30%

14

14

100%

100%

23.02 Inst.of AC Grills & Diffusers

1.50%

14

1.50%

1.50%

14

14

100%

100%

23.03 Inst.of Water Pumps

0.40%

14

0.40%

0.40%

14

14

100%

100%

Condu. & Fix Sw.Boxes in


21.03
Blockwork
Condu. for Drainage & Water
21.04
Supply

Page 3 of 4

U-SI-P-(14)

CONSTRUCTION OF 160 VILLAS - DSOA


WEEKLY PROGRESS UPDATE 160V AS ON 24-Mar-14
CLUSTER P - 14 VILLAS
BASED ON EARLY START/EARLY FINISH (REV. 01, DATED 29.08.2013)

TOTAL

WTG.

NO OF VILLAS

ACHIEVED %

STATUS

REMARKS

SCOPE

PLANN

ACTUAL

PLANN

ACTUAL

PLANN

ACTUAL

LAST
WEEK

THIS
WEEK

23.04 Electrical Accessories

0.90%

14

0.90%

0.90%

14

14

100%

100%

23.05 Inst.of Light Fittings

0.60%

14

0.60%

0.60%

14

14

100%

100%

23.06 Switchgear Circuit Breakers

1.40%

14

1.40%

1.40%

14

14

100%

100%

23.07 Inst. of Sanitary Fittings & Wares

1.50%

14

1.50%

1.50%

14

14

100%

100%

24.00 Handing Over

1.70%

1.70%

1.08%

24.01 Testing & Commissioning.

0.85%

14

0.85%

0.85%

14

14

100%

100%

(12)

24.02 Disinfection.

0.32%

14

0.32%

0.00%

14

100%

0%

(14)

(14)

24.03 Snagging & Cleaning.

0.53%

14

0.53%

0.23%

14

100%

43%

(14)

(8)

Sl. No.s

Activities

100.00%

100.00% 99.38%

Page 4 of 4

U-SI-P-(14)