Professional Documents
Culture Documents
08 - Scheduling
08 - Scheduling
Copyright Information
The slides in this file are provided to faculty instructing MGT 500 on behalf of the Stevens Institute of Technology. Use is restricted to academic endeavors associated with the delivery of MGT 550 to students properly enrolled at the Stevens Institute of Technology. All other rights are reserved by the original owners of materials contained in this program. The slides contain copyrighted material that has been reproduced and/or adapted to the course syllabus under the doctrine of fair use for academic purposes. All slides in this course are copyrighted by the original source. Requests to reproduce materials for other purposes should be directed to the copyright owner identified in the bibliography that will be made available to faculty.
Module 8: Scheduling
Purpose: prepare students to understand the elements of a project schedule and the techniques commonly used to estimate time in a project plan.
Module 8 Objectives
The Scheduling Equation
Describe the scheduling equation and define its elements
Where
Scheduling Equation
Module 8 Objectives
Activity Types
Define and illustrate the difference between effortdriven and non-effort-driven tasks
Module 8 Objectives
Task Dependencies
Define mandatory, discretionary, and external dependencies
Module 8 Objectives
Logical Relationships
Define FF, SF, SS, and FF relationships Illustrate how changing relationships can be used to compress the project schedule
10
Dependency Relationships
FS: Finish to Start SF: Start to Finish
A B
March 31, 2002 For academic use only.
A B
PMBOK p 68, 69
11
Activity Sequencing
Determine activity types Define Logical Relationships Define task dependencies Define constraints
ASAP = Finish as soon as possible MSO date = Must start on specified date MFO date = Must finish on specified date SNLT date = Start no later than specified date SNET date = Start no earlier than specified date FNLT date = Finish no later than specified date FNET date = Finish no earlier than specified date
For academic use only. 12
Module 8 Objectives
Duration Estimation
Describe the beta distribution and illustrate how it is used to determine duration and uncertainty for an activity
13
Estimating Time
Consider:
work to be done person doing work equipment/resource requirements other commitments corporate overhead project overhead
For academic use only. 14
Obtaining Estimates
Estimate
optimistic, realistic and pessimistic times or costs
15
= 778,333
( P + 4M + O ) = 6
( P - O )2 62
= = 5,000
Natural
790 UCL 793
Unnatural
800
LCL =
March 31, 2002
3
For academic use only.
UCL =
+ 3
Keeney, 2000 16
17
Module 8 Objectives
Types of Network Diagrams
Describe the AON diagram and use it to illustrate the forward and backward pass calculations Describe the AOA diagram and explain the role of dummy activities Emphasize that most software uses the AON format
18
19
Network Diagram
Visual Layout of Work Flow Determine Sequence of Activities Determine Predecessors, Successors Sequence Based on Work Flow Identify Parallel Activities Create Network Diagram
C A B D E F I J
Poli
H K
20
Cards-On-the-Wall Method
Easel Paper Software Development Yarn System Test
Masking Tape
Post-It Notes
FMC, p 164
21
22
PDM (AON)
Free Float Float Early Finish Free Float Float Early Finish
Duration
Duration
23
24
Forward Pass
A 3 B 10
C 16 FS6
F 5
D 1
March 31, 2002
E 10
For academic use only.
G 2
25
Forward Pass
A 0 3 3 B 3 10 13
C 3 16 19 FS6 4
F 22 5 27
D 3 1
E 10 10 20
For academic use only.
G 20 2 22
26
Backward Pass
A 0 3 0 3 3 B 3 10 13 22 12 C 3 16 19 6 22 D 3 1 3 FS6 4 4 E 10 10 20 10 20
For academic use only.
F 22 5 27 22 27 G 20 2 22 20 22
27
Float
A 0 3 0 0 3 3 B 3 10 13 22 12 C 3 16 19 6 22 D 3 1 3 0 FS6 4 4 E 0 10 10 20 10 20
For academic use only.
F 22 5 27 22 27 G 20 2 22 20 22
28
ADM (AOA)
ACTIVITY DESCRIPTION
Duration
Uses I,j ordered pair notation to denote activities between nodes. Nodes represent events (start and end of an activity).
Installing ATM equipment 3 days
29
ADM Principles
The name of the activity and the duration are specified on the arrow. Nodes delineate ends of the arrow. Only one arrow can join two nodes. If two activities can occur in parallel, a dummy node must be added to terminate the second activity. A dummy activity has zero duration.
March 31, 2002 For academic use only. 30
ADM (AOA)
1
Task 1 4d
In order to show that Node 4 cannot happen until Nodes 2 and 3 have occurred, we need to add a dummy activity to show the dependency. Dummy activities MUST have 0 duration.
March 31, 2002 For academic use only. 31
mm Du y
4
Test 2 5
1
2
32
Module 8 Objectives
Gantt Chart
Describe the Gantt chart and use an MS-Project template to illustrate it Emphasize that the Gantt chart can be used to help create the time-phased budget discussed in Chapter 7
33
34
15
3.1
Identify
Team
Members
1 day
16
3.2
Verify
Team
Members
Acceptance
6 days
17
3.3
Schedule
Kickoff
Meeting
1 day
18
3.4
Hold
Kickoff
Meeting
1 day
19
3.5
Identify
Technical
Tracks
6 days
20
3.6
Team
Members
To
Technical
1 day
21
3.7
Technical
Team
Web
Site
5 days
22
23
Call
For
Papers
25 days
24
4.1
Write
Technical
Track
Descriptions
15 days
25
4.2
Write
Call
for
Papers
5 days
Project Budget
$15 $10 ($000) $5 $0 W1 W2 W3 W4 W5 A W6 B C W7 D
35
Resources by Week
Keeney, 2001
Reading Assignments
From Chapter 8
Text
Pp 302 348
For Chapter 9
Text
Pp 361 388
36