This report analyzes the lifting of a boatlanding structure using a 3D computer model. It details the boatlanding's weight, lifting configuration, load cases considered, and results of the structural analysis. The key loads included the structure's self-weight, appurtenances, and couple forces to match the center of gravity. The analysis found that under the expected load combinations, including dynamic factors, all member forces and joint capacities were within allowable limits. Therefore, the report concludes the boatlanding can be safely lifted as designed.
This report analyzes the lifting of a boatlanding structure using a 3D computer model. It details the boatlanding's weight, lifting configuration, load cases considered, and results of the structural analysis. The key loads included the structure's self-weight, appurtenances, and couple forces to match the center of gravity. The analysis found that under the expected load combinations, including dynamic factors, all member forces and joint capacities were within allowable limits. Therefore, the report concludes the boatlanding can be safely lifted as designed.
This report analyzes the lifting of a boatlanding structure using a 3D computer model. It details the boatlanding's weight, lifting configuration, load cases considered, and results of the structural analysis. The key loads included the structure's self-weight, appurtenances, and couple forces to match the center of gravity. The analysis found that under the expected load combinations, including dynamic factors, all member forces and joint capacities were within allowable limits. Therefore, the report concludes the boatlanding can be safely lifted as designed.
EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS CONTRACTOR: PTSC M&C SUB CONTRACTOR: VIETSOVPETRO BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT
Document No.: 2013-1489-6R-3011 VIETSOVPETRO PTSC M&C CLJOC REV. NO. DATE PREPARED BY APPROVED BY REVIEWED BY APPROVED BY APPROVED BY NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE NAME SIGN DATE A 07.04. 14 VDC 07.04. 14 PCK 07.04. 14
B 14.05. 14 TVD 14.05. 14 PNV 14.05. 14
0 15.05. 14 TVD 15.05. 14 PNV 15.05. 14
STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 2 of 19
Revision No: 0 Date: 15 May 2014
SuTuVangSouthWest REVISION RECORD SHEET
NO. REV. NO. CONTENT OF REVISION DATE OF REVISION 1 A Issued for Review and Comment 18 April 2014 2 B Re-Issued for Review and Comment 14 May 2014 3 0 Approved For Construction 15 May 2014
STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 3 of 19
APPENDIX- A : WEIGHT OF BOATLANDING ................................................................ 12 APPENDIX- B : BOATLANDING LIFTING CONFIGURATION ................................. 13 APPENDIX- C : BOATLANDING SACS MODEL PLOT .............................................. 14 APPENDIX D : BOATLANDING SACS MODEL INPUT FILE ................................... 15 APPENDIX E : BOATLANDING SACS OUTPUT FILE .............................................. 16 APPENDIX F : LIFTING RIGGING PADEYE CHECK ................................................... 17 APPENDIX G : BOATLANDING STRUCTURAL DRAWING ........................................ 18 APPENDIX H : SLING AND SHACKLE CERTIFICATE ................................................. 19
STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 4 of 19
Revision No: 0 Date: 15 May 2014
SuTuVangSouthWest 1.0 INTRODUCTION 1.1 DEFINITION CLJOC : Cuu Long Joint Operating Company VSP : Vietsovpetro Joint Venture SVSW : Su Tu Vang South West WHP : Well Head Platform 1.2 PURPOSE The purpose of this Boatlandings Offshore Lifting Analysis Report is to provide detailed evaluation of the lifting performance of Drilling Module by crane barge. The Boatlandings Offshore Lifting Analysis is carried out in this report with C.O.G shift cases. 1.3 GENERAL INFORMATION Cuu Long Joint Operating has embarked in the development of STV Extension Plan - STV South West (SVSW) Project located in Block 15-1, offshore Vietnam. This development consists of an unmanned tripod jacketed platform (SVSW) with minimum facility which tie-back and operated from the adjacent STV-CPP. The development of this field will be carried out by utilizing 3 slots consist of one (1) existing well using single Xmas Tree and two (2) future dual well Xmas Trees. Processing of the SVSW wellstream fluids will be carried out on the STV-CPP facilities which will also supply gas to SVSW for gas lifting. STV-CPP will alsocontrol and monitor SVSW. 1.4 SCOPE This report presents the summary of the results of Boatlandings Offshore Lifting Analysis Report at installation field, verify all slings to ensure that no damage will occur when offshore installation. 1.5 REFERENCE The following design code and specification are adopted: Design Code: - API RP2A(WSD) 21st Edition-American Petroleum Institute - AISC Manual of Steel Construction (ASD) 9th Edition-American Institute of Steel Construction Other Reference - Weight Of Boatlanding For Lifting :Refer to Appendix A1 STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 5 of 19
Revision No: 0 Date: 15 May 2014
SuTuVangSouthWest - Boatlanding lifting Configuration; Doc. No. : 2013-1489-66-3036 - SVSW WHP Jacket Weight Control Report; Doc. No. : 2013-3289-6J-0005 Rev 0 2.0 BOATLANDING LIFTING ANALYSIS 2.1 COMPUTER MODEL. 3-Dimensional (3D) computer model is created to simulate Boatlanding by using SACS computer program. The computer model for Boatlanding lifting is shown below:
Figure 1: Boatlanding Lifting Analysis Model A hook point (Joint HOOK) was simulated as fixed point (111111) in all translational and rotational directions, to be located vertically over the model COG. It is the only vertical load STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 6 of 19
Revision No: 0 Date: 15 May 2014
SuTuVangSouthWest support in the model and will be connected by sling elements to the lift points. Four (4) lifting slings were modelled as tubular members with members end fixities release (000011-000111) such that it were capable of taking only axial tension loads. Two (2) lateral spring elements (Joint B019 and Joint B020) are modeled and used to maintain structural equilibrium during analyses.
Figure 2: Boundary Condition The initial model coordinate system is as follow: Global X-axis : Longitudinal, perpendicular with Boatlanding Grid A,B; X=0 at Boatlanding Grid 1 Global Y-axis : parallel with Boatlanding Grid A,B; Y=0 at center of distance with Boatlanding Grid A to with Boatlanding Grid B. Global Z-axis : Vertical; positive upwards; z=0 at mean seal level (M.S.L=0). The coordinate system is shown below : STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 7 of 19
Revision No: 0 Date: 15 May 2014
SuTuVangSouthWest
Figure 3: Coordinate System Coordinate of CoG of Boalanding in SACS coordination system: X= 0.19 m Y= 0.77 m Z= 0.87 m 2.2 DESIGN LOAD This section presents the summary of manually input and computer-generated loadings. Dead weight of modelled member is obtained as self-generated by SACS. The lifting will be executed in calm climate. Hence, it is reasonably assumed that rain and wind effect on Boatlanding structure is negligible. The Basic Load Description is listed in table below: Load considerded in the structural analysis are as flow: Load condition Description Load name Self weight of Subsea Wellhead Template 1 Computer Generated Main subsea model structural self weight DEAD Appurtenances and miscellaneous steel weights 2 Double plates BL-DOPL Barge Bumper BL-BUMPE Fender BL-FENDE Grating BL-GRATT Handrail BL-HANDR Ladder BL-LADDE Mooring Bit BL-MORIG Padeye for lifting BL-PADEY Stair BL-STAIR 3 Couples Force COUPLE TOTAL
Table 1: LOAD CONDITION STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 8 of 19
Revision No: 0 Date: 15 May 2014
SuTuVangSouthWest The couple force to match COG is shown in the table below: Coordinate of CoG follow WCR in sacs mode: X= -0.2 m Y= -0.63 m Coordinate of CoG follow result of SACS X= -0.19 m Y= -0.77 m X(m)= -0.01 m Y(m)= 0.14 m Load case X(m) Y(m) POINTS P(KN) 3 -0.01 0.14 B064 12.64 B065 -10.94 B062 13.24 D238 -14.94
Table 2: Couple Force To Match Wcr COG Description Load Case Basic Load (kN) Load Factor Factored Load (kN) Computer Generated Selfweight 1 370.47 1.13 418.6 Un-modeled weight 2 86.89 1.13 98 Couple force 3 0 1 0 Total Load (Load Combine GRV) 516.6
Table 3 : Basic Load Case STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 9 of 19
Revision No: 0 Date: 15 May 2014
SuTuVangSouthWest 2.3 DYNAMIC LOAD FACTORS The dynamic load factors for offshore installation lift operation are as per API RP 2A (WSD) : Members connected to lifting points DLF=2.00 All other members DLF=1.35 2.4 LOAD COMBINATION Load Com. Load Combinations & Load Conditions CB GRV 3 GRV 1.13 1.0 LC1 1.35 LC2 2.0
Table 4 : Load Combine 3.0 SUMMARY OF RESULTS The Boatlanding members and joint stress obtained from the structural strength analysis for offshore installation lift were checked against the allowable values in accordance with API RP 2A and AISC code requirements. Results of analysis are presented in the following sections : 3.1 HOOK LOAD AND SLING FORCES The hook loads and sling forces are given in the following tables : Load Case Hook Loads (kN) Fx Fy (Fz+Rigging load) x DAF GRV - - (516.6+20) x 1.3 = 697.58
Table 5: Boatlanding Hook Load
The hook capacity of 150 MT for aux.hook of Truong Sa Crane Barge is greater than the hook load listed above, hence this crane is satisfactory for the proposed Boatlanding lift. STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 10 of 19
The above slings forces are used for the rigging & pad eye checks. 3.2 MEMBER AND JOINT UNITY CHECKS 3.2.1. MEMBER UNITY CHECKS. Member design code check was performed in accordance with API RP2A (WSD) and AISC- ASD. Analysis result indicate that all the member strength and joints unity check ratios for Boatlanding are less than 0.50 ( ignore all sling members). Members connected to lifting points with unity check 0.15 are list below : Member Member Section Max.UC Load Case DAF Group B036-B064 BL4 40.64x12.7thk. 0.17 LC2 2 B060-B071 BL4 40.64x12.7thk. 0.18 LC2 2 B062-B071 BL4 40.64x12.7thk. 0.20 LC2 2
Table 7: Boatlanding Uc Members Connected To Lifting Point STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 11 of 19
Revision No: 0 Date: 15 May 2014
SuTuVangSouthWest The maximum unity check of all other members are list below: Member Member Section Max.UC Load Case DAF Group B079-B081 BL4 40.64x12.7thk. 0.19 LC1 1.35
Table 8: Boatlanding All Members With Maximum UC 3.2.2. JOINT UNITY CHECKS. Joints with maximum unity check of all other members are list below : Joints Max. UC Load Case DAF B071 0.54 LC2 2
Table 9: Boatlanding Joints With Maximum Uc 4.0 CONCLUSION The structural integrity of the Boatlanding was analysed for offshore installation lift operation. Members and joints stressed obtained were checked against the allowable values in accordance with API RP 2A and AISC code requirements. Results of the analysis and checks indicated that all stress ratios are less than unity. It is thus concluded that the Boatlanding is structurally adequate during offshore lift. The lifting padeye and rigging strength checks also shown that the proposed lifting configuration is satisfactory for Boatlanding offshore installation lift operation. STV EXTENSION STV SOUTH WEST PROJECT EPCI FOR WHP-SVSW, PIPELINES AND CPP MODIFICATIONS Document No.: 2013-1489-6R-3011 BOATLANDINGS OFFSHORE LIFTING ANALYSIS REPORT Page: 12 of 19