In This lesson you will learn how to create cash flow and man power histogram
from primavera and represent them on excel for better graphics.
A: How to create Cash Flow To create cash flow in excel we have two methods, Method 1 is to let the primavera do all the calculation and distribution of money on the time and just draw the charts in excel. Method 2 is to let the excel do every thing for you, calculate and distribute the money over the time.
Method no. 1 Create cash flow from primavera: Cash flow could be created by primavera 6 version 7 using the reports section, However i found primavera 6 v7 reports are not very clear that every one can do it simply, Therefore we are going to see step by step how to create planned values and earned values using primavera p6 v7 reports. 1- Open reports section from tools tap then reports then reports as per photo below :
Open report tap [private]2- From the report group Tabular select the report called CT-01 Monthly Project Cash flow and then click on wizard icon on the right as per photo below
Select monthly cash flow report 3- The report wizard window will open, just click next as per photo below
click next 4- From configure selected subject area under activities click columns
click column icom 5-from available options on the left under earned value group select planned value cost and earned value cost (double click to move items from available option on the the left to the selected options in the right) Then click apply Then OK
How to use primavera 6 version 7 reports to create cash flow 5 6- Then click next
How to use primavera 6 version 7 reports to create cash flow 6 7- from the date options click time interval fields.
How to use primavera 6 version 7 reports to create cash flow 7 8- from available options on the left under earned value group select earned value cost, cum earned value cost, planned value cost and cum planned value cost then click OK
How to use primavera 6 version 7 reports to create cash flow 8 9- click next
How to use primavera 6 version 7 reports to create cash flow 9 10- put your report title then click next
How to use primavera 6 version 7 reports to create cash flow 10 11- Congratulations !! report generated click run report
How to use primavera 6 version 7 reports to create cash flow 11 12- choose HTML file and from output file select the location the report will be saved then click OK
How to use primavera 6 version 7 reports to create cash flow 12 13- now the internet explorer should open and this step is tricky one , if your internet explorer not your default browser like if you are using Firefox or Google chrome, go to the location the report saved and right click the open with internet explorer, otherwise the copy and paste will not work probably.
How to use primavera 6 version 7 reports to create cash flow 13 You should should see something like this
How to use primavera 6 version 7 reports to create cash flow 14 14- Copy values of Earned Value, Cum. Earned Value, Planned Value and Cum Planned Value from internet explorer to any excel sheet and create cashflow easily, Or download the attached sample and it will create the cashflow based on the values from primavera
Download the sample sheet: Download the sample sheet
Copy values from internet explorer to the excel sheet
How to use primavera 6 version 7 reports to create cash flow 15 You will get the cash flow chart based on your inputs
Cash flow chart sample
Method no. 2 Create cash flow from Excel:
Another Method to create cash flow from excel: How to create a time schedule, Gantt chart, Bar chart and cash flow using the attached excel sheet. This Microsoft Excel sheet is fully automated and it will create the cash flow and draw the gantt chart for you. (see the video below for more information)
What is Gantt chart: Reference to Wikipedia A Gantt chart is a type of bar chart, developed by Henry Gantt in the 1910s, that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project. Some charts also show the dependency (i.e. precedence network) relationships between activities. Gantt charts can be used to show current schedule status using percent-complete shadings and a vertical TODAY line as shown here.
How is my Microsoft Gantt Chart working : 1- The sheet is based on working days, First step is to identify the holidays and week ends
2- Fill the budget cost, planned start and planned finish , the activity duration (working days), planned value, planned % as of data date will be calculated automatically based on step no. 1 (see the video below for more information)
bar chart
3- fill the actual date and the actual % completed and all other values will be filled automatically. (see the video below for more information)
4- Cash flow will be created automatically (see the video below for more information)