In This lesson you will learn how to create cash flow and man power histogram

from primavera and represent them on excel for better graphics.



A: How to create Cash Flow
To create cash flow in excel we have two methods, Method 1 is to let the primavera do all the
calculation and distribution of money on the time and just draw the charts in excel. Method 2 is
to let the excel do every thing for you, calculate and distribute the money over the time.

Method no. 1 Create cash flow from primavera:
Cash flow could be created by primavera 6 version 7 using the reports section, However i found
primavera 6 v7 reports are not very clear that every one can do it simply, Therefore we are going
to see step by step how to create planned values and earned values using primavera p6 v7
reports.
1- Open reports section from tools tap then reports then reports as per photo below :

Open report tap
[private]2- From the report group Tabular select the report called CT-01 Monthly Project Cash
flow and then click on wizard icon on the right as per photo below


Select monthly cash flow report
3- The report wizard window will open, just click next as per photo below


click next
4- From configure selected subject area under activities click columns


click column icom
5-from available options on the left under earned value group select planned value cost and
earned value cost (double click to move items from available option on the the left to the selected
options in the right) Then click apply Then OK



How to use primavera 6 version 7 reports to create cash flow 5
6- Then click next


How to use primavera 6 version 7 reports to create cash flow 6
7- from the date options click time interval fields.

How to use primavera 6 version 7 reports to create cash flow 7
8- from available options on the left under earned value group select earned value cost, cum
earned value cost, planned value cost and cum planned value cost then click OK


How to use primavera 6 version 7 reports to create cash flow 8
9- click next

How to use primavera 6 version 7 reports to create cash flow 9
10- put your report title then click next

How to use primavera 6 version 7 reports to create cash flow 10
11- Congratulations !! report generated click run report

How to use primavera 6 version 7 reports to create cash flow 11
12- choose HTML file and from output file select the location the report will be saved then click
OK

How to use primavera 6 version 7 reports to create cash flow 12
13- now the internet explorer should open and this step is tricky one , if your internet explorer
not your default browser like if you are using Firefox or Google chrome, go to the location the
report saved and right click the open with internet explorer, otherwise the copy and paste will not
work probably.

How to use primavera 6 version 7 reports to create cash flow 13
You should should see something like this

How to use primavera 6 version 7 reports to create cash flow 14
14- Copy values of Earned Value, Cum. Earned Value, Planned Value and Cum Planned Value
from internet explorer to any excel sheet and create cashflow easily, Or download the attached
sample and it will create the cashflow based on the values from primavera

Download the sample sheet: Download the sample sheet

Copy values from internet explorer to the excel sheet

How to use primavera 6 version 7 reports to create cash flow 15
You will get the cash flow chart based on your inputs

Cash flow chart sample


Method no. 2 Create cash flow from Excel:

Another Method to create cash flow from excel:
How to create a time schedule, Gantt chart, Bar chart and
cash flow using the attached excel sheet.
This Microsoft Excel sheet is fully automated and it will create the cash flow and draw the gantt
chart for you. (see the video below for more information)


What is Gantt chart: Reference to Wikipedia A Gantt chart is a type of bar chart, developed
by Henry Gantt in the 1910s, that illustrates a project schedule. Gantt charts illustrate the start
and finish dates of the terminal elements and summary elements of a project. Terminal elements
and summary elements comprise the work breakdown structure of the project. Some charts also
show the dependency (i.e. precedence network) relationships between activities. Gantt charts can
be used to show current schedule status using percent-complete shadings and a vertical
TODAY line as shown here.

How is my Microsoft Gantt Chart working : 1- The sheet is based on working days, First step is
to identify the holidays and week ends

2- Fill the budget cost, planned start and planned finish , the activity duration (working days),
planned value, planned % as of data date will be calculated automatically based on step no. 1
(see the video below for more information)

bar chart

3- fill the actual date and the actual % completed and all other values will be filled automatically.
(see the video below for more information)

4- Cash flow will be created automatically (see the video below for more information)