An Update On Work Requirements & Equipment

Layouts
5 New Engines (Wartsila 12V32)
Engine Deck Lowered (To Accommodate 4 of the engines)
New Engine Compartment in Sack Store for #5 Engine
New Sea Water Cooling Pumps
New Engine Cooling Heat Exchangers
New HV & LV Switchboards
New SCRs together with new SCR Room (located in pumproom store)
New HV Transformers to be located behind former boiler room
New Starting Air Compressors
Relocation of Main Air Compressors
Ventillation
Exhaust Piping
New associated piping (Fresh Water Cooling, Sea Water Cooling, Fuel
Oil, Starting Air


Engine Installation
Combustion Air
Engine Exhaust
Machinery Space Ventilation
Cable Runs
ECR & SCR Room AC


Method of getting engines into correct position
Sequence of installation
Hooking up systems
Mechanical Completion
Commissioning
Commissioning other equipment


First Three Engines Arrive:



BEGINNING OF NOVEMBER



The Remaining Two Engines Arrive:



END OF NOVEMBER



Task Item Start Finish
Secure new Generator sets 17/06/08 17/06/08
1st Generator sets ready ex-work 25/09/08 25/09/08
2nd Generator set ready ex-work 25/09/08 25/09/08
3rd Generator set ready ex-work 25/09/08 25/09/08
4th Generator set ready ex-works 15/10/08 15/10/08
5th Generator set ready ex-works 15/10/08 15/10/08
1st Generator sets Arrival at Site 08/11/08 08/11/08
2nd Generator set Arrival at Site 08/11/08 08/11/08
3rd Generator set Arrival at Site 08/11/08 08/11/08
4th Generator set Arrival at Site 28/11/08 28/11/08
5th Generator set Arrival at Site 28/11/08 28/11/08
Milestone Dates
Task Item Start Finish
New Engine Deck 01/10/08 03/11/08
5
th
Engine Deck 15/10/08 07/11/08
1st Generator set 09/11/08 30/11/08
Placement 09/11/08 13/11/08
Hook-up 13/11/08 30/11/08
2nd Generator set 13/11/08 27/11/08
Placement 13/11/08 16/11/08
Hook-up 16/11/08 27/11/08
3rd Generator set (#5 Engine) 16/11/08 04/12/08
Placement 16/11/08 23/11/08
Hook-up 23/11/08 04/12/08
Construction/Install Dates
Task Item Start Finish
4th Generator set 29/11/08 13/12/08
Placement 29/11/08 02/12/08
Hook-up 03/12/08 13/12/08
5th Generator set 03/12/08 16/12/09
Placement 03/12/08 05/12/08
Hook-up 06/12/08 16/12/08
Deck Foundation & Plating over of
hatch opening to MP Room 27/10/08 10/11/08
Side & Fwd Bulkheads 17/10/08 31/10/08
FR 50 Bulkhead Access Weld Up 18/12/08 24/12/08
FR 50 WT Door Fit 28/12/08 10/01/09
Construction/Install Dates
Task Item Start Finish
SCR Room

Access cut for MCC space 24/10/08 31/10/08
Door & walkway from Pumproom 24/10/08 08/11/08
Fwd Bulkhead Insert Plating 24/10/08 30/10/08
Insulate SCR Room Space 01/11/08 08/11/08
Installation Of SCRs 09/11/08 23/11/08
Installation of MCCs 09/11/08 23/11/08
Installation of Air Conditioning 23/11/08 23/12/08
Close up of Escape Ladder Space 01/11/08 08/11/08
Construction/Install Dates
Task Item Start Finish
HV Switchboard Room

Foundations 5/11/08 20/11/08
Transformer Room Doors Re-Position 5/11/08 15/11/08
Forward Bulkhead 5/11/08 15/11/08
Ventilation (Install Trunking) 15/11/08 29/11/08
Install HV Switchboards 29/11/08 08/12/08
Construction/Install Dates
First Three Engines Arrive:



BEGINNING OF NOVEMBER



The Remaining Two Engines Arrive:



END OF NOVEMBER



READY TO SAIL:



END OF MARCH 2009