This document outlines the startup schedule and activities for several plants over a period of 8 days from June 17th to June 25th. It involves pressurizing and starting up the Naphtha Hydrotreating (NHT) plant on June 17th, starting the boilers on June 17th-18th, circulating naphtha through the gas plant and fine tuning parameters from June 19th-20th, starting up the dryers for the Isomerization unit from June 20th-21st, preparing desorbent for the Isom unit from June 21st-23rd, starting up the Isom unit on June 23rd-24th, and fine tuning the Isom unit from June 24th
This document outlines the startup schedule and activities for several plants over a period of 8 days from June 17th to June 25th. It involves pressurizing and starting up the Naphtha Hydrotreating (NHT) plant on June 17th, starting the boilers on June 17th-18th, circulating naphtha through the gas plant and fine tuning parameters from June 19th-20th, starting up the dryers for the Isomerization unit from June 20th-21st, preparing desorbent for the Isom unit from June 21st-23rd, starting up the Isom unit on June 23rd-24th, and fine tuning the Isom unit from June 24th
This document outlines the startup schedule and activities for several plants over a period of 8 days from June 17th to June 25th. It involves pressurizing and starting up the Naphtha Hydrotreating (NHT) plant on June 17th, starting the boilers on June 17th-18th, circulating naphtha through the gas plant and fine tuning parameters from June 19th-20th, starting up the dryers for the Isomerization unit from June 20th-21st, preparing desorbent for the Isom unit from June 21st-23rd, starting up the Isom unit on June 23rd-24th, and fine tuning the Isom unit from June 24th
NHT start up plan NHT System pressurization 0 17-Jun-14 17-Jun-14 On 17 th june @ 14:00 hrs system is pressurized with fuel gas at 170 PSIG & Compressor will start at 15:00 hrs. Hydrogen gas flow shall be maintained so that 300 SCF Hydrogen/bbl of Naphtha and 180 psia hydrogen partial pressure can be achieved. Burners Light up (NHT) 0 17-Jun-14 17-Jun-14 On 17 th june @ 18:00 hrs Burners will be lighted up. Gradually increase furnace temperature at a rate of 25 o C/hr till 175 o C at furnace outlet is achieved. 7 hrs are required to achieve RIT. NHT feed cut in temperature achieved 0 17-Jun-14 17-Jun-14 On 18 th June 01:00 hrs, RIT will be achieved to 175 0 C. NHT feed cut in from tank-26 1 18-Jun-14 19-Jun-14 On 18 th june @ 02:00 hrs feed cut in will start & system will be kept on circulation. On getting on spec. Naphtha (less than 0.5 ppm sulphur @ reactor outlet), system flushing will be completed on 19 th June @ 07:00 hrs. Boilers start up plan Boiler start up 0 17-Jun-14 18-Jun-14 On 17 th june @ 18:00 hrs Burner will be lighted up. Initially burners will be light up on fuel gas from ORC-I after achieving 40 bar(g) pressure at steam drum switch burners to oil firing. Gas plant start up plan Sweet naphtha circulation in gas plant. 0 19-Jun-14 19-Jun-14 On 19 th june @ 08:00 hrs circulation of sweet Naphtha from NHT plant to Gas plant and maintaining column bottom levels. Gas Plant parameters fine tuning 1 19-Jun-14 20-Jun-14 On 19 th june @ 09:00 hrs commission reboilers steam, stablize the system and maintain plant parameters as provided by advisory (total n-butane in Gas Plant feed shall dump in naphtha @ De-butanizer, propane and partial iso-butane shall be in LPG stream). Gas plant parameters fine tuning will be completed on 20 th june @ 09:00 hrs. Isom unit Pre-Start up activity Dryer start up 1 20-Jun-14 21-Jun-14 On 20 th june @ 10:00 hrs dryers will start up, 12 hrs drying cycle is required for each dryer. Expected moisture level (less than 0.1 wt ppm) can be achieved after 24 hrs. Desorbent Preparation Desorbent Preparation on ORC-II Naphtha 2 21-Jun-14 23-Jun-14 On 21 st june @ 11:00 hrs morning fixing the isom unit parameters for desorbent preparation. Fixing the parameters will take 24 hrs and 24 hrs is required to get required quantity. Isom unit Start up Isom unit Start up 1 23-Jun-14 24-Jun-14 On 23 rd june @ 12:00 hrs Isom unit will start up. Fine tuning of unit Isom unit parameters fine tuning 1 24-Jun-14 25-Jun-14 On 24 th june @ 13:00 hrs fine tuning of isom unit will start. Fine tuning will be completed on 25th june @ 13:00 hrs. Note: 1- Isom unit shedule will be finalized tomorrow morning after discussion with AVP Technical. 40 3- LPG contains higher amount of propane. 2- On 20th June, Heavy Naphtha to ORC-I platformer will be started. Heavy naphtha transfer line must be available before 20th June. Start up Schedule Sr.No Description of Activities Schedule as on 17-06-14 Comments