Duration

(days) Start Date Finish Date


NHT start up plan
NHT System pressurization 0
17-Jun-14 17-Jun-14
On 17
th
june @ 14:00 hrs system is pressurized with fuel gas at 170 PSIG & Compressor will
start at 15:00 hrs. Hydrogen gas flow shall be maintained so that 300 SCF Hydrogen/bbl of
Naphtha and 180 psia hydrogen partial pressure can be achieved.
Burners Light up (NHT) 0
17-Jun-14 17-Jun-14
On 17
th
june @ 18:00 hrs Burners will be lighted up. Gradually increase furnace temperature
at a rate of 25
o
C/hr till 175
o
C at furnace outlet is achieved. 7 hrs are required to achieve
RIT.
NHT feed cut in temperature achieved 0
17-Jun-14 17-Jun-14
On 18
th
June 01:00 hrs, RIT will be achieved to 175
0
C.
NHT feed cut in from tank-26 1 18-Jun-14 19-Jun-14
On 18
th
june @ 02:00 hrs feed cut in will start & system will be kept on circulation. On
getting on spec. Naphtha (less than 0.5 ppm sulphur @ reactor outlet), system flushing will
be completed on 19
th
June @ 07:00 hrs.
Boilers start up plan
Boiler start up 0 17-Jun-14 18-Jun-14
On 17
th
june @ 18:00 hrs Burner will be lighted up. Initially burners will be light up on fuel
gas from ORC-I after achieving 40 bar(g) pressure at steam drum switch burners to oil firing.
Gas plant start up plan
Sweet naphtha circulation in gas plant. 0 19-Jun-14 19-Jun-14
On 19
th
june @ 08:00 hrs circulation of sweet Naphtha from NHT plant to Gas plant and
maintaining column bottom levels.
Gas Plant parameters fine tuning 1 19-Jun-14 20-Jun-14
On 19
th
june @ 09:00 hrs commission reboilers steam, stablize the system and maintain
plant parameters as provided by advisory (total n-butane in Gas Plant feed shall dump in
naphtha @ De-butanizer, propane and partial iso-butane shall be in LPG stream). Gas plant
parameters fine tuning will be completed on 20
th
june @ 09:00 hrs.
Isom unit Pre-Start up activity
Dryer start up 1 20-Jun-14 21-Jun-14
On 20
th
june @ 10:00 hrs dryers will start up, 12 hrs drying cycle is required for each dryer.
Expected moisture level (less than 0.1 wt ppm) can be achieved after 24 hrs.
Desorbent Preparation
Desorbent Preparation on ORC-II Naphtha 2 21-Jun-14 23-Jun-14
On 21
st
june @ 11:00 hrs morning fixing the isom unit parameters for desorbent
preparation. Fixing the parameters will take 24 hrs and 24 hrs is required to get required
quantity.
Isom unit Start up
Isom unit Start up 1 23-Jun-14 24-Jun-14 On 23
rd
june @ 12:00 hrs Isom unit will start up.
Fine tuning of unit
Isom unit parameters fine tuning 1 24-Jun-14 25-Jun-14
On 24
th
june @ 13:00 hrs fine tuning of isom unit will start. Fine tuning will be completed on
25th june @ 13:00 hrs.
Note:
1- Isom unit shedule will be finalized tomorrow morning after discussion with AVP Technical.
40
3- LPG contains higher amount of propane.
2- On 20th June, Heavy Naphtha to ORC-I platformer will be started. Heavy naphtha transfer line must be available before 20th June.
Start up Schedule
Sr.No Description of Activities
Schedule as on 17-06-14
Comments