Activity ID Activity Name Original

Duration
Start Finish
Culvert Rehabilitation In Glenn County Culvert Rehabilitation In Glenn County
62 06-Jun-14 A 22-Sep-14
Submittals Submittals
14 06-Jun-14 A 15-Jul-14
4M1804.SUB.100 WPCP Submitted 0 06-Jun-14 A
4M1804.SUB.110 WPCP Re-Submitted 0 23-Jun-14 A
4M1804.SUB.120 Safety Plan Re-Submitted 0 17-Jun-14 A
4M1804.SUB.130 Lead Compliance Plan Submittals 0 27-Jun-14*
4M1804.SUB.140 Safety Plan Approval By Caltrans 14 23-Jun-14 A 15-Jul-14
4M1804.SUB.150 Lead Compliance Plan Approval By Caltrans 10 30-Jun-14 15-Jul-14
Construction Construction
45 21-Jul-14 22-Sep-14
4M1804.100 Construction Start 0 21-Jul-14*
4M1804.110 Construction Finish 0 22-Sep-14
Location 1 Location 1 5 21-Jul-14 25-Jul-14
4M1804.LOC1.100 Remove Fence, Culvert & Marker 1 21-Jul-14 21-Jul-14
4M1804.LOC1.110 Install Marker, ESA Fence, Cleaning & Inspection Of Pipe 1 22-Jul-14 22-Jul-14
4M1804.LOC1.120 CIPPL 2 23-Jul-14 24-Jul-14
4M1804.LOC1.130 Cleaning & Inspection 1 25-Jul-14 25-Jul-14
Location 2 Location 2 5 28-Jul-14 01-Aug-14
4M1804.LOC2.100 Remove Fence, Culvert & Marker, Cleaning & Inspection 1 28-Jul-14 28-Jul-14
4M1804.LOC2.110 Remove SC Slope Protection, Install Fence Type WM & BW 1 29-Jul-14 29-Jul-14
4M1804.LOC2.120 71" X 41" Steel FES, Install Misc. Steel 1 30-Jul-14 30-Jul-14
4M1804.LOC2.130 Misc. Steel 1 31-Jul-14 31-Jul-14
4M1804.LOC2.140 Minor Concrete (Invert Paving), Install Marker 1 01-Aug-14 01-Aug-14
Location 3 Location 3 5 04-Aug-14 08-Aug-14
4M1804.LOC3.100 Remove & Install Marker, Cleaning & Inspect Of Culvert 1 04-Aug-14 04-Aug-14
4M1804.LOC3.110 Cleaning & Inspection 1 05-Aug-14 05-Aug-14
4M1804.LOC3.120 Misc Steel 2 06-Aug-14 07-Aug-14
4M1804.LOC3.130 Minor Concrete (Invert Paving), Install Marker 1 08-Aug-14 08-Aug-14
Location 4 Location 4 5 11-Aug-14 15-Aug-14
4M1804.LOC4.100 Remove Fence, Culvert & Marker 1 11-Aug-14 11-Aug-14
4M1804.LOC4.110 Ditch Excavation, Grade To Day Light, Install 18" CSP, Cleaning & Inspect Of Culvert 1 12-Aug-14 12-Aug-14
4M1804.LOC4.120 CIPPL 2 13-Aug-14 14-Aug-14
4M1804.LOC4.130 Install Marker 1 15-Aug-14 15-Aug-14
Location 5 Location 5 5 18-Aug-14 22-Aug-14
4M1804.LOC5.100 Remove Fence, Culvert & Marker 1 18-Aug-14 18-Aug-14
4M1804.LOC5.110 Ditch Excavation, Grade To Day Light, Install 18" CSP, Cleaning & Inspect Of Culvert 1 19-Aug-14 19-Aug-14
4M1804.LOC5.120 CIPPL 2 20-Aug-14 21-Aug-14
4M1804.LOC5.130 Install Marker 1 22-Aug-14 22-Aug-14
Location 6 Location 6 5 25-Aug-14 29-Aug-14
4M1804.LOC6.100 Remove & Install Marker,CIPPL, Cleaning & Inspect Of Culvert 1 25-Aug-14 25-Aug-14
4M1804.LOC6.110 CIPPL, Cleaning & Inspect Of Culvert 4 26-Aug-14 29-Aug-14
Location 7 Location 7 5 02-Sep-14 08-Sep-14
4M1804.LOC7.100 Remove Marker, Ditch Excavation, Grade To Day Light, Cleaning & Inspect Of Culvert 1 02-Sep-14 02-Sep-14
4M1804.LOC7.110 Minor Concrete Footing, Minor Concrete Structure, Install Marker 1 03-Sep-14 03-Sep-14
02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06
June 2014 July 2014 August 2014 September 2014
October 2014
22-Sep-14, Culvert R
15-Jul-14, Submittals
WPCP Submitted
WPCP Re-Submitted
Safety Plan Re-Submitted
Lead Compliance Plan Submittals
Safety Plan Approval By Caltrans
Lead Compliance Plan Approval By Caltrans
22-Sep-14, Construction
Construction Start
Construction Finish
25-Jul-14, Location 1
Remove Fence, Culvert & Marker
Install Marker, ESA Fence, Cleaning & Inspection Of Pipe
CIPPL
Cleaning & Inspection
01-Aug-14, Location 2
Remove Fence, Culvert & Marker, Cleaning & Inspection
Remove SC Slope Protection, Install Fence Type WM & BW
71" X 41" Steel FES, Install Misc. Steel
Misc. Steel
Minor Concrete (Invert Paving), Install Marker
08-Aug-14, Location 3
Remove & Install Marker, Cleaning & Inspect Of Culvert
Cleaning & Inspection
Misc Steel
Minor Concrete (Invert Paving), Install Marker
15-Aug-14, Location 4
Remove Fence, Culvert & Marker
Ditch Excavation, Grade To Day Light, Install 18" CSP, Cleaning &
CIPPL
Install Marker
22-Aug-14, Location 5
Remove Fence, Culvert & Marker
Ditch Excavation, Grade To Day Light, Install 18" CSP, Clea
CIPPL
Install Marker
29-Aug-14, Location 6
Remove & Install Marker,CIPPL, Cleaning & Inspec
CIPPL, Cleaning & Inspect Of Culvert
08-Sep-14, Location 7
Remove Marker, Ditch Excavation, Grade T
Minor Concrete Footing, Minor Concrete S
03-4M1804 - Culvert Rehabilitation In Glenn County
26-Jun-14 23:18
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 2
CPM Schedule Provided By: Pushpa Services
Activity ID Activity Name Original
Duration
Start Finish
4M1804.LOC7.120 Misc. Steel 1 04-Sep-14 04-Sep-14
4M1804.LOC7.130 Invert Paving 1 05-Sep-14 05-Sep-14
4M1804.LOC7.140 Cleaning & Inspect Of Culvert 1 08-Sep-14 08-Sep-14
Location 8 Location 8 4 09-Sep-14 12-Sep-14
4M1804.LOC8.100 Remove Culvert & Marker, 18" HDPE Corrugated, Concrete Backfill, Place HMA 1 09-Sep-14 09-Sep-14
4M1804.LOC8.110 Grade To Daylight, Roadway Excavation 1 10-Sep-14 10-Sep-14
4M1804.LOC8.120 Shoulder Backing 1 11-Sep-14 11-Sep-14
4M1804.LOC8.130 Clearing & Grubbing, Install Marker 1 12-Sep-14 12-Sep-14
Location 9 Location 9 4 15-Sep-14 18-Sep-14
4M1804.LOC9.100 Remove Culvert & Marker, 18" HDPE Corrugated, Concrete Backfill, Place HMA 1 15-Sep-14 15-Sep-14
4M1804.LOC9.110 Grade To Daylight, Roadway Excavation 1 16-Sep-14 16-Sep-14
4M1804.LOC9.120 Shoulder Backing 1 17-Sep-14 17-Sep-14
4M1804.LOC9.130 Clearing & Grubbing, Install Marker 1 18-Sep-14 18-Sep-14
Punch List Punch List 2 19-Sep-14 22-Sep-14
4M1804.PUN.100 PunchList 2 19-Sep-14 22-Sep-14
02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06
June 2014 July 2014 August 2014 September 2014
October 2014
Misc. Steel
Invert Paving
Cleaning & Inspect Of Culvert
12-Sep-14, Location 8
Remove Culvert & Marker, 18" HDP
Grade To Daylight, Roadway Excavation
Shoulder Backing
Clearing & Grubbing, Install Marker
18-Sep-14, Location 9
Remove Culvert & Marker, 1
Grade To Daylight, Roadwa
Shoulder Backing
Clearing & Grubbing, Install Marker
22-Sep-14, Punch List
PunchList
03-4M1804 - Culvert Rehabilitation In Glenn County
26-Jun-14 23:18
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 2
CPM Schedule Provided By: Pushpa Services