BUILDING CONSTRUCTION 1 [ARC 1523]

Assignment 1: Construction Activities and Process





Tan Foo Wong (0310004)

Week 1









Construction Activity 1: Site Preparation
Duration: 7 Days
Materials:
Equipment: Measuring Tools, Shovel, Construction carts, Construction Use Rubbish Bin, hammer
Skilled worker: General Worker (5)
Technical information: Clear up and checking the soil conditional of site








Week 2



Construction Activity 1: Site Preparation
Duration: 7 Days
Materials:
Equipment: Measuring Tools, Shovel, Construction carts, Construction Use Rubbish Bin, hammer
Skilled worker: General Worker (5)
Technical information: set up the temporary site office, determine the exact boundaries for metal deck
fence
Construction Activity 2: Setting Up for foundation construction
Duration: 7 Days
Materials:
Equipment: Marking Tools, Measuring Tools
Skilled worker: General Worker (2), Site Supervisors, Architect, Contractor
Technical information: Determine and marking the piling location



Week 3

Construction Activity 2: Foundation Construction (Grid 8 to 10)
Duration: 7 Days
Materials: Pre Cast Concrete Pile
Equipment: hydraulic piling machine
Skilled worker: General Worker (4), Machine Driver (1)
Technical information: Concrete Pile extends downward deep into the soil.

Week 4







Construction Activity 1: Foundation Construction Grid 11 to 14
Duration: 7 Days
Materials: Pre Cast Concrete Pile
Equipment: hydraulic piling machine
Skilled worker: General Worker (4), Machine Driver (1)
Technical information: Concrete Pile extends downward deep into the soil.
Week 5










Construction Activity 2: Foundation Construction
Duration: 7 Days
Materials: Pre Cast Concrete Pile Cap
Equipment: Concrete, Crane
Skilled worker: General Worker (4), Crane Driver (1)
Technical information: Pile Cap connect to the pile

Week 6


Construction Activity 1: Ground Beam (Grid 8 to 11)
Duration: 7 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw
Skilled worker: Carpenter (2), bar bender (2), general worker (1)
Technical information:
Construction Activity 2: Stump from pile caps
Duration: 7 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw
Skilled worker: Carpenter (2), bar bender (2), general worker (1)
Technical information:

Week 7






Construction Activity 1: Ground Beam (Grid 11 to 14)
Duration: 7 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw
Skilled worker: Carpenter (2), bar bender (2), general worker (1)
Technical information: ground beam connected to stumps

Construction Activity 2: Ground Floor Slab (Preparation)
Duration: 7 Days
Materials: Sand, Aggregate, Hard core, BRC mesh
Equipment: Plate vibrator (1), Excavator (1)
Skilled worker: Excavator Driver (1), general worker (3)
Technical information: Preparation before pour concrete

Week 8

Construction Activity 1: Ground Floor Slab (Pour Concrete)
Duration: 7 Days
Materials: Concrete Grade 30
Equipment: Concrete vibrator (2), Alloy Concrete
Skilled worker: general worker (6)
Technical information: Suspended Concrete Slab on top of ground beam

Construction Activity 2: Footing
Duration: 3 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw
Skilled worker: Carpenter (2), bar bender (2), general worker (2)
Technical information: For Car Porch Column








Week 9
Construction Activity 1: Ground Floor Slab (Pour Concrete)
Duration: 7 Days
Materials: Concrete Grade 30
Equipment: Concrete vibrator (2), Alloy Concrete
Skilled worker: general worker (6)
Technical information: Suspended Concrete Slab on top of ground beam


Week 10


Construction Activity 2: Column (Grid 8 to 11)
Duration: 7 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw
Skilled worker: Carpenter (2), bar bender (2), general worker (1)
Technical information: The Ground Floor Column is connected to Stump and start create form for
column (Grid 8 to 11) within 3 day and pour in the concrete grade 30.













Week 11







Construction Activity 1: Ground Floor Column (Grid 11 to 14)
Duration: 7 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw
Skilled worker: Carpenter (2), bar bender (2), general worker (1)
Technical information: Remove the Column Formwork (Grid 8 to 10), and use it at column (Grid 11 to
14)

Week 12






Construction Activity 1: First Floor Beam + First Floor Slab Formwork
Duration: 7 days
Materials: BRC, Reinforcement, Timber Plywood
Equipment: bar bending machine (1), table saw, Scaffolding (20 Set)
Skilled worker: Carpenter (3), bar bender (2), general worker (4)
Technical information: Scaffolding provide a temporary walkway on first floor, create timber wood
form for first floor slab and beam
Week 13

Construction Activity 1: First Floor Beam + First Floor Slab Form Work
Duration: 7 days
Materials: BRC, Reinforcement, Timber Plywood
Equipment: bar bending machine (1), table saw, Scaffolding (20 Set)
Skilled worker: Carpenter (3), bar bender (3), general worker (5)
Technical information: Put the BRC as reinforcement concrete


Construction Activity 2: Plumbing and Electrical Work
Duration: 7 Days
Materials: PVC Pipe, electric item
Equipment:
Skilled worker: Electrical and Plumbing specified worker (3)
Technical information: Pipe need to put inside the slab in order to create pathway for electrical
wiring
Week 14


Construction Activity 1: First Floor Slab + First Floor Beam (Concrete)
Duration: 7 Days
Materials: Concrete Grade 30, Concrete vibrator (1), Alloy Concrete, Crane
Equipment: Concrete vibrator (2), Alloy Concrete, Crane, Scaffolding with stair (5 Set)
Skilled worker: general worker (5), Crane and alloy driver
Technical information: Suspended Concrete Slab on top of first floor beam and column, take one
week to complete the slab and remove the formwork



Week 15
Construction Activity 1: First Floor Slab + First Floor Beam (Concrete)
Duration: 7 Days
Materials: Concrete Grade 30, Concrete vibrator (1), Alloy Concrete, Crane
Equipment: Concrete vibrator (2), Alloy Concrete, Crane, Scaffolding with stair (5 Set)
Skilled worker: general worker (5), Crane and alloy driver
Technical information: Suspended Concrete Slab on top of first floor beam and column, take one
week to complete the slab and remove the formwork








Week 16








Construction Activity 1: Second floor Column (Grid 8 to 10)
Duration: 7 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw, Scaffolding with stair (5 Set)
Skilled worker: Carpenter (2), bar bender (2), general worker (2)
Technical information: First floor column is connected to ground floor column

Week 17







Construction Activity 1: Second floor Column (Grid 11 to 14)
Duration: 7 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw, Scaffolding with stair (5 Set)
Skilled worker: Carpenter (2), bar bender (2), general worker (2)
Technical information: Remove the Column Formwork (Grid 8 to 10), and use it at column (Grid 11 to
14)
Week 18
Construction Activity 1: Second Floor Beam + Second Floor Slab Form Work
Duration: 7 days
Materials: BRC, Reinforcement, Timber Plywood
Equipment: bar bending machine (1), table saw, Scaffolding (20 Set)
Skilled worker: Carpenter (3), bar bender (2), general worker (4)
Technical information: Scaffolding provide a temporary walkway on second floor




















Week 19

Construction Activity 1: Second Floor Beam + Second Floor Slab Form Work
Duration: 7 days
Materials: BRC, Reinforcement, Timber Plywood
Equipment: bar bending machine (1), table saw, Scaffolding (20 Set)
Skilled worker: Carpenter (3), bar bender (2), general worker (4)
Technical information: Scaffolding provide a temporary walkway on second floor

Construction Activity 2: Plumbing and Electrical Work
Duration: 7 Days
Materials: PVC Pipe, electric item
Equipment:
Skilled worker: Electrical and Plumbing specified worker (4)
Technical information: Pipe need to put inside the slab













Week 20



Construction Activity 1: Second Floor Slab + Second Floor Beam (Concrete)
Duration: 7 Days
Materials: Concrete Grade 30, Concrete vibrator (1), Alloy Concrete, Crane
Equipment: Concrete vibrator (2), Alloy Concrete, Crane
Skilled worker: general worker (5), Crane and alloy driver
Technical information: Suspended Concrete Slab on top of first floor beam














Week 21








Construction Activity 1: Third Floor Column
Duration: 7 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw
Skilled worker: Carpenter (2), bar bender (2), general worker (1)
Technical information: Third floor column is connected to second floor column

Week 22

Construction Activity 1: Third Floor Beam
Duration: 7 days
Materials: timber formwork, Reinforcement,
Equipment: bar bending machine (1), table saw
Skilled worker: Carpenter (3), bar bender (2), general worker (2)
Technical information:
Week 23
Construction Activity 1: Staircase Formwork
Duration: 7 days
Materials: timber formwork, Reinforcement, Timber Formwork
Equipment: bar bending machine (1), table saw
Skilled worker: Carpenter (3), bar bender (2), general worker (2)
Technical information: Create form for the staircase from ground floor to third floor
Construction Activity 2: Door Frame Installation (Ground Floor
Duration: 7 days
Materials: timber,
Equipment: table saw, Hammer, Levelling Ruler, and Measurement Tape
Skilled worker: Door Worker (2), general worker (2)
Technical information: To Install the Door Frame according to the layout plan.
Construction Activity 3: Brickwork (Grid 7)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water,
Equipment: Brick Hammer (1) , Masonry Brushes(3), Rose Brick Trowels(3),Sled Runners(3)
Carts(3)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.
Week 24
Construction Activity 1: Brickwork (Grid 8 to 9a)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins,
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.

Construction Activity 2: Staircase Formwork (First Floor to Second Floor)
Duration: 7 days
Materials: timber formwork, Reinforcement, Timber Formwork
Equipment: bar bending machine (1), table saw
Skilled worker: Carpenter (3), bar bender (2), general worker (2)
Technical information: Create form for the staircase from ground floor to third floor


Week 25

Construction Activity 1: Brickwork (Grid 9a to 14)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins,
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.

Construction Activity 2: Staircase (Concrete- Ground Floor to First Floor)
Duration: 7 days
Materials: Concrete Grade 30, Concrete vibrator (1), Alloy Concrete, Crane
Equipment: Concrete vibrator (2), Alloy Concrete, Crane
Skilled worker: general worker (5), Crane and alloy driver
Technical information: Staircase reinforcement Connected to first floor slab





Week 26



Construction Activity 1: Brickwork
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins,
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.
Week 27

Construction Activity 1: First Floor Brickwork (Grid 7)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins,
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3), Scaffolding ( 20 set)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.

Construction Activity 2: Staircase (Concrete- First Floor to Second Floor)
Duration: 7 days
Materials: Concrete Grade 30, Concrete vibrator (1), Alloy Concrete, Crane
Equipment: Concrete vibrator (2), Alloy Concrete, Crane
Skilled worker: general worker (5), Crane and alloy driver
Technical information: Staircase reinforcement Connected to first floor slab
Week 28

Construction Activity 1: First Floor Brickwork (Grid 12 14, Grid 5)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins,
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3), Scaffolding (20 set)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.

Week 29

Construction Activity 1: First Floor Brickwork (Grid 2)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins,
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3), Scaffolding (20 set)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.

Week 30

Construction Activity 1: First Floor Brickwork (Interior)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins,
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3), Scaffolding (20 set)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.

Week 31

Construction Activity 1: Second Floor Brickwork (Grid 5, 6, 7)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3), Scaffolding (20 set)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.


Week 32

Construction Activity 1: Second Floor Brickwork (Grid 2)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3), Scaffolding (20 set)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.

Week 33

Construction Activity 1: Second Floor Brickwork (Grid 2)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3), Scaffolding (20 set)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.

Week 34

Construction Activity 1: Roof Truss Installation
Duration: 7 days
Materials: Light Weight Steel
Equipment: Hammer (3), Circular saws (1), Cordless (3), Stair,
Skilled worker: General Workers (2), Roof Truss worker (3)
Technical information: On Site measure and custom make the truss for roof installation. Trusses sit
on top of the second floor beam and put into the brick wall

Construction Activity 2: Plasterwork (Exterior Wall)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), plastering sponge (3)
Skilled worker: General Workers (2), Plastering Worker (3)
Technical information:


Week 35

Construction Activity 1: Plasterwork (Exterior Wall)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Long Float (3), plastering sponge (3)
Skilled worker: General Workers (2), Plastering Worker (3)
Technical information:

Construction Activity 2: Roof Metal Deck Installation
Duration: 7 days
Materials: Structural Metal Roof Deck, G.I Gutter
Equipment: Hammer (3), Circular saws (1), Cordless (4), Stair,
Skilled worker: General Workers (2), Roof Worker (4)
Technical information:


Week 36

Construction Activity 1: Plasterwork (Exterior Wall)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Long Float (3), plastering sponge (3)
Skilled worker: General Workers (2), Plastering Worker (3)
Technical information:
Construction Activity 2: Third Floor Brickwork (Cover up the roof truss)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3), Scaffolding (20 set)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.

Week 37

Construction Activity 1: Plasterwork (Exterior Wall-
Ground floor Finish)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic
Float (3), Long Float (3), plastering sponge (5)
Skilled worker: General Workers (2), Plastering
Worker (3)
Technical information:




Construction Activity 2: Third Floor Brickwork (Cover up the roof truss)
Duration: 7 days
Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins
Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3)
Carts (3), Scaffolding (20 set)
Skilled worker: General Workers (3), Brick worker (3)
Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for
brick worker.


Week 38

Construction Activity 1: Plasterwork (Exterior Wall-First floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (20 Set), Long Float (5),
plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information:
Construction Activity 2: Plasterwork (interior Wall-Ground floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (2 Set), Long Float (5),
plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (4)
Technical information:
Week 39

Construction Activity 1: Plasterwork (Exterior Wall-First floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (20 Set), Long Float (5),
plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Construction Activity 2: Plasterwork (interior Wall-Ground floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (2 Set), Long Float (4),
plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (4)
Technical information:
Week 40

Construction Activity 1: Plasterwork (Exterior Wall-First floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (20 Set), Long Float (5)
plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information:

Construction Activity 2: Plasterwork (interior Wall-Ground floor Finish)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (2 Set), Long Float (5)
plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (4)
Technical information:
Week 41

Construction Activity 1: Plasterwork (Exterior Wall-First floor Finish)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (20 Set), Long Float (5),
plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information:




Week 42

Construction Activity 1: Plasterwork (Exterior Wall-Second Floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (50 Set), Long Float (5),
plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information:
Construction Activity 2: Plasterwork (interior Wall-First floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (2 Set), plastering sponge (3)
Skilled worker: General Workers (2), Plastering Worker (4)
Technical information:

Week 43

Construction Activity 1: Plasterwork (Exterior Wall-Second Floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (50 Set), Long Float (5), Long
Float (5), plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information:

Construction Activity 2: Plasterwork (interior Wall-First floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (2 Set), Long Float (5), Long
Float (5), plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (4)
Technical information:
Week 44
Construction Activity 1: Plasterwork (Exterior Wall-Second Floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (50 Set), Long Float (5), Long
Float (5), plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information:

Construction Activity 2: Plasterwork (interior Wall-First floor Finish)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (2 Set), Long Float (5), Long
Float (5), plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information:


Week 45


Construction Activity 1: Plasterwork (Exterior Wall and Interior-Second Floor)
Duration: 7 days
Materials: Sand, Cement, Water, Lime
Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (50 Set), Long Float (5), Long
Float (5), plastering sponge (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information:

Construction Activity 2: Skim Coating (Interior Wall- Ground Floor)
Duration: 7 days
Materials: Joint Compound
Equipment: Mud Pan (5), Taping Knife (5), Sander (5), Putty Knife (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information: Skim coating is the process of applying a layer of muddy plaster compound to
rough or damaged walls to either smooth or repair them



Week 46

Construction Activity 1: Wall Painting (Ground Floor emulsion paint)
Duration: 7 days
Materials: emulsion paint
Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set)
Skilled worker: Painting Worker (5)
Technical information: To Provide basic protection to the plastering layer and enhance the Paint
effect.

Construction Activity 2: Skim Coating (Interior Wall- First Floor)
Duration: 7 days
Materials: Joint Compound
Equipment: Mud Pan (5), Taping Knife (5), Sander (5), Putty Knife (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information: Skim coating is the process of applying a layer of muddy plaster compound to
rough or damaged walls to either smooth or repair them



Week 47

Construction Activity 1: Wall Painting (First Floor - emulsion paint)
Duration: 7 days
Materials: emulsion paint
Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set)
Skilled worker: Painting Worker (5)
Technical information: To Provide basic protection to the plastering layer and enhance the Paint
effect.

Construction Activity 2: Skim Coating (Interior Wall- Second Floor)
Duration: 7 days
Materials: Joint Compound
Equipment: Mud Pan (5), Taping Knife (5), Sander (5), Putty Knife (5)
Skilled worker: General Workers (2), Plastering Worker (5)
Technical information: Skim coating is the process of applying a layer of muddy plaster compound to
rough or damaged walls to either smooth or repair them



Week 48

Construction Activity 1: Wall Painting (Second Floor -
emulsion paint)
Duration: 7 days
Materials: emulsion paint
Equipment: Roller (3), Brush (3), Extension Stick (3),
Scaffolding (3 Set)
Skilled worker: Painting Worker (5)
Technical information: To Provide basic protection to the
plastering layer and enhance the Paint effect.

Construction Activity 2: Door Installation
Duration: 7 days
Materials: Door, nails, Sliding Door with Tempered Glass
Equipment: Hammer (2), Circular Saw (1), Levelling Ruler (2),
Measuring Tape (2), Cordless (3)
Skilled worker: General Worker (1), Door Installer (2)







Construction Activity 3: Window Installation
Duration: 7 days
Materials: Aluminium Window with Tempered Glass, nails,
Equipment: Hammer (2), Cordless (3), Levelling Ruler (2), Measuring Tape (2)
Skilled worker: General Worker (1), Window Installer (2)

Week 49

Construction Activity 1: Wall Painting (Top Coating)
Duration: 7 days
Materials: emulsion paint
Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set)
Skilled worker: Painting Worker (10)
Technical information: To Provide basic protection to the plastering layer and enhance the Paint
effect.
Construction Activity 2: Window Installation
(Second Floor)
Duration: 7 days
Materials: Aluminium Window with Tempered
Glass, nails,
Equipment: Hammer (2), Cordless (3), Levelling
Ruler (2), Measuring Tape (2)
Skilled worker: General Worker (1), Window
Installer (2)

Construction Activity 3: Door Installation (Second Floor and Third Floor)
Duration: 7 days
Materials: Door, nails, Sliding Door with Tempered Glass
Equipment: Hammer (2), Circular Saw (1), Levelling Ruler (2), Measuring Tape (2), Cordless (3)
Skilled worker: General Worker (1), Door Installer (2)
Week 50

Construction Activity 1: Wall Painting (Top Coating)
Duration: 7 days
Materials: emulsion paint
Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set)
Skilled worker: Painting Worker (10)
Technical information: To Provide basic protection to the plastering layer and enhance the Paint
effect.

Construction Activity 2: Louvers installation
Duration: 7 days
Materials: Aluminium Louvers, Wood Louvers, Nails
Equipment: Hammer (2), Measuring Tape (2), Cordless (3)
Skilled worker: General Worker (1), Louvers Installer (2)









Week 51
Construction Activity 1: Staircase Hander Installation
Duration: 7 days
Materials: Aluminium
Equipment: Hammer, Nail
Skilled worker: General Worker (1), Glass Installer (2)

Construction Activity 2: Glass Fence Installation
Duration: 7 days
Materials: Tempered Glass
Equipment: Grove, Silicon
Skilled worker: General Worker (1), Glass Installer (2)







Week 52

Construction Activity 2: Painting - Final Touch Up
Material: Paint
Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set)
Duration: 7 days
Skilled worker: Paint Worker (2)