Construction Activity 1: Site Preparation Duration: 7 Days Materials: Equipment: Measuring Tools, Shovel, Construction carts, Construction Use Rubbish Bin, hammer Skilled worker: General Worker (5) Technical information: Clear up and checking the soil conditional of site
Week 2
Construction Activity 1: Site Preparation Duration: 7 Days Materials: Equipment: Measuring Tools, Shovel, Construction carts, Construction Use Rubbish Bin, hammer Skilled worker: General Worker (5) Technical information: set up the temporary site office, determine the exact boundaries for metal deck fence Construction Activity 2: Setting Up for foundation construction Duration: 7 Days Materials: Equipment: Marking Tools, Measuring Tools Skilled worker: General Worker (2), Site Supervisors, Architect, Contractor Technical information: Determine and marking the piling location
Week 3
Construction Activity 2: Foundation Construction (Grid 8 to 10) Duration: 7 Days Materials: Pre Cast Concrete Pile Equipment: hydraulic piling machine Skilled worker: General Worker (4), Machine Driver (1) Technical information: Concrete Pile extends downward deep into the soil.
Week 4
Construction Activity 1: Foundation Construction Grid 11 to 14 Duration: 7 Days Materials: Pre Cast Concrete Pile Equipment: hydraulic piling machine Skilled worker: General Worker (4), Machine Driver (1) Technical information: Concrete Pile extends downward deep into the soil. Week 5
Construction Activity 2: Foundation Construction Duration: 7 Days Materials: Pre Cast Concrete Pile Cap Equipment: Concrete, Crane Skilled worker: General Worker (4), Crane Driver (1) Technical information: Pile Cap connect to the pile
Week 6
Construction Activity 1: Ground Beam (Grid 8 to 11) Duration: 7 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1), bar bending machine (1), table saw Skilled worker: Carpenter (2), bar bender (2), general worker (1) Technical information: Construction Activity 2: Stump from pile caps Duration: 7 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1), bar bending machine (1), table saw Skilled worker: Carpenter (2), bar bender (2), general worker (1) Technical information:
Week 7
Construction Activity 1: Ground Beam (Grid 11 to 14) Duration: 7 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1), bar bending machine (1), table saw Skilled worker: Carpenter (2), bar bender (2), general worker (1) Technical information: ground beam connected to stumps
Construction Activity 2: Ground Floor Slab (Preparation) Duration: 7 Days Materials: Sand, Aggregate, Hard core, BRC mesh Equipment: Plate vibrator (1), Excavator (1) Skilled worker: Excavator Driver (1), general worker (3) Technical information: Preparation before pour concrete
Week 8
Construction Activity 1: Ground Floor Slab (Pour Concrete) Duration: 7 Days Materials: Concrete Grade 30 Equipment: Concrete vibrator (2), Alloy Concrete Skilled worker: general worker (6) Technical information: Suspended Concrete Slab on top of ground beam
Construction Activity 2: Footing Duration: 3 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1), bar bending machine (1), table saw Skilled worker: Carpenter (2), bar bender (2), general worker (2) Technical information: For Car Porch Column
Week 9 Construction Activity 1: Ground Floor Slab (Pour Concrete) Duration: 7 Days Materials: Concrete Grade 30 Equipment: Concrete vibrator (2), Alloy Concrete Skilled worker: general worker (6) Technical information: Suspended Concrete Slab on top of ground beam
Week 10
Construction Activity 2: Column (Grid 8 to 11) Duration: 7 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1), bar bending machine (1), table saw Skilled worker: Carpenter (2), bar bender (2), general worker (1) Technical information: The Ground Floor Column is connected to Stump and start create form for column (Grid 8 to 11) within 3 day and pour in the concrete grade 30.
Week 11
Construction Activity 1: Ground Floor Column (Grid 11 to 14) Duration: 7 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1), bar bending machine (1), table saw Skilled worker: Carpenter (2), bar bender (2), general worker (1) Technical information: Remove the Column Formwork (Grid 8 to 10), and use it at column (Grid 11 to 14)
Week 12
Construction Activity 1: First Floor Beam + First Floor Slab Formwork Duration: 7 days Materials: BRC, Reinforcement, Timber Plywood Equipment: bar bending machine (1), table saw, Scaffolding (20 Set) Skilled worker: Carpenter (3), bar bender (2), general worker (4) Technical information: Scaffolding provide a temporary walkway on first floor, create timber wood form for first floor slab and beam Week 13
Construction Activity 1: First Floor Beam + First Floor Slab Form Work Duration: 7 days Materials: BRC, Reinforcement, Timber Plywood Equipment: bar bending machine (1), table saw, Scaffolding (20 Set) Skilled worker: Carpenter (3), bar bender (3), general worker (5) Technical information: Put the BRC as reinforcement concrete
Construction Activity 2: Plumbing and Electrical Work Duration: 7 Days Materials: PVC Pipe, electric item Equipment: Skilled worker: Electrical and Plumbing specified worker (3) Technical information: Pipe need to put inside the slab in order to create pathway for electrical wiring Week 14
Construction Activity 1: First Floor Slab + First Floor Beam (Concrete) Duration: 7 Days Materials: Concrete Grade 30, Concrete vibrator (1), Alloy Concrete, Crane Equipment: Concrete vibrator (2), Alloy Concrete, Crane, Scaffolding with stair (5 Set) Skilled worker: general worker (5), Crane and alloy driver Technical information: Suspended Concrete Slab on top of first floor beam and column, take one week to complete the slab and remove the formwork
Week 15 Construction Activity 1: First Floor Slab + First Floor Beam (Concrete) Duration: 7 Days Materials: Concrete Grade 30, Concrete vibrator (1), Alloy Concrete, Crane Equipment: Concrete vibrator (2), Alloy Concrete, Crane, Scaffolding with stair (5 Set) Skilled worker: general worker (5), Crane and alloy driver Technical information: Suspended Concrete Slab on top of first floor beam and column, take one week to complete the slab and remove the formwork
Week 16
Construction Activity 1: Second floor Column (Grid 8 to 10) Duration: 7 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1), bar bending machine (1), table saw, Scaffolding with stair (5 Set) Skilled worker: Carpenter (2), bar bender (2), general worker (2) Technical information: First floor column is connected to ground floor column
Week 17
Construction Activity 1: Second floor Column (Grid 11 to 14) Duration: 7 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1), bar bending machine (1), table saw, Scaffolding with stair (5 Set) Skilled worker: Carpenter (2), bar bender (2), general worker (2) Technical information: Remove the Column Formwork (Grid 8 to 10), and use it at column (Grid 11 to 14) Week 18 Construction Activity 1: Second Floor Beam + Second Floor Slab Form Work Duration: 7 days Materials: BRC, Reinforcement, Timber Plywood Equipment: bar bending machine (1), table saw, Scaffolding (20 Set) Skilled worker: Carpenter (3), bar bender (2), general worker (4) Technical information: Scaffolding provide a temporary walkway on second floor
Week 19
Construction Activity 1: Second Floor Beam + Second Floor Slab Form Work Duration: 7 days Materials: BRC, Reinforcement, Timber Plywood Equipment: bar bending machine (1), table saw, Scaffolding (20 Set) Skilled worker: Carpenter (3), bar bender (2), general worker (4) Technical information: Scaffolding provide a temporary walkway on second floor
Construction Activity 2: Plumbing and Electrical Work Duration: 7 Days Materials: PVC Pipe, electric item Equipment: Skilled worker: Electrical and Plumbing specified worker (4) Technical information: Pipe need to put inside the slab
Week 20
Construction Activity 1: Second Floor Slab + Second Floor Beam (Concrete) Duration: 7 Days Materials: Concrete Grade 30, Concrete vibrator (1), Alloy Concrete, Crane Equipment: Concrete vibrator (2), Alloy Concrete, Crane Skilled worker: general worker (5), Crane and alloy driver Technical information: Suspended Concrete Slab on top of first floor beam
Week 21
Construction Activity 1: Third Floor Column Duration: 7 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete vibrator (1), bar bending machine (1), table saw Skilled worker: Carpenter (2), bar bender (2), general worker (1) Technical information: Third floor column is connected to second floor column
Week 22
Construction Activity 1: Third Floor Beam Duration: 7 days Materials: timber formwork, Reinforcement, Equipment: bar bending machine (1), table saw Skilled worker: Carpenter (3), bar bender (2), general worker (2) Technical information: Week 23 Construction Activity 1: Staircase Formwork Duration: 7 days Materials: timber formwork, Reinforcement, Timber Formwork Equipment: bar bending machine (1), table saw Skilled worker: Carpenter (3), bar bender (2), general worker (2) Technical information: Create form for the staircase from ground floor to third floor Construction Activity 2: Door Frame Installation (Ground Floor Duration: 7 days Materials: timber, Equipment: table saw, Hammer, Levelling Ruler, and Measurement Tape Skilled worker: Door Worker (2), general worker (2) Technical information: To Install the Door Frame according to the layout plan. Construction Activity 3: Brickwork (Grid 7) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Equipment: Brick Hammer (1) , Masonry Brushes(3), Rose Brick Trowels(3),Sled Runners(3) Carts(3) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker. Week 24 Construction Activity 1: Brickwork (Grid 8 to 9a) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins, Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Construction Activity 2: Staircase Formwork (First Floor to Second Floor) Duration: 7 days Materials: timber formwork, Reinforcement, Timber Formwork Equipment: bar bending machine (1), table saw Skilled worker: Carpenter (3), bar bender (2), general worker (2) Technical information: Create form for the staircase from ground floor to third floor
Week 25
Construction Activity 1: Brickwork (Grid 9a to 14) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins, Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Construction Activity 2: Staircase (Concrete- Ground Floor to First Floor) Duration: 7 days Materials: Concrete Grade 30, Concrete vibrator (1), Alloy Concrete, Crane Equipment: Concrete vibrator (2), Alloy Concrete, Crane Skilled worker: general worker (5), Crane and alloy driver Technical information: Staircase reinforcement Connected to first floor slab
Week 26
Construction Activity 1: Brickwork Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins, Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker. Week 27
Construction Activity 1: First Floor Brickwork (Grid 7) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins, Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3), Scaffolding ( 20 set) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Construction Activity 2: Staircase (Concrete- First Floor to Second Floor) Duration: 7 days Materials: Concrete Grade 30, Concrete vibrator (1), Alloy Concrete, Crane Equipment: Concrete vibrator (2), Alloy Concrete, Crane Skilled worker: general worker (5), Crane and alloy driver Technical information: Staircase reinforcement Connected to first floor slab Week 28
Construction Activity 1: First Floor Brickwork (Grid 12 14, Grid 5) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins, Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3), Scaffolding (20 set) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Week 29
Construction Activity 1: First Floor Brickwork (Grid 2) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins, Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3), Scaffolding (20 set) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Week 30
Construction Activity 1: First Floor Brickwork (Interior) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins, Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3), Scaffolding (20 set) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Week 31
Construction Activity 1: Second Floor Brickwork (Grid 5, 6, 7) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3), Scaffolding (20 set) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Week 32
Construction Activity 1: Second Floor Brickwork (Grid 2) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3), Scaffolding (20 set) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Week 33
Construction Activity 1: Second Floor Brickwork (Grid 2) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3), Scaffolding (20 set) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Week 34
Construction Activity 1: Roof Truss Installation Duration: 7 days Materials: Light Weight Steel Equipment: Hammer (3), Circular saws (1), Cordless (3), Stair, Skilled worker: General Workers (2), Roof Truss worker (3) Technical information: On Site measure and custom make the truss for roof installation. Trusses sit on top of the second floor beam and put into the brick wall
Construction Activity 1: Plasterwork (Exterior Wall) Duration: 7 days Materials: Sand, Cement, Water, Lime Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Long Float (3), plastering sponge (3) Skilled worker: General Workers (2), Plastering Worker (3) Technical information:
Construction Activity 2: Roof Metal Deck Installation Duration: 7 days Materials: Structural Metal Roof Deck, G.I Gutter Equipment: Hammer (3), Circular saws (1), Cordless (4), Stair, Skilled worker: General Workers (2), Roof Worker (4) Technical information:
Week 36
Construction Activity 1: Plasterwork (Exterior Wall) Duration: 7 days Materials: Sand, Cement, Water, Lime Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Long Float (3), plastering sponge (3) Skilled worker: General Workers (2), Plastering Worker (3) Technical information: Construction Activity 2: Third Floor Brickwork (Cover up the roof truss) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3), Scaffolding (20 set) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Construction Activity 2: Third Floor Brickwork (Cover up the roof truss) Duration: 7 days Materials: Red Brick, Sand, Cement, Water, Steel Bar, Line and Pins Equipment: Brick Hammer (1), Masonry Brushes (3), Rose Brick Trowels (3), Sled Runners (3) Carts (3), Scaffolding (20 set) Skilled worker: General Workers (3), Brick worker (3) Technical information: General worker to mix up the 3:2,1 sand, cement, water to create mortar for brick worker.
Construction Activity 1: Plasterwork (Exterior Wall-Second Floor) Duration: 7 days Materials: Sand, Cement, Water, Lime Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (50 Set), Long Float (5), Long Float (5), plastering sponge (5) Skilled worker: General Workers (2), Plastering Worker (5) Technical information:
Construction Activity 2: Plasterwork (interior Wall-First floor) Duration: 7 days Materials: Sand, Cement, Water, Lime Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (2 Set), Long Float (5), Long Float (5), plastering sponge (5) Skilled worker: General Workers (2), Plastering Worker (4) Technical information: Week 44 Construction Activity 1: Plasterwork (Exterior Wall-Second Floor) Duration: 7 days Materials: Sand, Cement, Water, Lime Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (50 Set), Long Float (5), Long Float (5), plastering sponge (5) Skilled worker: General Workers (2), Plastering Worker (5) Technical information:
Construction Activity 2: Plasterwork (interior Wall-First floor Finish) Duration: 7 days Materials: Sand, Cement, Water, Lime Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (2 Set), Long Float (5), Long Float (5), plastering sponge (5) Skilled worker: General Workers (2), Plastering Worker (5) Technical information:
Week 45
Construction Activity 1: Plasterwork (Exterior Wall and Interior-Second Floor) Duration: 7 days Materials: Sand, Cement, Water, Lime Equipment: Plastering trowel (3), Hawk (3), Plastic Float (3), Scaffolding (50 Set), Long Float (5), Long Float (5), plastering sponge (5) Skilled worker: General Workers (2), Plastering Worker (5) Technical information:
Construction Activity 2: Skim Coating (Interior Wall- Ground Floor) Duration: 7 days Materials: Joint Compound Equipment: Mud Pan (5), Taping Knife (5), Sander (5), Putty Knife (5) Skilled worker: General Workers (2), Plastering Worker (5) Technical information: Skim coating is the process of applying a layer of muddy plaster compound to rough or damaged walls to either smooth or repair them
Week 46
Construction Activity 1: Wall Painting (Ground Floor emulsion paint) Duration: 7 days Materials: emulsion paint Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set) Skilled worker: Painting Worker (5) Technical information: To Provide basic protection to the plastering layer and enhance the Paint effect.
Construction Activity 2: Skim Coating (Interior Wall- First Floor) Duration: 7 days Materials: Joint Compound Equipment: Mud Pan (5), Taping Knife (5), Sander (5), Putty Knife (5) Skilled worker: General Workers (2), Plastering Worker (5) Technical information: Skim coating is the process of applying a layer of muddy plaster compound to rough or damaged walls to either smooth or repair them
Week 47
Construction Activity 1: Wall Painting (First Floor - emulsion paint) Duration: 7 days Materials: emulsion paint Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set) Skilled worker: Painting Worker (5) Technical information: To Provide basic protection to the plastering layer and enhance the Paint effect.
Construction Activity 2: Skim Coating (Interior Wall- Second Floor) Duration: 7 days Materials: Joint Compound Equipment: Mud Pan (5), Taping Knife (5), Sander (5), Putty Knife (5) Skilled worker: General Workers (2), Plastering Worker (5) Technical information: Skim coating is the process of applying a layer of muddy plaster compound to rough or damaged walls to either smooth or repair them
Week 48
Construction Activity 1: Wall Painting (Second Floor - emulsion paint) Duration: 7 days Materials: emulsion paint Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set) Skilled worker: Painting Worker (5) Technical information: To Provide basic protection to the plastering layer and enhance the Paint effect.
Construction Activity 2: Door Installation Duration: 7 days Materials: Door, nails, Sliding Door with Tempered Glass Equipment: Hammer (2), Circular Saw (1), Levelling Ruler (2), Measuring Tape (2), Cordless (3) Skilled worker: General Worker (1), Door Installer (2)
Construction Activity 3: Window Installation Duration: 7 days Materials: Aluminium Window with Tempered Glass, nails, Equipment: Hammer (2), Cordless (3), Levelling Ruler (2), Measuring Tape (2) Skilled worker: General Worker (1), Window Installer (2)
Week 49
Construction Activity 1: Wall Painting (Top Coating) Duration: 7 days Materials: emulsion paint Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set) Skilled worker: Painting Worker (10) Technical information: To Provide basic protection to the plastering layer and enhance the Paint effect. Construction Activity 2: Window Installation (Second Floor) Duration: 7 days Materials: Aluminium Window with Tempered Glass, nails, Equipment: Hammer (2), Cordless (3), Levelling Ruler (2), Measuring Tape (2) Skilled worker: General Worker (1), Window Installer (2)
Construction Activity 3: Door Installation (Second Floor and Third Floor) Duration: 7 days Materials: Door, nails, Sliding Door with Tempered Glass Equipment: Hammer (2), Circular Saw (1), Levelling Ruler (2), Measuring Tape (2), Cordless (3) Skilled worker: General Worker (1), Door Installer (2) Week 50
Construction Activity 1: Wall Painting (Top Coating) Duration: 7 days Materials: emulsion paint Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set) Skilled worker: Painting Worker (10) Technical information: To Provide basic protection to the plastering layer and enhance the Paint effect.
Construction Activity 2: Louvers installation Duration: 7 days Materials: Aluminium Louvers, Wood Louvers, Nails Equipment: Hammer (2), Measuring Tape (2), Cordless (3) Skilled worker: General Worker (1), Louvers Installer (2)
Week 51 Construction Activity 1: Staircase Hander Installation Duration: 7 days Materials: Aluminium Equipment: Hammer, Nail Skilled worker: General Worker (1), Glass Installer (2)
Construction Activity 2: Glass Fence Installation Duration: 7 days Materials: Tempered Glass Equipment: Grove, Silicon Skilled worker: General Worker (1), Glass Installer (2)
Week 52
Construction Activity 2: Painting - Final Touch Up Material: Paint Equipment: Roller (3), Brush (3), Extension Stick (3), Scaffolding (3 Set) Duration: 7 days Skilled worker: Paint Worker (2)