Professional Documents
Culture Documents
Draft 2
Draft 2
Draft 2
1.1 Background
Canada and the United States. More than 16 million cars, trucks and
per cent of Canada-United States truck trade. In 2001 alone, this two-
and American trade and tourism increase through the years, projected
additional border crossing which will have the capacity to handle the
currently spans across the Detroit River and links up Detroit and Windsor
before a driver can reach the border crossing they need to cross several
street lights within the city core. This causes large traffic jams and
impede on the overall traffic ease of the city. This is why the new border
stages such that the traffic flow matches the facility capacity. Once the
Border Crossing Plaza site. This report will contain two parts: Firstly, a
report .In addition to that the technical report should follow best
management guideline.
The western edge of the proposed site runs along the Detroit River. The
Parkway and Broadway Street. The site measures 54.3 ha. By looking at
existing site terrain inclines towards the South Eastern edge of the
proposed site. At the same time, it is fairly flat; the elevation difference
proposed site borders and area. The calculations and design specifications
will be based on those drawings. The map below was obtained from
Google EarthTM.
Figure 2.1 - Plaza Site Outlined
The 54.3 hectare area to be used for the proposed Canadian Plaza is
and assumed that the entire existing area is cultivated land. The
resulting runoff coefficients for the existing condition are C = 0.34 and
0.47 for 5 year & 100 year storm event respectively.(see table 2.1)
Table 2.1 – Runoff Coefficient for Use in the Rational Method
Character of
Return Period (years)
Surface
Undeveloped 5 100
Cultivated land
0.34 0.47
Flat, 0 – 2%
Developed
The data information was gathered from MNR, DRIC draft environmental
soils including:
materials, granular materials consisting of sand and gravel, sands and silty
metres below ground surface in the clayey silt and silty clay materials. The
silty clay, clayey silt, sand and gravel and sands are considered to be slightly
Michael
3 Stormwater Management Design
Water Quality:
is also connected two major highways. This means that chemical spills
of a later generation and they are made with toxic chemicals such as
asbestos, lead and PCB’s. During a rainfall, theses chemicals can make
their way into the leachate and contaminate the water system i.e: the
Sediment Control:
Water is a highly abrasive medium and with enough time, water will
earth under the roads can compromise the structural integrity of any
and landslides. For the safety of drivers these large driving surfaces
North and the East sides of the site may contain large amounts of
can cause sewers to be filled with sediment and destroy fish habitat in
the river.
Road Safety:
drive on. In addition to that, we want to make sure that during a heavy
100 year rainfall, water is properly diverted from driving surfaces and
3.2 Considerations
Plaza requires quality, quantity and erosion controls for the peak flows
from the Plaza, as the increase in impervious area will increase the
overall peak flows from the site, as well as the overall pollutant
event.
Based on the results and the site conditions, the solutions retained
were storage SWMP’s and oil/grit separators. The storage SWMP’s will
provide quality treatment, erosion control and quantity control for the
the green spaces south of the proposed plaza and a linear open
channel/wetland feature. These green spaces can be converted to
channel. The pond system provides closer outlets for the sewer
flow from one pond to the other. The pond system would control the
with the Plaza, a shut off valve or alternative damming procedure will
From the conceptual report, the BMP’s of our storm water management
system would include ponds and a large channel leading up to the pond.
The quality and quantity pond would be located at the most western
2. Water has a much shorter distance to flow into the Detroit River if
along the southern edge of the site. The channel will be in this
configuration because:
1. The channel will be at the bottom of the site slope in such a way that
excess rainwater is forced to flow towards channel and does not pool
2. It will run along the greatest length of the site, catching a majority of
Water Flow
Detoit River Trend
Wet Pond
does not cause excess rainwater to fall into neighboring properties and
water after construction because the run off coefficient for the soil would
increase. The runoff coefficient of asphalt is 0.90, this means that during
properly.
drainage area that is concerned with. This map was obtained from The
would flow into the site. This area is a critical value in determining the
following section.
Figure 3.03: Outlined drainage area based on rough contour outline
Figure 3.04: Outlined existing drainage area based surrounding drainage
structure on area
Pre-development condition:
that the site is highly flat. The existing elevation difference between the
highest and lowest part of our channel is 2.72m over a 1110m span. The
MOE 2003 storm water management guideline outlines that grass swales are
ideal storm water management structures for flat terrain. Thus the main
entrance to the projected pond entrance along the southern edge of the site.
The elevation data was obtained from the city of Windsor corporation
website.
Design Constraints:
The design constraints of the proposed site are mainly the flatness and
cannot have floors lower than the water tables otherwise they will
The ground water table level is 3m below the surface. Figure 3.06
Figure 3.06: Ground water table is at 173.00m. The MOE 2003 guideline
specifies that a 0.50m clearance is required between the ground water table
and the pond floor. The pond floor is thus at an elevation of 173.50m. The
175.00m elevation was determined as the lowest channel floor elevation since
the pond water surface must be lower than the swale floor. The predevelopment
ground elevations the pond is 176.00m.The current ground conditions at the
swale entrance is 178.72m
Manning’s equation:
the water level of our channel for a 100 year storm. The water elevation
V=kn*R23*S0.5
Q=1.49n*AR23S0.5
Q: 100 year Post Development flow m3/s. For our site area it is
9.3305m3/s
channels
A: MOE 2003 STMWTR Guideline specifies that the swale will need a
A=(B+Zy)y
specifies 6m
Z is defined as the horizontal distance per meter of the side slope MOE
y is the height and water level of the trapezoid for a 100 year storm it is
6m Base (MOE
2003)
R=(B+Zyy/(B+2*y1+Z20.5)^(23)
S: Channel Slope, after optimization the best slope to use given the site
constraints is 0.20%. This is a very minor slope however given the water
table depth, site elevation and resulted channel depth this value is the
most optimal.
Now that all values are define we solve for y in the following equation:
0=B+ZyyB+ZyyB+2*y1+Z20.523-Q*n/(1.49*S0.5)
Due to the fact we will be designing many channel in this project we have
Y100mc(main channel)
Y100mc=0.75m
Y5mc=0.49m
Now we know the drainage depth here are the drainage channel
dimensions:
Figure 3.08: Channel Profile
In this design section we will consider the runoff predicted to enter our
site from neighboring lands. Figure 3.04 and 3.05 demonstrate that there
is a considerable amount of runoff that will find itself onto our site due to
the pre existing drainage pattern. Because we cannot interfere with the
natural drainage pattern this area and so we must let the water pass
standards. So we will simply route the water flow from surrounding sites
In Figure 3.10 we see that the total drainage area has been split into 3
main areas: Our site are, The Major Secondary Drainage Area and the
Minor Drainage
Swale
Major drainage
Culvert (under the
road)
A two-cell facility which separates water quality and erosion control from
quantity control will be discussed in this section. The quality control cell was
designed as an artificial wet pond, and the quantity control cell was designed
as a dry detention area to receive flows only when quality pond filled.
Flood Control
levels for the lands draining to the facility for 5 to 100 year design
Erosion Control
incorporated.
Water Quality
active storage was in addition to that provided for flood and erosion
control.
10
20
30
40
4.1
Runoff Computation
Rational method was used in determining for the peak flows of both
Drainage Area
The drainage area to be used in the design should include all those
areas which will reasonable or naturally drain to the storm system. The
area term in the Rational Method formula represents the total area
tributary under consideration. For this proposed site, the drainage area
Runoff Coefficient
developed flows are C = 0.34 for 5 year event, and C = 0.47 for 100
composite runoff coefficient value of 0.5472 for 5 year and 0.7009 for
Table 3.1 – Drainage Areas, Land Covers and Runoff Coefficients for
Post-development
Runoff Coefficient
Description Area (m2) Area (ha)
5 year 100 year
Under the requirement of City of Windsor, 5-year and 100 year storm
the time required for flow to reach the pond from the most remote part
of the drainage area. Upland method was used for determining the
Tc = L / (3600 * V)
V – velocity (ft/s)
The velocity can be estimated by knowing the land use and the slope
(see Fig. 3.1 ). From the figure, the velocity is estimated to be 2.75 ft/s
intensity duration-frequency curve (IDF curve). The IDF curve used for
mm/hr and 75 mm/hr for 5 year and 100 year storm event respectively.
Figure 3.1 – Intensity Duration-Frequency Curve (IDF Curves) - City
of Windsor
Source: Environment Canada – Atmospheric Environment Services
4.2.1Design Criteria
The rational method was used in the determining pre- and post-
storage volumes.
40
4.1
The tributary area of the pond will be 63.9 hectares of which 33.2
900mm diameter piped splitter storm sewer and via an overland flow
swale. Outlet control will be provided by means of a 650mm orifice
placed within the 875mm outlet pipe. The pond bottom will be graded
events. The pond invert (174.7 m) is above the level of the local water
table (173.5 m), and the side slope gradient has been reduced to 4:1 to
The proposed pond was calculated into the 5 and 100 year post-
flows. The pre-developed flows are 2.7759 m3/s and 6.2564 m3/s for 5
year and 100 year storm events respectively with an existing runoff
coefficient of 0.34 for 5 year and 0.47 for 100 year storm events and a
4.4675 m3/s and 9.3305 m3/s for 5 year and 100 year storm events
coefficient of 0.5472 for 5 year and 0.7009 for 100 year storm events
5 yr 100 yr 5 yr 100 yr
Runoff
0.34 0.47 0.5472 0.7009
Coefficient
Design Parameters
The maximum water level during the 1:100 storm event will be
1.1Design Criteria
As indicated on Drawing X, the proposed development will discharge
Based on the above information, and with reference to Table 3.2 in the
A flow splitter or flow diversion structure was used to direct the first fraction
of runoff (commonly called the “first flush”) into the quality pond, while
bypassing excess flows from 100 year event around the facility into a bypass
Runoff water is conveyed to the quality pond via the main open channel.
Once the main open channel reaches its design capacity, water backs up in
the channel and into the flow splitter itself. When the water level reaches
The bypass is created and controlled by a weir in the flow splitter structure.
Bypass Elevation – the elevation of the bypass weir dictates the maximum
elevation of the water in the channel. Therefore, the bypass elevation is set
to equal to the design water elevation (which is 5 yrs storm event). Using
this method, the flow will only start to bypass the weir once the channel has
Inlet areas should be protected to reduce erosion. The outfall from the
channel to the pond shall be modified to prevent erosion by use of large rip-
emergent vegetation.
Outlet Design
convey flows out of the facility . The weir has been sized to pass a flow
equivalent to the design flow into the facility with a maximum water
constructed to protect the shoreline from erosion. The rip-rap will have a
erosion control mat that will line the flow route will extend underneath the
Other considerations
The end-of-pipe facility should be designed with a sediment forebay to
improve pollutant removal by trapping larger particles near the inlet of the
A landscaping plan for a stormwater pond and its buffer should be prepared
a pond design, either along the aquatic bench, the safety bench and side
Data Collection
The data information was gathered from MNR, DRIC draft environmental
The subsurface conditions in the Windsor area are characterized by flat-lying soils
including:
Beneath the existing pavement structures, topsoil and / or surficial fill materials,
granular materials consisting of sand and gravel, sands and silty sands were
surface in the clayey silt and silty clay materials. The silty clay, clayey silt, sand
and gravel and sands are considered to be slightly erodible and the silty sands are
Qpost = Cpost * I * A
Flow
Post-
development
Peak Flow, Qpost
Storage
Pre-
Required,
development
S
Peak Flow, Qpre
Time
Tbase = 2tc or 2.67 tc
Pre-development (100 years)
Pre-development (5 year)
Post-development (5 year)
Area Coefficient
Buildings/Concrete: 1.66 ha 0.8
Paved Area: 29.0 ha 0.77
Landscape Area: 33.22 ha 0.34
Orifice
Qo = c * A * sqrt(2 * g * H)
The smallest diameter orifice to ensure that clogging does not occur in a
stormwater system is 75 mm. The preferred minimum orifice size is 100mm where
the effects of freezing are a concern. 5 year storm was used to control the size of
the orifice. Therefore,
Qo = Qpre5
Pond Design
Water table: 3 m below surface
Length to width ratio: 4 to 1
Permanent Pool Depth: Max. depth 2.5m mean depth: 1 – 2 m
Active Storage Depth: Water Quality and erosion control max 1.0m total
2m