Loading, Unloading, Stacking

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 37

DESCRIPTION OF ITEM NO 1: Loading or unloading into or from Railway

Wagons lead within one chain Shingle, sand,


ballast, surkhi ashes, kankar, brick bats, coal.
Lime or 1000 Nos. tiles size 12"x6"x2" or
9"x4"x1" properly laid and stacked.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour
Unskilled Cooly 1.00 No 140.00 P. Day 140.00
Total 140.00
Sundries 10.00 Percent 14.00
Total 154.00
Contractor's Profit & Overheads 20.00 Percent 30.80
Total 184.80
Item Rates
Labour Rate Per 100 Cft Rs. 147.84 Say 147.85
Labour Rate Per Cum Rs. 52.22 Say 52.20
CHAPTER NO. 2
LOADING UNLOADING AND STACKING
Unit Rate (British System) per 100 Cft
Page 1
DESCRIPTION OF ITEM NO 2: Loading or unloading bricks into or from Railway
Wagons laid and stacked lead within one chain.
a) Bricks 10" size.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour
Unskilled Cooly 1.25 No 140.00 P. Day 175.00
Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50
Contractor's Profit & Overheads 20.00 Percent 38.50
Total 231.00
Item Rates
Labour Rate Per 1000 Nos Rs. 184.80 Say 184.80
Unit Rate (British System) per 1000 Nos
Page 2
Item No. 2 Loading or unloading bricks into or from Railway
Wagons laid and stacked lead within one chain.
b) Bricks 9" or smaller size.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour
Unskilled Cooly 1.00 No 140.00 P. Day 140.00
Total 140.00
Sundries 10.00 Percent 14.00
Total 154.00
Contractor's Profit & Overheads 20.00 Percent 30.80
Total 184.80
Item Rates
Labour Rate Per 1000 Nos Rs. 147.84 Say 147.85
Unit Rate (British System) per 1000 Nos
Page 3
DESCRIPTION OF ITEM NO 3: Loading or unloading into or from Railway
Wagons cement in bags (from inside or outside
the go-down) and stacking within one chain.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Bags
Labour
Unskilled Cooly 1.25 No 140.00 P. Day 175.00
Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50
Contractor's Profit & Overheads 20.00 Percent 38.50
Total 231.00
Item Rates
Labour Rate Per 100 Bags Rs. 184.80 Say 184.80
Unit Rate (British System) per 100 Bags
Page 4
DESCRIPTION OF ITEM NO 4: Loading or unloading into of from Railway
Wagons empty cement bags (from inside or
outside the go-down) and stacking.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos.
Labour
Unskilled Cooly 0.12 No 140.00 P. Day 16.80
Total 16.80
Sundries 10.00 Percent 1.68
Total 18.48
Contractor's Profit & Overheads 20.00 Percent 3.70
Total 22.18
Item Rates
Labour Rate Per 100 Nos Rs. 22.18 17.74 Say 17.75
125
Unit Rate (British System) per 100 Nos
Page 5
DESCRIPTION OF ITEM NO 5: Loading or unloading into or from Railway
Wagons (from inside or outside the go-down) and
stacking white lime in bags.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Mds
Labour
Unskilled Cooly 0.75 No 140.00 P. Day 105.00
Total 105.00
Sundries 10.00 Percent 10.50
Total 115.50
Contractor's Profit & Overheads 20.00 Percent 23.10
Total 138.60
Item Rates
Labour Rate Per 100 Mds Rs. 110.88 Say 110.90

Labour Rate Per 100 Kg Rs. 2.97 Say 2.95
Unit Rate (British System) per 100 Mds
Page 6
DESCRIPTION OF ITEM NO 6: Loading or unloading into or from Railway
Wagons structural steel, joists, broad, narrow or
meter gauge rail and rail fastening etc.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Ton
Labour
Unskilled Cooly 0.60 No 140.00 P. Day 84.00
Total 84.00
Sundries 10.00 Percent 8.40
Total 92.40
Contractor's Profit & Overheads 20.00 Percent 18.48
Total 110.88
Item Rates

Labour Rate Per Ton Rs. 88.70 Say 88.70
Labour Rate per Tonne Rs. 87.30 Say 87.30
Unit Rate (British System) per Ton
Page 7
DESCRIPTION OF ITEM NO 7: Loading or unloading 45 gallons drum full into
or from Railway Wagons lead upto one chain.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Unskilled Cooly 0.06 No 140.00 P. Day 8.40
Total 8.40
Sundries 10.00 Percent 0.84
Total 9.24
Contractor's Profit & Overheads 20.00 Percent 1.85
Total 11.09
Item Rates
Labour Rate Per Each Rs. 11.09 Say 11.10
Unit Rate (British System) per Each
Page 8
DESCRIPTION OF ITEM NO 8: Loading or unloading packages or stock of all
sorts upto I cwt. except cement in jute or paper
bags.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Labour
Unskilled Cooly 0.03 No 140.00 P. Day 4.20
Total 4.20
Sundries 10.00 Percent 0.42
Total 4.62
Contractor's Profit & Overheads 20.00 Percent 0.92
Total 5.54
Item Rates
Labour Rate Per Each No. Rs. 5.54 Say 5.55
Unit Rate (British System) per Each
Page 9
DESCRIPTION OF ITEM NO 9: Loading or unloading sleepers other than wooden
including stacking lead within one chan in.
a) Broad gauge sleepers.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos.
Labour
Unskilled Cooly 2.50 Nos 140.00 P. Day 350.00
Total 350.00
Sundries 10.00 Percent 35.00
Total 385.00
Contractor's Profit & Overheads 20.00 Percent 77.00
Total 462.00
Item Rates
Labour Rate Per 100 Nos Rs. 369.60 Say 369.60
Unit Rate (British System) per 100 Nos
Page 10
Item No. 9 Loading or unloading sleepers other than wooden
including stacking load within one chan in.
b) Metre guage and narrow guage sleepers.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour
Unskilled Cooly 1.25 No 140.00 P. Day 175.00
Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50
Contractor's Profit & Overheads 20.00 Percent 38.50
Total 231.00
Item Rates
Labour Rate Per 100 Nos Rs. 184.80 Say 184.80
Unit Rate (British System) per 100 Nos
Page 11
DESCRIPTION OF ITEM NO 10: Loading or unloading timber logs or timber for
shuttering into or from Railway Wagons of any
gauge including stacking, lead within one chain.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 20 Ton
Labour
Unskilled Cooly 5.00 Nos 140.00 P. Day 700.00
Total 700.00
Sundries 10.00 Percent 70.00
Total 770.00
Contractor's Profit & Overheads 20.00 Percent 154.00
Total 924.00
Item Rates
Labour Rate Per Ton Rs. 46.20 Say 46.20
Per Tonne Rs. 45.47 Say 45.45
Unit Rate (British System) per Ton
Page 12
DESCRIPTION OF ITEM NO 11: Loading or unloading bhoosa in Railway Wagons
lead upto 150 feet.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Mds
Labour
Unskilled Cooly 3.00 Nos 140.00 P. Day 420.00
Total 420.00
Sundries 10.00 Percent 42.00
Total 462.00
Contractor's Profit & Overheads 20.00 Percent 92.40
Total 554.40
Item Rates
Labour Rate Per 100 Mds. Rs. 443.52 Say 443.50
Labour Rate Per 100 Kg Rs. 11.88 Say 11.90
Unit Rate (British System) per 100 Mds
Page 13
DESCRIPTION OF ITEM NO 12: Loading or unloading timber scrap or wooden
plugs into or from Railway Wagons and stacking
within one chain lead.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1.25 Ton
Labour
Unskilled Cooly 0.50 No 140.00 P. Day 70.00
Total 70.00
Sundries 10.00 Percent 7.00
Total 77.00
Contractor's Profit & Overheads 20.00 Percent 15.40
Total 92.40
Item Rates
Labour Rate Per Ton Rs. 73.92 Say 73.90
Labour Rate Per Tonne Rs. 72.75 Say 72.75
Unit Rate (British System) per Ton
Page 14
DESCRIPTION OF ITEM NO 13: Loading or unloading pitching stone or spawl
from Railway Wagons of any gauge (including
clearing 5 feet away from the rail)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft.
Labour
Unskilled Cooly 0.37 No 140.00 P. Day 51.80
Total 51.80
Sundries 10.00 Percent 5.18
Total 56.98
Contractor's Profit & Overheads 20.00 Percent 11.40
Total 68.38
Item Rates
Labour Rate Per 100 Cft Rs. 54.70 Say 54.70
Labour Rate Per Cum Rs. 19.32 Say 19.30
Unit Rate (British System) per 100 Cft
Page 15
DESCRIPTION OF ITEM NO 14: Loading or unloading building stone (including
clearing 5 feet away from rails)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft.
Labour
Unskilled Cooly 0.48 No 140.00 P. Day 67.20
Total 67.20
Sundries 10.00 Percent 6.72
Total 73.92
Contractor's Profit & Overheads 20.00 Percent 14.78
Total 88.70
Item Rates
Labour Rate Per 100 Cft Rs. 70.96 Say 70.95
Labour Rate Per Cum Rs. 25.06 Say 25.05
Unit Rate (British System) per 100 Cft
Page 16
DESCRIPTION OF ITEM NO 15: Unloading oil, bitumen tar etc.
a) Crude oil (to be pumped from tank wagon, into
tank).
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Gallons
Labour
Unskilled Cooly 1.25 No 140.00 P. Day 175.00
Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50
Contractor's Profit & Overheads 20.00 Percent 38.50
Total 231.00
Item Rates
Labour Rate Per 1000 Gln. Rs. 184.80 Say 184.80
Labour Rate Per 100 Liters Rs. 4.07 Say 4.05
Unit Rate (British System) per 1000 Gln
Page 17
Item No. 15 Unloading oil, bitumen tar etc.
b) Crude oil (drained by gravity).
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Gallons
Labour
Unskilled Cooly 1.25 No 140.00 P. Day 175.00
Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50
Contractor's Profit & Overheads 20.00 Percent 38.50
Total 231.00
Item Rates

Labour Rate Per 1000 Gln. Rs. 184.80 Say 184.80

Labour Rate Per 100 Liters Rs. 4.07 Say 4.05

Unit Rate (British System) per 1000 Gln
Page 18
Item No. 15 Unloading oil, bitumen tar etc.
c) Crude oil materials from Railway Wagons.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft
Labour
Unskilled Cooly 0.16 No 140.00 P. Day 22.40
Total 22.40
Sundries 10.00 Percent 2.24
Total 24.64
Contractor's Profit & Overheads 20.00 Percent 4.93
Total 29.57
Item Rates
Labour Rate Per 100 Cft Rs. 23.65 Say 23.65
Labour Rate Per Cum Rs. 8.35 Say 8.35
Unit Rate (British System) per 100 Cft
Page 19
Item No. 15 Unloading oil, bitumen tar etc.
d) Fuel oil from tank into empty drums and stacking
within one chain.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 45 Ton
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates

Labour Rate Per Ton Rs. 65.71 Say 65.70
Labour Rate Per Tonne Rs. 64.67 Say 64.65
Unit Rate (British System) per Ton
Page 20
Item No. 15 Unloading oil, bitumen tar etc.
e) Petrol (2 gallon tin)
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour
Unskilled Cooly 0.63 Nos 140.00 P. Day 88.20
Total 88.20
Sundries 10.00 Percent 8.82
Total 97.02
Contractor's Profit & Overheads 20.00 Percent 19.40
Total 116.42
Item Rates
Labour Rate Per 100 Nos Rs. 93.14 Say 93.15
Unit Rate (British System) per 100 Nos
Page 21
Item No. 15 Unloading oil, bitumen tar etc.
f) Kerosine oil (4 gallons tin).
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour
Unskilled Cooly 1.25 Nos 140.00 P. Day 175.00
Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50
Contractor's Profit & Overheads 20.00 Percent 38.50
Total 231.00
Item Rates
Labour Rate Per 100 Nos Rs. 184.80 Say 184.80
Unit Rate (British System) per 100 Nos
Page 22
DESCRIPTION OF ITEM NO 16: Removing and stacking within one chain lead.
a) Stones, Spawl, Brick Bats, shingle, sand, lime.
Surki, ashes, Kankar & Coal etc.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft
Labour
Unskilled Cooly 0.50 No 140.00 P. Day 70.00
Total 70.00
Sundries 10.00 Percent 7.00
Total 77.00
Contractor's Profit & Overheads 20.00 Percent 15.40
Total 92.40
Item Rates
Labour Rate Per 100 Cft Rs. 73.92 Say 73.90
Labour Rate Per Cum Rs. 26.11 Say 26.10
Unit Rate (British System) per 100 Cft
Page 23
Item No. 16 Removing and stacking within one chain lead.
b) Bricks
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 15,000 Nos
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per 1000 Nos Rs. 197.12 Say 197.10
Unit Rate (British System) per 1000 Nos
Page 24
Item No. 16 Removing and stacking within one chain lead.
c) Broad gauge wooden sleepers
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,500 Nos
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per 100 Nos Rs. 118.27 Say 118.25
Unit Rate (British System) per 100 Nos
Page 25
Item No. 16 Removing and stacking within one chain lead.
d) Metre gauge or narrow gauge wooden sleepers.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 4,200 Nos
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per 100 Nos Rs. 70.40 Say 70.40
Unit Rate (British System) per 100 Nos
Page 26
Item No. 16 Removing and stacking within one chain lead.
e) Rails, girders, pipes, cement etc.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 90 Ton
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per Ton Rs. 32.85 Say 32.85
Labour Rate Per Tonne Rs. 32.33 Say 32.35
Unit Rate (British System) per Ton
Page 27
Item No. 16 Removing and stacking within one chain lead.
f) Bridge and crossing timber etc.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 750 Nos
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per 100 Nos Rs. 394.24 Say 394.25
Unit Rate (British System) per 100 Nos
Page 28
DESCRIPTION OF ITEM NO 17: Loading into Wagons Girders, Rails, permanent
way material (except wooden sleepers) iron work,
M.S. Bars, Pipes, etc. including lead one chain
and stacking inside Wagons.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 40 Ton
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per Ton Rs. 73.92 Say 73.90
Labour Rate Per Tonne Rs. 72.75 Say 72.75
Unit Rate (British System) per Ton
Page 29
DESCRIPTION OF ITEM NO 18: Unloading from Wagons Girders, Rails,
permanent way material (except wooden sleepers)
iron work, M.S. Bars, Pipes, etc. lead upto one
chain but excluding stacking.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 70 Ton
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per Ton Rs. 42.24 Say 42.25
Labour Rate Per Tonne Rs. 41.57 Say 41.55
Unit Rate (British System) per Ton
Page 30
DESCRIPTION OF ITEM NO 19: Loading into Wagons, wooden broad gauge
sleepers including one chain lead and stacking.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1,000 Nos
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per 100 Nos Rs. 295.68 Say 295.70
Unit Rate (British System) per 100 Nos
Page 31
DESCRIPTION OF ITEM NO 20: Unloading wooden broad gauge sleepers from
Wagons including one chain lead and stacking.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,100 Nos
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per 100 Nos Rs. 140.80 Say 140.80
Unit Rate (British System) per 100 Nos
Page 32
DESCRIPTION OF ITEM NO 21: Loading metre gauge or narrow gauge wooden
sleepers including one chain lead and stacking
inside Wagons.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,000 Nos
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per 100 Nos Rs. 147.84 Say 147.85
Unit Rate (British System) per 100 Nos
Page 33
DESCRIPTION OF ITEM NO 22: Unloading metre gauge or narrow gauge wooden
sleepers including one chain lead but excluding
stacking
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 3,800 Nos
Labour
Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00
Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00
Contractor's Profit & Overheads 20.00 Percent 492.80
Total 2,956.80
Item Rates
Labour Rate Per 100 Nos Rs. 77.81 Say 77.80
Unit Rate (British System) per 100 Nos
Page 34
DESCRIPTION OF ITEM NO 23: Loading Bridge and grossing timber including
one chain lead and stacking.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour
Unskilled Cooly 4.00 Nos 140.00 P. Day 560.00
Total 560.00
Sundries 10.00 Percent 56.00
Total 616.00
Contractor's Profit & Overheads 20.00 Percent 123.20
Total 739.20
Item Rates
Labour Rate Per 100 Nos Rs. 591.36 Say 591.35
Unit Rate (British System) per 100 Nos
Page 35
DESCRIPTION OF ITEM NO 24: Unloading Bridge and crossing timber including
one chain lead but excluding stacking.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour
Unskilled Cooly 2.00 Nos 140.00 P. Day 280.00
Total 280.00
Sundries 10.00 Percent 28.00
Total 308.00
Contractor's Profit & Overheads 20.00 Percent 61.60
Total 369.60
Item Rates
Labour Rate Per 100 Nos Rs. 295.68 Say 295.70
NOTE :
Rate for loading and unloading for Mobile trucks/ boats, item 1-15 will be 80%
of the rate of Railway Wagons.
Unit Rate (British System) per 100 Nos
Page 36
DESCRIPTION OF ITEM NO 25: Loading or unloading bitumen, asphalt or tar in
drums, into or from Railway Wagons lead upto
one chain.
Detail
Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 25 Ton
Labour
Unskilled Cooly 6.00 Nos 140.00 P. Day 840.00
Total 840.00
Sundries 10.00 Percent 84.00
Total 924.00
Contractor's Profit & Overheads 20.00 Percent 184.80
Total 1,108.80
Item Rates
Labour Rate Per Ton Rs. 44.35 Say 44.35
Labour Rate Per Tonne Rs. 43.65 Say 43.65
Unit Rate (British System) per Ton
Page 37