Fixed Nozzle Desuperheater Manual

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

OPERATION AND MAINTENANCE MANUAL

FIXED NOZZLE DESUPERHEATER

Specialists in Process Efficiency and Energy Conservation


FIXED NOZZLE DESUPERHEATER
8. Check the pipeline geometry and ensure that there is a
INSTALLATION
MINIMUM AVAILABLE STRAIGHT LENGTH OF 4.5 METERS
A fixed nozzle desuperheater in conjunction with the cooling FROM THE POINT OF SPRAY. (Please install the same steam
water control valve and temperature loop reduces the superheat pipe size for which the fixed nozzle desuperheater has been
of inlet steam and thereby the temperature. The low temperature designed. In case of oversize or undersize of the steaam pipe,
steam can then be used for other processes and utilities the downstream temperature will NOT be maintained resulting in
water carry over and water hammering). You can, however,
While installing a Fixed nozzle desuperheater, following need to
install bends / elbows / tees after a straight length of 4.5 meters
be taken care of :
9. The temperature sensor (thermocouple, RTD and
1. Before installing the nozzle insert in the steam pipe, the water
temperature transmitter) shall have to be mounted on the steam
circuit needs to be thoroughly flushed with the designated water
pipe at a distance of AT LEAST 12 METERS from the point of
pressure for 25 minutes. While flushing, please ensure that the
water injection. The maximum distance of temperature sensor /
Forbes Marshall Arca water control valve, isolation valves and
transmitter location can be 18 – 20 meters from the point of
bypass valve are kept in 100% open condition in case these are
water injection. This is a very important parameter for the
of welded connection. In case of flanged bodies, all the valves
temperature control circuitry and it should be followed
need be removed from the water circuitry and the line flushed
for about 10 minutes.
COLD CHECKING / LOOP CHECKING
2. The above activity will ensure that no foreign particles shall
enter into the steam line from the water line. This will also avoid 1. The control loop shall be programmed as per the process
any clogging of the nozzles due to impurities and suspended requirement (single loop controller, multi loop controller, SCADA,
particles present in water PLC and DCS)

3. Check whether the strainer has become clogged in the 2. Check whether proper cabling has been done between the
cleansing process. In the event of clogging, remove the temperature sensor and the controller. Also check whether
straining element, clean properly and reassemble strainer proper input signals are being received by the controller or not

4. Now connect the nozzle insert to the water circuitry (keeping 3. Check whether the controller is giving proportional control
the nozzle insert outside the steam pipe) and flush again for 5 output signals or not
minutes at the designated water pressure and visually inspect
4. The controller output signal shall be connected with proper
the atomization of the water (which should look like a fine
polarity to the I/P or E/P convertor (or electropneumatic
fountain)
positioner of the water control valve, as the case may be for
5. Now install the nozzle insert into the steam pipe. your equipment)

6. Check the nozzle insert to ensure that the nozzle is at the 5. Before giving any impulse air connection, the airline shall be
centre of your steam pipeline. In case of multiple nozzles, please flushed for about 5 minutes (depends on the compressor
ensure that the central nozzle sprays from the centerline of your capacity) for any dirt, dust, oil and moisture. The signal air shall
pipe. Proper mixing of atomized water with steam ensures be given (through the air filter regulator) to the pneumatic
efficient temperature control (please make sure that no water is instrument as per recommendation on the control valve name
sprayed on the wall of the pipeline, which may result in water plate. Ensure that no leakage is observed after bubble test
carry over which will lead to water hammering and inaccurate
6. After steps 1 – 5 above, set the controller in manual mode,
temperature control)
calibrate the water control valve from 0 – 100% (the control
7. Perform COLD CHECKING with designated water pressure range of the control valve will be from 15% to 85% ONLY). Any
and temperature after 1 – 6 has been completed. Ensure that no control range below 15% and above 85% will not contribute to
leakage has been observed in the water circuitry the controllability of the process.
FIXED NOZZLE DESUPERHEATER
FINAL COMMISSIONING MAINTENANCE
1. Ensure that the process is put on the manual mode on the Maintenance of the VND is straightforward and does not require
low load. any special tools or training.

2. Charge the recommended pressure and temperature water Care should be taken during any maintenance operation,
into the water circuitry with control valve in closed condition. particularly when working with grinders, compressed air and
rotating machinery.
3. Charge steam and run the process with designed loads.
Before removing the Desuperheater from the system ensure that
4. Manually open the control valve through controller gradually both steam and water pipework are pressureless and vented.
and observe the feedback of the process temperature in the Isolate any electrical appliances to the actuator and / or
controller. ancilliaries, prior to disconnection. Vent and remove instrument
air supply piping. Loosen steam flange and water flange bolting,
5. Gradually open the water control valve manually and check but vent connections before complete removal.
the position of opening where the temperature set point is met.
Once the temperature set point is met, keep the valve in the The Desuperheater may now be removed from the system. It is
same position and make a changeover from manual to auto recommended that the Desuperheater is transported to a
mode. convenient workshop which has a workbench and vice. Lift the
unit by means of straps around the body.
6. Once the control system is changed to auto mode, fine tune
the P.I.D values for optimum control Do not attempt to lift the Desuperheater

7. Observe the process for 1 – 2 hours with variation in loads


for the design parameters. Your system is commissioned.
FIXED NOZZLE DESUPERHEATER

GUIDELINES FOR MECHANICAL INSTALLATION


OF FIXED NOZZLE DESUPERHEATER
FIXED NOZZLE DESUPERHEATER

CORRECT INSTALLATION METHODS


FIXED NOZZLE DESUPERHEATER

P & I DIAGRAM
FIXED NOZZLE DESUPERHEATER

E/P CONVERTER
TYPICAL INSTRUMENTATION
WIRING/PNEUMATIC CONNECTION DIAGRAM
FIXED NOZZLE DESUPERHEATER
FIXED NOZZLE DESUPERHEATER

NOTES
Offices and Representatives
America South Asia Asia Pacific Africa Middle East
USA INDIA THAILAND EAST AFRICA UAE
Forbes Marshall, Inc. Forbes Marshall Pvt. Ltd. Forbes Marshall Pvt. Ltd. Forbes Marshall Pvt. Ltd. Al Hamas Trading Co (LLC)
P.O. Box 60670 PO Box # 29, Mumbai-Pune Rd., Room No.403,4th Floor PO Box 58338-00100 GPO Nairobi (For Instrumentation)
480 California Ave, Suite 102 Kasarwadi, Pune 411 034 House No.567, Seri 6 Road Kenya P.O.Box 19546
Palo Alto, CA 94306 Tel: 91 (0) 20-27149012/27145595 (Soi 51, Rama 9 Road), Suan Iuan Tel: +254-725490866/254-734763913 Dubai, U.A.E
Tel: +1 650 327-4227 / +1-650-321-4224 Fax : 91 (0) 20-27147379 Bangkok 10250 Fax: +254-20824405/824270 Tel: + 971-4-3350020 /
Fax: +1 650 327-4127 Email: exp@forbesmarshall.com Tel: +66 2 7203484/3 Email: africa@forbesmarshall.com +9714-3350020
Toll Free Tech Support #: 1 866 803-6224 +66-81-9020690 Telefax: + 971-4-3356648
Email: usasupport@forbesmarshall.com BANGLADESH Fax: .+00662-943-5500 ETHIOPIA Email: cos@forbesmarshall.com
Forbes Marshall Pvt. Ltd. Email: thailand@forbesmarshall.com Rapture Import & Export PLC sequeira.cedric@gmail.com
CANADA Rupsha Tower, C-3, vphillip@ksc.th.com Kolfe Keranio Sub-City,
Forbes Marshall Canada Inc. 3rd Floor Kebele13/14,House Nr.624, Technical Parts Co (LLC)
2425 Matheson Blvd. East, 8th Floor 7, Kemal Attaturk Avenue, INDONESIA P.O.Box 28447/1000 (For Boilers)
Mississauga, ON Road#17, Behind Brac Bank, Forbes Marshall Pvt. Ltd. Addis Ababa P.O.Box 5071
L4W 5K4 Dhaka - Bangladesh Blok NC 8 No.11 Ethiopia Dubai, U.A.E.
Canada Tel: +88 028811501/+88 01711529502 Jalan Kelapa Lilin Raya Blok, Tel.:+251-911-145524 Tel: + 97142137808
Tel: + 905.361.2525 / +647-403-8169 E-mail : bangladesh@forbesmarshall.com Kelapa Gading Timur, Fax:+251-115-511479 /+971501572434
Fax: +905 361 6401 rajeshn@forbesmarshall.com Jakarta - Uttara Email: biruk.oasis@gmail.com Fax:+ 971-4-2823078
E-mail : cansupport@forbesmarshall.com Indonesia Email: mdas@forbesmarshall.com
sfpavri@forbesmarshall.com SRI LANKA Tel: +62 8 15199 17178 EGYPT
Forbes Marshall Lanka Pvt Ltd Email:harshad@forbesmarshall.com System Technique IRAN
COLUMBIA 12/5A, 1/1, Water Management Div. Unit 23. No.2, 18th Street,
CRA 58 # 167B – 19 INT: 1 Robert Gunawardane Mawatha MALAYSIA 17 El Mahrovky Street, Golfam Building, Naft Street, 4 Divari,
Portales del Norte Kirulapone,Colombo 06 Forbes Marshall Pvt Ltd Off Aswan Square, End of Ashrafi Esfehani, Pounak,
Bogota Colombia Tel: +94112512997 Suite 1904, 19th Floor Mohandseen, Cairo Tehran, Iran
Tel: + 57 316 721 15 10 Fax: + 94114511128 Kenanga International, Jalan Sultan Ismai P.O.Box 141 El-Gezirah, Tel: +98 912 1304598
Email: fsforbes@gmail.com Email: fmlanka@forbesmarshall.com 50250 Kuala Lumpur Egypt Email: m.m.rezaee@gmail.com
Malaysia Tel: + 202 3036935/ 3036952 / 81
NEPAL Tel: +60 32161 8260 / +601-76951296 +201168802964
Ekta Engineering and Marketing Pvt. Ltd. Fax: +60 32161 2220 Fax: + 202 3036897
Flat No. 402, Bagmah Chambers, Email:mvr@forbesmarshall.com Email: mc@forbesmarshall.com
Milan Marg Chowk,
Tripureshwar Teku Road, Khatmandu, VIETNAM
Nepal Email : vphillip@ksc.th.com
Tel : +977 9851022039 / Tel : +66-81-9020690
+97714247676 / 4238131
Fax : +97714238131
Email : ekta@ecomail.com.np
Rev2/0907/Beriwals

Specialists in Process Efficiency and Energy Conservation

You might also like