This document outlines procedures for erecting bulk units in shipbuilding. It discusses lifting procedures such as identifying cranes and their capacities, determining block sizes, and arranging lifting points. It also covers preparing reference lines and points for alignment and developing block erection schedules. Hazards of lifting large structures are examined, including unbalanced lifting potentially causing falls and injuries to workers. Accurate positioning is important to avoid mismatched joining of parts during construction.
This document outlines procedures for erecting bulk units in shipbuilding. It discusses lifting procedures such as identifying cranes and their capacities, determining block sizes, and arranging lifting points. It also covers preparing reference lines and points for alignment and developing block erection schedules. Hazards of lifting large structures are examined, including unbalanced lifting potentially causing falls and injuries to workers. Accurate positioning is important to avoid mismatched joining of parts during construction.
This document outlines procedures for erecting bulk units in shipbuilding. It discusses lifting procedures such as identifying cranes and their capacities, determining block sizes, and arranging lifting points. It also covers preparing reference lines and points for alignment and developing block erection schedules. Hazards of lifting large structures are examined, including unbalanced lifting potentially causing falls and injuries to workers. Accurate positioning is important to avoid mismatched joining of parts during construction.
This document outlines procedures for erecting bulk units in shipbuilding. It discusses lifting procedures such as identifying cranes and their capacities, determining block sizes, and arranging lifting points. It also covers preparing reference lines and points for alignment and developing block erection schedules. Hazards of lifting large structures are examined, including unbalanced lifting potentially causing falls and injuries to workers. Accurate positioning is important to avoid mismatched joining of parts during construction.
a) To outline the procedures of lifting the blocks,units and modules to the building berth or dock.
b) To explore the erection scheduling methods.
c) To examine the hazards in lifting bulk structure
12.2 LIFTING PROCEDURES
Lifting procedure is a method of lifting the ships bulk structure such as blocks, units, and modules to the building berth or dock. The procedure should be well considered because it involves large and heavy structures, which conceives many hazards both to the production process as well as to the human safety.
The lifting procedure considerations would include the followings:
a) Lifting facilities
The lifting facilities available for lifting the blocks onto the berth or dock should be identified far before the blocks are ready to be lifted. It was when the size and weight of the blocks were determined prior to their construction in the assembly shop. Cranes that are commonly used for lifting the blocks are gantry crane which is also known as Goliath crane, telescopic mobile crane, hammerhead crane, floating crane, and level luffing crane.
The decision of using the type and capacity of certain crane is based on investment cost and utilisation of the crane, the type and size of ships will be built, the efficiency and practicality of using it etc., some considerations of choosing the type of crane are shown in the following matrix of merits and drawbacks: No Type of crane Merits Drawbacks 1 Goliath crane - High lifting capacity - Can cover the whole area of dock or berth - Very stable - Good operator visibility - High invesment cost - Not applicable on side launch berth 2 Telescopic mobile crane - Can move around easily - Suitable for lifting small units - Lower investment cost - Can be hired - Limited in lifting capacity - Not very stable - Limited operator visibility - Limited coverage 3 Hammerhead crane - High lifting capacity - Very stable - Good operator visibility - Good coverage - Applicable for side launch
- High invesment cost - Operate only from one side
4 Floating crane - High lifting capacity - Can be operate from water front - Good for complementary task
- Limited coverage - Limited stability - High invesment cost - Not applicable on end launch - Limited operator visibility - 5 Level luffing crane - High lifting capacity - Can work in tandem - Applicable in all type of launch - Limited stability - Limited coverage
Figure 12.5 Level luffing crane
12-4
b) Size and weight of blocks In most modern shipyards that implement advanced outfitting method blocks and modules are completed in the assembly shop or on the assembly yard, in order to minimise the joining process on the berth or dock. It is a common practice to construct the blocks as large as possible as the lifting facilities allow. There are some advantages in having large and complete blocks to be erected to the berth or dock, but the drawbacks should also be considered.
Advantages and disadvantages of large block structure Advantages Disadvantages Minimum work on berth/dock Need high capacity of cranage Shorter construction time on berth/dock Demand high accuracy of block structure Better product quality More difficult to align the blocks Less disruption to complete the block Need higher skill to lift the blocks
Some considerations that should be made in deciding the size and weight of the blocks with regard to the efficientcy, practicallities, and cost effectiveness of the shipyard are as follows: The capacity of the transporter available to transfer the blocks to the berth or dock. The lifting capacity of cranes available on the berth or dock. The access available for transporting the blocks to the berth or dock. The alignment methods that will be implemented on berth or dock. The lifting methods that will be implemented.
Figure 12.6 Block transporting
12-5
c) Arrangement of lifting points
The shape of modules or blocks to be erected to the berth or dock are not always symmitrical, therefore in order to obtain a good balance in lifting the blocks, the positioning of lifting points needs to be considered well.
Some considerations in arranging the lifting points are as follows:
The shape of the structure to be lifted The position of its center of gravity The position of strong and weak structural members The framing system of the structure The lifting method to be applied
For proper alignment of the blocks on building berth or dock reference lines are drawn on the floor and walls (for dock) with some indication of their positions relative to the centerline for floor reference lines, and relative height and distances from the floor for horizontal and vertical reference lines as shown in the following illustration:
Reference lines and reference points are not only drawn on the floor and walls of the berth or dock, but also drawn on the blocks and on some of their structural members. Prior to joining the block is positioned on the prepared stools or on top of other blocks, the reference lines and reference points are used as guidance for its correct position. e) block alignment Unlike building a boat or conventional method where the ship was constructed piece by piece, most of the ships now are built in blocks and modules. The blocks and modules are aligned on their designated positions prior being tack welded and joined one to another. Block alignment is important for obtaining a good shape of the ships hull, and for proper joining of the internal structural and outfiting parts. In block aligning reference lines and points both on the berth and on other blocks are used as guidnace for its position, and a number of tools are also being used such as theodolite and laser beam.
Vertical reference line Horizontal reference line CL Floor reference line Figure 12.9 Docks reference lines Figure 12.10 Theodolite
12-7
12.3 ERECTION SCHEDULE The completion of blocks joining dependent on the launching method that will be implemented. If the ship is launched on the slipway for safety reasons, most of the super structure usually will be completed on the quay after the launching, but if the ship is floated out the whole structure would be completed on the berth or dock. The effectiveness of blocks joining process among other things will be determined by the block erection schedule. Many aspects should be considered in order to obtain an optimum block erection schedule these include: The position of blocks in the ship structure The blocks joining sequences The work content and the time needed to construct each block in the shop The work content and the time needed to join each block Traditionally block erection schedule was done manually using past project or experienced data, which generally very time consuming and very unaccurate. Some computer programmes have been introduced to do the scheduling task using numerical algorithm and visual simulation. Information for block erection schedule would come in many ways include: Network diagram Blocks layout sketches Block erection matrix
Figure 12.11 Block alignment
Block Number Preceding Block DB 3 PS DB 4 SB DB 3 SB DB 3 PS DB 2 PS DB 3 SB DB 2 SB DB 2 PS DB 1 PS DB 2 SB DB 1 SB DB 1 PS Figure 12.14 Preceding Block Successing Blocks Erection Due Joining time (days) DB 4 SB DB 3 SB 3 Jan 09 DB 3 PS DB 2 PS 6Jan 09 DB 3 SB DB 2 SB 9 Jan 09 DB 2 PS DB 1 PS 12 Jan 09 DB 2 SB DB 1 SB 15 Jan 09 DB 1 PS FP 1 19 Jan 09 Figure 12.12 Block structural breakdown Figure 12.13 Network diagram 14 Example of blocks erection schedule matrix 12-8 Joining time (days) 3 3 3 3 4 4
12-9
12.4 LIFTING HAZARDS There are some hazards that need to be anticipated in lifting a bulk structure such as block, module, and unit, because of the potential risks that might create fatal consequences both to the human safety as well as to the work being carried out. a) Identified hazards The lifting hazards that may be identified among other things are: Unsymmetrical shape of the module, unit, or block being lifted that might cause unballance lifting and the structure fall down. Size and weight of the structure being lifted that make the lifting process more dificult to control. Cranes working in tandem might cause unsynchronised movement and lifting speed and break the ropes or lifting points. Improper securing of lifting points which might caused the lifting points pulled off the structure. Inaccurate positioning of the structure which can cause mismatch of the joining parts. Unqualified operator being emplyed may violate the lifting procedures
b) Potential risks The potential risks due to lifting hazards can be categorised into two groups as follows: Production risks Safety risks Rework Injury to the people Damage of the structure Inconvenient working condition Lengthen the production time Work disruption Extra working cost Work does not meet the standards
c) Risks reduction Actions that could be made to reduce the risks due to lifting hazards are: Implement proper lifting procedures Employ qualified lifting operators Examine the structure and the facilities before undertaking the task Arrange the lifting points properly by considering the shape and weight of the structure
12.6 CONCLUDING REMARKS a) Lifting procedure is a method of lifting the ships bulk structure to the building berth or dock.
12-10
b) The lifting procedure considerations would include: Lifting facilities Size and weight of blocks Arrangement of lifting points Preparation of fererence lines and ponits Blocks alignment
c) Considerations on erection schedule should include: The position of blocks in the ship structure The blocks joining sequences The work content and the time needed to construct each block in the shop The work content and the time needed to join each block
d) Hazards that need to be identified in lifting bulk structure include: Unsymmetrical shape of the structure Size and weight of the structure Cranes working in tandem Improper securing of lifting points Inaccurate positioning of the structure Unqualified operator being employed
e) Potential risks in lifting bulk structure can be grouped into production risks and safety risks.
f) Some consideration for reducing risks include: Implement proper lifting procedures Employ qualified lifting operators Examine the structure and the facilities before undertaking the task Arrange the lifting points properly by considering the shape and weight of the structure