The document summarizes Indonesia's electricity infrastructure and long-term plan from 2013-2022. It details that as of 2013, Indonesia had 36,897 MW of installed generation capacity, 38,937 km of transmission lines, and 777,962 km of distribution lines. It projects electricity demand to increase from 189 TWh in 2013 to 385 TWh in 2022. To meet this demand, Indonesia plans to add 59.5 GW of new generation capacity through coal, gas, geothermal, and hydro plants. Total investment in generation, transmission and distribution from 2013-2022 is projected to be $121.8 billion, with IPPs accounting for 43% of investment.
Original Description:
PLN's presentation at Tokyo March 2014. Here you could
The document summarizes Indonesia's electricity infrastructure and long-term plan from 2013-2022. It details that as of 2013, Indonesia had 36,897 MW of installed generation capacity, 38,937 km of transmission lines, and 777,962 km of distribution lines. It projects electricity demand to increase from 189 TWh in 2013 to 385 TWh in 2022. To meet this demand, Indonesia plans to add 59.5 GW of new generation capacity through coal, gas, geothermal, and hydro plants. Total investment in generation, transmission and distribution from 2013-2022 is projected to be $121.8 billion, with IPPs accounting for 43% of investment.
The document summarizes Indonesia's electricity infrastructure and long-term plan from 2013-2022. It details that as of 2013, Indonesia had 36,897 MW of installed generation capacity, 38,937 km of transmission lines, and 777,962 km of distribution lines. It projects electricity demand to increase from 189 TWh in 2013 to 385 TWh in 2022. To meet this demand, Indonesia plans to add 59.5 GW of new generation capacity through coal, gas, geothermal, and hydro plants. Total investment in generation, transmission and distribution from 2013-2022 is projected to be $121.8 billion, with IPPs accounting for 43% of investment.
1 Tokyo , 06 March 2014 Moch. Sofyan m.sofyan@pln.co.id Head of New & Renewable Division of PT PLN (Persero) INDONESIA ELECTRICITY INFRASTRUCTURE, Today & Tomorrow JICA Senior Officer Program 2 36,897 MW of installed capacity out which represents 83% of capacity in Indonesia 38,937 kmc of transmission lines 77,514 MVA of transmission transformer capacity 777,962 kmc of distribution lines 41,987 MVA of transformer capacity PLN 100% PLN 100% Transmission Distribution Generation PLN 83% IPP 17% PLN is a major integrated electric utility company in Indonesia 3 31% 2% 28% 12% 27% 22% 76% 24% PLN distributes and sells electricity to several customer types. The electricity sold is either generated by PLN or purchased from IPPs. Generation Composition PLNs Generating Capacity Electricity Transmitted and Distributed by Customer Type Number of Customers by Type (in millions) (in TWh) 8 9 9 10 11 6 23 25 27 28 31 16 48 46 51 55 60 32 50 55 60 65 72 37 129 135 147 158 174 91 0 30 60 90 120 150 180 2008 2009 2010 2011 2012 1H 2013 Public Business Industrial Residential 1.0 1.1 1.2 1.2 1.3 1.4 1.7 1.9 1.9 2.0 2.2 2.3 0.05 0.05 0.05 0.05 0.05 0.05 36 37 39 43 46 48 39 40 42 46 50 52 0.0 10.0 20.0 30.0 40.0 50.0 2008 2009 2010 2011 2012 1H 2013 Public Business Industrial Residential Total Hydro 10% Steam- Turbine 40% Gas- Turbine 10% Combined Cycle 24% Geothermal 1% Diesel 15% Others 0.01% Total: 36,897 MW Own Production 76% Purchased 24% Total: 106,164 GWh Electricity Demand Forecast 2013-2022 4 Tahun 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Demand (TWh) 189 207 226 244 264 284 306 329 356 385 Elec. Ratio ( % ) 79.6 82.6 85.9 88.9 91.9 93.7 96.3 96.8 97.4 97.7 Electricity Demand Projection Comparation : RUPTL & RUKN 5 Average growht of Electricity Demand RUPTL 2013-2022 as of 8,4%, lower than RUPTL 2012-2021 (8,7%) and Draft RUKN 2012-2031 (10,1%). TWh New Power Plant Capacity Addition (Incl. IPP) 6 Total additional capacity until 2022 is around 59,5 GW. Contribution of IPP will be increased. . Additional capacity : CFPP : 37,7 GW GeoPP: 6,2 GW CCGT : 4,8 GW GT/Gas Engine : 3,6 GW Hidro/Mini Hidro : 6,9 GW Others : 0,2 GW Transmission System Development (by Voltage Level) 7 Hydro Geothermal Coal Gas LNG Oil 500 kVAC: 5559 kms 500 kVDC: 1100 kms 275 kV AC: 5895 kms 250 kVDC: 462 kms 150 kV: 38.700 kms 70 kV: 3824 kms Total approx 55.539 kms Substation Development (by Voltage Level) 8 500/275 kV: 3500 MVA 500/150 kV: 32.173 MVA 500 kVDC : 3.000 MVA 275/150 kV: 11.570 MVA 250 kVDC : 600 MVA 150/70 kV : 640 MVA 150/20 kV : 75.595 MVA 70/20 kV : 5.725 MVA Total approx 132.803 MVA Generation Mixed Projection 9 214 683 GWh 437 207 GWh Coal Coal - 2,0 4,0 6,0 8,0 10,0 12,0 14,0 16,0 18,0 20,0 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Total Investasi PLN+IPP Total Investasi PLN Pembangkit PLN+IPP Transmisi Distribusi Pembangkit PLN 10 Investment for 2013-2022 IPP Investment share of 43 % Generation PLN : 38,1 billion US$ Generation PLN+IPP : 89,9 billion US$ Transmission : 17,4 billionUS$ Distribution : 14,5 billion US$ Total PLN : 68,3 billion US$ Total PLN+IPP : 121,8 billion US$ 10 Billion US$ Expansion Plan for Java Bali System 11 GITET 500 kV eksisting SUTET eksisting Kit 500 kV eksisting SURALAYA PLTU Jawa Tengah #1: 1.000 MW (2018) #2: 1.000 MW (2019) PLTU Indramayu #4: 1.000 MW (2022) #5: 1.000 MW (2022) Upper Cisokan PS #1: 260 MW (2017) #2: 260 MW (2017) #3: 260 MW (2017) #4: 260 MW (2017) PLTU Adipala #1: 660 MW (2014) PLTU Jawa-7 #1: 1.000 MW (2019) #2: 1.000 MW (2020) PLTU Banten #1: 625 MW (2016) PLTU Jawa-4 #5: 1.000 MW (2019) #6: 1.000 MW (2020) PLTU Jawa-1 #2: 1.000 MW (2018) PLTU Jawa-5 & 6 #1: 1.000 MW (2018) #2: 1.000 MW (2019) #3: 1.000 MW (2021) #4: 1.000 MW (2021) AMPLA CILEGON M.TAWAR CIBATU CIRATA SAGULING BEKASI TASIKMALAYA BANDUNG SELATAN UNGARAN T.JATI B PEDAN KEDIRI PAITON GRATI KRIAN GRESIK NEW SURALAYA NGIMBANG CAWANG SURALAYA KEMBANGAN BANGIL KESUGIHAN /RAWALO CILACAP GANDUL TAMBUN CAWANG-2 BANTUL KAPAL SURABAYA SELATAN TANDES CIGERELENG ADIPALA DEPOK HVDC CIBINONG M.KARANG PRIOK CIBATU-2 CISOKAN INDRAMAYU UJUNGBERUNG MANDIRANCAN JAWA-1 JAWA-3 T.JATI A MATENGGENG PEMALANG JATENG DURIKOSAMBI NEW BLRJA LENGKONG BANTEN HVDC BOGOR-X PLTU Jawa-3 #1: 660 MW (2019) #2: 660 MW (2020) Matenggeng PS #1: 225 MW (2020) #2: 225 MW (2020) #3: 225 MW (2021) #4: 225 MW (2021) PLTU Cilacap #3: 600 MW (2016) PLTGU Jawa-2 #3: 750 MW (2018) PLTGU Jawa-1 #4: 750 MW (2017) GITET 500 kV rencana SUTET rencana Kit 500 kV rencana Sumatera Jawa HVDC Interconnection 12 13 Sistem JAWA P U A A ~ U ~ ~ ~ ~ ~ ~ P A P ~ ~ U U ~ ~ ~ ~ P P U A U U U ~ ~ ~ ~ ~ ~ ~ ~ U U U U P P P ~ P ~ ~ P P U ~ G G G G G P P Prabumulih Baturaja Tarahan Tes HEPP Sukamerindu Bangko Tl. Kelapa Mariana Lubuk Linggau Payo Selincah Adijaya B. Tegi HEPP 1 . PLTG Apung 2. PLTG Ex Pulo Gadung 3 . IPP Palembang Timur Kiliranjao Salak Lubuk Alung Pauh Limo S.Haru Bagan Batu Kulim S. Penuh Pagar Alam Singkarak HEPP Pd. Luar Teluk Lembu Duri Banda Aceh Sigli Bireun Lhokseumawe Idie Tele Brastagi K. Tanjung G.Para P. Siantar Porsea Kisaran Aek Kanopan R. Prapat K. Pinang Panyabungan Asahan I HEPP Meulaboh Takengon Tembilahan Muara Bungo Bagan Siapi- api P. Kerinci Maninjau HEPP Manna Bangkinang Sibolga Glugur Mabar T . Morawa KIM Pd. Panjang Keramasan Simpang3 Sribawono Borang Gumawang New Tarahan Kalianda Sp.Banyak Mukomuko Simpang4 Tapak Tuan Sabulusalam PLTU P. Susu P. Pangarayan PLTU Riau Kemitraan Musi HEPP Sumbar Pessel PLTU L. Angin PLTG G. Megang Sistem JAWA Suka rame B. Umpu Tualang Cut Jantho Seulawah New G.Sakti Garuda Sakti TNB Malaysia Malaka 5 6 7 1 2 3 4 P. Pasir T. Tinggi Labuhan Tegineneng Sutami Binjai P. Geli Namorambe Titi Kuning Denai Galang P. Brandan Batusangkar Ombilin Payakumbuh Perawang Tenayan Siak Sri Indra Pura T. Kuantan Bungus Indarung Kt. Panjang HEPP Merangin HEPP Peusangan1-2 HEPP Blangkjeren Kuta Cane Lawe Mamas HEPP Pasir Putih Perbaungan Lamhotma Aur Duri PLTU Jambi (KPS) Lahat Bukit Asam Betung PLTU S. Belimbing PLTU Banjarsari PLTU K. Agung Kotabumi Bukit Kemuning PLTP L. Balai Liwa Bengkunat Natar Gd. Tataan Tlk . Betung Tlk. Ratai Wampu HEPP Metro PLTP Wai Ratai S. Lilin B. Lincir M. ENIM PLTU Meulaboh Pd. Sidempuan PLTP UluBelu Pagelaran K.Agung PLTP Rajabasa Langkapura Besai HEPP PLTP S. Sekincau Menggala P. Ratu PLTP Hulu Lais PLTP R. Dedap Muara Dua PLTP D. Ranau T. Tinggi Sekayu Kayu Agung T.Api-api GIS Kota I P.Baai Muara Bulian Sarolangun Muara Rupit K. Tungkal Kambang Pariaman PIP GIS Kota Solok PLTP G. Talang Kandis Minas Dumai KID D. Sanggul Tarutung PLTP P. Bukit Sidikalang Renun HEPP G.Tua PLTP Sarulla& Sipaholon Simangkok Asahan III HEPP Asahan IV&V HEPP Sei. Sei Rotan PLTP S. Merapi K.Namu P. Batu Ulee Kareng Samalanga C. Trueng P. Labu Rengat D Blang Pidie Pekalongan Argamakmur Mesuji Dipasena PLTA B. Toru Langsa U U A P S. Rumbai A G 275 kV AC 500 kV AC PLTP Seulawah 110 MW-2021/22 PLTU Riau Kemitraan (PLN-TNB-PTBA) 1200 MW-2018 PLTU Jambi 800 MW-2019/20 PLTU Sumsel 5 & 7 600 MW-2015/16/17 PLTU Banjarsari 230 MW-2014 PLTU Keban Agung 227 MW-2014 PLTU Sumsel-1 MT 600 MW-2020/21 PLTU Sumsel-6 600 MW-2019/20 PLTU Sumsel-8,9,10 3000 MW-2018/19 PLTU Pangkalan Susu #1,2 : 440 MW-2014/15 #3,4 : 400 MW-2016/17 PLTU Sumut-1:300 MW-2017 PLTU Sumut-2:600 MW-2020/21 PLTU Nagan Raya #1,2 : 200 MW-2013/14 #3,4 : 400 MW-2018/19 PLTA Batang Toru 510 MW-2022 PLTP Danau Ranau 110 MW-2022 PLTP Suoh Sekincau 220 MW-2021/22 PLTP Ulubelu 220 MW-2012 & 16/17 PLTP Rajabasa 220 MW-2021/22 PLTA Merangin 350 MW-2021 PLTP Sungai Penuh 110 MW-2022 PLTP Lumut Balai 220 MW-2017/18/19 PLTP Rantau Dedap 220 MW-2019/20 PLTU Teluk Sirih 224 MW-2013/14 PLTP Hulu Lais 110 MW-2018/19 PLTP Kepahiyang 220 MW-2020 PLTP Muara Laboh 220 MW-2017/18 PLTP Bonjol 165 MW-2022 PLTG/MG Peaking Riau & Jambi 300 MW-2016 PLTP Sarulla I&II 440 MW-2017/18 PLTP Sorik Merapi 240 MW-2020/21 PLTA Asahan III 174 MW-2017 PLTG/MG Peaking Lampung 200 MW-2016 HVDC PLTG/MG Arun & Sumbagut-1 400 MW-2015/16 Expansion Plan for Sumatera Expansion Plan for Kalimantan SABAH (MALAYSIA) SULAWESI SELATAN SULAWESI TENGAH Kuaro U Sangatta Bontang U Tj. Selor Tj. Redep U U U Karangjoang Manggarsari Industri G U Petung G G Maloi Melak Malinau Tidang Pale Kota Bangun A G G A U U Barikin Tanjung Rantau Buntok Palangkaraya Kuala Kurun Puruk Cahu Muara Teweh Kasongan Sampit Seberang Barito Selat Trisakti Mantuil Ulin Cempaka Batu Licin Kayutangi U D D D D D D D D U Amuntai Pelaihari A New Palangkaraya Kotabaru Satui Bandara G Sukamara Nangabulik Pangkalan Bun Kuala Pambuang Pangkalan Banteng U D U U U Parenggean U U U A G U U U U U U Ketapang Sukadana Sukadana Tayan Ngabang Bengkayang Sambas Singkawang Mempawah Parit Baru Siantan Sei Raya Kota Baru Sanggau Sekadau Sintang Putussibau Nanga Pinoh Kota Baru SERAWAK (MALAYSIA) 1 4 PLTG/MG Pontianak 100 MW-2017 PLTU Ketapang PLN : 20 MW-2015 IPP : 14 MW-2015 PLTU Parit Baru 100 MW-2015 PLTU Kalbar-2 2x200 MW-2020/21 PLTU Pantai Kura-Kura 55 MW-2015 PLTU Parit Baru Loan China 100 MW-2016 PLTU Kalbar-1 200 MW-2018/19 PLTA Nanga Pinoh 98 MW-2022 PLTG/MG Tj. Selor 15 MW-2015 PLTU Tj. Selor 14 MW-2014 PLTU Tj. Redep 14 MW-2014 PLTU Embalut (Eksp.) 50 MW-2014 PLTG Kaltim Peaking 100 MW-2013 PLTG Kaltim Peaker 2 100 MW-2016 PLTG Kaltim Peaker 3 50 MW-2021 PLTA Kelai 55 MW-2022 PLTU Kaltim-2 200 MW-2017/18 PLTG/MG Bangkanai 280 MW-2015/16/17 PLTU Kaltim-3 300 MW-2020/21 PLTGU Senipah 117 MW-2013/17 PLTU Muara Jawa 220 MW-2014 PLTU Kalsel-1 65 MW-2019 PLTA Kusan 65 MW-2022 PLTU Asam-Asam 130 MW-2013 PLTU Kalselteng-2 200 MW-2017 PLTG Kalsel Peaker 1 200 MW-2016 PLTU Pulang Pisau 120 MW-2015 PLTU Sampit 50 MW-2016 PLTU Kalselteng-3 100 MW-2019 U U G U U A U U U GU U U A U U U U U A G G PLTU Kalselteng-1 200 MW-2018/19 U 14 Transmission Expansion Plan for Sulawesi 15 SULAWESI TENGAH Jeneponto Bulukumba Sinjai Bone Kajuara Soppeng Sengkang Siwa Palopo Wotu Malili Makale Enrekang Sidrap Pare Pinrang Barru Pangkep Tonasa Maros Bosowa A A A U U U U A D G D A Tello Sungguminasa Tallasa U GU G Bakaru SULAWESI BARAT Bantaeng Punagaya U D U G A U P Likupang Bitung Tonsealama Sawangan Tasik Ria Teling Ranomut Paniki Kema Lopana Tomohon Kawangkoan Otam Lolak Bintauna Buroko P P P U Molibagu Isimu U Botupingge U U Marisa G SULAWESI SELATAN Lasusua Kolaka Unaaha Kendari Raha U P U U A U U U U Bau-Bau U A GORONTALO SULAWESI UTARA SULAWESI TENGGARA KALIMANTAN TIMUR Poso Kolonedale A Palu Baru Silae Talise U P Ampana Tentena G Toili Bunta Luwuk Moutong Leok Tolitoli Siboa U Polman Majene Mamuju U Pasangkayu Topoyo Mamuju Baru A A U U U 1 2 3 4 5 6 7 8 9 10 11 13 12 14 15 16 17 18 19 20 21 22 25 23 24 27 28 26 31 30 29 32 1. PLTU Sulut 3 100 MW-2018 2. PLTG/MG Minahasa 150 MW-2016 3. PLTA Sawangan 12 MW-2019 4. PLTU Sewa Amurang 50 MW-2016 5. PLTP Lahendong V & VI 40 MW-2017/18 6. PLTU Sulut I 50 MW-2016/17 7. PLTU TLG 20 MW-2013 8. PLTU Gorontalo 50 MW-2015 9. PLTG Gorontalo 100 MW-2017 10. PLTU Tolitoli 45 MW-2017 11. PLTGU Makassar peaker 450 MW-2016/17/18 12. PLTU Palu 3 100 MW-2018 13. PLTA Poso 2 130 MW-2021/22 14. PLTA Karama 450 MW-2020/21 15. PLTU Mamuju 50 MW-2016 16. PLTA Malea 90 MW-2020 17. PLTA Bonto Batu 110 MW-2019 18. PLTA Bakaru II 126 MW-2020 19. PLTGU Sengkang 180 MW-2013 20. PLTU Sulsel Barru 2 100 MW-2018 21. PLTU Punagaya 200 MW-2016 22. PLTU Jeneponto 2 200 MW-2018 23. PLTA Wotunohu 1 15 MW-2021 24. PLTU Sulbagut 1 100 MW-2019/20 25. PLTA Konawe 50 MW-2021 26. PLTU Kendari 4 100 MW-2024 27. PLTP Laenia 20 MW-2022 28. PLTU Kendari 50 MW-2016 29. PLTU Raha 6 MW-2016 30. PLTU Bau-Bau 20 MW & 14 MW-2014 31. PLTU Wangi 6 MW-2015/16 32. PLTA Poko 234 MW-2020/21 Thank You 16 - 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 IPP PLN Geothermal development plan to 2021 Most geothermal plants are expected to be commissioned between 2016 2020. Exploration and financing are the critical factors for those WKP not yet offered to investors/bidding has not taken place. According to regulation, most geothermal will be developed by IPP (89%) Most geothermal (93%) will be developed in Java and Sumatra. Hydropower development plan to 2021 0 200 400 600 800 1000 1200 1400 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 I n s t a l l e d
C a p a c i t y
( M W ) Year Java-Bali West Indonesia East Indonesia FTP II (11 projects with total 1753 MW) o PLN Projects : 3 large hydro power projects with the total 1269 MW (174 MW under construction, 1040 MW Pre construction and 55 MW under study and design) o IPP Projects : 8 large hydro power projects with the total 484 MW (45 MW HEPP under construction) Non FTP II : o 4 PLNs hydropower projects (266.4 MW) under construction o 4 IPPs hydropower projects (1,409 MW) under PPA negotiation o 39 Mini hydro ( PLN & IPP ) projects (166.2 MW) under construction