Professional Documents
Culture Documents
A Loss Minimum Re-Configuration Algorithm UNDER 3PH UNBALANCED CONDITION
A Loss Minimum Re-Configuration Algorithm UNDER 3PH UNBALANCED CONDITION
I. INTRODUCTION
T has been 20 years since Distribution Automation (DA)
systems including the optimal load transferring and fault
restoration functions began in Japan [1]. Currently, most
distribution feeders have been automated, and the aged DA
facilities must be replaced. In replacing the system, new
concepts must be introduced to the system. Future functions
of DA systems have been discussed in reference [2], etc. In a
new system being developed in Japan, the small DA systems
in business offices are unified and integrated into the ones in
2008 IEEE.
Min .
+ 1
( )
Loss ijt x ij t
t
V kunba
+2
t
I munba
(1)
The first term of the objective function (1) shows the total
distribution loss of the whole distribution network for the all
time zones under consideration. Second term shows the
penalty for the three phases voltage unbalance (the sum of
three phase unbalance of all the nodes). Third term represents
the penalty for the three phase current unbalance at the roots
of feeders (the sum of three phase unbalance of transformer
currents). Coefficients 1 and 2 are the penalty cost for the
sum of the three phase unbalances for voltage and current
respectively. Therefore, to minimize the objective function,
both distribution loss and three-phase unbalance of voltage
and current are minimized. Weights that determine which
factor of the objective function must be minimized most are
determined by selecting the values of 1 and 2 according to
the planners decision.
Constraints are defined for (2) line capacity, (3)
transformer capacity, (4) upper and lower limits of line-to-line
voltages, (5) upper and lower limits of phase voltages, (6)
power supply to all the nodes and (7) radial configuration.
Three phase power flow through Gauss-Seidel method [6] is
employed to calculate the power flow and three phase
unbalance of the voltage and current.
III. SOLUTION ALGORITHM
The formulated problem is a mixed integer programming
(MIP) problem, and is difficult to solve large scale problems.
Therefore, Tabu Search is employed to solve the MIP
problem. So as to reduce the number of decision variables, the
positions of open sectionalizing switches are memorized and
the optimal positions are determined through tabu search. To
apply tabu search, constraints (2)-(5) are relaxed to the
objective function. Then, the neighborhood solutions are
created not to violate constraints (6) and (7). The solution
algorithm is shown below.
(Solution algorithm)
(Step1) Initial three phases power flow is solved by GaussSeidel method.
For the all calculation cases, tabu length is set to10, and
2,000 iterations are calculated. The calculated results, for the
total 12MW (1MW for each position) generation and
1 = 2 = 0.001 are shown in Table 2.
f6
C S/S
(6)
(12)
11
(13)
12
(14) (15)
13
(20) (21)
19
(16)
17
(62)
f5
f4
#2
27
26
(27)
(7)
46
47
(46)
(8)
28
(28)
(47)
(80) (79)
97
81
41
(34)
(42)
34
42
(35)
(43)
35
43
(36)
(44)
60
(49) 52
(48) (50)
(96) (95)
(53)
(27)
28
80
99
(94)
(75)
59
(54)
A S/S
(57)
(6)
(12)
11
(13)
12
(14) (15)
13
(20) (21)
19
(16)
(22)
17
(62)
47
(46)
(8)
(102) (100)
(99)
(98)
(6)
(12)
11
(13)
12
27
26
(27)
(7)
28
(30)
(31)
33
41
(34)
(42)
(35)
#2
(46)
(8)
(47)
(48) (50)
80
99
(94)
(75)
27
26
f5
B S/S
(27)
(7)
28
PGab
f4
#2
(70)
46
47
(46)
(8)
C S/S
11
12
13
19
(16)
(22)
17
59
(54)
(101)
111
(57)
(62)
68
107
(58)
(102) (100)
106
(99)
(98)
C S/S
f1
105
f6
(6)
(12)
11
36
(37)
37
(38) (39)
(61)
27
26
(27)
(7)
28
(30)
(31)
PGab
#2
46
(8)
47
(46)
(47)
33
41
(42)
34
42
(35)
(43)
35
43
(49)
(48) (50)
44 (45)104
(40)
(34)
60
48
(83)
(82)
(84)
(80)
90
(87)
(79)
(92)
(78)
85
89
57
53
(52)
61
B S/S
(55)
(53)
97
81
(80)
90
(87)
(92)
(78)
85
89
(79)
PGab
100
99
97
81
80
98
(75)
76
52
(70)
57
58
(55)
(53)
A S/S
PGbc
(72)
PGbc
(44)
53
(52)
(69) (68)
(74) (73)
(94)
42
(49)
B S/S
(77)
75
43
PGab
60
PGab
(93)
(42)
(36)
f3
(9)
61
(54)
PGbc
59
111
(57)
(58)
#1
112
106
(101)
107
(102)
(100)
(99)
f1
105
(98)
(11)
(20) (21)
PGab
19
(16)
(22)
17
27
26
(27)
(7)
28
PGca
(24)
100
(96) (95)
80
99
(94)
(75)
76
(54)
(69) (68)
(74) (73)
47
(46)
48
(47)
PGbc
36
(37)
37
(38) (39)
PGca
35
(36)
60
(49)
44 (45)104
(40)
89
(79)
(92)
(78)
85
97
81
PGab
99
80
(87)
(75)
(94)
76
(48) (50)
(44)
57
53
(52)
(55)
(53)
(54)
A S/S
(70)
PGbc
75
42
PGbc
B S/S
(93)
(69) (68)
(74) (73)
(72)
(43)
52
PGab
98
(42)
43
f3
61
(77)
90100
(96) (95)
41
(80)
(84)
(86)
(31)
(9)
(59)
62
#1
(82)
(83)
34
46
(60)
63
96
45
(30)
(34)
f4
(65)
(89)
33
#2
(61)
(63)
67
(29) (32)
(28)
68
23
(19)
f5
(62)
(26)
25
PGab
58
(57)
PGca
59
111
(58)
#1
112
(101)
107
(102)
(100)
106
(99)
105
(98)
f1
(11)
(93)
98
A S/S
(70)
75
(72)
#1
112
58
59
(57)
(101)
111
(58)
107
(102)
(100)
106
(99)
105
(98)
f1
(11)
0.6
Objective Function
Line loss [MW]
Volt. Unbalance[%]
Current
Unbalance[%]
(11)
(59)
62
(43)
18
(8)
(77)
(44)
52
f3
96
(38) (39)
(82)
(84)
(96) (95)
41
35
(14) (15)
13
PGbc
#1
(89)
(36)
f4
(9)
62
(86)
36 (37) 37
(59)
63
(29) (32)
(28)
(60)
(63)
45
f5
f1
105
(98)
#1
(83)
44 (45)104
(40)
(18)
(65)
(24)
18
(19)
(99)
96
(86)
(48) (50)
(13)
12
(11)
67
23
(18)
#1
106
107
(100)
(26)
25
(65)
24 (25) 95(90)(88) 91
(31)
48
(47)
PGca
(20) (21)
#1
112
(101)
(60)
63
PGbc
45
(35)
(14) (15)
A S/S
PGbc
#1
112
58
(102)
(61)
(89)
34
(12)
(58)
(63)
23
(30)
PGbc
A S/S
68
(24)
(35)
#1
(6)
111
(57)
67
(29) (32)
(28)
f6
(70)
75
(55)
(53)
(54)
(62)
25
(19)
PGbc
(72)
57
53
(52)
61
(74) (73)
(44)
60
(49) 52
48
(9)
f3
(77)
100
(87)
(96) (95)
(69) (68)
PGca
59
58
(55)
(53)
(22)
18
98
43
35
47
90
97
(43)
(36)
46
57
(20) (21)
19
17
(93)
42
34
f4
81
(86)
(40)
(92)
(78)
85
89
(29) (32)
(28)
(59)
62
(80) (79)
76
(73)
(72)
PGab
(44)
53
(52)
(16)
#1
45
f5
52
(49)
(14) (15)
13
PGab
(11)
96
(84)
(75)
(74)
42
(48) (50)
(34)
(83) (82)
80
99
(94)
98
(77)
(26)
f6
C S/S
f1
105
(65)
(89)
97
81
(93)
75
43
33
24 (25) 95(90)(88) 91
(87)
85
PGab
100
(96) (95)
(92)
(78)
(43)
PGbc
60
67
(24)
18
(19)
(60)
63
89
90
44 (45)104
(79)
(42)
(36)
48
(47)
95
(80)
(84)
41
35
B S/S
#1
(82)
(83)
91
(40)
PGca
PGab
96
(90) (88)
(38) (39)
(18)
(61)
(63)
68
23
(18)
#1
(26)
25
37
f3
61
#1
107 106
(58)
(37)
(9)
(59)
62
(101)
111
46
f4
#2
#1
C S/S
(31)
PGca
(70)
(65)
(86)
36
33
24
(60)
63
PGbc
(89)
(25)
34
112
58
PGca
(35)
(74) (73)
67
(29) (32)
(28)
(61)
(63)
45
(93)
75
(55)
27
26
(62)
68
23
(30)
98
(72)
57
53
(52)
PGbc
(26)
25
(24)
(19)
(77)
90
100
(87)
(92)
(78)
85
89
(22)
17
(34)
(84)
(20) (21)
19
(16)
#1
(86)
(40)
(14) (15)
13
PGab
B S/S
96
33
(13)
12
18
(7)
(29) (32)
48
f3
(9)
61
(12)
11
(18)
67
45
(30)
(59)
62
(6)
f5
24 (25)95(90)(88)91
(19)
(60)
63
f6
#1
(65)
(24)
18
(61)
(63)
68
23
(18)
#1
(26)
25
(22)
C S/S
Case1
0.089
0.089
0.0
0.0
Case2
0.829
0.221
1.822
105.2
Case3
0.649
0.243
1.090
73.46
]
W0.4
M
[s
so
L 0.2
Initial
0
0
12 15 18
Installed DG Capacity[MW]
Fig.7 Distribution loss vs. installed DG capacity
Loss for
=0
Loss for
=0.001
BIOGRAPHIES
800
]%
[e 600
sn
laa 400
bn 200
U
Initial
0
0
9 12 15 18
Unbalanse
for =0
Unbalanse
for =0.001
Instaled DG Capasity[MW]
(SICE) of Japan..
Fig.8 Average Tr. current unbalance vs. DG capacities
VI. REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]