LARSEN & TOUBRO ATCO SAUDI LLC

Wasit Inlet & Gas Processing Package-1


PROCEDURE FOR REPAIR TOUCH-UP PAINT OF EQUIPMENT,
STRUCTURAL AND PIPING



Date Document No. Rev. Page
13-AUG-2014 LTCWASITQCPR-18 0 Page 1 of 10


TABLE OF CONTENTS
1. PURPOSE
2. SCOPE
3. DEFINITIONS
4. REFERENCES
5. RESPONSIBILITIES
6. PROCEDURE
7. QUALITY CONTROL/ INSPECTION
8. SAFETY PRECUATIONS
9. ATTACHMENTS
9.1 APCS Painting system for piping
9.2 Organization chart
9.3 JSA




LARSEN & TOUBRO ATCO SAUDI LLC


Wasit Inlet & Gas Processing Package-1
PROCEDURE FOR REPAIR TOUCH-UP PAINT OF EQUIPMENT,
STRUCTURAL AND PIPING



Date Document No. Rev. Page
13-AUG-2014 LTCWASITQCPR-18 0 Page 2 of 10


1. PURPOSE
The purpose of this procedure is to assure proper paint applications, safe and controlled touch-up
painting of piping and components, equipment and structural steels in the field using correct materials
and equipment in accordance with SAUDI ARAMCO project specifications.
2. SCOPE
This method is applicable to piping and components, equipment and structural steels that require
touch-up/repair painting after installation. It does not cover FBE coated pipe. This applies to Paint
damage during transportation, handling and erection.
3. DEFINITIONS
Coating : an application of protective or decorative covering which can be
in the form of liquid, paste, tape or powder.
RFI : Request for Inspection
AFC : Approved for Construction
APCS : Approved protective coating system
SATIP : Saudi Aramco typical inspection plan
SAES : Saudi Aramco Engineering Standards
SAEP : Saudi Aramco Engineering Procedure
SAIC : Saudi Aramco Inspection Checklist
SATR : Saudi Aramco Test Report
SAMSS : Saudi Aramco Material System Specifications
WFT : Wet Film Thickness


LARSEN & TOUBRO ATCO SAUDI LLC


Wasit Inlet & Gas Processing Package-1
PROCEDURE FOR REPAIR TOUCH-UP PAINT OF EQUIPMENT,
STRUCTURAL AND PIPING



Date Document No. Rev. Page
13-AUG-2014 LTCWASITQCPR-18 0 Page 3 of 10


DFT : Dry Film Thickness
MSDS : Material Safety Data Sheet

4. REFERENCES
SAES-H-100 : Coating Materials & Application Requirements for Industrial
Facilities
SAES-H-102 : Safety Requirements for Coating Application
SAES-H-101 : Approved Protective Coating System for Industrial Plants &
Equipment
SAES-H- 101V : Approved Saudi Aramco data sheets- painting and coating
SAEP-316 : performance qualification of coating personnel
SAES-H-001 : Coating selection & application requirement for industrial plant &
equipment
SSPC-SP1 : solvent cleaning specification
SSPC-SP2 : hand tool cleaning specification
SSPC-SP3 : power tool cleaning specification
SSPC-PA2 : measurement of dry paint thickness
SAIC-H-2032 : Repair and/ or touch-up coatings
5. RESPONSIBILITIES
Painting Supervisor:


LARSEN & TOUBRO ATCO SAUDI LLC


Wasit Inlet & Gas Processing Package-1
PROCEDURE FOR REPAIR TOUCH-UP PAINT OF EQUIPMENT,
STRUCTURAL AND PIPING



Date Document No. Rev. Page
13-AUG-2014 LTCWASITQCPR-18 0 Page 4 of 10


Ensure full compliance by all painting foremen, painters, scaffolder and labor regarding execution
of the work In accordance with Saudi Aramco project requirement and specifications. Confirm the
availability of material, tool, equipment and required personnel who carry out the work. Conduct
brief meeting with all the involved personnel in painting.
Quality Control Inspector
Monitor daily coating activities and conduct inspections in accordance with approved project
SATIP and associated documents. Prepare daily documentation and final acceptance documents
when required. Maintain close relationship with customer representative.
Safety supervisor
Check the work areas for any unsafe conditions. Ensure that all safety requirements have been
adequately addressed and work shall be carried out in accordance with Saudi Aramco project
safety procedures.
Engineering Department
Prepare method of statement in accordance with project specifications and submit to Saudi
Aramco for review and approval. Provide AFC drawings, material specification and other related
document require on coating job.
6. PROCEDURE
6.1 General requirement
6.1.1 Ensure that supervisor and coating applicator hold valid coating certification card
issued by Saudi Aramco
6.1.2 Saudi Aramco Paint data sheet for coating system (APCS) are always available on
site.
6.1.3 Prepared surfaces and Sanded areas are cleaned of any contaminants by brushing
or by air blowing with clean dry air.


LARSEN & TOUBRO ATCO SAUDI LLC


Wasit Inlet & Gas Processing Package-1
PROCEDURE FOR REPAIR TOUCH-UP PAINT OF EQUIPMENT,
STRUCTURAL AND PIPING



Date Document No. Rev. Page
13-AUG-2014 LTCWASITQCPR-18 0 Page 5 of 10


6.1.4 All edges of the original coating are feathered out at least 50mm beyond bare metal
6.1.5 Gloss of existing coating are removed by sanding or by equivalent means prior to
over coating.
6.1.6 Paint shall not be applied if one of the following conditions exists (unless paint is
specifically formulated for averted condition)
a. Substrate temperature is less than 10
0
C of the temperature limit given in the
applicable Saudi Aramco Data Sheet.
b. Substrate temperature less than 3
0
C above the dew point.
c. Maximum surface temperature during paint application shall not exceed paint
Manufacturer recommendations as per Technical Data Sheet.
6.1.7 Paint material for touch up is supplied by the same manufacturer. If paint material
or coating used for repair/ touch \-up is different from original applied coaing
system, paint material for touch up meets OVER Coating Compatibility Chart (SAES-
H-001)
6.1.8 Paint shall not be applied during adverse weather conditions such as; but not
restricted to following.
a. Wind is strong enough to blow sand, salt spray or other foreign matter to the
surface being painted
b. Rain
6.1.9 Cover areas adjacent to defects with adhesive tape before commencing paint touch-
up, apply paint by observing WFT&DFT requirement for particular system with
required overlapping, maintain the recoating interval period and remove the
adhesive tape.

6.2 Storage


LARSEN & TOUBRO ATCO SAUDI LLC


Wasit Inlet & Gas Processing Package-1
PROCEDURE FOR REPAIR TOUCH-UP PAINT OF EQUIPMENT,
STRUCTURAL AND PIPING



Date Document No. Rev. Page
13-AUG-2014 LTCWASITQCPR-18 0 Page 6 of 10


6.2.1 Paints and thinners shall be stored in well ventilated buildings and storage
temperatures as recommended in manufactures data sheet
6.2.2 Paint material used at construction site must be covered with appropriate canvas,
tarpaulins, or equivalent for temporary storage period not to exceed 14 days
6.2.3 Temperature sensitive polymerization paint materials must be stored in air
conditioned storage area to maintain the temperature as recommended in
manufacturers data sheet
6.2.4 Each paint container should be marked in accordance with 09-SAMSS-060.
6.2.5 Paint should not be used from a container showing sign of leakage
6.2.6 Paint which have exceed the self-life shall be set aside and not be used
6.3 Provide scaffolding and man lift for elevated areas if required.
6.4 Pre inspections to evaluate paint system, type of damages, surface contaminations and
applicable repair paint system shall be done as per Saudi Aramco Applicable Standard and
Procedures.
6.5 Repair procedure for immersion coatings
6.5.1 Surface preparation shall be done as per manufacturers data sheet or Aramco
standard and specification
6.5.2 Clean defective area by solvent or detergent wash.
6.5.3 For areas less than 0.1m
2
, grind to a rough metal surface using at least an 80 grit
disc sander. Feather edge the coating at least 50mm beyond bare metal.
6.5.5 Remove dust and debris by brush or vacuum


LARSEN & TOUBRO ATCO SAUDI LLC


Wasit Inlet & Gas Processing Package-1
PROCEDURE FOR REPAIR TOUCH-UP PAINT OF EQUIPMENT,
STRUCTURAL AND PIPING



Date Document No. Rev. Page
13-AUG-2014 LTCWASITQCPR-18 0 Page 7 of 10


6.5.6 Coating shall be applied observing the WFT and DFT requirements for the
particular system. Recoating intervals shall be in accordance with the
manufacturers data sheets.
6.5.7 Cover areas adjacent to defects with heavy duty textile or fabric adhesive tape
before commencing repair or patch up.
6.5.8 Apply coating by brush for areas less than 0.1m2 to the original specification
except that the first coat of a multi-coat system shall be thinned.
6.6 Repair of coating for Atmospheric services
6.6.1 Surface preparation and application shall be done as per manufacturers data sheet
or Aramco standard/ specification
6.6.2 Using appropriate equipment and tools prepare the surface and apply
paint/coating to repair/ touch up specified equipment, structural steels and piping.
6.6.3 Coating shall be applied observing the WFT and DFT requirements for the
particular system. Re coating intervals shall be accordance with the manufacturers
data sheets
6.6.4 Succeeding application of coats are inspected and accepted per SAIC-H-2030
6.6.5 Total DFT of repair coating is measured per SAIC-H-2031. DFT confirms to the
specific requirement of the respective APCS data sheet.

7. QUALITY CONTROL/INSPECTION
Requirement for quality and acceptance criteria shall confirm to SAES-H-100, section 9.
8. SAFETY PRECAUTION:


LARSEN & TOUBRO ATCO SAUDI LLC


Wasit Inlet & Gas Processing Package-1
PROCEDURE FOR REPAIR TOUCH-UP PAINT OF EQUIPMENT,
STRUCTURAL AND PIPING



Date Document No. Rev. Page
13-AUG-2014 LTCWASITQCPR-18 0 Page 8 of 10


8.1 Read the material data sheet and be aware of manufacturers recommendation.
8.2 Wear full body harness when working at heights
8.3 Wear blasting and painting protective clothing and working gears. The personnel shall
wear breathing apparatus when carrying out internal blasting and spraying activities.
8.4 Secured tools while working at height
8.5 Adequate PPE provide according from MSDS.
8.6 Other safety requirements shall conform to SAES-H-102
8.7 A Job safety Analysis as attached will be implemented during works.
9. ATTACHMENT:
9.1 APCS painting system for piping
9.2 Organization chart
9.3 JSA









LARSEN & TOUBRO ATCO SAUDI LLC


Wasit Inlet & Gas Processing Package-1
PROCEDURE FOR REPAIR TOUCH-UP PAINT OF EQUIPMENT,
STRUCTURAL AND PIPING



Date Document No. Rev. Page
13-AUG-2014 LTCWASITQCPR-18 0 Page 9 of 10


Attachment -9.2
ORGANIZATION CHART
















PAINTING SUPERVISOR
SAFETY OFFICER
PAINTING FOREMAN
PERMIT RECEIVER
PAINTER
PAINTER HELPER
QA/QC


LARSEN & TOUBRO ATCO SAUDI LLC


Wasit Inlet & Gas Processing Package-1
PROCEDURE FOR REPAIR TOUCH-UP PAINT OF EQUIPMENT,
STRUCTURAL AND PIPING



Date Document No. Rev. Page
13-AUG-2014 LTCWASITQCPR-18 0 Page 10 of 10



METHOD OF STATEMENT FOR
REPAIR TOUCH-UP PAINT OF EQUIPMENT, STRUCTURAL AND PIPING
DOCUMENT NO.: LTC-WASIT-QC-PR-18 REV-0


0
13-08-14
Issued for
Approval

Rev. Date Description Prepared By Reviewed By Approved By Approved By

PROJECT WASIT INLET & GAS PROCESSING PACKAGE-1
CONTRACT NO.
6600026167 ( IK )
BI NO.
10-00914-0002
JOB ORDER NO.
11049-D
CLIENT ARAMCO
CONTRACTOR SK ENGINEERING & CONSTRUCTION
SUB-CONTRACTOR LARSEN & TOUBRO ATCO SAUDI LLC