Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 28

ThyssenKrupp

Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004
Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
CONTENTS
SCHEDULE A CONTRACT PRICE
SCHEDULE B SCHEDULE OF RATES - CONTRACT
SCHEDULE B1-B11 SCHEDULE OF RATES - CONTRACT (BREAK DOWN)
SCHEDULE C SCHEDULE OF RATES - HOUR / DAYWORKS RATE
(To be proposed by Contractor)
SCHEDULE OF PRICE AND RATES
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule A
Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
Item No. Description Price Thai Baht
1 Sch.A Mobilization and establishment of site facilities 4,500,000.00
2 Sch.A Management and Supervision 15,800,000.00
3 Sch.A Demobilization from site 1,250,000.00
4 TOTAL LUMP SUM PRICE for Sch.A 21,550,000.00
5 Sch.B1 Pipe fabrication and installation (estimated price) 28,944,194.00
6 Sch.B2 Tie-In work (estimated price) 397,500.00
7 Sch.B3 Pipe supports fabrication and installation (estimated price) 5,576,200.00
8 Sch.B4 Paint pipe spools and pipe supports (estimated price) 2,313,750.00
9 Sch.B5 Installation of Valves (estimated price) 443,400.00
10 Sch.B6 Pressure test (estimated price) 1,250,000.00
11 Sch.B7 NDT (estimated price) 1,003,910.00
12 Sch.B8 Post Weld Heat Treatment (estimated price) -
13 Sch.B9 Equipment Internal Installation (estimated price) 18,457,454.70
14 Sch.B10 Miscellaneous Work (estimated price) 7,020,500.00
15 SUBTOTAL of items 5 - 14 65,406,908.70
16 Profit and Overhead on item - 13 Subtotal 9,811,036.31
17 TOTAL PRICE for Sch.B 75,217,945.01
TOTAL PRICE 96,767,945.01
CONTRACT PRICE
a) The price's set out in this Schedule constitutes the Contract Price for the full performance of the WORKS in accordance with the Contract. The Contract
Price is a lump sum and is inclusive of all costs and the like to perform the WORKS including Temporary Works and Defects Liability. Profit and overhead
shall be included as a separate portion, Item No 7 and shall be fixed and only subject to variance/adjustment if the value of Item No 6 SUBTOTAL is
increased by + (plus) 20% (twenty percent) or decreased - (minus) 20% (twenty percent). The Lump Contract Price is in the currency as stated below and is
fixed and firm and not subject to fluctuation, except as specifically provided for in accordance with the Contract.
b) Where the Contract Price is expressed as" Estimated Contract Price" then the basis of the Contract is Schedule of Rates and the "Estimated Contract
Price" is calculated as the total of all rates items extended by multiplying the estimated quantities by the CONTRACTORS rates. In all other respects rates
and prices shall be inclusive as above.
c) Should the ESTIMATED CONTRACT PRICE be varied by more than 20% (twenty percent) then Contract shall:- 1) If increased by more than 20% (twenty
percent) be entiled to 10% profit and overhead on the amount which exceeds the 20%. 2) If decreased by more than 20% (twenty percent) then decrease
the profit and overhead by 10% when the decreased amount exceeds the 20%
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule A
Title of Works: Piping Fabrication and Erection / Mechanical Erection Rev 00
Section 2: Contract Price Breakdown
Item No. Description Unit Quantity Rate Total Thai Baht Manhours
1 Mobilise to site L/S
1 4,500,000.00 4,500,000.00
2 Management and supervision L/S
1 15,800,000.00 15,800,000.00
3 Demobilise from site L/S
1 1,250,000.00 1,250,000.00
21,550,000.00
CONTRACT PRICE BREAKDOWN
The amounts shown in this Schedule are the breakdown of the Lump Sum Contract Price for accounting and progress payment purposes and are inclusive of all customs duties and
assessments, taxes, insurances, permits, fees, transport, delivery, escorts, craneage, labour, inspection, providing amenities as necessary, consumables, temporary construction materials,
tools, plant, equipment, temporary services, derived from compliance with the requirements of the Contract and other like charges.
TOTAL FOR INDIRECT
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004
Schedule B
Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
Item
No.
Unit
Qty
Estimated
Unit Rate
(Thai Baht)
Amount
Estimated
1 B1 Piping Fabrication and installation
Under Ground Piping
- FRP Pipe DB 663.00 2,500 1,657,500.00
Above Ground Piping
- Welding Type
- Carbon Steel DB 16,199.00 494 8,002,306.00
- Carbon Steel ( to Hot dip Galv. after fab. pipe spool) DB 425.00 1,058 449,650.00
- Stainless Steel TP304L abnd TP316L DB 23,246.00 803 18,666,538.00
- Threaded Type
- Galvanized DB 500.00 250 125,000.00
- Plastic pipe
- PE 100 DB 144 300 43,200.00
2 B2 Tie-in Work
Welding type DB 50.00 7,500 375,000.00
Flanged type Point 5.00 4,500 22,500.00
3 B3 Pipe Support Fabrication & Installation
- Fabrication and Installation Kgs. 51,440.00 108 5,548,200.00
- Installation only (Spring support, etc.) Ea 10.00 2,800 28,000.00
4 B4 Painting Work Sq.m 3,145.00 736 2,313,750.00
5 B5 Valves Installation Ea 756.00 587 443,400.00
6 B6 Pressure Test lot 1.00 1,250,000 1,250,000.00
7 B7 Non Destrcutive Testing Joint 1,979.00 507 1,003,910.00
8 B8 Post Weld Heat Treatment Joint N/A
9 B9 Equipment Internal Installation Lot 1.00 18,457,455 18,457,454.70
10 B10 Miscellaneous Work Lot 1.00 7,020,500 7,020,500.00
TOTAL ESTIMATED CONTRACT PRICE 65,406,908.70
Description
Where the Contract Price is expressed as"Estimated Contract Price" in Schedule A then the basis of the Contract is Schedule of Rates and the "Estimated
Contract Price" is calculated as the total of all rates items below, each extended by multiplying the estimated quantities by the CONTRACTORS rates.
SCHEDULE OF RATES - CONTRACT - B



ThyssenKrupp
Industrial Solutions
Project No. : 01-5004 Schedule B1
Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
Item Unit Q'ty
Est. Unit
Price
Est. Total Price Remarks
1 PIPING WORK 1
1.1 DIRECT COST
1.1.1 Under Ground Piping
1.1.1.1 FRP Pipe
- Pipelines DN: 15 DI - -
- Pipelines DN: 20 DI - -
- Pipelines DN: 25 DI - -
- Pipelines DN: 40 DI - -
- Pipelines DN: 50 DI - -
- Pipelines DN: 80 DI 3 2,500.00 7,500.00
- Pipelines DN: 100 DI 16 2,500.00 40,000.00
- Pipelines DN: 150 DI 198 2,500.00 495,000.00
- Pipelines DN: 200 DI 336 2,500.00 840,000.00
- Pipelines DN: 250 DI 110 2,500.00 275,000.00
- Pipelines DN: 300 DI - -
- Pipelines DN: 350 DI - -
- Pipelines DN: 400 DI - -
- Pipelines DN: 450 DI - -
- Pipelines DN: 500 DI - -
SUBTOTAL FOR UG PIPING 663 1,657,500.00
1.1.2 Above Ground Piping
1.1.2.1 Welding Type
- Carbons Steel (A53 Gr.B, A106 Gr.B, API 5L Gr.B)
- Pipelines DN: 15 DI 1,558 450.00 701,100.00
- Pipelines DN: 20 DI 85 450.00 38,250.00
- Pipelines DN: 25 DI 2,103 450.00 946,350.00
- Pipelines DN: 40 DI 1,684 450.00 757,800.00
- Pipelines DN: 50 DI 2,778 450.00 1,250,100.00
- Pipelines DN: 65 DI 72 450.00 32,400.00
- Pipelines DN: 80 DI 862 450.00 387,900.00
- Pipelines DN: 100 DI 962 550.00 529,100.00
- Pipelines DN: 150 DI 1,615 550.00 888,250.00
- Pipelines DN: 200 DI 1,373 550.00 755,150.00
- Pipelines DN: 250 DI 2,951 550.00 1,623,050.00
- Pipelines DN: 300 DI 156 550.00 85,800.00
- Pipelines DN: 350 DI -
- Pipelines DN: 400 DI -
- Pipelines DN: 450 DI -
- Pipelines DN: 500 DI -
- Pipelines DN: 600 DI -
- Pipelines DN: 700 DI -
- Pipelines DN: 800 DI -
SUBTOTAL FOR AG CABON STEEL 16,199.0 7,995,250.00
- Non-Metallic pipe PE 100 (butt- fusion)
- Pipelines DN: 15 DI 111 300.00 33,300.00
- Pipelines DN: 20 DI - -
- Pipelines DN: 25 DI 33 300.00 9,900.00
- Pipelines DN: 40 DI - -
- Pipelines DN: 50 DI - -
- Pipelines DN: 80 DI - -
- Pipelines DN: 100 DI - -
- Pipelines DN: 150 DI - -
- Pipelines DN: 200 DI - -
The scope of items included in Schedule B1 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this
schedule are a set of quantities, derived electronically from design data. These quantities are issued to clarify the basis of the Schedule of Rates quantities and are for
INFORMATION ONLY to establish the ESTIMATED PRICE. The final quantities for DB will be remeasured on completion of the works and the rate set out in this Schedule will be
applied to the final quantities to establish the final value.
LOY KRATHONG PROJECT
Description
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
ThyssenKrupp
Industrial Solutions
Project No. : 01-5004 Schedule B1
Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
Item Unit Q'ty
Est. Unit
Price
Est. Total Price Remarks
1 PIPING WORK 1
The scope of items included in Schedule B1 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this
schedule are a set of quantities, derived electronically from design data. These quantities are issued to clarify the basis of the Schedule of Rates quantities and are for
INFORMATION ONLY to establish the ESTIMATED PRICE. The final quantities for DB will be remeasured on completion of the works and the rate set out in this Schedule will be
applied to the final quantities to establish the final value.
LOY KRATHONG PROJECT
Description
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
- Pipelines DN: 250 DI - -
- Pipelines DN: 300 DI - -
- Pipelines DN: 350 DI - -
- Pipelines DN: 400 DI - -
- Pipelines DN: 450 DI - -
- Pipelines DN: 500 DI - -
- Pipelines DN: 600 DI - -
- Pipelines DN: 700 DI - -
- Pipelines DN: 800 DI - -
SUBTOTAL FOR AG PE 100 144.0 43,200.00
- Stainless Steel TP-304L
- Pipelines DN: 15 DI 612 600.00 367,200.00
- Pipelines DN: 20 DI 66 600.00 39,600.00
- Pipelines DN: 25 DI 1,730 600.00 1,038,000.00
- Pipelines DN: 40 DI 45 600.00 27,000.00
- Pipelines DN: 50 DI 1,578 600.00 946,800.00
- Pipelines DN: 80 DI 846 600.00 507,600.00
- Pipelines DN: 100 DI 1,238 700.00 866,600.00
- Pipelines DN: 150 DI 749 700.00 524,300.00
- Pipelines DN: 200 DI 1,570 700.00 1,099,000.00
- Pipelines DN: 250 DI 1,118 700.00 782,600.00
- Pipelines DN: 300 DI - -
- Pipelines DN: 350 DI - -
- Pipelines DN: 400 DI 37 850.00 31,450.00
- Pipelines DN: 450 DI - -
- Pipelines DN: 500 DI 46 850.00 39,100.00
- Pipelines DN: 600 DI - -
- Pipelines DN: 700 DI 64 850.00 54,400.00
- Pipelines DN: 750 DI 345 850.00 293,250.00
- Pipelines DN: 800 DI 258 850.00 219,300.00
- Stainless Steel TP-316L
- Pipelines DN: 15 DI 157 700.00 109,900.00
- Pipelines DN: 20 DI 12 700.00 8,400.00
- Pipelines DN: 25 DI 429 700.00 300,300.00
- Pipelines DN: 40 DI 59 700.00 41,300.00
- Pipelines DN: 50 DI 1,615 700.00 1,130,500.00
- Pipelines DN: 80 DI 495 700.00 346,500.00
- Pipelines DN: 100 DI 1,508 850.00 1,281,800.00
- Pipelines DN: 125 DI 5 850.00 4,250.00
- Pipelines DN: 150 DI 5,975 850.00 5,078,750.00
- Pipelines DN: 200 DI 686 850.00 583,100.00
- Pipelines DN: 250 DI 39 1,250.00 48,750.00
- Pipelines DN: 300 DI 47 1,250.00 58,750.00
- Pipelines DN: 350 DI 109 1,250.00 136,250.00
- Pipelines DN: 400 DI - -
- Pipelines DN: 450 DI - -
- Pipelines DN: 500 DI - -
- Pipelines DN: 600 DI 828 1,500.00 1,242,000.00
- Pipelines DN: 700 DI - -
- Pipelines DN: 750 DI 69 1,500.00 103,500.00
- Pipelines DN: 800 DI - -
- Pipelines DN: 900 DI 911 1,500.00 1,366,500.00
ThyssenKrupp
Industrial Solutions
Project No. : 01-5004 Schedule B1
Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
Item Unit Q'ty
Est. Unit
Price
Est. Total Price Remarks
1 PIPING WORK 1
The scope of items included in Schedule B1 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this
schedule are a set of quantities, derived electronically from design data. These quantities are issued to clarify the basis of the Schedule of Rates quantities and are for
INFORMATION ONLY to establish the ESTIMATED PRICE. The final quantities for DB will be remeasured on completion of the works and the rate set out in this Schedule will be
applied to the final quantities to establish the final value.
LOY KRATHONG PROJECT
Description
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
SUBTOTAL FOR AG SS TP 304L,316L 23,246.0 18,676,750.00
1.1.2.2 Threaded Type
- Galvanized Pipe (CS+Hot Dip Galvnized)
- Pipelines DN: 15 (completed with Galvanized) DI -
- Pipelines DN: 20 (completed with Galvanized) DI -
- Pipelines DN: 25 (completed with Galvanized) DI 20 250.00 5,000.00
- Pipelines DN: 40 (completed with Galvanized) DI 25 250.00 6,250.00
- Pipelines DN: 50 (completed with Galvanized) DI 30 250.00 7,500.00
- Pipelines DN: 80 (to be hot dip Galvanized) DI 66 1,200.00 79,200.00
- Pipelines DN: 100 (to be hot dip Galvanized) DI 359 1,200.00 430,800.00
- Pipelines DN: 150 DI -
- Pipelines DN: 200 DI -
- Pipelines DN: 250 DI - -
- Pipelines DN: 300 DI - -
- Pipelines DN: 350 DI - -
- Pipelines DN: 400 DI - -
- Pipelines DN: 450 DI - -
- Pipelines DN: 500 DI - -
- Pipelines DN: 600 DI - -
- Pipelines DN: 700 DI - -
- Pipelines DN: 800 DI - -
SUBTOTAL FOR AG THREADED TYPE 500.0 528,750.00
40,752.0 28,901,450.00
Sub Total to Schedule B1
ThyssenKrupp
LOY KRATHONG PROJECT Industrial Solutions
Schedule B2
Project No. : 01-5004
Rev Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
Heat Trace Heat Trace
Type
THK
(mm)
E=Electrical
S=Steam
Pressure
(Barg)
Temp
(Deg C)
Pressure
(Barg)
Temp
(Deg C)
Type
THK
(mm)
E=Electrical
S=Steam
1 IP-P-VENDOR/BIR-0001 (HOLD) 6" (HOLD) N/A 6 40 8 75 U-1000/2714/6"/CO2 6" 2714 - - N/A 130040-010604-PID-UTL-501 CO2 Vapour VISUAL N/A Flanged
SPX is to confirm the
operating pressure of CO2
2 IP-P-VENDOR/BIR-0002 (HOLD) 4" (HOLD) N/A 20 300 FV/36 350 U-1001/1802/4"/Ve36 4" 1802 H 70 N/A 130040-010604-PID-UTL-501 Ve36 Vapour VISUAL N/A Flanged
3 IP-P-VENDOR/BIR-0003 (HOLD) 2" (HOLD) N/A 16 78 FV/36 300 U-1034/1802/2"/Ec36 2" 1802 H 70 N/A 130040-010604-PID-UTL-501 Ec36 Liquid VISUAL N/A Flanged
4 IP-P-VENDOR/BIR-0004 (HOLD) 4" (HOLD) N/A 3 36 5 50 U-1003/1771/4" /Ep 4" 1771 - - N/A 130040-010604-PID-UTL-501 Ep Liquid VISUAL N/A Flanged
5 IP-P-VENDOR/BIR-0005 (HOLD) 6" (HOLD) N/A 5 36 8 50 U-1004/1701/6"/Eb 6" 1701 - - N/A 130040-010604-PID-UTL-501 Eb Liquid VISUAL N/A Flanged
6 IP-P-VENDOR/BIR-0006 Cooling tower basin N/A (HOLD) N/A 0.05 31 10 50 U-1005/1701/10"/Er 12" 1701 - - N/A 130040-010604-PID-UTL-501 Er Liquid 100 % RT N/A Welded
7 IP-P-VENDOR/BIR-0007 Cooling tower N/A (HOLD) N/A 0.6 38 10 60 U-1006/1701/10"/Err 10" 1701 - - N/A 130040-010604-PID-UTL-501 Err Liquid 100 % RT N/A Welded
8 IP-P-VENDOR/BIR-0008 (HOLD) 8" (HOLD) N/A 11 36 14 50 U-1007/1771/8"/Ei 8" 1771 - - N/A 130040-010604-PID-UTL-501 Ei Liquid 100 % RT N/A Welded
10 IP-P-VENDOR/BIR-0010 40-A/150001-SS5 1 1/2" (HOLD) N/A 7 36 10 50 U-1009/2704/2"/Ai 2" 2704 - - N/A 130040-010604-PID-UTL-501 Ai Vapour 100 % RT N/A Welded
11 IP-P-VENDOR/BIR-0011 (HOLD) 2" (HOLD) N/A 3.2 36 5 50 U-1035/_/2"/H2 2" (HOLD) - - N/A 130040-010604-PID-UTL-501 H2 Vapour 100 % RT N/A Welded
12 IP-P-VENDOR/BIR-0012 (HOLD) (HOLD) (HOLD) N/A 10 36 14 50 U-1154/_/N2 (HOLD) (HOLD) - - N/A 130040-010604-PID-UTL-501 N2 Vapour 100 % RT N/A Welded
GENERAL NOTE
1) SPX is to confirm type of Tie-in above
Type of Tie-in shall be specificed as followings;
Flanged = Tie-in requires bolt up to provided flanges connections.
Welded = Tie-in requires welding to existing lines (hot work and line shut down).
Hot-tap = Tie-in requies installation of valved stub to existing line or split tee for same size connection (avoid shut down).
Cold-tap = Tie-in requires installation to existing line by stub branch or split tee (line shut down line).
2) (HOLD) = SPX to confirm
Insulation Short
descri
ption
of line
Operating
Condition
NDE
PWHT /
Stress
Relieve
Tie-in No.
Existing Line New Line
P&ID No.
Type of Tie-
in (See also
General
Notes)
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
The scope of items included in Schedule B2 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These quantities are issued to clarify the basis of the Schedule of Rates quantities and
are for INFORMATION ONLY to establish the ESTIMATED PRICE. The final quantities for DB will be remeasured on completion of the works and the rate set out in this Schedule will be applied to the final quantities to establish the final value.
Design Condition
New Line No.
Line
Size
(inch)
Remarks Pipe
Class
Insulation
Tie In list Pricing table
Fluid
Service
Fluid
Phase Exiting Line No.
Line Size
(Inch)
Pipe
Class
No.
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule B3
Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
Pipe Support Description Q'ty Weight Kgs Rate per Kgs Price
1. Fabrication and installation
- Fabrication and Install Pipe Shoes, U-bolts, Clamp (Painting is
included) For Carbon Steel Pipe 8,210 120.00 985,200.00
- Fabrication and Install Pipe Shoes, U-bolts, Clamp (Painting is
included) For Stainless Steel Pipe 12,000 120.00 1,440,000.00
- Fabrication and Install Steel standard Pipe Supports Standard
and Special pipe support ( Painting is Included)
For Carbon Steel Pipe and
Stainless 31,230 100.00 3,123,000.00
2. Installation Only
- Install only For Spring Supports 10 2,500.00 25,000.00
For PTFE sliding plate 10 300.00 3,000.00
51,440 5,576,200.00
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
The scope of items included in Schedule C3 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a
set of quantities, derived electronically from design data. These quantities are issued to clarify the basis of the Schedule of Rates quantities and are for INFORMATION ONLY to establish the
ESTIMATED PRICE. The rate set out in this Schedule will be applied to the final quantities to establish the final value.
PIPE SUPPORT FABRICATION&INSTALLATION BY CONTRACTOR
Sub Total to Schedule B3
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004
Schedule B4
Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
Unit rate Total
Q'ty Unit Baht/M
2
Baht
1 A1 Non-Insulated carbon steel (inside building) 1,100.00
- Surface praparation ISO-8501-1 -
- Required primer,intermediate and final layer total dry film thickness 160 micron -
650.00 715,000.00
2 A2 Non-Insulated carbon steel (outside building) 700.00
- Surface praparation-ISO-8501-1 -
- Required primer,intermediate and final layer total dry film thickness 320 micron -
1050.00 735,000.00
3 B1 Non-Insulated galvanized steel (inside building) 15.00
- Surface praparation-Sweep blast -
- Required primer and final layer total dry film thickness 120 micron -
550.00 8,250.00
4 B2 Non-Insulated galvanized steel (outside building) 80.00
- Surface praparation-Sweep blast -
- Required primer, intermediate and final layer total dry film thickness 200 micron -
600.00 48,000.00
5 C2 Insulated carbon steel (outside building) 50.00
- Surface praparation ISO-8501-1 -
- Required primer and final layer total dry film thickness 100 micron -
550.00 27,500.00
6 D1 Insulated stainless steel (inside building) 1,200.00
- Surface praparation-Sweep blast -
- Required primer and final layer total dry film thickness 200 micron - -
650.00 780,000.00
3,145.00 2,313,750.00 Sub Total to Schedule B4
Unit Area
(m
2
)
Total Area
(m
2
)
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
The scope of items included in Schedule B4 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a set of quantities, derived electronically
from design data. These quantities are issued to clarify the basis of the Schedule of Rates quantities and are for INFORMATION ONLY to establish an ESTIMATED PRICE. The final quantities for the painting of the pipe spools will
be remeasurable from the isometric drawings and these rates shall be applied, method of measurement will be from flange face to flange face, measuring through all fittings but excluding valves (valves not painted). Pipe spools with
no flange will be remeasurable from weld joint to weld joint .
Price Table For Painting of Piping Fabrication & Installation
Item
Seq
Paint
System
Paint System
Quantity
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004
Title of Works: Piping Fabrication and Erection / Mechanical Erection Rev 00
Section : Contract Price Breakdown
Quantity Unit price Total price
pc Baht/pc Baht
1 Manual Valve Installation (Flange type) -
- Valves DN: 15 110 200.00 22,000.00
- Valves DN: 20 24 200.00 4,800.00
- Valves DN: 25 276 200.00 55,200.00
- Valves DN: 40 3 250.00 750.00
- Valves DN: 50 64 250.00 16,000.00
- Valves DN: 80 20 350.00 7,000.00
- Valves DN: 100 39 350.00 13,650.00
- Valves DN: 150 73 1,500.00 109,500.00
- Valves DN: 200 9 1,800.00 16,200.00
- Valves DN: 250 20 2,500.00 50,000.00
- Valves DN: 300 1 3,500.00 3,500.00
- Valves DN: 350 -
- Valves DN: 400 -
- Valves DN: 500 -
- Valves DN: 600 -
2 Control Valve, Instruments In-line Installation (Flange Type) -
- DN: 15 10 500.00 5,000.00
- DN: 20
- DN: 25 36 500.00 18,000.00
- DN: 40 -
- DN: 50 17 500.00 8,500.00
- DN: 80 7 -
- DN: 100 8 850.00 6,800.00
- DN: 150 16 2,000.00 32,000.00
- DN: 200 13 3,000.00 39,000.00
- DN: 250 9 3,500.00 31,500.00
- DN: 300 1 4,000.00 4,000.00
-
-
-
756 443,400.00 Sub Total to Schedule B6
Item Description
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Schedule B5
The scope of items included in Schedule B6 are defined in the following table together with the manner in which the items are measured
and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These quantities are
issued to clariy the basis of the Schedule of Rates quantities and are for INFORMATION ONLY to establish the ESTIMATED PRICE. The
final quantities of Valves will be remeasured with Isometric drawings and the rate set out in this Schedule will be applied to the final
quantities to establish the final value.
Table of Vale Installation
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004
Schedule B6
Rev 00
NUMBER RATE EACH TOTAL REMARKED
BLIND IN/OUT Pcs 1 150,000.00 250,000.00
GASKETS Each 1 150,000.00 150,000.00
TEST PACK Pack 1 650,000.00 850,000.00
1,250,000.00 Sub Total to Schedule B7
DESCRIPTION
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Title of Works: Piping Fabrication and Erection / Mechanical Erection
PRICE TABLE FOR PRESURE TEST
THESE ARE THE ESTIMATE NUMBER USED FOR
REFERENCE ONLY. THE COST OF PRESSURE TEST
SHALL BE INCLUDED IN UNIT RATE OF BAHT PER DB.
AS STAGED IN C-9.
ALL PIPING CLASS
Item Unit
PRICE COMPONENT (BAHT)
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Schedule B7
Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
Rate Per joint Other Costs Price
1 Rediographic Exam. (RT)
- RT DN: 15 266 420.00 111,720
- RT DN: 20 50 420.00 21,000
- RT DN: 25 427 420.00 179,340
- RT DN: 40 120 420.00 50,400
- RT DN: 50 300 420.00 126,000
- RT DN: 80 76 420.00 31,920
- RT DN: 100 87 600.00 52,200
- RT DN: 150 139 720.00 100,080
- RT DN: 200 46 900.00 41,400
- RT DN: 250 42 900.00 37,800
- RT DN: 300 2 900.00 1,800
- RT DN: 350 1 1,000.00 1,000
- RT DN: 400 1 1,000.00 1,000
- RT DN: 450 0 -
- RT DN: 500 1 1,250.00 1,250
- RT DN: 600 4 1,500.00 6,000
- RT DN: 700 1 1,750.00 1,750
- RT DN: 750 2 1,750.00 3,500
- RT DN: 800 1 1,750.00 1,750
- RT DN: 900 3 2,000.00 6,000
2 Liquid Dry Penetration Testing (PT)
- PT DN: 15 30 300.00 9,000
- PT DN: 20 25 300.00 7,500
- PT DN: 25 43 300.00 12,900
- PT DN: 40 12 300.00 3,600
- PT DN: 50 - - -
- PT DN: 80 - - -
- PT DN: 100 - - -
- PT DN: 150 - - -
- PT DN: 200 - - -
3 PMI 300.00 650.00 195,000
Sub Total to Schedule B8 1,979.00 1,003,910.00
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Project No. : 01-5004
The scope of items included in Schedule B8 are defined in the following table together with the manner in which the items are measured and payments made. Attached to
this schedule are a set of quantities, derived electronically from design data. These quantities are issued to clarify the basis of the Schedule of Rates quantities and are for
INFORMATION ONLY to ESTABLISH THE ESTIMATED PRICE. The final quantities will measured at the completion of the works and the rates applied to the final
quantitative to establish the final value.
PRICE TABLE FOR PIPE NDT
Item
Number of
joint
PRICE COMPONENTS (BAHT)
Description
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Schedule B8
Rev 00
Title of Works: Piping Fabrication and Erection / Mechanical Erection
Rate Per joint Other Costs Price
1 Post Weld Heat Treatment (PWHT)
- PWHT DN: 15 none
- PWHT DN: 20 none
- PWHT DN: 25 none
- PWHT DN: 40 none
- PWHT DN: 50 none
- PWHT DN: 80 none
- PWHT DN: 100 none
- PWHT DN: 150 none
- PWHT DN: 200 none
- PWHT DN: 250 none
- PWHT DN: 300 none
- PWHT DN: 350 none
- PWHT DN: 400 none
- PWHT DN: 450 none
- PWHT DN: 500 none
-
-
-
Sub Total to Schedule B9 None -
Item
Number of
joint
PRICE COMPONENTS (BAHT)
Description
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Project No. : 01-5004
The scope of items included in Schedule B9 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this
schedule are a set of quantities, derived electronically from design data. These quantities are issued to clarify the basis of the Schedule of Rates quantities and are for
INFORMATION ONLY to ESTABLISH THE ESTIMATED PRICE. The final quantities will measured at the completion of the works and the rates applied to the final
quantitative to establish the final value.
PRICE TABLE FOR PIPE PWHT
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule B9
No. Kg U/P AMOUNT U/P AMOUNT U/P AMOUNT U/P AMOUNT AMOUNT
1 P1 TR-SD/1 SD silo 1 34,000 8.00 272,000.00 25.00 850,000.00 2.00 68,000.00 35.00 1,190,000.00 1,190,000.00
2 P1 TR-SD/2 SD silo 1 34,000 8.00 272,000.00 25.00 850,000.00 2.00 68,000.00 35.00 1,190,000.00 1,190,000.00
3 P1 VB-TRSD/1 SD silo vibrating bottom 1 1,530 8.00 12,240.00 6.00 9,180.00 2.00 3,060.00 16.00 24,480.00 24,480.00
4 P1 VB-TRSD/2 SD silo vibrating bottom 1 1,530 8.00 12,240.00 6.00 9,180.00 2.00 3,060.00 16.00 24,480.00 24,480.00
5 P7 TR/1 Silo 0/50 + 27/50 1 3,000 15.00 45,000.00 60.00 180,000.00 2.00 6,000.00 77.00 231,000.00 231,000.00
6 P7 TR/2 Silo 0/50 + 27/50 1 3,000 15.00 45,000.00 60.00 180,000.00 2.00 6,000.00 77.00 231,000.00 231,000.00
7 P7 TR/3 Silo 0/50 + 27/50 1 3,000 15.00 45,000.00 60.00 180,000.00 2.00 6,000.00 77.00 231,000.00 231,000.00
8 P7 TR/4 Silo 0/50 + 27/50 1 3,000 15.00 45,000.00 60.00 180,000.00 2.00 6,000.00 77.00 231,000.00 231,000.00
9 P7 VB-TR/1 Vibrating bin activators 0/50 + 27/50 1 290 15.00 4,350.00 10.00 2,900.00 5.00 1,450.00 30.00 8,700.00 8,700.00
10 P7 VB-TR/2 Vibrating bin activators 0/50 + 27/50 1 290 15.00 4,350.00 10.00 2,900.00 5.00 1,450.00 30.00 8,700.00 8,700.00
11 P7 VB-TR/3 Vibrating bin activators 0/50 + 27/50 1 290 15.00 4,350.00 10.00 2,900.00 5.00 1,450.00 30.00 8,700.00 8,700.00
12 P7 VB-TR/4 Vibrating bin activators 0/50 + 27/50 1 290 15.00 4,350.00 10.00 2,900.00 5.00 1,450.00 30.00 8,700.00 8,700.00
13 P7 TR/5 Silo 0/13 1 3,000 15.00 45,000.00 60.00 180,000.00 2.00 6,000.00 77.00 231,000.00 231,000.00
14 P7 TR/6 Silo 0/13 1 3,000 15.00 45,000.00 60.00 180,000.00 2.00 6,000.00 77.00 231,000.00 231,000.00
15 P7 TR/7 Silo 0/13 1 3,000 15.00 45,000.00 60.00 180,000.00 2.00 6,000.00 77.00 231,000.00 231,000.00
16 P7 TR/8 Silo 0/13 1 3,000 15.00 45,000.00 60.00 180,000.00 2.00 6,000.00 77.00 231,000.00 231,000.00
17 P7 VB-TR/5 Vibrating bin activators 0/13 1 290 15.00 4,350.00 10.00 2,900.00 5.00 1,450.00 30.00 8,700.00 8,700.00
18 P7 VB-TR/6 Vibrating bin activators 0/13 1 290 15.00 4,350.00 10.00 2,900.00 5.00 1,450.00 30.00 8,700.00 8,700.00
19 P7 VB-TR/7 Vibrating bin activators 0/13 1 290 15.00 4,350.00 10.00 2,900.00 5.00 1,450.00 30.00 8,700.00 8,700.00
20 P7 VB-TR/8 Vibrating bin activators 0/13 1 290 15.00 4,350.00 10.00 2,900.00 5.00 1,450.00 30.00 8,700.00 8,700.00
21 P14 ECR-TRSD/1 SD silo outlet rotary valve 1 160 25.00 4,000.00 20.00 3,200.00 5.00 800.00 50.00 8,000.00 8,000.00
22 P14 ECR-TRSD/2 SD silo outlet rotary valve 1 160 25.00 4,000.00 20.00 3,200.00 5.00 800.00 50.00 8,000.00 8,000.00
23 P14 TR-EMOTSD/1 Lump breaker hopper 1 1,000 8.00 8,000.00 8.00 8,000.00 3.00 3,000.00 19.00 19,000.00 19,000.00
Total (BAHT)
Labor (BAHT) SubTotal Item Tag Equipment (BAHT)
Tool & Consum.
(BAHT)
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Section 2: Contract Price Breakdown
The scope of items included in Schedule B5 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These qua
Installation Cost
Empty
Weight
Equip
Type
Description
Price Table for Equipment Installation
Remark
Qty
Page 17 of 36
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule B9
No. Kg U/P AMOUNT U/P AMOUNT U/P AMOUNT U/P AMOUNT AMOUNT
Total (BAHT)
Labor (BAHT) SubTotal Item Tag Equipment (BAHT)
Tool & Consum.
(BAHT)
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Section 2: Contract Price Breakdown
The scope of items included in Schedule B5 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These qua
Installation Cost
Empty
Weight
Equip
Type
Description
Price Table for Equipment Installation
Remark
Qty
24 P14 TR-EMOTSD/2 Lump breaker hopper 1 1,000 8.00 8,000.00 8.00 8,000.00 3.00 3,000.00 19.00 19,000.00 19,000.00
25 P14 EMOT-SD/1 SD lump breaker 1 450 12.00 5,400.00 10.00 4,500.00 5.00 2,250.00 27.00 12,150.00 12,150.00
26 P14 EMOT-SD/2 SD lump breaker 1 450 12.00 5,400.00 10.00 4,500.00 5.00 2,250.00 27.00 12,150.00 12,150.00
27 P14 TR-TPVSD DVSD buffer hopper 1 400 12.00 4,800.00 10.00 4,000.00 5.00 2,000.00 27.00 10,800.00 10,800.00
28 P14 TPV-SD DVSD dosing screw 1 850 15.00 12,750.00 15.00 12,750.00 5.00 4,250.00 35.00 29,750.00 29,750.00
29 P14 CP-TPPSD SD pneumatic transport compressor 1 580 15.00 8,700.00 18.00 10,440.00 5.00 2,900.00 38.00 22,040.00 22,040.00
30 P14 CY-TPPSD SD pneumatic transport cyclone 1 1,000 8.00 8,000.00 12.00 12,000.00 5.00 5,000.00 25.00 25,000.00 25,000.00
31 R ECR-CYSVA Rotary valve outlet CYSVA 1 180 18.00 3,240.00 56.00 10,080.00 28.00 5,040.00 102.00 18,360.00 18,360.00
32 R ECR-DPSVA Rotary valve outlet DPCYSVA 1 180 18.00 3,240.00 56.00 10,080.00 28.00 5,040.00 102.00 18,360.00 18,360.00
33 R ECR-VT/1 Rotary valve to sieves 1 180 18.00 3,240.00 56.00 10,080.00 28.00 5,040.00 102.00 18,360.00 18,360.00
34 R ECR-VT/2 Rotary valve to sieves 1 180 18.00 3,240.00 56.00 10,080.00 28.00 5,040.00 102.00 18,360.00 18,360.00
35 R ECR-TR/1 BIR Silo outlet rotary valve 1 150 18.00 2,700.00 56.00 8,400.00 28.00 4,200.00 102.00 15,300.00 15,300.00
36 R ECR-TR/2 BIR Silo outlet rotary valve 1 150 18.00 2,700.00 56.00 8,400.00 28.00 4,200.00 102.00 15,300.00 15,300.00
37 R ECR-TR/3 BIR Silo outlet rotary valve 1 150 18.00 2,700.00 56.00 8,400.00 28.00 4,200.00 102.00 15,300.00 15,300.00
38 R ECR-TR/4 BIR Silo outlet rotary valve 1 150 18.00 2,700.00 56.00 8,400.00 28.00 4,200.00 102.00 15,300.00 15,300.00
39 R ECR-TR/5 BIR Silo outlet rotary valve 1 150 18.00 2,700.00 56.00 8,400.00 28.00 4,200.00 102.00 15,300.00 15,300.00
40 R ECR-TR/6 BIR Silo outlet rotary valve 1 150 18.00 2,700.00 56.00 8,400.00 28.00 4,200.00 102.00 15,300.00 15,300.00
41 R ECR-TR/7 BIR Silo outlet rotary valve 1 150 18.00 2,700.00 56.00 8,400.00 28.00 4,200.00 102.00 15,300.00 15,300.00
42 R ECR-TR/8 BIR Silo outlet rotary valve 1 150 18.00 2,700.00 56.00 8,400.00 28.00 4,200.00 102.00 15,300.00 15,300.00
43 R VD-TRSD/1 SD silo inlet diverter valve 1 70 30.00 2,100.00 57.00 3,990.00 28.00 1,960.00 115.00 8,050.00 8,050.00
44 R VD-TRSD/2 SD silo inlet diverter valve 1 70 30.00 2,100.00 57.00 3,990.00 28.00 1,960.00 115.00 8,050.00 8,050.00
45 R VD-/1 BIR silos feeding diverter valve1 1 40 30.00 1,200.00 57.00 2,280.00 28.00 1,120.00 115.00 4,600.00 4,600.00
46 R VD-/2 BIR silos feeding diverter valve2 1 40 30.00 1,200.00 57.00 2,280.00 28.00 1,120.00 115.00 4,600.00 4,600.00
Page 18 of 36
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule B9
No. Kg U/P AMOUNT U/P AMOUNT U/P AMOUNT U/P AMOUNT AMOUNT
Total (BAHT)
Labor (BAHT) SubTotal Item Tag Equipment (BAHT)
Tool & Consum.
(BAHT)
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Section 2: Contract Price Breakdown
The scope of items included in Schedule B5 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These qua
Installation Cost
Empty
Weight
Equip
Type
Description
Price Table for Equipment Installation
Remark
Qty
47 R VD-TPVTR/9 Diverter valve outlet TPV 0/13 (FFS 1 or 2) 1 30 30.00 900.00 57.00 1,710.00 28.00 840.00 115.00 3,450.00 3,450.00
48 R VD-TPVTR/8 Diverter valve outlet TPV 0/13 Pharma (FFS 1 or 2) 1 30 30.00 900.00 57.00 1,710.00 28.00 840.00 115.00 3,450.00 3,450.00
49 R VD-TPVTR/7 Diverter valve outlet TPV 0/50 + 27/50 (FFS1 or 2) 1 30 30.00 900.00 57.00 1,710.00 28.00 840.00 115.00 3,450.00 3,450.00
50 A TPV-ESS Centrifuge outlet screw conveyor 1 525 60.00 31,500.00 15.00 7,875.00 8.00 4,200.00 83.00 43,575.00 43,575.00
51 A TPV-TR/4 Screw conveyor to silos 0/13 Pharma 1 800 60.00 48,000.00 15.00 12,000.00 8.00 6,400.00 83.00 66,400.00 66,400.00
52 A TPV-TR/5 Screw conveyor to silos 0/13 FCC 1 800 60.00 48,000.00 15.00 12,000.00 8.00 6,400.00 83.00 66,400.00 66,400.00
53 A TPV-TR/3 Screw conveyor to silo 27/50 (or 0/50) 1 800 60.00 48,000.00 15.00 12,000.00 8.00 6,400.00 83.00 66,400.00 66,400.00
54 A TPV-TR/2 Screw conveyor to silos 0/50 TEC/Z or HN 1 800 60.00 48,000.00 15.00 12,000.00 8.00 6,400.00 83.00 66,400.00 66,400.00
55 A TPV-TR/1 Screw conveyor to silos 0/50 TEC/Z 1 700 60.00 42,000.00 15.00 10,500.00 8.00 5,600.00 83.00 58,100.00 58,100.00
56 A TPV-TR/6 Screw conveyor left/right outlet silos 0/50 TEC/Z or HN 1 800 60.00 48,000.00 15.00 12,000.00 8.00 6,400.00 83.00 66,400.00 66,400.00
57 A TPV-TR/7 Screw conveyor left/right outlet silos 0/50 + 27/50 1 800 60.00 48,000.00 15.00 12,000.00 8.00 6,400.00 83.00 66,400.00 66,400.00
58 A TPV-TR/9 Screw conveyor left/right outlet silos 0/13 1 800 60.00 48,000.00 15.00 12,000.00 8.00 6,400.00 83.00 66,400.00 66,400.00
59 A TPV-TR/8 Screw conveyor left/right outlet silos 0/13 Pharma 1 800 60.00 48,000.00 15.00 12,000.00 8.00 6,400.00 83.00 66,400.00 66,400.00
60 A TPV-FFS/1 Screw conveyor to FFS1 1 500 60.00 30,000.00 15.00 7,500.00 8.00 4,000.00 83.00 41,500.00 41,500.00
61 A TPV-FFS/2 Screw conveyor to FFS2 1 400 60.00 24,000.00 15.00 6,000.00 8.00 3,200.00 83.00 33,200.00 33,200.00
62 A TPV-BB Screw conveyor to BB 1 1,500 60.00 90,000.00 15.00 22,500.00 8.00 12,000.00 83.00 124,500.00 124,500.00
63 A TPV-SVA SVA inlet screw conveyor 1 500 60.00 30,000.00 15.00 7,500.00 8.00 4,000.00 83.00 41,500.00 41,500.00
64 P6 VT/1 Vibrating sieve 1 1 1,700 45.00 76,500.00 15.00 25,500.00 8.00 13,600.00 68.00 115,600.00 115,600.00
65 P6 VT/2 Vibrating sieve 2 1 1,700 45.00 76,500.00 15.00 25,500.00 8.00 13,600.00 68.00 115,600.00 115,600.00
66 P6 VT-FFS/1 Safety sieve # 3,2 x 3,2 mm to FFS1 1 450 25.00 11,250.00 20.00 9,000.00 5.00 2,250.00 50.00 22,500.00 22,500.00
67 P6 VT-FFS/2 Safety sieve # 3,2 x 3,2 mm to FFS2 1 450 25.00 11,250.00 20.00 9,000.00 5.00 2,250.00 50.00 22,500.00 22,500.00
68 A TRS-VT Sieves distribution conveyor 1 2,210 45.00 99,450.00 15.00 33,150.00 5.00 11,050.00 65.00 143,650.00 143,650.00
69 A TRS-0/13 Conveyor to TPV 0/13 1 2,500 45.00 112,500.00 15.00 37,500.00 5.00 12,500.00 65.00 162,500.00 162,500.00
Page 19 of 36
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule B9
No. Kg U/P AMOUNT U/P AMOUNT U/P AMOUNT U/P AMOUNT AMOUNT
Total (BAHT)
Labor (BAHT) SubTotal Item Tag Equipment (BAHT)
Tool & Consum.
(BAHT)
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Section 2: Contract Price Breakdown
The scope of items included in Schedule B5 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These qua
Installation Cost
Empty
Weight
Equip
Type
Description
Price Table for Equipment Installation
Remark
Qty
70 A TRS-FFS/2 Collecting conveyor to FFS2 1 6,000 35.00 210,000.00 18.00 108,000.00 5.00 30,000.00 58.00 348,000.00 348,000.00
71 A TRS-FFS/1 Collecting conveyor to FFS1 1 2,000 30.00 60,000.00 18.00 36,000.00 5.00 10,000.00 53.00 106,000.00 106,000.00
72 A DV-SD SD dissolver 1 7,573 20.00 151,460.00 12.00 90,876.00 2.00 15,146.00 34.00 257,482.00 257,482.00
73 A CR BIR crystalliser 1 34,320 6.00 205,920.00 15.00 514,800.00 1.00 34,320.00 22.00 755,040.00 755,040.00
74 A RG-CR CR cooler 1 35,525 6.00 213,150.00 15.00 532,875.00 1.00 35,525.00 22.00 781,550.00 781,550.00
75 A RS-LDCB LDCB vessel 1 17,428 8.00 139,420.80 10.00 174,276.00 2.00 34,855.20 20.00 348,552.00 348,552.00
76 A RS-EM Mother liquor vessel 1 9,123 10.00 91,233.00 10.00 91,233.00 2.00 18,246.60 22.00 200,712.60 200,712.60
77 A FLS LDCB sand filter 1 13,016 10.00 130,164.00 10.00 130,164.00 2.00 26,032.80 22.00 286,360.80 286,360.80
78 A RS-HCY HCY vessel 1 217 25.00 5,415.00 25.00 5,415.00 5.00 1,083.00 55.00 11,913.00 11,913.00
79 A RS-Edch Hot demineralised water vessel 1 5,870 10.00 58,695.00 12.00 70,434.00 5.00 29,347.50 27.00 158,476.50 158,476.50
80 A HCY BIR slurry hydrocyclone 1 352 25.00 8,807.50 12.00 4,227.60 5.00 1,761.50 42.00 14,796.60 14,796.60
81 A CY-SVA SVA cyclone 1 2,314 15.00 34,710.00 100.00 231,400.00 5.00 11,570.00 120.00 277,680.00 277,680.00
82 A CV-SVA SVA feeding small tank 1 1,902 15.00 28,533.00 15.00 28,533.00 5.00 9,511.00 35.00 66,577.00 66,577.00
83 A HX-RGCR Heat exchanger for RGCR 1 1,369 10.00 13,690.00 10.00 13,690.00 5.00 6,845.00 25.00 34,225.00 34,225.00
84 A RH-Ed Demineralised water heater 1 170 10.00 1,700.00 10.00 1,700.00 5.00 850.00 25.00 4,250.00 4,250.00
85 A FLC-CO2 CO2 filter 1 390 10.00 3,900.00 10.00 3,900.00 5.00 1,950.00 25.00 9,750.00 9,750.00
86 A FLC-CaCl2 CaCl2 filter 1 390 10.00 3,900.00 10.00 3,900.00 5.00 1,950.00 25.00 9,750.00 9,750.00
87 A FL-Ed Demineralised water filter 1 110 10.00 1,100.00 10.00 1,100.00 5.00 550.00 25.00 2,750.00 2,750.00
88 R AGIT-DVSD DVSD agitator 1 1,560 35.00 54,600.00 30.00 46,800.00 4.00 6,240.00 69.00 107,640.00 107,640.00
89 R AGIT-CVSVA CVSVA agitator 1 1,500 35.00 52,500.00 30.00 45,000.00 4.00 6,000.00 69.00 103,500.00 103,500.00
90 R PC-CR CR recycle pump 1 4,130 60.00 247,800.00 13.00 53,690.00 6.00 24,780.00 79.00 326,270.00 326,270.00
91 R PC-RGCR RGCR recycle Ed pump 1 3,000 60.00 180,000.00 15.00 45,000.00 8.50 25,500.00 83.50 250,500.00 250,500.00
92 R PC-DVSD DVSD outlet pump 1 600 60.00 36,000.00 50.00 30,000.00 17.00 10,200.00 127.00 76,200.00 76,200.00
Page 20 of 36
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule B9
No. Kg U/P AMOUNT U/P AMOUNT U/P AMOUNT U/P AMOUNT AMOUNT
Total (BAHT)
Labor (BAHT) SubTotal Item Tag Equipment (BAHT)
Tool & Consum.
(BAHT)
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Section 2: Contract Price Breakdown
The scope of items included in Schedule B5 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These qua
Installation Cost
Empty
Weight
Equip
Type
Description
Price Table for Equipment Installation
Remark
Qty
93 R PC-LDCB LDCB pump 1 600 60.00 36,000.00 50.00 30,000.00 17.00 10,200.00 127.00 76,200.00 76,200.00
94 R PC-LCR BIR slurry outlet CR pump 1 600 60.00 36,000.00 50.00 30,000.00 17.00 10,200.00 127.00 76,200.00 76,200.00
95 R PC-Edch1 Edch Pump 1 600 60.00 36,000.00 50.00 30,000.00 17.00 10,200.00 127.00 76,200.00 76,200.00
96 R PC-Edch2 Edch Pump 1 600 60.00 36,000.00 50.00 30,000.00 17.00 10,200.00 127.00 76,200.00 76,200.00
97 R PC-Er Cooling water pump 1 2,600 60.00 156,000.00 18.00 46,800.00 4.00 10,400.00 82.00 213,200.00 213,200.00
98 R PC-EM Mother liquor pump 1 600 60.00 36,000.00 18.00 10,800.00 4.00 2,400.00 82.00 49,200.00 49,200.00
99 R PC-VSB/1 VSB pumps 1 110 60.00 6,600.00 25.00 2,750.00 12.00 1,320.00 97.00 10,670.00 10,670.00
100 R PC-VSB/2 VSB pumps 1 110 60.00 6,600.00 25.00 2,750.00 12.00 1,320.00 97.00 10,670.00 10,670.00
101 R PC-HXRGCR HXRGCR pump 1 500 60.00 30,000.00 25.00 12,500.00 12.00 6,000.00 97.00 48,500.00 48,500.00
102 R PC-EdGN Ed pump to GN Ve 1 1,300 60.00 78,000.00 25.00 32,500.00 12.00 15,600.00 97.00 126,100.00 126,100.00
103 R PC-FO1 Wash sump (1st compartment) vertical pump 1 600 60.00 36,000.00 25.00 15,000.00 12.00 7,200.00 97.00 58,200.00 58,200.00
104 R PC-FO2 Wash sump vertical pump 1 600 60.00 36,000.00 25.00 15,000.00 12.00 7,200.00 97.00 58,200.00 58,200.00
105 R PC-PDA/1 CaCl2 30% dosing pump 1 200 60.00 12,000.00 25.00 5,000.00 12.00 2,400.00 97.00 19,400.00 19,400.00
106 R PC-PDA/2 CaCl2 30% dosing pump 1 200 60.00 12,000.00 25.00 5,000.00 12.00 2,400.00 97.00 19,400.00 19,400.00
107 P9 ESS Centrifuge 1 5,000 60.00 300,000.00 10.00 50,000.00 5.00 25,000.00 75.00 375,000.00 375,000.00
108 A VTL-DVSD DVSD fan 1 500 60.00 30,000.00 10.00 5,000.00 5.00 2,500.00 75.00 37,500.00 37,500.00
109 A VTL-WET Wet building wall extraction fan 1 200 60.00 12,000.00 10.00 2,000.00 5.00 1,000.00 75.00 15,000.00 15,000.00
110 P3 VTL-SVA SVA fan with silencer 1 2,000 60.00 120,000.00 20.00 40,000.00 5.00 10,000.00 85.00 170,000.00 170,000.00
111 P3 FL-SVA SVA fan inlet air filter (two stages) 1 2,000 60.00 120,000.00 20.00 40,000.00 5.00 10,000.00 85.00 170,000.00 170,000.00
112 P3 RH-SVA SVA air heater 1 1,200 45.00 54,000.00 20.00 24,000.00 5.00 6,000.00 70.00 84,000.00 84,000.00
113 P DP-FFS/1 Packaging dedusters (bag filters, one on each TRS) 1 2,700 45.00 121,500.00 15.00 40,500.00 5.00 13,500.00 65.00 175,500.00 175,500.00
114 P DP-FFS/2 Packaging dedusters (bag filters, one on each TRS) 1 2,700 45.00 121,500.00 15.00 40,500.00 5.00 13,500.00 65.00 175,500.00 175,500.00
115 P VTL-DPFFS/1 Fans for packaging dedusters 1 280 45.00 12,600.00 20.00 5,600.00 5.00 1,400.00 70.00 19,600.00 19,600.00
Page 21 of 36
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule B9
No. Kg U/P AMOUNT U/P AMOUNT U/P AMOUNT U/P AMOUNT AMOUNT
Total (BAHT)
Labor (BAHT) SubTotal Item Tag Equipment (BAHT)
Tool & Consum.
(BAHT)
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Section 2: Contract Price Breakdown
The scope of items included in Schedule B5 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These qua
Installation Cost
Empty
Weight
Equip
Type
Description
Price Table for Equipment Installation
Remark
Qty
116 P ECR-DPFFS/1 Rotary valves outlet packaging dedusters 1 300 45.00 13,500.00 20.00 6,000.00 5.00 1,500.00 70.00 21,000.00 21,000.00
117 P VTL-DPFFS/2 Fans for packaging dedusters 1 280 45.00 12,600.00 20.00 5,600.00 5.00 1,400.00 70.00 19,600.00 19,600.00
118 P ECR-DPFFS/2 Rotary valves outlet packaging dedusters 1 300 45.00 13,500.00 20.00 6,000.00 5.00 1,500.00 70.00 21,000.00 21,000.00
119 P DP-TRSD SD silos dust filter 1 2,000 45.00 90,000.00 35.00 70,000.00 5.00 10,000.00 85.00 170,000.00 170,000.00
120 P DP-VT Sieves dedusting - bag filter 1 15 35.00 525.00 25.00 375.00 20.00 300.00 80.00 1,200.00 1,200.00
121 P DP-TRS0/13 TRS dedusting - bag filter 1 15 35.00 525.00 25.00 375.00 20.00 300.00 80.00 1,200.00 1,200.00
122 P DP-TR/1 BIR Silo deduster (bag filter) 1 15 35.00 525.00 25.00 375.00 20.00 300.00 80.00 1,200.00 1,200.00
123 P DP-TR/2 BIR Silo deduster (bag filter) 1 15 35.00 525.00 25.00 375.00 20.00 300.00 80.00 1,200.00 1,200.00
124 P DP-TR/3 BIR Silo deduster (bag filter) 1 15 35.00 525.00 25.00 375.00 20.00 300.00 80.00 1,200.00 1,200.00
125 P DP-TR/4 BIR Silo deduster (bag filter) 1 15 35.00 525.00 25.00 375.00 20.00 300.00 80.00 1,200.00 1,200.00
126 P DP-TR/5 BIR Silo deduster (bag filter) 1 15 35.00 525.00 25.00 375.00 20.00 300.00 80.00 1,200.00 1,200.00
127 P DP-TR/6 BIR Silo deduster (bag filter) 1 15 35.00 525.00 25.00 375.00 20.00 300.00 80.00 1,200.00 1,200.00
128 P DP-TR/7 BIR Silo deduster (bag filter) 1 15 35.00 525.00 25.00 375.00 20.00 300.00 80.00 1,200.00 1,200.00
129 P DP-TR/8 BIR Silo deduster (bag filter) 1 15 35.00 525.00 25.00 375.00 20.00 300.00 80.00 1,200.00 1,200.00
130 P FLM-DPSVA CYSVA bag filter 1 1,280 35.00 44,800.00 35.00 44,800.00 5.00 6,400.00 75.00 96,000.00 96,000.00
131 P DP-SVA CYSVA deduster 1 1,280 35.00 44,800.00 35.00 44,800.00 5.00 6,400.00 75.00 96,000.00 96,000.00
132 P10 VSB Venturi scrubber 1 6,200 15.00 93,000.00 20.00 124,000.00 5.00 31,000.00 40.00 248,000.00 248,000.00
133 P11 FLCA/1-2 LDCB carbon bed 1 99,050 3.00 297,150.00 5.00 495,250.00 1.00 99,050.00 9.00 891,450.00 891,450.00
134 P2 BWF/1-2 Second step LDCB filter 1 860 25.00 21,500.00 25.00 21,500.00 5.00 4,300.00 55.00 47,300.00 47,300.00
135 P4 GN-Ve Steam generator (main heat exchanger) 1 2,050 25.00 51,250.00 10.00 20,500.00 5.00 10,250.00 40.00 82,000.00 82,000.00
136 P4 RH-GN Steam generator (pre heater) 1 420 25.00 10,500.00 5.00 2,100.00 5.00 2,100.00 35.00 14,700.00 14,700.00
137 P4 RS-EcGNVe GNVe condensates vessel 1 2,050 25.00 51,250.00 10.00 20,500.00 5.00 10,250.00 40.00 82,000.00 82,000.00
138 P4 SEP-Ve Steam separator 1 2,050 25.00 51,250.00 10.00 20,500.00 5.00 10,250.00 40.00 82,000.00 82,000.00
Page 22 of 36
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule B9
No. Kg U/P AMOUNT U/P AMOUNT U/P AMOUNT U/P AMOUNT AMOUNT
Total (BAHT)
Labor (BAHT) SubTotal Item Tag Equipment (BAHT)
Tool & Consum.
(BAHT)
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Section 2: Contract Price Breakdown
The scope of items included in Schedule B5 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These qua
Installation Cost
Empty
Weight
Equip
Type
Description
Price Table for Equipment Installation
Remark
Qty
139 P15 N/A Demineralised water production (skid) N/A 112,000 BY SPX
140 P13 N/A Spray Dryer 1 2,500 25.00 62,500.00 10.00 25,000.00 5.00 12,500.00 40.00 100,000.00 100,000.00
141 P5 CP-Ac Air compressor 1 3,430 25.00 85,750.00 10.00 34,300.00 5.00 17,150.00 40.00 137,200.00 137,200.00
142 P5 SH-CPAc/1 to 2 CPAc dryer 1 2,000 15.00 30,000.00 10.00 20,000.00 5.00 10,000.00 30.00 60,000.00 60,000.00
143 P5 FL-Ac Air filter 1 21 50.00 1,069.00 20.00 427.60 20.00 427.60 90.00 1,924.20 1,924.20
144 P5 RS-Ac Compressed air tank 1 7,000 25.00 175,000.00 8.00 56,000.00 5.00 35,000.00 38.00 266,000.00 266,000.00
145 A SPM-FFS/1-2 Magnetic separators to FFS1/2 1 100 50.00 5,000.00 20.00 2,000.00 20.00 2,000.00 90.00 9,000.00 9,000.00
146 A UV-Ed Demineralised water UV 1 500 25.00 12,500.00 15.00 7,500.00 5.00 2,500.00 45.00 22,500.00 22,500.00
147 P8 FFS/1 FFS bagging machine Pharma (0/13) 1 9,200 20.00 184,000.00 15.00 138,000.00 5.00 46,000.00 40.00 368,000.00 368,000.00
148 P8 FFS/2 FFS bagging machine (27/50 or 0/50) 1 9,200 20.00 184,000.00 15.00 138,000.00 5.00 46,000.00 40.00 368,000.00 368,000.00
149 P8 03Z101 Clean room for FFS Pharma 1 4,000 25.00 100,000.00 12.00 48,000.00 5.00 20,000.00 42.00 168,000.00 168,000.00
150 P8 30H101 Bag conveyors 1 2,400 45.00 108,000.00 15.00 36,000.00 5.00 12,000.00 65.00 156,000.00 156,000.00
151 P8 30H102 Bag conveyors 1 2,400 45.00 108,000.00 15.00 36,000.00 5.00 12,000.00 65.00 156,000.00 156,000.00
152 P8 PAL/1 Palletiser for FFS1 1 13,000 25.00 325,000.00 15.00 195,000.00 5.00 65,000.00 45.00 585,000.00 585,000.00
153 P8 PAL/2 Palletiser for FFS2 1 13,000 25.00 325,000.00 15.00 195,000.00 5.00 65,000.00 45.00 585,000.00 585,000.00
154 P8 HOUS Stretch hooding machine 1 3,500 45.00 157,500.00 15.00 52,500.00 5.00 17,500.00 65.00 227,500.00 227,500.00
155 P12 BB-BIR Emergency manual bigbag station 1 2,500 45.00 112,500.00 15.00 37,500.00 5.00 12,500.00 65.00 162,500.00 162,500.00
156 P12 BB-PRG Vibrating big-bag loading system 1 1,500 25.00 37,500.00 15.00 22,500.00 5.00 7,500.00 45.00 67,500.00 67,500.00
157 A ECH/1 Samplers (0/50) 1 80 35.00 2,800.00 15.00 1,200.00 5.00 400.00 55.00 4,400.00 4,400.00
158 A ECH/2 Samplers (VT1 0/13) 1 80 35.00 2,800.00 15.00 1,200.00 5.00 400.00 55.00 4,400.00 4,400.00
159 A ECH/3 Samplers (VT1 27/50) 1 80 35.00 2,800.00 15.00 1,200.00 5.00 400.00 55.00 4,400.00 4,400.00
160 A ECH/4 Samplers (VT2 0/13) 1 80 35.00 2,800.00 15.00 1,200.00 5.00 400.00 55.00 4,400.00 4,400.00
161 A ECH/5 Samplers (VT2 27/50) 1 80 35.00 2,800.00 15.00 1,200.00 5.00 400.00 55.00 4,400.00 4,400.00
Page 23 of 36
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule B9
No. Kg U/P AMOUNT U/P AMOUNT U/P AMOUNT U/P AMOUNT AMOUNT
Total (BAHT)
Labor (BAHT) SubTotal Item Tag Equipment (BAHT)
Tool & Consum.
(BAHT)
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Section 2: Contract Price Breakdown
The scope of items included in Schedule B5 are defined in the following table together with the manner in which the items are measured and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These qua
Installation Cost
Empty
Weight
Equip
Type
Description
Price Table for Equipment Installation
Remark
Qty
162 R N/A Hoist Centrifuge N/A 5,000 15.00 75,000.00 10.00 50,000.00 5.00 25,000.00 30.00 150,000.00 150,000.00
163 R N/A Hoist Drop Zone N/A 1,200 50.00 60,000.00 15.00 18,000.00 5.00 6,000.00 70.00 84,000.00 84,000.00
Sub Total to Schedule B5 612,975 8,435,307 18,457,454.70
NOTE:
1. Installation details and scope of work refer to TKIS-PI-000-EC-0021 - Construction Contract Requisition for Mechanical and Piping Work
Equipment Group
A Stationary Equipment
R Rotating
U Package unit
Package No. Desicription
P1 SD silos with wibrating bottoms
P2 Back-wash filters
P3 SVA hot air production
P4 Steam generation
P5 Dry air production
P6 Sieves distribution conveyor with rotary valves
P7 BIR silos with vibrating bin activators
P8 Packaging lines
P9 Centrifuge with hydraulic group
P10 Venturi scrubber
P11 Carbon bed filters
P12 Big bag station package
P13 Spray dryer package
P14 SD pneumatic transport package
P15 Demineralised water production skid
Page 24 of 36
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule B10
Rev 00
Unit Q'ty
1 Grouting work -
- Equipment grouting Cu.m 10 65,000.00 650,000.00
- Pipe support foundation and grouting Cu.m 25 65,000.00 1,625,000.00
2 Under Ground Piping -
- Excavation work for pipe size 8" ( Deep 0.9 m.) m. 200 2,500.00 500,000.00
- Sand lot 1 200,000.00 200,000.00
3
Special item and Fire protection equipmet Items -
Standard Wet bulb sprinkler nozzle (install only) Ea 651 250.00 162,750.00
Outdoor Fire Hose Box (install only) Ea 6 3,500.00 21,000.00
Indoor Fire Hose Carbinet (install only) Ea 14 3,500.00 49,000.00
Fire Water Hydrant (install only) Ea 6 4,000.00 24,000.00
Fixed Fire Monitor (install only) Ea 3 4,000.00 12,000.00
Portable Dry Chemical (install only) Ea 33 2,500.00 82,500.00
Deluge valv size 3" Ea 1 2,000.00 2,000.00
Safety Shower and Eye washer (install only) Ea 2 6,500.00 13,000.00
Portable Eye washer (install only) Ea 9 3,000.00 27,000.00
Expension Joint (install only) Ea 2 2,000.00 4,000.00
Sampling Valve (install only) Ea 10 1,500.00 15,000.00
Supple sleeve, clamp connection (install only) Ea 40 350.00 14,000.00
Spring Support (install only) Ea 10 2,500.00 25,000.00
-
Sampling point cabinet (material + labor) Ea 10 35,000.00 350,000.00
Duct S/S 1 1,250,000.00 1,250,000.00
Support Outside on pave Ea 90 5,200.00 468,000.00
Support Outside unpave Ea 50 6,500.00 325,000.00
Structure Support for Silo /Load cell kg 10,000 120.00 1,200,000.00
4 Manpower supply for commissioning Man-Day 1 1,250.00 1,250.00
-
-
-
-
Sub Total to Schedule B11 7,020,500.00
SCHEDULE OF RATES - CONTRACT - METHOD OF MEASUREMENT & PAYMENT - B
Title of Works: Piping Fabrication and Erection / Mechanical Erection
The scope of items included in Schedule B11 are defined in the following table together with the manner in which the items are
measured and payments made. Attached to this schedule are a set of quantities, derived electronically from design data. These
quantities are issued to clarify the basis of the Schedule of Rates quantities and are for INFORMATION ONLY to ESTABLISH THE
ESTIMATED PRICE. The final quantities will measured at the completion of the works and the rates applied to the final quantitative
to establish the final value.
Table of Miscellaneous Work
TOTAL ( Baht) Item Description UNIT Price
Quantity
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
SCHEDULE OF RATES - HOUR / DAYWORKS - C
Project No. : 01-5004 Schedule C
Rev 00
Title of Works: Mechanical and Piping Fabrication and Erection
Labour rates shall include overhead, profit, supervision, insurance,
accommodation, consumables, small tools,PPE
Plant rates shall include overhead, profit, fuel, maintenance, insurance,
consumables, operator's wages
Materials percentage shall include overheads, profit, freight, handling,
administration. Payment of material costs shall be evidenced by
CONTRACTOR
Value of any dayworks shall be included in the Final Contract price, one
Change Order will be issued on completion of the day works to establish
the final contract price
Item No. Description Unit Rate
1 LABOUR
FOREMAN Baht/Hour 350.00
FITTER Baht/Hour 200.00
HELPER Baht/Hour 180.00
PAINTER Baht/Hour 200.00
LABORERS Baht/Hour 180.00
WELDER Baht/Hour 450.00
MILLWRIGHT Baht/Hour 400.00
2 MANAGEMENT AND SUPERVISION
PROJECT MANAGER Baht/Hour 850.00
SITE MANAGER Baht/Hour 650.00
ENGINEER Baht/Hour 450.00
SUPERVISOR Baht/Hour 450.00
3 PLANT
TRUCK CRANE (Incld.Fuel) 5 Tons Baht/Day 8,000.00
GENERATOR (Incld.Fuel) 90 KVA Baht/Day 8,000.00
AIR COMPRESSOR (Incld.Fuel) 375 CFM Baht/Day 8,000.00
WELDING GENERATOR (Incld.Fuel) 700 AMP Baht/Day 5,000.00
PICK UP (Incld.Fuel) 1 Tons Baht/Day 1,500.00
MOBILE CRANE (Incld.Fuel) 25-80 Tons Baht/Day 90,000.00
MOBILE CRANE (Incld.Fuel) 100-150 Tons Baht/Day 120,000.00
TRUCK AND TRAILER (Incld.Fuel) Baht/Day 15,000.00
AC/DC WELDING M/C 300 AMP Baht/Day 350.00
GRINDING M/C 4" Baht/Day 200.00
GRINDING M/C 7" Baht/Day 250.00
DRILLING M/C Baht/Day 250.00
HOLIDAY DETECTOR Baht/Day 10,000.00
4 MATERIALS
ORIGINAL PRICE 15%
Remark : 1. This offered rate is for normal working day and work period from 8.00 AM to 5.00 PM
for Monday to Saturday only.
2. If working for Sunday and Holiday the unit rate should be 2 time of offered rate. ( 8.00 AM to 5.00 PM ).
3. If working for overtime of normal working day ( After 5.00 PM ), the unit rate should be 1.5 time
of offered rate.
4. If working for overtime of Sunday and Holiday ( After 5.00 PM ), the unit rate shound be 3 time
of offered rate.
The Rates set out in this Schedule shall be used to value additions to the scope of Work where dayworks is instructed. Rates shall be all inclusive of all
costs , in particular, the following
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule C1
Rev 00
Title of Works: Mechanical and Piping Fabrication and Erection
Item No. Description Unit Rate
1 TEMPORARY GASKET (Rate 150/300#) Compress fiber
- DN: 15 Baht/piece 25.00
- DN: 20 Baht/piece 30.00
- DN: 25 Baht/piece 35.00
- DN: 40 Baht/piece 40.00
- DN: 50 Baht/piece 50.00
- DN: 80 Baht/piece 60.00
- DN: 100 Baht/piece 100.00
- DN: 150 Baht/piece 150.00
- DN: 200 Baht/piece 220.00
- DN: 250 Baht/piece 300.00
- DN: 300 Baht/piece 550.00
- DN: 350 Baht/piece 650.00
- DN: 400 Baht/piece 900.00
2 TEMPORARY GASKET (Rate 150/300#) Spiral wound Carbon steel
- DN: 15 Baht/piece 40.00
- DN: 20 Baht/piece 50.00
- DN: 25 Baht/piece 60.00
- DN: 40 Baht/piece 70.00
- DN: 50 Baht/piece 100.00
- DN: 80 Baht/piece 170.00
- DN: 100 Baht/piece 250.00
- DN: 150 Baht/piece 360.00
- DN: 200 Baht/piece 400.00
- DN: 250 Baht/piece 520.00
- DN: 300 Baht/piece 700.00
- DN: 350 Baht/piece 760.00
- DN: 400 Baht/piece 950.00
3 TEMPORARY GASKET (Rate 150/300#) Spiral wound Stainless steel
- DN: 15 Baht/piece 90.00
- DN: 20 Baht/piece 120.00
- DN: 25 Baht/piece 140.00
- DN: 40 Baht/piece 210.00
- DN: 50 Baht/piece 270.00
- DN: 80 Baht/piece 430.00
- DN: 100 Baht/piece 600.00
- DN: 150 Baht/piece 1,050.00
- DN: 200 Baht/piece 1,200.00
- DN: 250 Baht/piece 1,300.00
- DN: 300 Baht/piece 1,700.00
- DN: 350 Baht/piece 2,300.00
- DN: 400 Baht/piece 2,500.00
The Rates set out in this Schedule shall be used to value additions to the scope of Work where dayworks is instructed. Rates shall be all inclusive of all
costs.
SCHEDULE OF RATES - UNIT OF EMPORARY MATERAILS FOR COMMISSIONING - C
ThyssenKrupp
Industrial Solutions
LOY KRATHONG PROJECT
Project No. : 01-5004 Schedule C1
Rev 00
Title of Works: Mechanical and Piping Fabrication and Erection
Item No. Description Unit Rate
The Rates set out in this Schedule shall be used to value additions to the scope of Work where dayworks is instructed. Rates shall be all inclusive of all
costs.
SCHEDULE OF RATES - UNIT OF EMPORARY MATERAILS FOR COMMISSIONING - C
4 TEMPORARY BLIND AND SPADE (Rate 150/300#)
- DN: 15 Baht/piece 150.00
- DN: 20 Baht/piece 180.00
- DN: 25 Baht/piece 200.00
- DN: 40 Baht/piece 360.00
- DN: 50 Baht/piece 460.00
- DN: 80 Baht/piece 820.00
- DN: 100 Baht/piece 1,540.00
- DN: 150 Baht/piece 2,300.00
- DN: 200 Baht/piece 3,500.00
- DN: 250 Baht/piece 4,200.00
- DN: 300 Baht/piece 4,800.00
- DN: 350 Baht/piece 5,200.00
- DN: 400 Baht/piece 6,000.00

You might also like