07 PMP Training Notes

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 46

PMI Exam Study Notes Sajid Jambagi

TABLE OF CONTENTS
PROJECT MANAGEMENT KNOWLEDGE AREAS & 44 Processes...................................................................................2
PMBOK (Project Maa!e"et Bo#$ o% Ko&'e#!e(................................................................................................................)
Chapter 1 Introduction (Project Management Framework).....................................................................................................7
Chapter 2 Project Lie C!c"e and organi#ation........................................................................................................................$
Chapter % Project Management Proce&&e& or a project........................................................................................................1'
Chapter ( I)*+,-.*I/) Management................................................................................................................................11
Chapter 0 1C/P+ Management.............................................................................................................................................1%
Chapter 2 *IM+ Management................................................................................................................................................12
Chapter 7 C/1* Management................................................................................................................................................2'
Chapter 3 45.LI*6 Management.........................................................................................................................................2%
Chapter $ 7 85M.) -+1/5-C+ Management......................................................................................................................27
Chapter 1' C/MM5)IC.*I/)1 Management....................................................................................................................%1
Chapter 11 -I19 Management...............................................................................................................................................%(
Chapter 12 P-/C5-+M+)* Management...........................................................................................................................%3
Chapter 1% Proe&&iona" -e&pon&i:i"itie&...............................................................................................................................(2
POSS*BLE E+AM ,-EST*ONS..............................................................................................................................................4.
Page 1 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
PROJECT MANAGEMENT KNOWLEDGE AREAS & 44 Processes
Ko&'e#!e Areas Major Processes Pr/"ar$ *01ts Too's & Tec2/31es Pr/"ar$ O1t01ts
*NTEGRAT*ON C1MMMIC
Develop Project Charter Developing the project charter
that formall a!thori"e# a
project or a project pha#e
$% Contract &'hen applica(le)
*% Project Statement of +or,
-% Enterpri#e environmental factor#
4% Organi"ational Proce## A##et#
$% Project Selection .etho/#
*% Project .anagement
.etho/olog &P..)
-% Project .anagement
0nformation ##tem&P.0S)
4% E1pert 2!/gment
$% Project Chapter
Develop Preliminar
Project Scope Statement
Developing Preliminar Project
Scope Statement that provi/e#
high level #cope narrative%
$% Project Charter
*% Project Statement of +or,
-% Enterpri#e Environmental Factor#
4% Organi"ational Proce## A##et#
$% P..
*% P.0S
-% E1pert 2!/gment
$% Preliminar project Scope Statement
Develop Project
.anagement Plan
Doc!menting the action#
nece##ar to /efine3 prepare3
integrate an/ coor/inate all
#!(#i/iar plan# into a project
management plan%
$% Preliminar project Scope Statement
*% Project .anagement Proce##e#
-% Enterpri#e Environmental Factor#
4% Organi"ational Proce## A##et#
$% P..
*% P.0S
-% E1pert 2!/gment
$% Project .anagement Plan
Direct an/ .anage Project
E1ec!tion
E1ec!ting the 'or, /efine/ in
the project management plan to
achieve the project4#
re5!irement# /efine/ in the
project #cope #tatement%
$% Project .anagement Plan
*% Approve/ Corrective action#
-% Approve/ Preventive Action#
4% Approve/ Change 6e5!e#t#
7% Approve/ /efect repair
6% 8ali/ate/ /efect 6epair
9% A/mini#trative Clo#!re Proce/!re
$% P..
*% P.0S
$% Delivera(le#
*% 6e5!e#te/ Change#
-% +or, Performance 0nformation
4% 0mplemente/ corrective action#
7% 0mplemente/ Preventive action#
6% 0mplemente/ Change 6e5!e#t#
9% 0mplemente/ /efect repair
.onitor an/ Control
Project +or,
.onitoring an/ Controlling the
proce##e# !#e/ to initiate3 plan3
e1ec!te3 an/ clo#e a project to
meet the performance
o(jective# /efine/ in the project
management plan
$% Project .anagement Plan
*% +or, Performance 0nformation
-% 6ejecte/ Change 6e5!e#t#
$% P..
*% P.0S
-% Earne/ 8al!e Techni5!e
4% E1pert 2!/gment
$% 6ecommen/e/ corrective action#
*% 6ecommen/e/ Preventive action#
-% 6ecommen/e/ Defect 6epair
4% Foreca#t#
7% 6e5!e#te/ Change#
0ntegrate/ Change Control 6evie'ing all change re5!e#t#3
approving change#3 an/
controlling change# to the
/elivera(le# an/ organi"ational
proce## a##et#%
$% Project .anagement Plan
*% Delivera(le#
-% +or, Performance 0nformation
4% 6e5!e#te/ Change#
7% 6ecommen/e/ corrective action#
6% 6ecommen/e/ Preventive action#
9% 6ecommen/e/ Defect 6epair
$% P..
*% P.0S
-% E1pert 2!/gment
$%Project .anagement Plan&!p/ate#)
*% Project Scope Statement &!p/ate#)
-% Delivera(le#
4% Approve/ corrective action#
7% Approve/ corrective action#
6% Approve/ Change 6e5!e#t#
9% 6ejecte/ Change 6e5!e#t#
:% Approve/ Defect 6epair
;% 8ali/ate/ Defect 6epair
Clo#e Project Finali"ing all activitie# acro##
all of the project management
proce## gro!p# to formall clo#e
the project or a project pha#e%
$% Project .anagement Plan
*% Contract Doc!mentation
-% Delivera(le#
4% +or, Performance 0nformation
7% Enterpri#e environmental factor#
6% Organi"ational Proce## A##et#
$% P..
*% P.0S
-% E1pert 2!/gment
$% A/mini#trative clo#!re Proce/!re
*% Contract clo#!re Proce/!re
-% Final Pro/!ct3 Service or re#!lt
4% Organi"ational Proce## A##et# &!p/ate#)
SCOPE Pac, Dnamite
With 4erifie/ Care
(P<=>C)
Scope Planning Creating a project #cope
management plan that
/oc!ment# ho' the project
#cope 'ill (e /efine/3 verifie/3
controlle/ an/ ho' the 'or,
(rea,/o'n #tr!ct!re 'ill (e
create/ an/ /efine/%
$% Project charter
*% Preliminar Project Scope Statement
-% Project .anagement Plan
4% Organi"ational Proce## A##et#
7% Enterpri#e environmental factor#
$% E1pert 2!/gment
*% Template#3 form#3 #tan/ar/#
$% Project Scope .anagement Plan
Scope Definition Developing a /etaile/ project
#cope #tatement a# the (a#i# for
f!t!re project /eci#ion#%
$% Project charter
*% Preliminar Project Scope Statement
-% Project Scope .anagement Plan
4% Organi"ational Proce## A##et#
7% Approve/ Change re5!e#t#
$% Pro/!ct anal#i#
*% Sta,ehol/er anal#i#
-% Alternative# 0/entification
4% E1pert 2!/gment
$% Project Scope Statement
*% Project Scope .anagement plan
&!p/ate#)
-% 6e5!e#te/ change#
Create +BS S!(/ivi/ing the major project
/elivera(le# an/ project 'or,
into #maller more managea(le
component#
$% Project Scope Statement
*% Project Scope .anagement Plan
-% Organi"ational Proce## A##et#
4% Approve/ Change re5!e#t#
$% +or, Brea,/o'n Str!ct!re
Template#
*% Decompo#ition
$% Project Scope Statement &<p/ate#)
*% Project Scope .anagement plan
&!p/ate#)
-% Scope (a#eline
4% +or, Brea,/o'n Str!ct!re
7% +BS /ictionar
6% 6e5!e#te/ change#
Scope 8erification Formali"ing acceptance of the
complete/ project /elivera(le#%
$% Project Scope Statement
*% Project Scope .anagement Plan
-% +BS /ictionar
4% Delivera(le#
$% 0n#pection $% Accepte/ /elivera(le#
*% 6e5!e#te/ Change#
-% 6ecommen/e/ corrective action#
Scope Control Controlling change# to the
project #cope%
$% Project Scope Statement
*% Project Scope management plan
-% +or, (rea,/o'n #tr!ct!re
4% +BS /ictionar
7% +or, Performance information
$% 8ariance anal#i#
*% 6e planning
-% Change Control ##tem
4% Config!ration .anagement
##tem
$% Project Scope Statement &!p/ate#)
*% Scope Ba#eline &!p/ate#)
-% +or, Brea,/o'n Str!ct!re &!p/ate#)
4% +BS Dictionar &!p/ate#)
7% Project .anagement plan &!p/ate#)
Page 2 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
6% Performance report#
9% Approve/ Change re5!e#t#
6% Organi"ational Proce## A##et# &<p/ate#)
9% 6ecommen/e/ Corrective action
:% 6e5!e#te/ change#
T*ME
<1-<<C
Activit Definition 0/entifing the #pecific
#che/!le activitie# that nee/ (e
performe/ to pro/!ce the
vario!# project /elivera(le#
$% Enterpri#e environmental factor#
*% Organi"ational Proce## A##et#
-% Project Scope Statement
4% Project .anagement Plan
7% +or, (rea,/o'n #tr!ct!re
6% +BS /ictionar
$% Decompo#ition
*% Template#
-% 6olling 'ave planning
4% Planning component
7% E1pert 2!/gment
$% Activit Li#t
*% Activit Attri(!te#
-% .ile#tone li#t
4% 6e5!e#t Change#
Activit Se5!encing 0/entifing an/ /oc!menting
/epen/encie# among #che/!le
activitie#
$% Project Scope Statement
*% Activit li#t
-% Activit Attri(!te#
4% .ile#tone li#t
7% Approve/ Change 6e5!e#t#
$% PD.
*% AD.
-% Sche/!le Net'or, template#
4% Depen/enc /etermination
7% Appling lea/# an/ lag#
$% Project Sche/!le Net'or, /iagram#
*% Activit li#t &!p/ate#)
-% Activit attri(!te# &!p/ate#)
4% 6e5!e#te/ change#
Activit 6e#o!rce
E#timating
E#timating the tpe an/
5!antitie# of re#o!rce# re5!ire/
to perform each #che/!le
activit
$% Enterpri#e environmental factor#
*% Organi"ational Proce## A##et#
-% Project .anagement Plan
4% Activit li#t
7% Activit Attri(!te#
6% 6e#o!rce Availa(ilit
$% Bottom=!p e#timating
*% Alternative# Anal#i#
-% P!(li#he/ e#timate/ /ata
4% Project .anagement Soft'are
7% E1pert 2!/gment
$% Activit re#o!rce re5!irement#
*% Activit attri(!te# &!p/ate#)
-% 6e#o!rce calen/ar &!p/ate#)
4% 6e#o!rce Brea,/o'n Str!ct!re
7% 6e5!e#te/ change#
Activit D!ration
E#timating
E#timating the n!m(er of 'or,
perio/# that 'ill (e nee/e/ to
complete each #che/!le
activitie#%
$% Enterpri#e environmental factor#
*% Organi"ational Proce## A##et#
-% Project Scope Statement
4% Project .anagement Plan
%6i#, regi#ter
%Activit Co#t e#timate#
7% Activit li#t
6% Activit Attri(!te#
9% Activit 6e#o!rce re5!irement#
:% 6e#o!rce Calen/ar
$% Analogo!# e#timating
*% Parametric e#timating
-% Three=point e#timate#
4% 6e#erve Anal#i#
7% E1pert j!/gment
$% Activit D!ration e#timate#
*% Activit attri(!te# &!p/ate#)
Sche/!le Development Anal"ing activit #e5!ence#3
/!ration#3 re#o!rce
re5!irement#3 an/ #che/!le
con#traint# to create the project
#che/!le%
$% Enterpri#e environmental factor#
*% Project Scope Statement
-% Project .anagement Plan
% 6i#, regi#ter
4% Activit li#t
7% Activit Attri(!te#
6% Project Sche/!le net'or, /iagram#
9% Activit 6e#o!rce re5!irement#
:% 6e#o!rce Calen/ar#
;% Activit /!ration e#timate#
$% Sche/!le Net'or, anal#i#
*% Critical path metho/
-% Sche/!le Compre##ion
4% +hat=if #cenario anal#i#
7% 6e#o!rce leveling
6% Critical chain metho/
9% Project management #oft'are
:% Appling calen/ar#
;% A/j!#ting lea/# an/ lag#
$>% Sche/!le mo/el
$% Project #che/!le
*% Sche/!le mo/el /ata
-% Sche/!le (a#eline
4% 6e#o!rce re5!irement# &!p/ate#)
7% Activit attri(!te# &!p/ate#)
6% Project calen/ar &!p/ate#)
9% 6e5!e#te/ Change#
:% Project .anagement Plan &!p/ate#)
%Sche/!le .anagement Plan &!p/ate#)
Sche/!le Control Controlling change# to the
project #che/!le%
$% Sche/!le management plan
*% Sche/!le (a#eline
-% Performance report#
4% Approve/ Change re5!e#t#
$% Progre## 6eporting
*% Sche/!le change control
##tem
-% Performance mea#!rement
4% Project management #oft'are
7% 8ariance anal#i#
6% Sche/!le compari#on (ar chart#
$% Sche/!le mo/el /ata &!p/ate#)
*% Sche/!le (a#eline &!p/ate#)
-% Activit li#t &!p/ate#)
4% Activit Attri(!te# &!p/ate#)
7% Performance mea#!rement#
6% 6e5!e#te/ change#
9% 6ecommen/e/ Corrective action#
:% Project .anagement Plan &!p/ate#)
;% Organi"ational Proce## A##et# &!p/ate#)
COST EBC ra/io i# free of
co#t%
Co#t E#timating Developing an appro1imation of
the co#t# of the re#o!rce#
nee/e/ to complete project
activitie#
$% Enterpri#e environmental factor#
*% Organi"ational Proce## A##et#
-% Project Scope Statement
4% +or, (rea,/o'n #tr!ct!re
7% +BS /ictionar
6% Project .anagement Plan
Sche/!le .anagement Plan
Staffing .anagement Plan
6i#, 6egi#ter
$% Analogo!# e#timating
*% Determine 6e#o!rce Co#t
6ate#
-% Bottom=!p e#timating
4% Parametric e#timating
7% Project .anagement Soft'are
6% 8en/or Bi/ anal#i#
9% 6e#erve anal#i#
:% Co#t of ?!alit
$% Activit Co#t e#timate#
*% Activit Co#t E#timate S!pporting /etail
-% 6e5!e#te/ Change#
4% Co#t management plan &!p/ate#)
Co#t B!/geting Aggregating the e#timate/ co#t#
of in/ivi/!al activitie# or 'or,
pac,age# to e#ta(li#h a co#t
(a#eline%
$% Project Scope Statement
*% +or, (rea,/o'n #tr!ct!re
-% +BS /ictionar
4% Activit Co#t e#timate#
7% Activit Co#t E#timate S!pporting
/etail
6% Project Sche/!le
9% 6e#o!rce Calen/ar#
:% Contract
;% Co#t management plan
$% Co#t aggregation
*% 6e#erve Anal#i#
-% Parametric E#timating
4% F!n/ing Limit reconciliation
$% Co#t (a#eline
*% Project f!n/ing re5!irement#
-% Co#t management plan &!p/ate#)
4% 6e5!e#te/ Change#
Co#t Control 0nfl!encing the factor# that
create co#t variance# an/
controlling change# to the
$% Co#t (a#eline
*% Project f!n/ing re5!irement#
-% Performance report#
$% Co#t change control ##tem
*% Performance mea#!rement
Anal#i#
$% Co#t e#timate# &!p/ate#)
*% Co#t (a#eline &!p/ate#)
-% Performance .ea#!rement#
Page % o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
project (!/get% 4% +or, performance information
7% Approve/ Change re5!e#t#
6% Project management plan
-% Foreca#ting
4% Project performance revie'#
7% Project .anagement #oft'are
6% 8ariance .ea#!rement
4% Foreca#te/ Completion
7% 6e5!e#te/ Change#
6% 6ecommen/e/ corrective action#
9% Organi"ation proce## a##et# &!p/ate#)
:% Project management plan &!p/ate#)
,-AL*T5 The 3 !alit -=
PAC,% (% P.C)
?!alit Planning 0/entifing 'hich 5!alit
#tan/ar/# are relevant to the
project an/ /etermining ho' to
#ati#f them%
$% Enterpri#e environmental factor#
*% Organi"ational Proce## A##et#
-% Project Scope Statement
4% Project .anagement Plan
$% Co#t=Benefit anal#i#
*% Benchmar,ing
-% De#ign of e1periment#
4% Co#t of 5!alit &CO?)
7% A//itional 5!alit Planning
Tool#
$% ?!alit management plan
*% ?!alit .etric#
-% ?!alit Chec,li#t#
4% Proce## 0mprovement Plan
7% ?!alit Ba#eline
6% Project .anagement Plan &!p/ate#)
Perform ?!alit
A##!rance
Appling the planne/
##tematic 5!alit activitie# to
en#!re that project emplo# all
proce##e# nee/e/ to meet
re5!irement#
$% ?!alit management plan
*% ?!alit .etric#
-% Proce## 0mprovement Plan
4% +or, performance 0nformation
7% ?!alit control .ea#!rement#
6% Approve/ Change 6e5!e#t#
9% 0mplemente/ Corrective Action#
:% 0mplemente/ Preventive Action#
;% 0mplemente/ Change 6e5!e#t#
$>% 0mplemente/ Defect 6epair
$% ?!alit planning tool# an/
techni5!e#
*% ?!alit a!/it#
-% Proce## anal#i#
4% ?!alit control tool# an/
techni5!e#
$% 6e5!e#te/ Change#
*% Corrective Action#
-% Organi"ation proce## a##et# &!p/ate#)
4% Project management plan &!p/ate#)
Perform ?!alit Control .onitoring #pecific project
re#!lt# to /etermine 'hether
the compl 'ith relevant
5!alit #tan/ar/# an/ i/entifing
'a# to eliminate ca!#e# of
!n#ati#factor performance%
$% ?!alit management plan
*% ?!alit .etric#
-% ?!alit Chec,li#t#
4% Organi"ation proce## a##et#
7% +or, performance 0nformation
6% Approve/ Change 6e5!e#t#
9% Delivera(le#
$% Ca!#e an/ effect /iagram
*% Control chart#
-% Flo'=charting
4% @i#togram
7% Pareto chart
6% 6!n Chart
9% Scatter /iagram
:% Stati#tical #ampling
;% 0n#pection
$>% Defect repair revie'
$% ?!alit Control .ea#!rement#
*% 8ali/ate/ Defect 6epair
-% ?!alit Ba#e line &!p/ate#)
4% 6ecommen/e/ Corrective Action#
7% 6ecommen/e/ Preventive Action#
6% 6e5!e#te/ Change#
9% 6ecommen/e/ Defect 6epair
:% Organi"ation proce## a##et# &!p/ate#)
;% 8ali/ate/ /elivera(le#
$>% Project management plan &!p/ate#)
6-MAN
RESO-RCE
P.<
@!man 6e#o!rce Planning 0/entifing an/ /oc!menting
project role#3 re#pon#i(ilitie#
an/ reporting relation#hip# a#
'ell a# creating the #taffing
management plan
$% Enterpri#e Environmental Factor#
*% Organi"ational Proce## A##et#
-% Project management plan
%Activit re#o!rce re5!irement#
$% Organi"ation chart# an/
po#ition /e#cription#
*% Net'or,ing
-% Organi"ational theor%
$% 6ole# an/ re#pon#i(ilitie#
*% Project Organi"ation chart#
-% Staffing management plan
Ac5!ire Project Team O(taining the h!man re#o!rce#
nee/e/ to complete the project%
$% Enterpri#e Environmental Factor#
*% Organi"ational Proce## A##et#
-% 6ole# an/ re#pon#i(ilitie#
4% Project Organi"ation chart#
7% Staffing management plan
$% Pre=a##ignment
*% Negotiation
-% Ac5!i#ition
4% 8irt!al team#
$% Project Staff A##ignment#
*% 6e#o!rce Availa(ilit
-% Staffing management plan &!p/ate#)
Develop Project Team 0mproving the competencie#
an/ interaction of team
mem(er# to enhance project
performance%
$% Project Staff A##ignment#
*% 6e#o!rce Availa(ilit
-% Staffing management plan
$% Aeneral management #,ill#
*% Training
-% Team=(!il/ing activitie#
4% Aro!n/ r!le#
7% Co=location
6% 6ecognition an/ re'ar/#
$% Team Performance a##e##ment
.anage Project Team Trac,ing team mem(er
performance3 provi/ing
fee/(ac,3 re#olving i##!e#3 an/
coor/inating change# to enhance
project performance
$% Organi"ational Proce## A##et#
*% Project Staff A##ignment#
-% 6ole# an/ re#pon#i(ilitie#
4% Project Organi"ation chart#
7% Staffing management plan
6% Team Performance a##e##ment
9% +or, Performance 0nformation
:% Performance 6eport#
$% O(#ervation an/ conver#ation
*% Project performance apprai#al#
-% Conflict management
4% 0##!e log
$% 6e5!e#te/ Change#
*% 6ecommen/e/ Corrective Action#
-% 6ecommen/e/ Preventive Action#
4% Organi"ation proce## a##et# &!p/ate#)
6% Project management plan &!p/ate#)
COMM-N*CAT*
ONS
CIPM
Comm!nication# Planning Determining the information
an/ comm!nication# nee/# of
the #ta,ehol/er#
$% Enterpri#e Environmental Factor#
*% Organi"ational Proce## A##et#
-% Project Scope Statement
4% Project management plan
%Con#traint#
%A##!mption#
$% Comm!nication#
re5!irement anal#i#
*% Comm!nication#
Technolog
$% Comm!nication management plan
0nformation Di#tri(!tion .a,ing nee/e/ information
availa(le to project #ta,ehol/er#
in a timel manner
$% Comm!nication management plan $% Comm!nication #,ill#
*% 0nformation gathering an/
retrieval ##tem#
-% 0nformation /i#tri(!tion
metho/#
4% Le##on# learne/ Proce##
$% Organi"ational Proce## A##et# &!p/ate#)
*% 6e5!e#te/ Change#
Page ( o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Performance 6eporting Collecting an/ /i#tri(!ting
performance information% Thi#
incl!/e# Stat!# reporting3
progre## mea#!rement an/
foreca#ting
$% +or, Performance 0nformation
*% Performance .ea#!rement#
-% Foreca#te/ completion
4% ?!alit control mea#!rement#
7% Project management plan
Performance mea#!rement
(a#eline
6% Approve/ Change re5!e#t#
9% Delivera(le#
$% 0nformation pre#entation tool#
*% Performance information
gathering an/ compilation
-% Stat!# revie' meeting#
4% Time reporting ##tem#
7% Co#t reporting ##tem#
$% Performance report#
*% Foreca#t#
-% 6e5!e#te/ Change#
4% 6ecommen/e/ Corrective Action#
7% Organi"ational Proce## A##et# &!p/ate#)
.anage Sta,ehol/er# .anaging comm!nication# to
#ati#f the re5!irement# of an/
re#olve i##!e# 'ith project
#ta,ehol/er#%
$% Comm!nication# management plan
*% Organi"ational Proce## A##et#
$% Comm!nication# .etho/#
*% 0##!e Log#
$% 6e#olve/ 0##!e#
*% Approve# Change 6e5!e#t#
-% Approve/ corrective action#
4% Organi"ational Proce## A##et# &!p/ate#)
7% Project management plan &!p/ate#)
R*SK It?& ri&k! to ha@e
an I4 in <C.
6i#, .anagement
Planning
Deci/ing ho' to approach an/
plan ri#, management activitie#%
$% Enterpri#e Environmental Factor#
*% Organi"ational Proce## A##et#
-% Project Scope Statement
4% Project .anagement Plan
$% Planning meeting# an/ anal#i# $% 6i#, management plan
6i#, 0/entification Determining 'hich ri#,# are
li,el to affect the project B
/oc!menting their
characteri#tic#
$% Enterpri#e Environmental Factor#
*% Organi"ational Proce## A##et#
-%6i#, management plan
4% Project Scope Statement
7% Project .anagement Plan
$%Doc!mentation revie'#
*% 0nfo=gathering techni5!e#
-% Chec,li#t anal#i#
4% A##!mption# anal#i#
7% Diagramming techni5!e#
$%6i#, 6egi#ter
?!alitative 6i#, Anal#i# A##e##ing the impact an/
li,elihoo/ of i/entifie/ ri#,#%
$% Organi"ational Proce## A##et#
*% 6i#, 6egi#ter
-% Project Scope Statement
4% Project .anagement Plan
$% 6i#, pro(a(ilit B impact
a##e##ment
*% Pro(a(ilit an/ impact matri1
-% 6i#, /ata 5!alit a##e##ment
4% 6i#, Categori"ation
7% 6i#, !rgenc a##e##ment
$%6i#, 6egi#ter &<p/ate#)
?!antitative 6i#, Anal#i# A proce## that anal"e#
n!mericall the pro(a(ilit of
each ri#, an/ it# con#e5!ence on
project o(jective#
$% Organi"ational Proce## A##et#
*% Project Scope Statement
-% 6i#, .anagement Plan
4% 6i#, 6egi#ter
7% Project .anagement Plan
C Project Sche/!le .anagement Plan
C Project Co#t .anagement Plan
$% Data Aathering an/
repre#entation techni5!e#
&0ntervie'ing3 pro(a(ilit
/i#tri(!tion an/ E2)
*% ?!antitative 6i#, anal#i# B
mo/eling techni5!e#% &Sen#itivit3
E.83 Deci#ion Tree)
$% 6i#, 6egi#ter &<p/ate#)
6i#, 6e#pon#e Planning Developing option# B
/etermining action# to enhance
opport!nitie# to re/!ce threat#
to project o(jective#
$% 6i#, .anagement Plan
*% 6i#, 6egi#ter
$% Strategie# for negative ri#, or
threat#
*% Strategie# for po#itive ri#, or
opport!nitie#
-% Strategie# for (oth threat# an/
opport!nitie#
4% Contingenc re#pon#e #trateg
$% 6i#, 6egi#ter &<p/ate#)
*% Project .anagement Plan &<p/ate#)
-% 6i#, relate/ contract!al agreement#
6i#, .onitoring B
Control
Trac,ing i/entifie/ ri#,3
monitoring re#i/!al ri#,#3 an/
i/entifing ne' ri#,3 en#!ring
the e1ec!tion of ri#, plan# an/
eval!ating the effectivene## in
re/!cing ri#,%
$% 6i#, .anagement Plan
*% 6i#, 6egi#ter
-% Approve/ Change 6e5!e#t#
4% +or, Performance 0nformation
7% Performance 6eport#
$% 6i#, rea##e##ment
*% 6i#, a!/it#
-% 8ariance an/ tren/ anal#i#
4% Technical performance
mea#!rement
7% 6e#erve anal#i#
6% Stat!# .eeting#
$% 6i#, 6egi#ter &<p/ate#)
*% 6e5!e#te/ Change#
-% 6ecommen/e/ Corrective action#
4% 6ecommen/e/ Preventive action#
7% Organi"ational proce## a##et &<p/ate)
6% Project .anagement Plan &<p/ate#)
PROC-REMENT PP11.C
Plan P!rcha#e# B
Ac5!i#ition#
Determining 'hat to proc!re
an/ 'hen (make or :u!)
$% Enterpri#e Environmental Factor#
*% Organi"ational Proce## A##et#
-% Project #cope #tatement
4% +BS
7% +BS Dictionar
6% Project .anagement Plan
$% .a,e or (! anal#i#
*% E1pert j!/gment
-% Contract tpe#
$% Proc!rement mgmt plan
*% Contract Statement&#) of +or,
-% .a,e or B! Deci#ion#
4% 6e5!e#te/ Change#
Plan Contracting Preparing the /oc!ment# nee/e/
to #!pport #olicitation
$% Proc!rement management plan
*% Contract Statement&#) of 'or,
-% .a,e or B! Deci#ion#
4% Project .anagement Plan
$% Stan/ar/ form#
*% E1pert j!/gment
$% Proc!rement /oc!ment#
*% Eval!ation criteria
-% Contract Statement of 'or, &!p/ate#)
6e5!e#t Seller 6e#pon#e# O(taining 5!otation#3 (i/#3
offer#3 or propo#al# (an&wer
Aue&tion&)
$% Organi"ational Proce## A##et#
*% Proc!rement .anagement Plan
-% Proc!rement Doc!ment#
$% Bi//er conference#
*% A/verti#ing
-% Develop 5!alifie/ #eller# li#t
$% ?!alifie/ #eller# li#t
*% Proc!rement Doc!ment Pac,age
-% Propo#al#
Select Seller# 0nvolve# the receipt of (i/# or
propo#al# an/ the application of
eval!ation criteria to #elect a
provi/er
$% Organi"ational Proce## A##et#
*% Proc!rement .anagement Plan
-% Eval!ation Criteria
4% Proc!rement Doc!ment Pac,age
7% Propo#al#
6% ?!alifie/ Seller# Li#t
9% Project .anagement Plan
$% +eighting ##tem
*% 0n/epen/ent e#timate#
-% Screening ##tem
4% Contract Negotiation
7% Seller 6ating S#tem
6% E1pert 2!/gment
9% Propo#al Eval!ation
Techni5!e#
$% Selecte/ Seller#
*% Contract
-% Contract .anagement Plan
4% 6e#o!rce Availa(ilit
7% Proc!rement .anagement Plan
&<p/ate#)
6% 6e5!e#te/ change#
Contract A/mini#tration En#!ring that the #eller4#
performance meet# contract!al
re5!irement#
$% Contract
*% Contract .anagement Plan
-% Selecte/ Seller#
4% Performance 6eport#
7% Approve/ change re5!e#t#
6% +or, Performance information
$% Contract change control ##tem
*% B!er con/!cte/ performance
revie'
-% 0n#pection# an/ a!/it#
4% Performance reporting
7%Pament ##tem
$% Contract Doc!mentation
*% 6e5!e#te/ Change#
-% 6ecommen/e/ Corrective action#
4% Organi"ational Proce## a##et# &<p/ate#)
7% Project .anagement plan &!p/ate#)
C Proc!rement .anagement Plan
Page 0 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
6% Claim# a/mini#tration
9% 6ecor/# management ##tem
:% 0nformation technolog
C Contract management plan
Contract Clo#eo!t Pro/!ct verification an/
a/mini#tration clo#eo!t
(ini&h)
$% Proc!rement management Plan
*% Contract management plan
-% Contract /oc!mentation
4% Contract clo#!re proce/!re
$% Proc!rement a!/it#
*% 6ecor/# .anagement S#tem
$% Clo#e/ Contract#
*% Organi"ational proce## a##et# &<p/ate#)
Page 2 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
PMBOK (Project Maa!e"et Bo#$ o% Ko&'e#!e(
C2a0ter 7 8 *tro#1ct/o (Project Maa!e"et 9ra"e&or:(
PMBOK = The P!rpo#e of P.BOD A!i/e i# to i/entif that #!(#et of Project .anagement Bo/ of Dno'le/ge that i#
generall recogni"e/ a# goo/ practice%
Project E Temporar an/ <ni5!e3 Temporar al#o applie# to project team3 opport!nitie# an/ .ar,et 'in/o'% Project i#
temporar (!t the pro/!ct3 #ervice or re#!lt i# it create# i# !#!all inten/e/ to (e long la#ting%
Pro!ress/;e E'a<orat/o = Progre##ivel mean# Fprocee/ing in #tep#G contin!ing #tea/il ( increment#3H 'hile e"a:orated
mean# F'or,e/ o!t 'ith care an/ /etailG /evelope/ thoro!ghlH
Projects (Te"0orar$ & -/31e( & O0erat/os (re0et/t/;e( Co""o C2aracter/st/cs
$% Performe/ ( People
*% Con#traine/ B limite/ 6e#o!rce#
-% Planne/3 E1ec!te/ an/ Controlle/
Project "aa!e"et = Application of ,no'le/ge3 #,ill#3 tool#3 an/ techni5!e# to project activitie# to meet project
re5!irement#%
PM* .em(er# A/here to E Co/e of Ethic#
PMP a/here to E Co/e of Profe##ional Con/!ct
Tr/0'e Costra/t E Co#t3 Time an/ Scope I ?!alit3 6i#, an/ C!#tomer Sati#faction
Maa!e"et B$ Projects 8 .anagement of Project# an/ #ome ongoing operation#3 'hich can (e re/efine/ a# project# !#ing
FProject .anagementH% An organi"ation that a/opt# thi# approach /efine# it# activitie# a# project# in a 'a that i# con#i#tent
'ith /efinition of project%
$% Project *te!rat/o Maa!e"et = vario!# element# of the project are properl coor/inate/%
*% Project Sco0e Maa!e"et = incl!/e# all the 'or, re5!ire/3 to complete the project #!cce##f!ll%
-% Project T/"e Maa!e"et = en#!re timel completion of the project%
4% Project Cost Maa!e"et = complete/ 'ithin the approve/ (!/get%
7% Project ,1a'/t$ Maa!e"et = project 'ill #ati#f the nee/# for 'hich it 'a# !n/erta,en
6% Project 61"a Reso1rce Maa!e"et = to ma,e the mo#t effective !#e of the people involve/ 'ith the project%
9% Project Co""1/cat/os Maa!e"et = to en#!re timel an/ appropriate generation3 collection3 /i##emination3
Storage3 an/ !ltimate /i#po#ition of project information%
:% Project R/s: Maa!e"et = i/entifing3 anal"ing3 an/ re#pon/ing to project ri#,%
;% Project Proc1re"et Maa!e"et = to ac5!ire goo/# an/ #ervice# from o!t#i/e the performing organi"ation%
Areas o% E=0ert/se
$% P.BOD
$% Project Life ccle Definition *% Five P. proce## gro!p# -% Nine Dno'le/ge area#
*% Application area ,no'le/ge3 #tan/ar/# an/ reg!lation#
-% <n/er#tan/ing Project environment
$%C!lt!ral an/ Social *%0nternational an/ political -%Ph#ical Environment
4% Aeneral .anagement Dno'le/ge an/ S,ill#
$%Planning *%Organi"ing -%Staffing 4%E1ec!ting 7%Control operation#
7% 0nterper#onal S,ill#
$%Comm!nication *%0nfl!enct -%Lea/er#hip 4%.otivation 7%Negotiation B Conflict re#ol!tion 6%Pro(lem Solving
Sta#ar# 7 i# a F/oc!ment approve/ ( a recogni"e/ (o/3 that provi/e#3 for common an/ repeate/ !#e3 r!le#3 g!i/eline#3 or
characteri#tic# for pro/!ct#3 proce##e# or #ervice# 'ith 'hich co"0'/ace /s ot "a#ator$.> Stan/ar/# #tart o!t a#
g!i/eline# an/ later 'ith 'i/e#prea/ a/aptation (ecome# accepte/ a# if the 'ere reg!lation#%
Re!1'at/o ? i# a F/oc!ment3 'hich la# /o'n pro/!ct3 proce## or #ervice characteri#tic#3 incl!/ing the applica(le
a/mini#trative provi#ion#3 'ith 'hich co"0'/ace /s "a#ator$.
Page 7 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Pro!ra" 8 Aro!p of relate/ Project# manage/ in a coor/inate/ 'a to o(tain (enefit# an/ control not availa(le from
managing them in/ivi/!all%
Port%o'/o E Collection of Project#3 Program# an/ other 'or, gro!pe/ together to facilitate effective management to meet
#trategic o(jective#%
PMO E Project .anagement Office3 Project office3 Program Office E Centrali"e an/ Coor/inate the management of project3
over#ee or a/mini#ter project3 program or (oth%
OPM. E P.04# organi"ational mat!rit mo/el%
E=0e#/tor E Staff A##i#tant an/ Comm!nication coor/inator% No Po'er to ma,e /eci#ion#
Coor#/ator E Some a!thorit3 po'er an/ report# to higher=level manager%
Page 3 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter 2 8 Project L/%e C$c'e a# or!a/@at/o
Project '/%e c$c'e = Organi"ation# performing project# 'ill !#!all /ivi/e each project into #everal project pha&e& to improve
management control% Collectivel3 the project pha#e# are ,no'n a# the project "ie c!c"e% <#!all the are #e5!ential%
Project L/%e C$c'e De%/e E
$% +hat technical 'or, to /o in each pha#e
*% +hen the /elivera(le# are to (e generate/3 ho' the are revie'e/3 verifie/ B vali/ate/%
-% +ho i# involve/ in each pha#e
4% @o' to control an/ approve each pha#e
Project P2ase = Each project pha#e i# mar,e/ ( completion of one or more /elivera(le#% A de"i@era:"e i# a tangi(le3
verifia(le 'or, pro/!ct% The concl!#ion of a project pha#e i# generall mar,e/ ( a revie' of (oth ,e /elivera(le# an/
project performance to /ate3 to a) /etermine if the project #ho!l/ contin!e into it# ne1t pha#e an/ () /etect an/ correct error#
co#t effectivel% The#e pha#e=en/ revie'# are often calle/ pha&e eBit&3 &tage gate&3 or ki"" point&%
Practice of overlapping pha#e# i# often calle/ a&t tracking%
Cost a# sta%%/! = level# are lo' at the #tart3 higher to'ar/# en/3 an/ /rop rapi/l a# the project /ra'# to a concl!#ion%
Co"0'et/o = The pro(a(ilit of #!cce##f!l completion generall get# progre##ivel higher a# the project contin!e#%
Sta:e2o'#er *%'1ece E On the final characteri#tic# of the project4# pro/!ct an/ the final co#t of the project i# highe#t at the
#tart an/ get# progre##ivel lo'er a# the project contin!e#%
R/s: 8 <ncertaint an/ hence ri#, of failing i# high at the (eginning an/ get progre##ivel le##erJ(etter a# project contin!e#
Ke$ sta:e2o'#ers E pm3 c!#tomer &(!J!#e)3 org3 team B #pon#or &pa#)3 Project .anagement team3 P.O
D/%%ereces = 0n general3 /ifference# (et'een or among #ta,ehol/er# #ho!l/ (e re#olve/ in favor of the c!#tomer%
Maa!/! = i# primaril concerne/ 'ith Fcon#i#tentl pro/!cing ,e re#!lt# e1pecte/ ( #ta,ehol/er#3H
Lea#/! = E#ta(li#hing /irection vi#ion of the f!t!re an/ #trategie#3 Aligning people to vi#ion3 .otivating an/ in#piring%
Pro<'e" #e%//t/o = re5!ire# /i#ting!i#hing (et'een ca!#e# an/ #mptom#%
Pro(lem# ma (e internal &a ,e emploee i# rea##igne/ to another project) or e1ternal &a permit re5!ire/ to (egin 'or, i#
/elae/)% Pro(lem# ma (e technical &/ifference# of opinion a(o!t the (e#t 'a to /e#ign a pro/!ct)3 managerial &a
f!nctional gro!p i# not pro/!cing accor/ing to plan)3 or interper#onal &per#onalit or #tle cla#he#)%
Or!a/@at/oa' Str1ct1re *%'1ece o Projects
F!nctional +ea, .atri1 Balance/ .atri1 Strong .atri1 Projecte/
P. a!thorit Little or None Limite/ Lo' to .o/erate .o/erate to @igh @igh to Total
6e#o!rce Availa(ilit Little or None Limite/ Lo' to .o/erate .o/erate to @igh @igh to Total
Project B!/get F!nctional .ngr F!nctional .ngr .i1e/ P. P.
P. 6ole Part Time Part Time F!ll Time F!ll Time F!ll Time
A/mini#trative Staff Part Time Part Time Part Time F!ll Time F!ll Time
Co"0os/te Or!a/@at/o E A f!nctional organi"ation ma create a #pecial project team to han/le a critical projectG the team
ma have #ome characteri#tic# of a project team in a projecti"e/ organi"ation% an/ ma have f!ll time a/min #taff from
/ifferent f!nctional /epartment#3 ma /evelop it# o'n #et of operating proce/!re# an/ ma operate o!t#i/e the #tan/ar/
formali"e/ reporting #tr!ct!re%
PMO E Can e1i#t in an ,in/ of organi"ation incl!/ing the f!nctional organi"ation%
P'a/! 8 Planning i# the onl P. Proce## gro!p that ha# a #pecific or/er of activitie#
Re'ease Reso1rces E 0# the La#t activit in the clo#ing proce## gro!p%
*terat/os E Start after 6i#, management (eca!#e onl after thi# final co#t an/ #che/!le can (e /etermine/%
Page $ o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter . 8 Project Maa!e"et Processes %or a 0roject
P/c: Process E Project .anager along 'ith team i# re#pon#i(le for pic,ing 'hat proce##e# are appropriate%
A00'/cat/o o% Processes E to the project i# iterative%
Coce0t o% /teract/o a"o! PM 0rocesses = &B She'hart B Deming) E PLAN E DO E C@ECD E ACT
Mo/tor/! & Cotro' E Aro!p not onl monitor# an/ control# the 'or, (eing /one 'ithin a proce## gro!p (!t al#o monitor#
an/ control# the entire project effort%
Process 7 i& Fa #erie# of action# (ringing a(o!t a re#!ltH
Process Gro10 E Are not project pha#e#% Proce## gro!p# are !#!all repeate/ for each pha#eJ#!( project%
*/t/at/! Process E Are often /one e1ternal to the project4# #cope of control%
Project C2arter E Approval an/ f!n/ing are han/le/ e1ternal to the project (o!n/arie#% Charter i# primaril concerne/ 'ith
a!thori"ing the project Jpha#e% 0t lin,# project to the ongoing 'or, of the organi"ation%
Ro''/! Wa;e P'a/! E Progre##ive /etailing of the project management plan i# calle/ rolling 'ave planning3 in/icating
plan i# an interactive an/ ongoing proce##%
E=ec1t/! Process Gro10 E .ajorit of the project (!/get 'ill (e #pent in performing E1ec!ting proce## gro!p%
*te!rate# C2a!e Cotro' E 0# performe/ thro!gho!t the project3 from project initiation thr! Project clo#!re%
Core processes Are Performed in same order & may be iterated several times during any
one phase
Facilitating processes- Performed intermittently and as needed during project planning, they
are not
Optional.
Page 1' o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter 4 8 *NTEGRAT*ON Maa!e"et
*te!rat/o Maa!e"et 8 <nification3 Con#oli/ation3 artic!lation an/ interactive action# that are cr!cial to project
completion% 0ntegration i# a(o!t ma,ing choice#3 a(o!t 'here to concentrate re#o!rce# an/ effort% 0t al#o involve# ma,ing
tra/eoff# among competing o(jective# an/ alternative#% P. an/ team m!#t a//re## ever proce## an/ level of /"0'e"etat/o
for proce##
Project De'/;era<'es 8 Nee/ to (e integrate/ 'ith ongoing operation#%
Reasos to start 0rojects 8 $% Pro(lem# *% .ar,et Opport!nit -%B!#ine## 6e5!irement#
Project C2arter ? $% A!thori"e project *% Aive# Project .anager A!thorit -%0##!e/ ( initiator or #pon#or e1ternal to project
organi"ation 'ho ha# the a!thorit to f!n/% 4% 0t i# (roa/ eno!gh that it /oe# not have to change a# the project change#%
Project C2arter Cota/
$% 6e5!irement# that #pecif C!#tomerJSpon#or Nee/#3 'ant# an/ e1pectation# *%B!#ine## Nee/# -%Project p!rpo#e or
j!#tification 4% A##igne/ P. a!thorit 7%Sta,ehol/er infl!ence 6%F!nctional organi"ation participation 9%A##!mption# B
Con#traint# :%B!#ine## ca#e an/ ret!rn on inve#tment ;%S!mmar B!/get
E;/ro"eta' Process Assets = Compan C!lt!re B Str!ct!re3 Aovernment or in/!#tr #tan/ar/#3 infra#tr!ct!re3 e1i#ting
h!man re#o!rce#3 per#onal a/mini#tration &@ire3 Fire3 performance)3 'or, a!thori"ation3 .ar,et place con/ition3 Sta,e
hol/er ri#, tolerance3 Commercial /ata(a#e3 P.0S
Or!a/@at/oa' Process Assets E Stan/ar/#3 Policie#3 Stan/ar/ Pro/!ct an/ Project Life Ccle#3 ?!alit policie# B
proce/!re3 performance mea#!rement criteria3 Template#3 Comm!nication re5!irement#3 Project Clo#!re A!i/eline#3 6i#,
Control proce/!re3 0##!e an/ Defect .anagement Proce/!re3 Change Control Proce/!re3 Proce/!re for Approving B i##!ing
'or, a!thori"ation% 0t al#o incl!/e Proce## .ea#!rement /ata(a#e3 project file#3 @i#torical information B Le##on# learne/3
Config!ration management /ata(a#e3 financial /ata(a#e containing la(or ho!r#3 co#t# B (!/get#%
Project Se'ect/o Met2o#s
$% Benefit .ea#!rement .etho/# &Comparative Approach)
$% Scoring .o/el#
*% Benefit Contri(!tion#
-% .!r/er (oar/ E Panel of people 'ho tr to #hoot /o'n a ne' project i/ea%
4% Peer 6evie'
7% Economic .o/el#
$% Benefit Co#t 6atio *% Ca#h Flo' -%0nternal 6et!rn 6ate 4% Pre#et 8al!e &P8) an/ net pre#ent val!e &NP8)
7%Opport!nit Co#t 6% Di#co!nte/ Ca#h Flo' 9% 6et!rn On 0nve#tment
*% Con#traine/ Optimi"ation .etho/# &.athematical .o/el#)
$% Linear *% Nonlinear -% Dnamic 4% 0nteger 7% .!ltiple O(jective Programming

Preliminary Project Scope Statement Contain
$%Project B Pro/!ct O(jective# *%6e5!irement# B Characteri#tic# -%Acceptance Criteria 4%Bo!n/arie# 7%6e5!irement# an/
Delivera(le# 6%Con#taint# 9%A##!mption# :%Project Organi"ation ;%0nitial Define/ 6i#,# $>%Sche/!le .ile#tone $$%0nitial
+BS $*%Or/er of .agnit!/e Co#t E#timate $-% Config!ration .anagement 6e5!irement#
Project Maa!e"et P'a E 0t /efine# ho' project i# e1ec!te/3 monitore/ an/ controlle/ an/ Clo#e/% P.P can (e either
#!mmar level or /etaile/ an/ can (e compo#e/ of one or more #!(#i/iar plan# an/ other component#% 0t contain# follo'ing
management plan#
1. Scope 2.Schedule .!ost ".#uality $.%is& '.!ommunication (.Procurement ).Schedule *aseline
+.Process improvement Plan 1,.Sta- 11..ile Stone list 12. %esource !alendar 1.!ost *aseline
1".#uality *aseline 1$.%is& %egister
Page 11 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Co%/!1rat/o Maa!e"et E 0t i# a #!( ##tem of overall project management information ##tem% 0t i# a mean# of
monitoring an/ controlling emerging project #cope again#t the #cope (a#elineG it# p!rpo#e i# to control change thro!gho!t the
project% 0t i# an /oc!mente/ proce/!re# !#e/ to appl technical an/ a/mini#trative /irection an/ #!rveillance to a!/it the
item# an/ ##tem to verif conformance re5!irement#% % 0t /oc!ment# the ph#ical characteri#tic# of formal project /oc!ment#
an/ #tep# re5!ire/ to control change# to them &e%g% 'o!l/ (e !#e/ ( a c!#tomer 'ho 'i#he# to e1pan/ the project #cope after
the performance mea#!rement (a#eline ha# (een e#ta(li#he/)% +hen more than one in/ivi/!al ha# #ign a C2arter3 o! have
to (e concerne/ 'ith competing nee/# an/ re5!irement# impacting o!r effort# on config!ration management
Co%/!1rat/o Maa!e"et Act/;/t/es 8 $%Config!ration 0/entification *%Config!ration Stat!# Acco!nting -%Config!ration
8erification an/ a!/iting
C2a!e Cotro' S$ste" E 0t i# a collection of formal /oc!mente/ proce/!re# that /efine ho' project /elivera(le# an/
/oc!mentation are controlle/3 change/ an/ approve/% 0t i# a #!(##tem of config!ration management% 0t m!#t al#o incl!/e
proce/!re# to han/le change# that ma (e approve/ 'itho!t prior revie' &e%g% re#!lt of an emergenc)
*te!rate# C2a!e Cotro' 8 0t i# performe/ from project inception thr! completion3 it incl!/e#
$% 0/entifing that a change nee/# to occ!r or ha# occ!rre/
*% .a,e #!re onl approve/ change# are implemente/
-% 6evie'ing an/ approving re5!e#te/ change#
4% .anaging approve/ change# a# an/ 'hen the occ!r an/ reg!lating them
7% .aintain integrit of (a#eline
6% 6evie' an/ approve all recommen/e/ corrective an/ preventive action#
9% Controlling an/ !p/ating #cope3 co#t3 (!/get3 #che/!le an/ 5!alit
:% Doc!menting impact of re5!e#te/ change#
;% 8ali/ating /efect repair
C2a!es = if the f!nctional manager 'ant# to ma,e a change to time a##ociate/ to a ta#, &change in goal# an/ o(jective# of
the Charter) an/ there i# not eno!gh re#erve3 #enior management &not the Project .anager) #ho!l/ a!thori"e the change% The
(e#t metho/ to contro" change# on the project i# to loo, for #o!rce# of change% The (e#t metho/ to dea" 'ith change# i# to
/irect the change# to the C2a!e Cotro' Boar#% Project Maa!er ha# a!thorit to approve #ome change re5!e#t#% @e i#
given a!thorit to approve Change# in Emergenc Sit!ation#%
*te!rate# c2a!e Cotro' E Occ!r# /!ring all the project management proce##e#%
Project Base'/e E #ho!l/ (e change/ for all implemente/ change#% Sometime#3 certain cla##ification of change# get#
a!tomatic approval on a project an/ /o not nee/ Change Control Boar/ approval%
Project P'a E a# an inp!t to team /evelopment3 the project plan /e#cri(e# the technical conte1t 'ithin 'hich the team
operate#%
Project E=ec1t/o E Altho!gh the pro/!ct#3 #ervice# or re#!lt# of the project are fre5!entl in the form of tangi(le
/elivera(le# #!ch a# (!il/ing3 roa/ or #oft'are3 /ta!/<'e /elivera(le# #!ch a# training i# al#o provi/e/%
Sc2e#1'e C2a!e Cotro' S$ste" E can incl!/e the paper3 ##tem# an/ approval# for a!thori"ing change#% The project
manager i# normall not the approval a!thorit3 an/ not all the change# approve/
Or!a/@at/o Process Assets E 0ncl!/e# an in/e1 B location of project /oc!mentation
Formal Acceptance Doc!mentation
Project File#
Clo#!re Doc!ment#
@i#torical information
Page 12 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter A 8 SCOPE Maa!e"et
Project Sco0e Maa!e"et = proce##e# re5!ire/ to en#!re that the project incl!/e# onl the 'or, re5!ire/ to complete the
project #!cce##f!ll%
Project Sco0e Maa!e"et P'a = Provi/e# g!i/ance on ho' project #cope 'ill (e /efine/3 /oc!mente/3 verifie/3 manage/
an/ controlle/ ( project management team% 0t incl!/e#
$% A proce## to prepare /etaile/ project #cope #tatement (a#e/ on preliminar project #cope #tatement
*% A proce## that ena(le# creation of +BS al#o e#ta(li#he# ho' +BS 'ill (e maintaine/ an/ approve/
-% @o' formal verification an/ acceptance of the complete/ project /elivera(le# 'ill (e o(taine/
4% A proce## to control change# to project #cope3 it i# /irectl lin,e/ to integrate/ change control
Sco0e State"et Cota/ E $%Project O(jective# *%Pro/!ct Scope De#cription -%Project 6e5!irement 4%Project Bo!n/arie#
7%Project Delivera(le# 6%Pro/!ct Acceptance Criteria 9% Con#traint# :% A##!mption# ;%Project Organi"ation $>%0nitial
i/entifie/ ri#,# $$%Sche/!le .ile#tone# $*%F!n/ Limitation $-%Co#t E#timate $4%Project Config!ration .anagement
6e5!irement# $7%Specification# $6%Approval 6e5!irement#
Ro''/! Wa;e P'a/! 8 The Project .anagement team !#!all 'ait# !ntil the /elivera(le or #!(project i# clarifie/ #o the
/etail# of the +BS can (e /evelope/% Thi# i# referre/ a# rolling 'ave planning% So +or, to (e performe/ in the near f!t!re i#
planne/ to the lo' level of the +BS3 'here a# 'or, to (e performe/ far into the f!t!re can (e planne/ at the relativel high
level of the +BS%
Brea: Do& Str1ct1res
$% +or, Brea, Do'n Str!ct!re &+BS)
*% Organi"ational Brea,/o'n Str!ct!re &OBS)
-% 6e#o!rce Brea,/o'n Str!ct!re &6BS)
4% 6i#, Brea,/o'n Str!ct!re &6BS)
7% Bill of .aterial# &BO.) E @ierarchical ta(!lation of ph#ical a##em(lie#3 #!(a##em(lie# B component# nee/e/ to
fa(ricate a man!fact!re/ pro/!ct%
WBS D/ct/oar$ 8 For each +BS Component3 +BS /ictionar incl!/e# a FCo#e o% Acco1t *#et/%/er>B a #tatement of
'or,3 re#pon#i(le organi"ation3 an/ a li#t of #che/!le mile#tone#% Other information can (e Contract information3 ?!alit
re5!irement# an/ technical reference%
Sco0e Base'/e E Approve/ /etaile/ project Scope #tatement3 +BS an/ +BS /ictionar are the #cope (a#eline%
Sco0e 4er/%/cat/o E to verif that the 'or, /one #ati#fie# the #cope of the project% 0t m!#t (e /one at the en/ of each pha#e% A
#imilar activit /!ring clo#!re i# Pro#1ct 4er/%/cat/o% Foc!#e# on c!#tomer acceptanceJperformance mea#!rement3 not
change to project #cope% Scope 8erification i# normall /one after 5!alit control &'hich chec,# for pro/!ct correctne##) (!t
the#e t'o proce##e# can (e performe/ in parallel% Occ!r /!ring the control pha#e of the project3 not at the en/% The revie' at
the en/ of the project pha#e i# calle/ pha#e e1it3 #tage gate3 or ,ill point%
*s0ect/o E Are calle/ 6evie'#3 Pro/!ct 6evie'#3 A!/it# an/ +al,thro!gh#%
Sco0e Cree0 E <ncontrolle/ change# are often referre/ a# project #cope creep%
4ar/ace Aa'$s/s E Project performance i# mea#!rement# are !#e/ to a##e## the magnit!/e of variation% 0t incl!/e# fin/ing
the ca!#e of variation relative to the #cope (a#eline%
Costra/ts ? A con#traint i# an applica(le re#triction that 'ill affect the performance of the project% For e1ample3 a
pre/efine/ (!/get i# a con#traint
Ass1"0t/os ? A##!mption# are factor# that3 for planning p!rpo#e#3 are con#i/ere/ to (e tr!e3 real3 or certain%
Deco"0os/t/o ? &$#t level E Project pha#e#3 *
n/
level E Delivera(le# &Brea, /o'n till co#t e#timate# can (e /one3 verif
/ecompo#ition correctne##) ) lo'e#t level of the +BS ma (e referre/ to a# work packages.
+or, not in the +BS i# o!t#i/e the #cope of the project%
Maa!e"et <$ O<ject/;e (MBO( E /etermining compan4# o(jective an/ ho' the project fit# into them% .BO foc!#e# on
the goal# of an activit rather than the activit it#elf &manager i# re#pon#i(le for re#!lt# rather than performing certain
activitie#)
Page 1% o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Project Sco0e = the 'or, that m!#t (e /one in or/er to /eliver a pro/!ctG completion i# mea#!re/ again#t the project p"an. 0t
incl!/e# meeting#3 report#3 anal#i# an/ all the other part# of P.%
Pro#1ct Sco0e = feat!re# an/ f!nction# that are to (e incl!/e/ in a pro/!ctG completion i# mea#!re/ again#t the Pro/!ct
re5!irement#. 0t can (e #!pplie/ a# a re#!lt of a previo!# project to /etermine the re5!irement#%
Des/! Sco0e E contain the /etaile/ project re5!irement# &!#e/ for FP contract)
Sco0e De%//t/o E #!(/ivi/ing major project /elivera(le#%
Deco"0os/! E #!(/ivi/ing project 'or, pac,age# into #maller3 more managea(le component# &activitie#Jaction #tep#)% The
he!ri#tic &r!le of th!m() !#e/ in project /ecompo#ition i# :> ho!r#%
Sco0e Maa!e"et P'a = /e#cri(e# ho' #cope 'ill (e manage/ an/ ho' change# 'ill (e integrate/ into projectG al#o
incl!/e# a##e##ment of e1pecte/ #ta(ilit of project #cope% &e%g% project manager 'o!l/ refer to the Scope .anagement Plan to
ma,e a change)
Sta:e2o'#er Maa!e"et E the project manager m!#t i/entif the #ta,ehol/er#3 /etermine their nee/# an/ e1pectation#3
then manage an/ infl!ence e1pectation# to en#!re project #!cce##% Project #!cce## /epen/# primaril on c1sto"er
sat/s%act/o%
WBS = #!(/ivi/ing project /elivera(le# into #maller3 more managea(le component#% 0t i# a /elivera(le=oriente/ gro!ping of
project element# that organi"e# an/ /efine# the total #cope of the project% 0t i# a comm!nication tool an/ it /e#cri(e# 'hat
nee/# to (e /one an/ 'hat #,ill# are re5!ire/% Anthing mi##ing in the +BS #ho!l/ (e a//e/% The $
#t
level #ho!l/ (e the
project life=ccle &not product)% The +BS i# create/ ( the team &help# to get (!=in) an/ it i# !#e/ to ma,e certain that all the
'or, i# covere/% 0t provi/e# a (a#i# for e#timating the project an/ help# to organi"e the 'or,% 0t# p!rpo#e i# to incl!/e the total
project #cope of all the 'or, that m!#t (e /one to complete the project% Define# the project4# #cope (a#eline%
The - mo#t common tpe# of +BS are ##temJ#!( ##tem#3 life=ccle pha#ing an/ organi"ational% W/t2o1t WBS
$% Project 'ill ta,e longer3 element# 'ill #lip thr! crac,#
*% Delivera(le oriente/3 not onl c!#tomer /elivera(le# (!t all /elivera(le#
-% Top /o'n effort to /ecompo#e 'or, into #mall piece#%
WBS D/ct/oar$ 8 Define# each item in the +BS3 incl!/ing /e#cription of the 'or, pac,age# an/ other planning info #!ch
a# #che/!le /ate#3 co#t (!/get# an/ #taff a##ignment#% 0t help# re/!ce Scope Creep an/ increa#e# !n/er#tan/ing%
+BS /ictionar can (e !#e/ a# a part of Wor: A1t2or/@at/o s$ste" to inform team mem(er# of 'hen their 'or, pac,age i#
going to #tart3 #che/!le mile#tone# an/ other info%
Sco0e State"et E Define an/ recor/ Re31/re"ets% A /oc!mente/ /e#cription of the o(jective#3 'or, content3 /elivera(le#3
an/ en/ pro/!ctG it incl!/e# a /e#cription of project a##!mption# an/ con#traint#% Provi/e# #ta,ehol/er# 'ith a common
!n/er#tan/ing of the #cope of the project an/ i# a #o!rce of reference for ma,ing f!t!re project /eci#ion#%
State"et o% Wor: = a narrative /e#cription of pro/!ct# or #ervice# to (e #!pplie/ !n/er contract%
Project C2arter = formal /oc!ment !#e/ an/ approve/ ( #enior management that e1plain# p!rpo#e of the project incl!/ing
(!#ine## nee/# a//re##e/ an/ the re#!lting pro/!ct &/elivera(le# an/ o(jective#)% 0t /e#cri(e# re#pon#i(ilitie# an/ a!thorit of
the project manager to appl organi"ational re#o!rce# to project activitie#% Clarification to the Project Charter m!#t (e
a//re##e/ to the #pon#or&#) 'ho approve/ the charter% 6e#o!rce# cannot (e committe/ 'itho!t the Charter% The Charter i# an
inp!t to ALL the project management proce##e#%
Wor: Pac:a!e = /elivera(le at the lo'e#t level of +BS% The are control point# in the +BS an/ are !#e/ for a##ignment# to
'or, center#% The are !#e/ to pa## a gro!p of 'or, for f!rther (rea,/o'n in the e1ec!tive organi"ation%
Cost Acco1t E one level a(ove the +or, Pac,age%
Ass1"0t/os E factor# that3 for planning p!rpo#e#3 are con#i/ere/ to (e tr!e3 real or certain
The principal so1rces o% 0roject %a/'1re are organi"ational factor#3 poorl i/entifie/ c!#tomer nee/#3 ina/e5!ate #pecifie/
project re5!irement#3 an/ poor planning an/ control%
Page 1( o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Costra/e# o0t/"/@at/o E incl!/e# analtic hierarch proce##3 logical frame'or, anal#i# an/ m!lti=o(jective
programming%
.o#t C2a!e Re31ests are the re#!lt ofK
An e1ternal event
An error or omi##ion in /efining the #cope of the pro/!ct
An error or omi##ion in /efining the #cope of the project
A val!e=a//ing change
A C2a!e Re31est i# the mo#t effective 'a of han/ling the /i#connect (et'een 'hat !#er# act!all 'ant an/ 'hat
management thin,# the 'ant% The project manager4# role relate/ to project change i# to infl!ence the factor# that affect
change% @e #ho!l/ a#, for a change or/er an/ loo, for impact# to the triple con#traint% Sco0e C2a!es on project can (e
minimi"e/ ( #pen/ing more time /eveloping the sco0e <ase'/e%
0f there i# eno!gh reser;e to accommo/ate a change3 the Project .anager can approve the change &'e are pai/ to manage the
#cope completion 'ithin o!r (!/get an/ re#erve#)
Page 10 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter C 8 T*ME Maa!e"et
Project T/"e Maa!e"et = proce##e# re5!ire/ to en#!re timel completion of the project
Act/;/t$ De%//t/o E /efine# activitie# that m!#t ta,e place to pro/!ce project /elivera(le#
Act/;/t$ E con#!me# time &eg te&ting)
E;ets E #pecifie/ accompli#hment J /oe# not con#!me time &eg te&ted)
T/"e Maa!e"et 8 0n #mall project# Activit Definition3 Se5!encing3 6e#o!rce E#timation3 D!ration E#timation an/
Sche/!le /evelopment are #o tightl lin,e/ that the are vie'e/ a# #ingle proce##%
Sc2e#1'e Maa!e"et P'a E Development of Sche/!le .anagement Plan i# part of Develop Project .anagement Plan
Proce##% S.P i# a #!(#i/iar plan of P.P an/ ma formal or informal3 highl /etaile/ or (roa/l frame/ /epen/ing on the
project%
Deco"0os/t/o &TT !#e/ in Activit Definition)
0nvolve# #!( /ivi/ing the +or, Pac,age# into #maller component# calle/ activitie#%
Activit Definition o!tp!t i# #che/!le activitie# not Delivera(le# &Create +BS o!tp!t i# Delivera(le#)
Activit li#t3 +BS an/ +BS /ictionar can (e /evelope/ either #e5!entiall or conc!rrentl%
Performe/ ( team mem(er# re#pon#i(le for the 'or, pac,age%
P'a/! Co"0oet &TT !#e/ in Activit Definition)
Cotro' Acco1t E From management Per#pective a control line i# /ra'n in the +BS @ierarch level#% All the Planning
component# a(ove thi# line (elong to 'hat i# calle/ the Control Acco!nt% All effort# performe/ 'ithin a control acco!nt are
/oc!mente/ in a control acco!nt plan%
P'a/! Pac:a!e 8 0t i# a +BS Component (elo' the control acco!nt (!t a(ove the 'or, pac,age%
Act/;/t$ L/st
Doe# not incl!/e an #che/!le activit that i# not re5!ire/ a# part of the project #cope
0t incl!/e# a activit i/entifier an/ #cope of 'or, /e#cription for each #che/!le activit in #!fficient /etail%
0t i# !#e/ in #che/!le mo/el an/ i# part of P.P&Project .anagement Plan)
Di#crete component# of Project Sche/!le (!t are not component# of the +BS%
Act/;/t$ Attr/<1tes E Contain Activit i/entifier3 activit Co/e3 Activit De#cription3 Pre/ece##or Activitie#3 S!cce##or
activitie#3 logical relation#hip#3 lea/# an/ lag#3 re#o!rce re5!irement#3 impo#e/ /ate#3 con#traint# an/ a##!mption#%
M/'estoe E Can (e man/ator or optional3 it a component of P.P3 incl!/e/ in SS an/ +BSD an/ !#e/ in #che/!le mo/el%
P. can impo#e a//itional mile#tone#%
9ra!"et Net&or: 8 Portion# of project #che/!le net'or, /iagram are often referre/ to a# a S!( net'or, or Fragment
Net'or,% S!( Net'or, template# are !#ef!l 'hen project ha# #everal i/entical or nearl i/entical /elivera(le#%
Lea# a# La! E Lea/ allo'# acceleration of the #!cce##or activit3 A lag /irect a /ela in S!cce##or activit%
Botto" -0 Est/"at/o &TT of 6e#o!rce E#timation) E E#timation i# /one for lo'er level item# an/ then aggregate/%
Act/;/t$ Reso1rce Est/"at/o E 0/entifie# tpe an/ 5!antitie# of re#o!rce# re5!ire/ for a #che/!le activit% The#e are
aggregate/ to /etermine the e#timate/ re#o!rce# for each 'or, pac,age%
RBS (Reso1rce Brea: Do& Str1ct1re( 8 O!tp!t of Activit 6e#o!rce E#timation proce##3 it i# a hierarchical #tr!ct!re of
re#o!rce# ( categor B tpe%
Act/;/t$ D1rat/o Est/"ate 8 Some in/ication of range of po##i(le val!e# &*+ee,# I or E * /a#)
TT %or Act/;/t$ D1rat/o Est/"at/o
7. Aa'o!o1s Est/"at/o E <#ing act!al /!ration of previo!# #imilar #che/!le activit% 0t i# project level3 given to P.
from .anagement or Spon#orG it i# a form of E1pert 2!/gment%
2. Para"etr/c Est/"at/o 8 ?!antit of +or, C Pro/!ctivit 6ate = $%6egre##ion Anal#i# &Scatter Diagram)
*%Learning C!rve% 6e#!lt# of Parametric E#timation can (ecome he!ri#tic#%
.. T2ree Po/t Est/"ates E .o#t Li,el3 Optimi#tic3 Pe##imi#tic%
Page 12 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
4. Reser;e Aa'$s/s
A. E=0ert J1#!"et
*"0ose# Dates 8 0mpo#e/ /ate# in Scope Statement &0JP to Sche/!le Development Proce##) re#trict the #tart or fini#h /ate%
Sc2e#1'e Net&or: Aa'$s/s (TT %or Sc2e#1'e De;e'o0"et(
$% Cr/t/ca' Pat2 Met2o# E Calc!late Project D!ration3 Critical path length an/ Float% Critical path can have > or
negative tota' %'oat%
*% Sc2e#1'e Co"0ress/o E Cra#hing &A//itional 6e#o!rce#) an/ Fa#t Trac,ing &Parallel)
-% W2at /% Scear/o E .onte Carlo Anal#i#
4% Reso1rce Le;e'/! E Applie/ after Critical Path .etho/3 Deep re#o!rce !#age at con#tant level
7% Cr/t/ca' C2a/ Met2o# E <#e# Pe##imi#tic re#o!rce availa(ilit3 A//# /!ration (!ffer# that are non 'or, #che/!le
activitie#%
Mote Car'o Aa'$s/s E $% Pro(a(ilit of Completion *% Pro(a(ilit of Completion in amo!nt of Co#t -%Pro(a(ilit of activit
in critical path 4% 6i#,
Project Sc2e#1'e 8 Sho!l/ at lea#t incl!/e planne/ #tart /ate an/ fini#h /ate for each #che/!le activit3 project #che/!le i#
preliminar till re#o!rce allocation# are /one3 'hich !#!all happen# (efore completion of P.P% Project #che/!le i# 'hen
pre#ente/ in #!mmar form i# calle/ a# ma#ter #che/!le or mile#tone #che/!le%
T/"e Est/"ate E Non=Calen/ar Sc2e#1'e E Calen/ar Ba#e/
6a""oc: Act/;/t$ E OJp of Sche/!le Development =L Bar Chart# =L For Control an/ management comm!nication3 the
(roa/er more comprehen#ive #!mmar activit calle/ @ammoc, Activit i# !#e/ (et'een mile#tone# or acro## m!ltiple
inter/epen/ent 'or, pac,age#%
Project et&or: #/a!ra"s. Project net'or, /iagram# are #chematic /i#pla# of the project4# activitie# an/ the logical
relation#hip# &/epen/encie#) among them%
Co#/! str1ct1re. .cti@itie& mu&t ha@e /ifferent attri(!te# &a# re#pon#i(ilit3 geographic area 3M = <#e/ for #orting)
Cr/t/ca' Pat2 Met2o# (CPM( (ML( Ncalc!late# #tart an/ fini#h /ate for each activit B "oat
Gra02/ca' E;a'1at/o a# Re;/e& Tec2/31e (GERT(Dallo'# for pro(a(ili#tic treatment of (oth net'or, logic an/
activit /!ration e#timate#% 0t i# a form of AD. &A Net'or, Dra'ing .etho/) that allo'# loop# (et'een activitie#% The
ea#ie#t e1ample i# 'hen o! have an activit to /e#ign a component an/ then te#t it%
Pro!ra" E;a'1at/o a# Re;/e& Tec2/31e &PERT) &OI4.LIPJ6)N!#e# a 'eighte/ average /!ration e#timate to
calc!late activit /!ration#%
Project Time .anagement
Arro' Diagramming .etho/
&AD.)K
PE6T an/ CP. foc!#e# on float /!ration3 to /etermine 'hich activitie# have the lea#t
#che/!ling fle1i(ilit% Activit on Arro'% Onl Sho' %//s2?to?start relation#hip
PE6T Program Eval!ation an/ 6evie' Techni5!e
Empha#i# on meeting #che/!le# 'ith fle1i(ilit on co#t
Three time e#timate# per activitK pe##imi#tic3 mo#t li,el3 an/ optimi#tic
The pro(a(ilit of completing a project at or later than it# e1pecte/ time i# 7>O
Event oriente/G !#e# /!mmG activit on arro' &AOA)
Fini#h=to=Start logical relation#hip
Time e#timate# appear on arro'
Critical Path .etho/ &CP.) Empha#i# on controlling co#t an/ leaving the #che/!le fle1i(le
One time e#timate per activit
Activit oriente/G !#e# /!mmG activit on arro'
Time e#timate# appear on arro'
Prece/ence Diagram .etho/
&PD.)
6epre#ent# improvement to PE6T an/ CP. ( a//ing lag relation#hip# to activitie#
PStart to StartG Start to Fini#hG Fini#h to StartG Fini#h to Fini#hQ
+or, i# /one /!ring activit% Arro' in/icate# /epen/anc
Activit on no/eG no /!mm
%//s2?to?start i# the mo#t commonl !#e/ tpe of logical relation#hip% Start?to?%//s2
relation#hip# are rarel !#e/
AE6T A net'or, /iagram /ra'ing metho/ that allo'# loop# (et'een ta#,#% 0t i# a metho/ of
#e5!encing &e%g% a project re5!ire# re/e#ign after completion of te#ting)
De0e#ec/es
.an/ator or @ar/ Often involve ph#ical or technological limitation# &(a#e/ on the nat!re of 'or, (eing
Page 17 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
/one)
Di#cretionar ma al#o (e calle/ preerred "ogic3 preerentia" "ogic3 or &ot "ogic%
SoftK /e#ira(le an/ c!#tomar &(a#e/ on e1perience)
PreferentialK preferre/ or man/ate/ ( a c!#tomer &al#o3 nee/ of the project #pon#or)
Define/ ( P. Team
E1ternal 0np!t nee/e/ from another project or #o!rce
Cr/t/ca' c2a/ i# a techni5!e that mo/ifie# the project #che/!le to acco!nt for limite/ re#o!rce#%
PERT We/!2te# A;era!e R &O I 4. I P)J6 #tan/ar/ /eviation R &P = O)J6 variance R #tan/ar/ /eviation
*
&To a//
#tan/ar/ /eviation#K convert to variance then a//G ta,e the #5!are root of the #!m)% Be#t metho/ 'hen o! have no hi#torical
/ata for a #imilar ta#,% 6e#!lt# i# the 7>O point &mean)%
Mote Car'o Aa'$s/s = comp!ter #im!lation of project o!tcome# !#ing PE6T e#timate#G re#!lt repre#ente/ in S c!rve%
Provi/e# the a(ilit to comp!te the pro(a(ilit of completing a project on a #pecific /a% Can al#o (e !#e/ to a##e## fea#i(ilit
of #che/!le !n/er a/ver#e con/ition# &eg 'hen a #che/!le con#traint i# i/entifie/)
6e1r/st/cs = r!le# of th!m(
Cr/t/ca' Pat2 E longe#t path &almo#t al'a# have no float)
Near Cr/t/ca' Pat2 E Path i# clo#e in /!ration to critical path3 the clo#e it i# the more 60SD project ha#%
4ar/ace = Plan min!# Act!al
9'oat E S'ac: E $%Free *% Total -% Project Float% Time an activit ma (e /elae/ from it# earl #tart 'itho!t /elaing the
project fini#h /ate% Difference (et'een the re5!ire/ en/ /ate an/ the e1pecte/ project completion /ate% A negative #lac, on
the critical path mean# that the project i# (ehin/ #che/!le%
9ree 9'oat E Amo!nt of time a ta#, can (e /elae/ 'itho!t /elaing the earl #tart of it# #!cce##or
Tota' 9'oat E amo!nt of time that an activit ma (e /elae/ from earl #tart 'itho!t /elaing the project fini#h /ate
La! E 'aiting time (et'een t'o ta#,# &negative lea/)
Sc2e#1'e Base'/e = the original3 approve/ project #che/!leG #ho!l/ never (e change/ 'itho!t proper revie' an/ approval%
An approve/ change #ho!l/ (e /oc!mente/ in 'riting% Sho!l/ (e create/ at the (eginning of the project an/ !#e/ /!ring the
project to ga!ge &mea#!re) overall project performance3 not j!#t #che/!le% The project Per%or"ace Meas1re"et Base'/e
#ho!l/ generall change onl in re#pon#e to a #cope or /elivera(le change% The project performance mea#!rement (a#eline#
#ho!l/ generall change onl in re#pon#e to a #cope or /elivera(le change%
Correct/;e act/o = in project time management primaril concern# e1pe/iting to en#!re that activitie# remain on #che/!le%
0# anthing /one to (ring e1pecte/ f!t!re #che/!le performance in line 'ith the project plan%
Re;/s/os are change# to the #che/!le/ #tart an/ fini#h /ate# in the approve/ project #che/!leG generall revi#e/ onl in
re#pon#e to #cope change#% Re<ase'//! ma (e nee/e/ to provi/e reali#tic /ata to mea#!re performance%
Sche/!ling an/ allocating re#o!rce# to "1't/0'e 0rojects ma affect #che/!le #lippage an/ in=proce## inventor%
The mo#t important element nece##ar for project control i# clear re5!irement#%
D1rat/o Co"0ress/o Met2o#s E occ!r# after activit /!ration e#timating an/ (efore finali"ing the #che/!le% 0ncl!/e
cras2/!B %ast trac:3
Cras2/! 8 'hen o! are 'orrie/ a(o!t time3 not #o m!ch a(o!t co#t#%
9ast Trac: 8 re#o!rce# in parallel3 involve increa#e re'or,% Sho!l/ fa#t trac, ta#,# on the critical path &float R >) in or/er to
#ave time%
Reso1rce Le;e'/! 8 often re#!lt# in a project /!ration that i# longer than the preliminar #che/!le% Reso1rce rea''ocat/o
from non=critical to critical path activitie# i# a common 'a to (ring the #che/!le (ac,3 or a# clo#e a# po##i(le3 to the
originall inten/e/ overall /!ration% So $% Sche/!le Can Slip *% Co#t increa#e
9//s2 to 9//s2 = activitie# m!#t fini#h on a #pecific #e5!ence
FStart o ear'/er t2a> & F9//s2 o 'ater t2a> E 6e#pectivel S$ an/ S* mo#t pop!lar /ate con#traint in project
management #oft'are%
Root Ca1se Aa'$s/s E !#e/ to i/entif the ca!#e of the variation
4ar/ace aa'$s/s E ,e element to time control% 9'oat ;ar/ace i# an e##ential planning component for eval!ating project
time performance%
Re;/s/o E categor of #che/!le !p/ate that re#!lt in change to the project4# #che/!le/ #tart or fini#h /ate#% Ne' target
#che/!le #ho!l/ (e the !#!al mo/e of #che/!le revi#ion%
Sc2e#1'e Maa!e"et P'a E /efine# ho' #che/!le change# 'ill (e manage/G ma (e formal or informal%
Sc2e#1'e C2a!e Cotro' S$ste" E /efine# proce/!re# for changing the project #che/!le an/ incl!/e# the /oc!mentation3
trac,ing ##tem#3 an/ approval level# re5!ire/ for a!thori"ing #che/!le change#%
Reso1rce P'a/!
Too's
6e#pon#i(ilit .atri1 0/entif 'ho /oe# 'hat at 'hat timeJpha#e of the project
Page 13 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
6e#o!rce Sprea/#heet ?!antifie# ho' m!ch 'or, i# nee/e/ from each re#o!rce /!ring each time perio/
6e#o!rce Aantt Chart 0/entif the perio/# of time &e%g% calen/ar /ate) 'hen a partic!lar re#o!rce i# 'or,ing on a
partic!lar ta#,
6e#o!rce @i#togram
&6e#o!rce Loa/ing
Chart)
8ertical (ar chart #ho'ing the total n!m(er of re#o!rce# nee/e/ /!ring each time perio/
Sc2e#1'/! Too's
Net'or,# &PE6T3 CP.3
PD.)
0nter/epen/encie#G ho' relate/
Barchart &Aantt) Effective progre## reporting toolG no logical relation#hip# #ho'n (et'een activitie#
.ile#tone Chart Significant event#G goo/ for comm!nicating #tat!# &!#e/ to trac, #!cce##)
Bar C2art (Grat C2art( E $% +ea, Planning Tool# *% Aoo/ reporting tool# -% No Depen/enc Sho'n 4% No 6e#o!rce#
#ho'n
Pro!ress Re0ort E 7>J7>3 *>J:>3 >J$>> E An Activit i# con#i/ere/ T percent complete 'hen it (egin# an/ get# cre/it of the
la#t $>>=T percent onl 'hen it i# complete/%
Page 1$ o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter ) 8 COST Maa!e"et
Cost Est/"at/! ? Developing an appro1imation &e#timate) of the co#t# of the re#o!rce# nee/e/ to complete project activitie#%
Cost B1#!et/! = Allocating the overall co#t e#timate to in/ivi/!al 'or, activitie#%
Cost Cotro' ? Controlling change# to the project (!/get%
Reso1rce P'a/!N/etermining 'hat re#o!rce# &people3 e5!ipment3 material#) an/ 'hat 5!antitie# of each #ho!l/ (e !#e/
to perform project activitie#%
L/%e C$c'e Cost/! E Broa/er vie' of Project Co#t .anagement3 'hich incl!/e# co#t of re#o!rce# nee/e/ to complete
#che/!le activitie# along 'ith effect of /eci#ion# on co#t of !#ing3 maintaining B #!pporting the pro/!ct3 #ervice or re#!lt of
the project%

Cost Maa!e"et P'a ? 0t i# create/ a# part of the Develop Project .anagement Plan proce##% 0t can e#ta(li#h
$% Preci#ion Level &U$>>3 U$>>> etc)
*% <nit# of .ea#!re &Staff ho!r#J/a#Jl!mp #!m etc)
-% Organi"ational Proce/!re Lin,# &Control Acco!nt3 co/e or acco!nt n!m(er /irectl lin,e/ acco!nting ##tem)
4% Control thre#hol/# &Agree/ amo!nt of variation allo'e/)
7% Earne/ 8al!e r!le# &$%Comp!tation Form!la *%Earne/ 8al!e Cre/it Criteria -%+BS Level)
6% 6eporting Format#
9% Proce## /e#cription# &Each of the three co#t management Proce##e#)
ROM E Acc!rac of project e#timate 'ill increa#e a# it progre##e#3 project at initial #tage# can have ro!gh or/er of magnit!/e
&6O.) in the range of E7> to I$>>O later it 'ill narro' to a range of E$> to I$7O%
Cot/!ec$ Reser;e = $%Project &,no'n <n,no'n#) E Part of Co#t Ba#eline
*%.anagement &<n,no'n <n,no'n#) E Part of Co#t B!/get
C2art o% Acco1ts = A chart of acco!nt# /e#cri(e# the co/ing #tr!ct!re !#e/ ( the performing organi"ation to report
financial information in it# general le/ger%
Aa'o!o1s est/"at/! = al#o calle/ top7down e&timating3 mean# !#ing the act!al co#t of a previo!#3 #imilar project
Parametric mo/eling = mathematical mo/el to pre/ict project co#t# = per #5!are foot of living #pace
Para"etr/c Est/"at/o E 0t !#e# #tati#tical relation#hip (et'een hi#torical /ata an/ other varia(le# to calc!late co#t e#timate%
0t can pro/!ce higher level# of acc!rac /epen/ing on #ophi#tication3 re#o!rce 5!antit an/ co#t /ata%
Botto"?10 est/"at/! = the co#t of in/ivi/!al activitie# or 'or, pac,age# rolle/ !p to get the e#timate for 'hole component%
Cost <ase'/e ? The co#t (a#eline i# a time=pha#e/ (!/get that 'ill (e !#e/ to mea#!re an/ monitor co#t performance on the
project% 0t i# #ho'n a# an S c!rve%
91#/! L/"/t Recoc/'/at/o E C!#tomer 'ill #et limit# on /i#(!r#ement of f!n/# for the project% F!n/ing Limit
6econciliation &TT of Co#t B!/geting) 'ill nece##itate the #che/!ling of 'or, to (e a/j!#te/ to #mooth or reg!late tho#e
e1pen/it!re#% 0t i# accompli#he/ ( placing impo#e/ /ate con#traint# for #ome 'or, pac,age#%
Project Per%or"ace Re;/e&s (TT o% Cost Cotro'( E $%8ariance Anal#i# *%Tren/ Anal#i# -%Earne/ 8al!e Techni5!e
Per%or"ace Meas1re"et Aa'$s/s &TT of Co#t Control)E P83 E83 AC3 ETC3 C83 S83 CP03 SP0
EAC ?Original e#timating a##!mption# 'ere f!n/amentall fla'e/3 or that the are no longer relevant to a change in
con/ition#% Form!laK EAC R AC I ETC%
C!rrent variance# are #een a# atpical an/ the project management team e1pectation# are that #imilar variance# 'ill not occ!r
in the f!t!re% Form!laK EAC R AC I BAC E E8%
+hen c!rrent variance# are #een a# tpical of f!t!re variance#% Form!laK EAC R AC I &&BAC E E8)JCP0)
Project Cost Maa!e"et Proce##e# re5!ire/ to en#!re that the project i# complete/ 'ithin the approve/ (!/get%
Bee%/t Cost Rat/o E1pecte/ 6even!e# J E1pecte/ Co#t#% .ea#!re (enefit# &pa(ac,) to co#t#G not j!#t profit#% The
Page 2' o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
higher the (etter &if rating over $3 the (enefit# are greater than the co#t#)
*tera' Rate o% Ret1r 0ntere#t 6ate 'hich ma,e# the P8 of co#t# e5!al to P8 of (enefit#
Pa$<ac: Per/o# N!m(er of time perio/# !p to the point 'here c!m!lative reven!e# e1cee/# c!m!lative co#t#%
+ea,ne## in thi# approach i# the lac, of empha#i# on the magnit!/e of the profita(ilit% Doe#
not acco!nt for time val!e of mone nor con#i/er val!e (enefit# after pa(ac,%
O00ort1/t$ Cost Co#t of choo#ing one alternative an/ therefore giving !p the potential (enefit# of another
alternativeK it i# the val!e of the project not #electe/ &lo#t opport!nit)%
S1: Cost E1pen/e/ co#t# 'hich #ho!l/ (e ignore/ 'hen ma,ing /eci#ion# a(o!t 'hether to contin!e
inve#ting in a project
La& o% D/"//s2/!
Ret1rs
Stra/!2t L/e
De0rec/at/o
The point (eon/ 'hich the marginal a//ition of re#o!rce# /oe# not provi/e a proportional
amo!nt of !tilit% Same amo!nt each time perio/ &e%g% $> E $> E $>)%
Tpe# $% Straight Line *% Accelerate/ &$% Do!(le Declining Balance *% S!m of Vear# Digit#)
Cot/!ec$ Reser;e Separate 5!antit of timeJmone for ,no'n !n,no'n#% De#igne/ to cover #pecific ri#, event#
previo!#l i/entifie/ an/ mea#!re/ in the 6i#, .anagement Proce##%
Maa!e"et Reser;e Separate 5!antit of timeJmone for !n,no'n !n,no'n#
Wor:/! Ca0/ta' C!rrent A##et# = C!rrent Lia(ilitie#
4a'1e Aa'$s/s Co#t re/!ction tool that con#i/er# 'hether f!nction i# reall nece##ar an/ 'hether it can (e
provi/e/ at a lo'er co#t 'itho!t /egra/ing performance or 5!alit% Fin/ing the lea#t e1pen#ive
'a to /o the #cope of 'or,%
4a'1e Est/"at/! Part of Co#t Control
4a'1e E!/eer/! Too' Tool for anal"ing a /e#ign3 /etermining it# f!nction3 an/ a##e##ing ho' to provi/e tho#e
f!nction# co#t effectivel%
AG?AG R1'e At (eginning3 charge 7>O of it# BC+S to the acco!nt% Charge remaining at completion%
Aa'o!o1s Est/"at/! Top /o'nG (a#e/ on #imilar project#% 6epre#ent# a form of e1pert j!/gment% Aive# project team
an !n/er#tan/ing of management4# e1pectation# &part of co#t (!/geting an/ co#t e#timating)
Botto"?10 Est/"at/! Detaile/ co#t e#timate# of 'or, pac,age# are aggregate/% +o!l/ provi/e (e#t overall 5!alit of
the e#timate%
Para"etr/c Est/"at/! 6elie# on ,no'le/ge of mathematical relation#hip#G mea#!re/ in UJ!nit &#cala(le3 5!antifia(le)%
0t /oe# not ma,e !#e of team e#timate% &part of co#t (!/geting an/ co#t e#timating)% <#ing a
mathematical mo/el to pre/ict the /!ration of a ta#, &e%g% ta,ing the average /!ration of all
pa#t ta#,#)
Re!ress/o Aa'$s/s Stati#tical techni5!e graphicall repre#ente/ on #catter /iagram
Lear/! C1r;e .athematicall mo/el# the int!itive notion that the more time# 'e /o #omething3 the fa#ter 'e
'ill (e a(le to perform
4ar/a<'e Costs Co#t# ri#e /irectl 'ith the #i"e an/ #cope of the project
9/=e# Costs Co#t# /o not changeG non=rec!rring &e%g% project #et!p co#t#)
D/rect Costs 0nc!rre/ /irectl ( a #pecific project% The P.0 'ant the team to participate in the co#t
e#timate# to get their (!=in%
*#/rect Costs Part of the overall organi"ationW# co#t of /oing (!#ine## an/ are #hare/ ( all project#% <#!all
comp!te/ a# a percentage of the /irect co#t#%
Cost acco1ts 6epre#ent the (a#ic level at 'hich project performance i# mea#!re/ an/ reporte/% The p!rpo#e
of co#t acco!nt# i# to monitor an/ report on project performance%
Cost C2a!e Cotro'
S$ste"s
0ncl!/e# the /oc!mentation3 trac,ing ##tem#3 an/ approval level# nee/e/ to a!thori"e a
change%
B1#!et 10#ates Sho!l/ (e the ne1t #tep# after an approve/ co#t (a#eline ha# change/ (eca!#e of a major change
on a project%
O0erat/! 0ro%/t Amo!nt of mone earne/K 6even!e E &/irect I in/irect co#t#)
D/sco1te# cas2?%'o&
a00roac2
Pre#ent val!e metho/ /etermine# the net pre#ent val!e of all ca#h flo' ( /i#co!nting it ( the
re5!ire/ rate of ret!rn%
Para"etr/c "o#e'/! 0nvolve# !#ing project characteri#tic# &parameter#) in a mathematical mo/el to pre/ict project
co#t#%
L/%e?C$c'e Cost Provi/e a pict!re of the total co#t for the pro/!ct &project3 operation# an/ maintenance)%
Project C'oseo1t &o!tp!t to co#t control) Proce## an/ proce/!re# /evelope/ for the clo#ing or canceling of
project#
Page 21 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
9or"1'as
E=0ecte# 4a'1e
Preset 4a'1e
Pro(a(ilit C 0mpact
F8 J &$ I r)
t
Cost 4ar/ace
C4
E8 R BAC C &'or, complete/Jtotal 'or, re5!ire/)
E8 E AC PBC+P E AC+PQ 8ariance C p"anned actua"
Sc2e#1'e 4ar/ace
S4
P8 R BAC C&Total time pa##e/ Jtotal #che/!le time)
E8 E P8 PBC+P E BC+SQ &if X>G 'or, complete/ i# le## than 'hat 'a# planne/)
Cost Per%or"ace *#e=
(CP*(
E8JAC PBC+P J AC+PQ I am getting DDDD out o each do""ar. (E1 goodF G1 :ad)
Sc2e#1'e Per%or"ace
*#e= (SP*(
E8JP8 PBC+P J BC+SQ I am progre&&ing at DDDDH o the rate origina""! p"anned
Est/"ate at Co"0'et/o
(EAC(
BAC J CP0
ACIETC &'hen original e#timate# are con#i/ere/ fla'e/)
ACIBAC=E8 &'hen everthing i# OD an/ variance 'ill not occ!r in the f!t!re)
ACI&&BAC=E8)JCP0) &'hen everthing i# OD an/ variance 'ill occ!r in the f!t!re)
Est/"ate to Co"0'et/o
(ETC(
EAC = AC or &BAC = E8) J CP0
4ar/ace at Co"0'et/o
(4AR(
BAC E EAC
H S0et ACJBAC
Cost 4ar/ace / H C8JE8
Sc2e#1'e 4ar/ace / H S8JP8
To Co"0'ete Per%or"ace
*#e= (TCP*(
&BAC=E8)J&BAC E AC)
BCWS (P4( @o' m!ch #ho!l/ (e /oneY Thi# i# the perormance mea&urement :a&e"ine%
BCWP (E4( @o' m!ch 'or, i# /oneY &Progre##) B!/gete/ co#t of 'or, performe/% 8al!e of the 'or,
complete/ in term# of 'hat o! (!/gete/ &o!r (a#eline)
ACWP (AC( @o' m!ch /i/ the Fi# /oneH 'or, co#tY
BAC B!/get at Completion E @o' m!ch i# (!/gete/ for the total jo(Y BAC 'o!l/ change ever
time there i# a f!n/e/ #cope change approve/ for activit to (e performe/ in the f!t!re%
EAC Ba#e/ on project performance an/ ri#, 5!antification
ETC E#timate to Completion
CP* C!m!lative CP0 /oe# not change ( more than $>O once a project i# appro1imatel *>O
complete% The CP0 provi/e# a 5!ic, #tati#tical foreca#t of final project co#t#%
E4IP4 JBCWPIBCWSK E8 e5!al# P8 'hen the project i# complete/%
AD +or, ?!antit&#cope of the activit) J Pro/!ction rate
S'o0e &cra#h co#t = normal co#t) J &cra#h time = normal time) G if X>3 a# the time re5!ire/ for a
projectJta#, /ecrea#e3 the co#t increa#e
Doc1"etat/o
Cost Maa!e"et P'a E &from Co#t E#timating) The action ta,en ( the project manager for all variance# are /e#cri(e/ in
the Co#t .anagement Plan%
Cost Ca'c1'at/os = Co#t# are more practical to calc!late at one level higher &Control Acco!nt) than 'or, pac,age level
Page 22 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter L 8 ,-AL*T5 Maa!e"et
Lo& !ra#e &a limite/ n!m(er of feat!re#) = 'o& 31a'/t$ &man (!g#)
Prec/s/o E Con#i#tenc that the val!e of repeate/ mea#!rement# have little #catter% Preci#e mea#!rement# ma not (e
acc!rate%
Acc1rate E 0t correctne## of mea#!re/ val!e3 acc!rate mea#!rement# ma not (e preci#e%
,1a'/t$ = 0# planne/3 /e#igne/ an/ (!ilt in3 not in#pecte/ in%
2o#eph 2!ran E ?!alit = Fitne## of <#e
E/'ar/ Deming E ?!alit 0mprovement E Plan3 Do3 Chec, an/ Act
Philip Cro#( E ?!alit E Conformance to re5!irement#3 A/vocate/ Prevention over in#pection an/ FZero Effect#H%
,1a'/t$ Maa!e"et 8Complement# Project .anagement% Both recogni"e the importance of C!#tomer #ati#faction3
prevention over in#pection#3 .anagement 6e#pon#i(ilit an/ Contin!o!# improvement%
Cost o% 31a'/t$ ? All 'or, to en#!re conformance to re5!irement# I nonconformance to re5!irement#%
Mar!/a' Aa'$s/s E Optimal ?!alit i# reache/ at the point 'here the increa#e/ reven!e from improvement e5!al
incremental co#t to #ec!re it%
,1a'/t$ Maa!e"et P'a E Provi/e# inp!t to the overall project management plan an/ m!#t a//re## ?!alit Control3
?!alit A##!rance an/ contin!e# proce## improvement for the project% Peer revie' ma not incl!/e in/ivi/!al# that 'or,e/
on the material (eing revie'e/%
Go'# P'at/! E Aiving C!#tomer# e1tra#3 it i# not recommen/e/%
,1a'/t$ Matr/= E Define# 'hat #omething i# an/ ho' to mea#!re it%
Process /"0ro;e"et P'a E S!(#i/iar of P.P3 it /etail# the #tep# for anal"ing proce##e# that 'ill facilitate the
i/entification of 'a#te an/ non val!e a//e/ activit3 it incl!/e#
$% Proce## (o!n/arie# *%Proce## config!ration -%Proce## matri1 4%Target# for improve/ performance%
,1a'/t$ Cotro' Meas1re"ets E 6e#!lt# of ?C activitie# that are fe/ (ac, to ?A to reeval!ate an/ anal"e the 5!alit
#tan/ar/# an/ proce##e# for performing organi"ation%
Process Aa'$s/s E TT of ?A3 it follo'# #tep# o!tline/ in Proce## improvement plan3 it incl!/e# root ca!#e anal#i#%
Se;e Bas/c Too's o% ,1a'/t$ E $%Ca!#e an/ Effect Diagram *%Control Chart# -%Flo'charting 4%@i#togram 7%Pareto Chart
6%6!n Chart 9%Scatter Diagram
Des/! o% e=0er/"ets = i# a #tati#tical metho/ that help# i/entif 'hich factor# might infl!ence #pecific varia(le#
O0erat/oa' #e%//t/os are al#o calle/ metric&
Pre;et/o &,eeping error# o!t of the proce##) an/ /s0ect/o &,eeping error# o!t of the han/# of the c!#tomer)%
To'eraces = &the re#!lt i# accepta(le if it fall# 'ithin the range #pecifie/ ( the tolerance) an/ control limit# &the proce## i# in
control if the re#!lt fall# 'ithin the control limit#)%
*s0ect/os = are vario!#l calle/ re@iew&3 product re@iew&3 audit&3 an/ wa"kthrough&G
The proce## ma (e changed to provi/e improvement#3 (!t it #ho!l/ not (e a/j!#te/ 'hen it i# in control%
Control chart E <L3LL
Pareto D/a!ra" E @i#togram3 or/ere/ fre5 of occ!rrence3 ta,e corrective action B :> pro(J*> ca!#e#
Stat/st/ca' sa"0'/! 7 Stati#tical #ampling involve# choo#ing part of a pop!lation of intere#t for in#pection
Tre# aa'$s/s involve# !#ing mathematical techni5!e# to foreca#t f!t!re o!tcome# (a#e/ on hi#torical re#!lt#%
Page 2% o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Project ,1a'/t$ Maa!e"et E proce##e# re5!ire/ to en#!re that the project 'ill #ati#f the nee/# for 'hich it 'a#
!n/erta,en%
,1a'/t$ i# the conformance to re5!irement#J#pecification# an/ to fitne## of !#e%
,1a'/t$ %1ct/o #e0'o$"et E provi/e (etter pro/!ct /efinition an/ pro/!ct /evelopment% 0t# main feat!re are to capt!re
the c!#tomer4# re5!irement#3 en#!re cro## f!nctional team'or,3 an/ lin, the main pha#e# of pro/!ct /evelopment%
Re&or: E action ta,en to (ring a non=conforming item into compliance% 6e'or, i# a fre5!ent ca!#e of project overr!n#%
,1a'/t$ 4ar/a<'e A 5!alit characteri#tic that i# mea#!ra(le
,1a'/t$ Attr/<1te A 5!alit characteri#tic that i# cla##ifie/ a# either conforming or nonconforming
Bec2"ar:/! Comparing practice# of other project#% Provi/e# a #tan/ar/ to mea#!re performance &time con#!ming)%
&e%g% inve#tigating 5!alit #tan/ar/# that other companie# are !#ing)
Stat/st/ca' Aa'$s/s 0nvolve# /etermining the pro(a(ilit of an occ!rrence
Tre# Aa'$s/s <#e# mathematical techni5!e# to foreca#t f!t!re o!tcome# (a#e/ on hi#torical re#!lt#G !#e/ to mea#!re
technical3 co#t3 an/ #che/!le performance
,1a'/t$ A1#/t Str!ct!re/ revie' of other 5!alit management activitie# performe/ to i/entif le##on# learne/ &!#e/
for proce## improvement) Part of ?!alit A##!rance% Provi/e management confi/ence that the project
'ill #ati#f relevant 5!alit #tan/ar/#%
*s0ect/o Prevent error# from reaching the c!#tomer (efore /eliver to the c!#tomer% Can (e /one thro!gho!t
pro/!ct /evelopment%
Des/! o%
E=0er/"ets
A techni5!e to i/entif 'hich varia(le# have the mo#t infl!ence on overall o!tcome# &part of ?!alit
Planning) &e%g% anal"e the colorJ#i"e com(ination that 'ill contri(!te mo#t to the f!nctionalit of the
ne' pro/!ct)% Can (e applie/ to co#t an/ #che/!le tra/eoff#%
9'o& c2art @elp anal"e ho' pro(lem# occ!r#
Attr/<1te Sa"0'/! .ea#!re# 'hether or not the re&u"t& conform# to #pecification#
4ar/a<'e Sa"0'/! Are characteri#tic o! 'ant to mea#!re &#i"e3 #hape3 'eight3 etcM)% An attri(!te i# 'hat o! are
mea#!ring% The re#!lt i# rate/ on a contin!o!# #cale that mea#!re# the /egree of conformit%
Ass/!a<'e Ca1ses Data point on a control chart that re5!ire# inve#tigation
S0ec/%/cat/o L/"/t Sho'# c!#tomer4# e1pectation# for 5!alit &on a control chart)
Cotro' C2art M@elp ne'l a##igne/ project manager /etermine 'hether the project i# o!t of control &in or/er to
verif 5!alit level)% Can (e !#e/ to monitor project management proce##e# #!ch a# co#car/3 #che/!le
variance3 vol!me an/ fre5!enc of #cope change#3 an/ error# in project /oc!ment#%
Stat/st/ca' Cotro'
C2art
Are !#e/ to monitor proce## variation# overtime% @elp people !n/er#tan/ an/ control their proce##
'or,%
FO1t o% Cotro'> Non=ran/om point# that are #till 'ithin the !pper an/ lo'er control limit
-00er a# Lo&er
Cotro' L/"/t o a
Cotro' C2art
Accepta(le range of variation of a proce##% P*he&e "imit& are &et :a&ed on the compan!I& Aua"it!
&tandard&. *he contro" "imit& are determined rom data o:tained rom the proce&& it&e".J
S0ec/%/cat/o L/"/t Fi1e/ ( the c!#tomer
Pareto D/a!ra" <#e/ to #ho' ho' re#!lt# 'ere generate/3 ( tpe or categor of i/entifie/ ca!#e
*s2/:a&a .a/e pop!lar Pareto Chart3 Ca!#e=an/=Effect Diagram an/ Control Chart
Ta!1c2/ Met2o# 0# !#e/ to e#timate the lo## a##ociate/ 'ith controlling or failing to control proce## varia(ilit% 0f o!
#elect goo/ /e#ign parameter#3 o! can pro/!ce pro/!ct# that are more forgiving an/ tolerant% The
tool help# /etermine the val!e or (rea,=even point of improving a proce## to re/!ce varia(ilit%
*SO MGGG Provi/e# a (a#ic #et of re5!irement# for a 5!alit ##tem3 'itho!t #pecifing the partic!lar# for
implementation%
C2ec:'/sts <#e/ to verif that a #et of re5!ire/ #tep# ha# (een performe/ in 5!alit control proce##
FStat/st/ca''$
*#e0e#et>
Determine if pro(lem# are relate/ (efore planning 'hat to /o a(o!t them
M1t1a''$ E=c'1s/;e 0f t'o event# cannot (oth occ!r in a #ingle trial &Y)
S0ec/a' Ca1se <n!#!al event
Ra#o" Ca1se Normal proce## variation
Page 2( o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Ca1se a# E%%ect
D/a!ra"
(9/s2<oe(
&$) Creative 'a to loo, at act!al ca!#e# an/ potential ca!#e# of a pro(lem
&*) Proce## of con#tr!cting help# #tim!late thin,ing a(o!t an i##!eG help# to organi"e tho!ght#G
generate# /i#c!##ion
&-) <#e/ to e1plore a 'i/e variet of topic#
&4) Al#o ,no'n a# 0#hi,a'a or Fi#h(one /iagram
,1a'/t$ P'a/! 6efer# to potential pro(lem#% Altho!gh it !#!all occ!r /!ring planning pha#e3 it can occ!r /!ring
e1ec!tion if there i# a change%
,1a'/t$ Cotro' 6efer# to #pecific performance of a ta#, &mea#!ring 5!alit an/ comparing re#!lt# to the 5!alit plan)
,1a'/t$ Ass1race 6efer# to overall 5!alit re5!irement# &#tan/ar/#) &e%g% eval!ating o@era"" project performance
reg!larl)
Cost o% ,1a'/t$
Co%or"ace No?Co%or"ace &mo#t acc!rate)
Planning Scrap
Training 6e'or, an/ repair
Proce## Control A//itional .aterial
De#ign an/ proce## vali/ation 6epair# an/ #ervice
Te#t an/ eval!ation Complaint#
?!alit a!/it# Lia(ilit
.aintenance an/ cali(ration Pro/!ct recall#
0n#pection Fiel/ #ervice
Fiel/ te#ting E1pe/iting
*"0act o% Poor ,1a'/t$
0ncrea#e/ co#t
Decrea#e/ pro/!ctivit
0ncrea#e/ ri#, an/
!ncertaint
0ncrea#e/ co#t# in monitoring
Aoal of the co#t of 31a'/t$ 0ro!ra" #ho!l/ (e . ? AH of total val!e%
Co#t of o?31a'/t$ i# e#timate/ to (e 72 ? 2GH of #ale#%
Cost o% ,1a'/t$ 0ncl!/e# Prevention Co#t# &training)3 Apprai#al# Co#t# &in#pectionJte#ting) an/ 0nternal &#crap3
re'or,)JE1ternal &'arrant) Fail!re co#t#
.anagement i# LAH re#pon#i(le for 5!alit% The team mem(er i# u"timate"! re#pon#i(le for 5!alit management% The project
manager i# primari"! re#pon#i(le for 5!alit management%
T'o component# of 0ro#1ct a;a/'a</'/t$ are re"ia:i"it! an/ maintaina:i"it!.
To effectivel !#e stat/st/ca' 31a'/t$ cotro'3 the project team #ho!l/ ,no' the /ifference# (et'een &pecia" cau&e& an/
random cau&e&%
1amp"ing an/ pro:a:i"it! are the mo#t important topic# to !n/er#tan/ in stat/st/ca' 0rocess cotro'%
Top management #ho!l/ /irect cot/1o1s /"0ro;e"et%
,1a'/t$ cotro' "eas1re"et are recor/# of 5!alit control te#ting an/ mea#!rement in a format for compari#on an/
anal#i# &inp!t to 5!alit a##!rance)%
Doc1"etat/o
?!alit .anagement Plan E /e#cri(e# metho/ for implementing 5!alit polic project 5!alit ##tem an/ organi"ational
#tr!ct!re#3 re#pon#i(ilitie#3 proce/!re#3 proce##e# an/ re#o!rce# nee/e/ to implement project 5!alit management%
T,M E Total ?!alit .anagement Philo#oph enco!rage# companie# an/ their emploee# to foc!# on fin/ing 'a# to
contin!o!#l improve 5!alit of their (!#ine## practice# an/ pro/!ct#%
Page 20 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Process Aa'$s/s E Le##on# learne/ in fir#t fe' ca#e# i# !#e/ to improve the proce## on the remaining one#%
Sta#ar# De;/at/o E From - point E#timate# R &P E O)J6
S/= S/!"a E Level of ?!alit% IJ= $ Sigma e5!al to 6:%*6O3 'hich i# percentage of occ!rrence# to fall (et'een the t'o
control limit#%
R1'e o% Se;e E Ba#e/ on @e!ri#tic#3 #even ran/om /ata point# gro!pe/ together in a #erie# 'ith in control limit% 0t
repre#ent# that the are not ran/om an/ #ho!l/ (e inve#tigate/%
Page 22 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter M ? 6-MAN RESO-RCE Maa!e"et
Eter0r/se E;/ro"eta' 9actors E &0JP to @6 Planning)
$% Organi"ational &'hich /epartment#3 their 'or,ing arrangement#3 relation#hip#)
*% Technical &Di#cipline# an/ Specialtie# nee/e/)
-% 0nterper#onal &Formal or informal reporting relation#hip#3 c!lt!re an/ lang!age /ifference# etc)
4% Logi#tical &@o' m!ch /i#tance)
7% Political &0n/ivi/!al goal# an/ agen/a#)
Costra/s 8 Organi"ational Str!ct!re3 Collective (argaining agreement#3 Economic Con/ition#.
Or!a/@at/oa' C2arts 8 @ierarchical3 .atri1 (a#e/ an/ Te1t Oriente/%
RBS 8 6e#o!rce Brea, Do'n Str!ct!re i# an hierarchical chart 'hich #ho'# (rea, /o'n of project ( re#o!rce tpe#% 6BS i#
helpf!l in trac,ing project co#t#3 aligne/ 'ith organi"ation# acco!nting ##tem3 can contain categorie# other than h!man
re#o!rce#%
RAM E 6e#pon#i(ilit a##ignment .atri13 can (e /evelope/ at vario!# level#% RAC* &6e#pon#i(le3 Acco!nta(le3 Con#!lt an/
0nform)
6a'o E%%ect E Ten/enc to rate high or lo' on all the factor# /!e to the impre##ion of a high or lo' rating on #ome #pecific
factor%
Or!a/@at/oa' t2eor$ E Provi/e# information regar/ing the 'a# that people3 team# an/ organi"ational !nit# (ehave%
Ro'es a# Res0os/</'/t/es E &OJP of @6 planning) 6ole3 A!thorit3 6e#pon#i(ilit an/ competenc
Sta%% Maa!e"et P'a E De#cri(e# 'hen an/ ho' h!man re#o!rce re5!irement# 'ill (e met% S.P can (e !p/ate/ (eca!#e
of promotion#3 retirement#3 illne##3 performance i##!e# an/ changing 'or,loa/#% S.P content#K
7. Sta%% ac31/s/t/o 8 internal or e1ternal or contract3 #ame location or /ifferent etc
2. T/"eta<'e E 6e#o!rce hi#togram i# prepare/3 (ar# (eon/ the ma1im!m availa(le ho!r# i/entif nee/ for reso1rce
'e;e'/! strate!$%
.. Re'ease cr/ter/a 8 .orale i# improve/ if tran#ition# are alrea/ planne/%
4. Tra//! Nee#s
A. Reco!/t/o a# re&ar#s
C. Co"0'/ace 8 +ith Aovernment reg!lation#
). Sa%et$
*ter0ersoa' S:/''s 8 Are al#o ,no'n a# #oft #,ill#
Maa!e"et o% Project tea"s E i# complicate/ in .atri1 organi"ation% -0'ae# tra//! ta,e# place a# a re#!lt of
o(#ervation3 conver#ation an/ project performance apprai#al#%
9/;e Sta!es o% Tea" De;e'o0"et E Forming3 Storming3 Norming3 Performing an/ A/jo!rning
K/c:o%% Meet/! E 0n/irect .etho/ to #tart team /evelopment% 0t #ho!l/ an#'er $%+h am 0 hereY *%+ho are o! an/ o!r
e1pectation# of meY -% +hat i# thi# team going to /oY 4%@o' i# the team going to /o thi# 'or,Y 7%@o' /o 0 fit into all thi#Y
Lessos Leare# %ro" Maa!e Project Tea" E
$% Project organi"ation chart#3 po#ition# an/ S.P
*% Aro!n/ r!le#3 conflict management techni5!e# an/ recognition#
-% Proce/!re# for 8irt!al team#3 co=location3 training an/ team (!il/ing
4% Special #,ill# an/ competencie# ( team mem(er# /i#covere/
7% 0##!e# an/ #ol!tion#
Project 61"a Reso1rce Maa!e"et = proce## re5!ire/ to ma,e the mo#t effective !#e of the people involve/ 'ith the
project
Page 27 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Res0os/</'/t$ Ass/!"et Matr/= (RAM( E Sho' 'ho /oe# 'hat &1Rper#on3 Rpha#e)% The mo#t important feat!re of the
6A. i# the participator /evelopment proce## involving all #ta,ehol/er#% Sho' 'ho i# participant3 'ho i# acco!nta(le3
'ho han/le# revie'#3 'ho provi/e# inp!t an/ 'ho m!#t #ign off on #pecific 'or, pac,age# or project pha#e#%
L/ear Res0os/</'/t$ C2art (LRC( E i/entifing re#pon#i(ilit3 a##ignment# ( 'or, pac,age# an/ action re5!ire/% Al#o
referre/ to a# 6A.%
Or!a/@at/oa' Brea:#o& Str1ct1re (ORS( ? A /epiction of the project organi"ation arrange/ #o a# to relate 'or,
pac,age# to organi"ation !nit#%
Reso1rces 6/sto!ra" E often part of Staffing .anagement PlanG #ho'# re#o!rce !#age &eg #taff ho!r#) per time perio/ &eg
',3 mth) of a #pecific jo( f!nction%
Re&ar#s a# Reco!/t/o S$ste"s == to (e effective3 m!#t ma,e the lin, (et'een performance an/ re'ar/ clear3 e1plicit
an/ achieva(le%
T$0es o% Po&er
Legitimate
&Formal)
Derive/ from formal po#ition
Coercive Pre/icate/ on fear
6e'ar/ 0nvolve# po#itive reinforcement an/ a(ilit to a'ar/ #omething of val!e
Project often nee/# their o'n re'ar/# ##tem to affect emploee performance% <#e/ correctl3 (ring the
team4# goal# an/ o(jective# in line 'ith each other an/ 'ith the project%
E1pert @el/ in e#teem (eca!#e of #pecial ,no'le/ge or #,ill &re5!ire# time)
6eferent A(ilit to infl!ence other# thro!gh chari#ma3 per#onalit3 etc%
The (e#t form# of po'er are generall 6e'ar/ an/ E1pert
Co%'/ct Maa!e"et
Avoi/anceJ+ith/ra'al
&0gnoring)
At lea#t one part 'ith/ra'# from conflict% Cool off perio/3 co!l/ (e lo#eJlo#e
6etreating from act!al or potential /i#agreementG /elaing &e%g% F2!#t /oc!ment the pro(lemH)
CompetitionJForcing E1erting one4# vie'pointG a la#t re#ort P'inJlo#eQ &e%g% FCall the c!#tomer an/ /eman/ that
o! receive the approval to/a%H
Compromi#ing Bargaining an/ #earching for #ol!tion#G neither part 'in# (!t each gain #ome #ati#faction
P'in=lo#eJ'in=lo#eQ thi# i# ver rarel a goo/ 'a to re#olve technical i##!e#%
Accommo/ation Oppo#ite of Competition% One part meet# other part nee/ at e1pen#e of hi# o'n% Lo#eJ+in
Colla(orating 0nvolve# incorporating m!ltiple i/ea# an/ vie'point# from people 'ith /ifferent per#pective#
an/ offer# a goo/ opport!nit to learn from other# &goo/ 'hen project i# too important to (e
compromi#e/) +inJ+in Be#t Strateg
NNSmoothing De=empha#i"e /ifference# an/ empha#i"e commonalitie#G frien/l (!t avoi/# #olving root
ca!#e#G /elaing &eg% .anager #a# an i##!e i# vali/ (!t /oe#n4t thin, it 'ill (e a (ig pro(lem
later)
CCPro(lem Solving J
Confrontation
A//re## conflict /irectl in pro(lem #olving mo/e P'inJ'inQ
Sources of
Conflict *N*T*AT*
ON
PLANN*
NG
E+EC-T*O
N &
CONTROL
CLOSE?
O-T
Most
tes/o
Prioritie# $ $ I
A/min Proce/!re# * -
Sche/!le# - * $ $ I
Technical 0##!e# * I
Per#onnel
6e#o!rce#
- - I
Per#onalit
Conflict
*
. ste0s o% 0ro<'e" so';/!O
$% Anal"e the #it!ation J Doc!ment the #it!ation
*% Develop alternative# 'ith the team
Page 23 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
-% Ao to management
Mot/;at/oa' T2eor$O Cotet & Process T2eor/es
ContentK F+hatH energi"e#3 /irect# (ehavior E
$% .a#lo'4# @ierarch of Nee/# Theor &Ph#iological3 Safet3 SocialJBelonging3 E#teem3 Self=Act!ali"ation)
*% @ert"(erg4# .otivatorJ@giene Theorie# &.otivatorK 6e#pon#i(ilit3 Self=Act!ali"ation3 E#teem3 Profe##ional Aro'th3
6ecognitionG @gieneK +or,ing Con/ition#3 Salar3 6elation#hip at +or,3 Social3 Safet3 Ph#iological)
Proce##K F@o'H per#onal factor# infl!ence (ehavior
$% .cAregor4# Theor T an/ Theor V &TK A##!me# people lac, am(ition3 /i#li,e re#pon#i(ilit3 are inherentl #elf=
centere/ an/ are not ver (rightG motivate ( re'ar/ an/ p!ni#hment% VK A##!me# people (ecome la" 'Jo
recognition3 'ill accept re#pon#i(ilit3 can (ecome #elf=motivate/ an/ e1erci#e #elf=controlG motivate ( removing
o(#tacle# an/ provi/ing #elf=/irecte/ environment%)
*% O!chi4# Theor ZJ2apane#e Theor & foc!# on team3 companG !#!all lifetime emploment3 collective
/eci#ionma,ing )
Ot2er Mot/;at/oa' T2eor/esO
Be2a;/or/s" E people (ehavior can (e mo/ifie/ thro!gh manip!lation of re'ar/# an/ p!ni#hment#
E=0ectac$ T2eor$ E .otivation i# e1plaine/ in term# of e1pectation# that people have a(o!t &$) their a(ilit to perform
effectivel on the jo(3 &*) the re'ar/# the might o(tain if the /o perform effectivel an/ &-) the val!e or /egree of
#ati#faction the anticipate from tho#e re'ar/#%
MBO E .ore #!pport to team3 not more po'er &remain to P.)
Lea#ers2/0 T2eor/esO
McGre!or 8 Theor T &emploee lac, am(ition) an/ Theor V &org #tr!ct!re are re#pon#i(le for motivation)
Taea<a1"?Sc2"/#t "o#e' E Contin!!m of lea/er#hip #tle# (et'een the a!tocratic an/ participative #tle#
B'a:e a# Mo1to E ref to managerial gri/ &Concern for People 8# Concern for Pro/!ction)3 'herea# $3$ i# lai##e" faire
mgmnt3 $3; i# Co!ntr Cl!( mgmnt3 ;3$ i# Ta#, oriente/ mgmnt3 737 i# Compromi#e mgmnt an/ ;3; i# team mgmnt%
9or"s o% Or!a/@at/o
F!nctional Aro!p# people ( #peciali"ation% Project manager ha# no formal a!thorit of re#o!rce# an/ m!#t rel on
informal po'er #tr!ct!re an/ hi# o'n interper#onal #,ill# to o(tain re#o!rce commitment# from
f!nctional manager#%
Project E1pe/itor 6etain# f!nctional (!t a//# a Project E1pe/itor 'ho #erve# a# a comm!nication# lin, an/ coor/inator for
the project acro## f!nctional !nit#
Project
Coor/inator
Similar to Project E1pe/itor e1cept the Coor/inator report# to a higher level manager an/ ha# #ome
a!thorit to a##ign 'or,
+ea, .atri1 8ertical f!nctional line# of a!thorit maintaine/ 'ith a relativel permanent hori"ontal #tr!ct!re
containing manager# for vario!# project#% Balance of po'er lean# to'ar/ the F!nctional .anager% Can
ca!#e a project to fall (ehin/ (eca!#e f!nctional manager# are p!lling re#o!rce# a'a to perform non=
project relate/ ta#,#% The Project .anager ma (e a(le to ma,e re#o!rce /eci#ion on hi# o'n (!t not
technical /eci#ion%
Strong .atri1 Same a# +ea, e1cept that the (alance of po'er lean# to'ar/# the Project .anager
Projecti"e/ A #eparate3 vertical #tr!ct!re i# e#ta(li#he/ for each project% All the project team mem(er# report /irectl
an/ #olel to the project manager%
NNMe"or/@e PMBOK FOr!a/@at/oa' Str1ct1re *%'1ece o Projects>
Tea" <1/'#/! i# mo#t /iffic!lt in a matri1 organi"ation% 0t# main p!rpo#e i# to improve team performance%
Tea" #e;e'o0"et i# (a#e/ on the /#/;/#1a' #e;e'o0"et of each mem(er%
Lea#ers2/0
St$'es
A1tocrat/c P. ma,e# /eci#ion 'itho!t #oliciting information from team
Cos1't/;e 0nten#ive information #olicite/G P. ma,e# /eci#ion
Page 2$ o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Coses1s Team ma,e# /eci#ionG open /i#c!##ion an/ information gathering ( team
S2are2o'#er Little or no information e1changeG team ha# !ltimate a!thorit for final /eci#ion
Ro'es o% t2e Project Maa!er 91ct/os o% t2e Project Maa!er
0ntegrator Planning
Comm!nicator Organi"ing
Team Lea/er Lea/ing
Deci#ion .a,er Controlling
Climate CreatorJB!il/er
Doc1"etat/o
Sta%%/! Maa!e"et P'a E /e#cri(e# 'hen re#o!rce# 'ill (e (ro!ght into an/ ta,en off the project%
E"0'o$ee Recor# -0#ate E a# part of clo#!re3 the project manager #ho!l/ !p/ate emploee4# recor/ 'ith the ne' #,ill#
ac5!ire/%
Reso1rce ca'e#ar 8 i/entifie# perio/ 'hen 'or, i# allo'e/%
Per%or"ace A00ra/sa'sEAssess"et E Project .anager 'ill collect information from team mem(er4# #!pervi#or# 'hen
project performance apprai#al# are complete/% Team Performance a##e##ment i# /one ( the P. in or/er to eval!ate an/
improve the effectivene## of team%
Co%'/cts / Or#er o% 9re31ec$ E $% Sche/!le *% Project Prioritie# -% 6e#o!rce# 4% Technical Opinion# 7% A/mini#trative
Proce/!re# 6% Co#t 9% Per#onalit
Ar</trat/o E The hearing an/ re#ol!tion of a /i#p!te performe/ ( a ne!tral part%
Per31/s/tes E Aiving Special re'ar/#
9r/!e Bee%/ts E Stan/ar/ (enefit# given to all emploee#%
Page %' o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter 7G 8 COMM-N*CAT*ONS Maa!e"et
Co""1/cat/os P'a/!N/etermining the information an/ comm!nication# nee/# of the #ta,ehol/er#K 'ho nee/# 'hat
information3 'hen the 'ill nee/ it3 an/ ho' it 'ill (e given to them% 0t i# often tightl lin,e/ 'ith enterpri#e environmental
factor# an/ organi"ational infl!ence#%
Art o% Co""1/cat/os E 0ncl!/e# Sen/er=receiver .o/el#3 Choice of .e/ia3 +riting Stle3 Pre#entation techni5!e# an/
.eeting .anagement Techni5!e#%
Project Co""1/cat/os Maa!e"et = proce## re5!ire/ to en#!re proper collection an/ /i##emination of project
information%
Co""1/cat/os Tec2o'o!$ 8 (TT of Comm!nication planning) factor# that affect the project incl!/e <rgenc of the nee/
for information3 Availa(ilit of technolog3 E1pecte/ Project Staffing3 Length of the Project an/ Project Environment%
CMP 8 Contain# #ta,ehol/er comm!nication re5!irement#3 information format3 content3 /etail level3 per#on re#pon#i(le3
metho/# or technologie#3 fre5!enc of comm!nication3 metho/# for C.P !p/ate#3 e#calation proce## B Alo##ar of common
term#%
Per%or"ace re0ort/! E Aenerall on Scope3 ?!alit3 Sche/!le an/ Co#t% B!t ma incl!/e information on 6i#, an/
Proc!rement%
Tea" Meet/!s E perio/ic team meeting# i# the mo#t effective 'a to accelerate the project integration proce##%
Per%or"ace Re;/e&s E meeting# hel/ to a##e## #tat!# an/Jor progre##%
Co""1/cat/os
Mo#e'
Comm!nicator The originator of the me##age
.e##age Tho!ght#3 feeling#3 or i/ea# re/!ce/ to [co/e[ that i# !n/er#too/ ( (oth #en/er an/ receiver
.e/i!m The vehicle or metho/ !#e/ to conve the me##age
6ecipient The per#on for 'hom the me##age i# inten/e/
PSen/erQ == Enco/ing Tran#mi##ion Deco/ing == P6eceiverQ Fee/(ac,
Co""1/cat/os C2ae's R &n
*
= n)J* or n&n=$)J*
Mthe fact that t'o team mem(er# are 'or,ing F/irectlH together /oe# not re/!ce the n!m(er of comm!nication channel#%
T/!2t Matr/= = all team mem(er# allocate/ in a #ingle office #pace
A @ariance i# con#i/ere/ to (e &igniicant if it jeopar/i"e# project o(jective#%
The p!rpo#e of 0roject 0'a #e;e'o0"et i# to create a /oc!ment to g!i/e project e1ec!tion an/ control%
The o!tp!t of 0roject 0'a e=ec1t/o con#i#t# of 'or, re#!lt# an/ change re5!e#t#%
T$0es o% Co""1/cat/os
Formal +ritten Project Charter3 .anagement Plan &thi# i# the (e#t tpe
of comm!nication metho/ to !#e 'hen there are
c!lt!ral /ifference# an/ /i#tance (et'een team
mem(er#)
0nformal +ritten Note#3 memo#
Formal 8er(al Pre#entation#
0nformal 8er(al Conver#ation#
Page %1 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
)oteK 77O of comm!nication# i# non=ver(al &it i# the mo#t important a#pect of a
conver#ation)
;>O of Project .anagerW# time i# #pent ac5!iring an/ comm!nicating
information
O<ject/;es o% a K/c:o%% Meet/!
Aet to ,no' each other
Set team goal# an/ o(jective#
6evie' project #tat!#
6evie' project plan#
0/entif pro(lem area#
E#ta(li#h re#pon#i(ilitie# an/ acco!nta(ilitie#
O(tain commitment#
Barr/ers to Co""1/cat/os (&2/c2 'ea# to
co%'/ct(
Lac, of clear comm!nication channel#
Ph#ical or temporal /i#tance
Diffic!ltie# 'ith technical lang!age
Di#tracting environmental factor#
Detrimental attit!/e#
The mo#t li,el re#!lt# of comm!nication (loc,er an/ mi#comm!nication a# a 'hole i# conflict%
B1/'#/! E%%ect/;e Tea" Co""1/cat/os
Be an effective comm!nicator
Be a comm!nication# e1pe/itor
Avoi/ comm!nication (loc,er#
<#e a [tight matri1[ &#ingle office #pace)
.a,e meeting# effective &meeting /!ring e1ec!tion i# the (e#t format to
comm!nicate)
Maa!e"et
St$'es
A!thoritarian Let# in/ivi/!al# ,no' 'hat i# e1pecte/ of them
Com(ative Eager to fight or (e /i#agreea(le over an #it!ation
Conciliator Frien/l an/ agreea(le
Di#r!ptive Ten/# to /i#r!pt !nit an/ ca!#e /i#or/er
Ethical @one#t an/ #incere
Facilitating Doe# not interfere 'ith /a=to=/a ta#,#3 (!t i# availa(le for help an/ g!i/ance 'hen nee/e/
0ntimi/ating 6epriman/# emploee# for the #a,e of a [to!gh g![ image
2!/icial Applie# #o!n/ j!/gment
Promotional C!ltivate# team #piritG re'ar/# goo/ 'or,G enco!rage# #!(or/inate# to reali"e their f!ll potential
Secretive Not open or o!tgoing in #peech3 activit3 or p!rpo#e
Maa!e"et S:/''s
Lea/ing E#ta(li#hing /irection3 aligning people3 an/ motivating an/ in#piring
Comm!nicating The e1change of information in a variet of /imen#ion#
Negotiating Conferring 'ith other# in or/er to come to term# or reach an agreement
Pro(lem Solving A com(ination of pro(lem /efinition an/ /eci#ion ma,ing
Page %2 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
0nfl!encing the
Organi"ation
The a(ilit to get thing# /one (a#e/ on an !n/er#tan/ing or the formal an/ informal #tr!ct!re# of
the organi"ation
Doc1"etat/o
Mthe prevailing mea#!rement of 'hat information to acc!m!late an/ comm!nicate on a project i# that it contri(!te# to it#
#!cce##%
Pro!ress Re0ort = #!mmari"e project #tat!#% Preferre/ report to 5!ic,l revie' 'here a project no' #tan/#%
Tre# Re0ort E #ho' performance over time &#ho'# if it i# improving or /eteriorating)
4ar/ace Re0ort E compare project re#!lt#3 loo,# at #pecific project item# or ta#,#
9orecast/! Re0ort E onl loo,# into the f!t!re
Stat1s Re0ort E relating a moment in time &#tatic)
Project P'a
Sta%%/! Maa!e"et P'a
Co""1/cat/os Maa!e"et P'a = #ho!l/ cover all pha#e# of the project
Per%or"ace re0orts 8 provi/e info on #che/!le performance3 there( alerting the team to pro(lem# that ma ari#e in
the f!t!re%
Lessos Leare# E One #ho!l/ not 'ait till the Project i# over3 the might (e #ent o!t a# the are create/% LL are create/ (
Sta,e @ol/er#3 P. Team3 P.3 Seller# an/ C!#tomer#
WBS E Can (e effective tool for comm!nicating in a #it!ation internal an/ e1ternal to the project%
Co""1/cat/o / Cotract E Everthing 'e /o i# more formal in contract environment%
Page %% o 46 La&t 5pdated
1';2;12
6eport# are a metho/ to
/i#tri(!te information3 not
j!#t to report on progre##
PMI Exam Study Notes Sajid Jambagi
C2a0ter 77 8 R*SK Maa!e"et
Project r/s: = 0# an !ncertain event or con/ition that3 if it occ!r#3 ha# a po#itive or a negative effect on a project o(jective%
A ri#, ha# a ca!#e an/3 if it occ!r#3 a con#e5!ence% 6i#, i/entification i# an iterative proce##% &2!#t li,e core proce##)
R/s: T$0es 8 $% B!#ine## &Aain or Lo##) *% P!re 6i#, &Onl 6i#, of Lo##)
P'a/! "eet/!s 7 Atten/ee# = project manager3 the project team lea/er#3 anone in the organi"ation 'ith re#pon#i(ilit to
manage the ri#, planning an/ e1ec!tion activitie#3 ,e #ta,ehol/er#3
,1a'/tat/;e R/s: Aa'$s/s E Prioriti"ing ri#,# for #!(#e5!ent f!rther anal#i# or action ( a##e##ing an/ com(ining their
pro(a(ilit of occ!rrence an/ impact.
,1at/tat/;e R/s: Aa'$s/s 8 N!mericall anal"ing the effect on overall project o(jective# of i/entifie/ ri#,#%
Att/t1#e a<o1t R/s: E Sho!l/ (e ma/e e1plicit3 Comm!nication a(o!t ri#, #ho!l/ (e hone#t an/ open% 6i#, re#pon#e reflect#
organi"ation# perceive/ (alance (et'een ri#, ta,ing an/ ri#, avoi/ance% Some one 'ho /oe# not 'ant to ta,e ri#,# i# #ai/ to
(e 6i#, Aver#e%
To'erace a# T2res2o'# E Tolerance are area# of ri#, that are accepta(le or !naccepta(le% A thre#hol/ i# the amo!nt of ri#,
that i# accepta(le%
R/s: Maa!e"et P'a E De#cri(e# ho' 6i#, .anagement 'ill (e #tr!ct!re/ an/ performe/3 it incl!/e#
$% Met2o#o'o!$ &Approach3 tool# an/ /ata #o!rce#)
*% B1#!et/! &6e#o!rce an/ Co#t E#timate)
-% T/"/! &+hen an/ ho' often)
4% R/s: Cate!or/es &6BS3 Aoo/ practice i# to revie' ri#, categorie# /!ring 6.P prior to 6i#, 0/entification Proce##)
7% De%//t/o o% R/s: Pro<a</'/t$ a# *"0act &<#e/ for ?!alitative 6i#, Anal#i#3 ?!alit B cre/i(ilit important)
6% Pro<a</'/t$ a# *"0act Matr/= &Loo, !p ta(le3 'ith impact categori"e/ a# Lo'3 .o/erate or @igh)
). Re;/se# Sta:e2o'#ers to'eraces
:% Re0ort/! 9or"ats &De#cri(e# 6i#, 6egi#ter Content# an/ format)
;% Trac:/! &A!/iting an/ Doc!mentation for LL)
*%or"at/o Gat2er/! Tec2/31es &0JP for 6i#, 0/entification) E $%Brain#torming *%De'02/ Tec2/31e -%0ntervie'ing
4%6oot ca!#e anal#i# 4%SWOT aa'$s/s
C2ec: L/st Aa'$s/s &0JP for 6i#, 0/entification) E Can (e (a#e/ on @i#torical information of previo!# #imilar project#3 the
lo'e#t level of 6BS can al#o (e !#e/ a# 6i#, Chec,li#t%
,1at/tat/;e R/s: Aa'$s/s
7. Data Gat2er/! a# Re0resetat/o Tec2/31e
$% 0ntervie'ing *%Pro(a(ilit Di#tri(!tion# &Beta D/str/<1t/o an/ Tr/a!1'ar D/str/<1t/o)
2. ,1at/tat/;e R/s: Aa'$s/s a# Mo#e'/! Tec2/31es
Sen#itivit Anal#i# E Determine 'hich ri#,# have mo#t potential impact3 Tora#o Diagram%
E1pecte/ .onetar 8al!e E Opport!nit e1pre##e/ a# Po#itive3 6i#, e1pre##e/ a# negative% .o/eling an/
Sim!lation i# recommen/e/ for Co#t B Sche/!le 6i#, anal#i# (eca!#e the are more po'erf!l an/ le##
#!(ject to mi#!#e than E.8 anal#i#%
Deci#ion tree anal#i# E Sho'# availa(le choice# an/ their po##i(ilitie#
.o/eling an/ Sim!lation E Done !#ing Mote Car'o Tec2/31e% Cost R/s: Aa'$s/s !#e CBS or +BS%
Sc2e#1'e R/s: aa'$s/s !#e PD.%
Strate!$ %or Pos/t/;e R/s: or O00ort1/t/es = SEE E Share3 E1ploit3 Enhance
Strate!$ %or Ne!at/;e R/s: or T2reats E AT. E Avoi/3 Tran#fer3 .itigate
Strate!$ %or Bot2 = Acceptance
Res/#1a' R/s:s E 6i#,# that are e1pecte/ to remain after planne/ re#pon#e# have (een ta,en3 a# 'ell a# tho#e have (een
/eli(eratel accepte/%
Seco#ar$ R/s:s E 6i#,# that ari#e a# a /irect o!tcome of implementing a ri#, re#pon#e%
Page %( o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Reco""e#e# Correct/;e Act/os E For 6i#, monitor an/ Control incl!/e Contingenc plan# an/ 'or,aro!n/ plan#% +or,
aro!n/ plan# are not initiall planne/ (!t are re5!ire/ to /eal 'ith emerging ri#,# that 'ere previo!#l !ni/entifie/ or
accepte/%
R/s: #ata<ase 7 A repo#itor that provi/e# for collection3 maintenance3 an/ anal#i# of /ata gathere/ an/ !#e/ in the ri#,
management proce##e#% <#e of thi# /ata(a#e 'ill a##i#t ri#, management thro!gho!t the organi"ation an/3 over time3 form the
(a#i# of a ri#, le##on# learne/ program%
R/s: Re!/ster E &OJP of 6i#, 0/entification)
$% Li#t of 0/entifie/ 6i#,# &incl!/ing root ca!#e# an/ a##!mption#)
*% Li#t of Potential 6e#pon#e#
-% 6oot ca!#e# of 6i#,#
4% <p/ate/ 6i#, Categorie# &6BS 'hich i# /evelope/ in 6.P i# enhance/ or amen/e/)
-0#ates a%ter ,1a'/tat/;e R/s: Aa'$s/s
7% 6elative 6an,ing or Priorit li#t of Project 6i#,#
6% 6i#,# gro!pe/ ( categorie#
9% Li#t of 6i#, re5!iring 6e#pon#e in the near term
:% +atch li#t of lo' priorit ri#,#
;% Tren/# in 6elative 6i#, anal#i# re#!lt#
-0#ates a%ter ,1at/tat/;e R/s: Aa'$s/s
$>% Pro(a(ili#tic Anal#i# of the project
$$% Pro(a(ilit of Achieving Co#t an/ Time O(jective
$*% Prioriti"e/ Li#t of ?!antifie/ 6i#,#
$-% Tren/# in ?!antitative 6i#, Anal#i# 6e#!lt#
-0#ates a%ter R/s: Res0ose P'a/!
$4% 0/entifie/ 6i#,#3 their /e#cription#3 area# of the project an/ ho' the affect project o(jective#
$7% 6i#, o'ner# an/ their re#pon#i(ilitie#
$6% Agree/ !pon re#pon#e #trategie#
$9% Smptom# an/ 'arning #ign# of ri#,# occ!rrence
$:% B!/get an/ Sche/!le activitie# re5!ire/ to implement the cho#en re#pon#e#
$;% Contingenc re#erve# of Time an/ Co#t% Contingenc Trigger#%
*>% Fall(ac, plan
*$% 6e#i/!al an/ Secon/ar 6i#,#
Project R/s: Maa!e"et E proce##e# concerne/ 'ith i/entifing3 anal"ing3 an/ re#pon/ing to !ncertaint% The mo#t li,el
ca!#e of poor ri#, management i# lac, of prioriti"e/ li#t of ri#,#%
T$0es o% R/s:
B1s/ess Normal ri#,# that offer gain an/ lo##
P1re E *s1ra<'e Onl lo##K propert /amage3 in/irect con#e5!ential lo##3 legal lia(ilit3 per#onnel% For ri#, 'e can
o!t#o!rce3 'e have contract% For p!re ri#,#3 'e o(tain in#!rance%
R/s: 9actors
6i#, event
6i#, pro(a(ilit
Amo!nt at Sta,e
Stat/st/ca' *#e0e#ece
Data Prec/s/o Ra:/!
Seco#ar$ R/s:
Occ!rrence of one event i# not relate/ to occ!rrence of the other
P!rpo#e i# to te#t the val!e of /ata &inp!t to ?!alitative Anal#i#)
&part of 6i#, 6e#pon#e Planning)
Pat2 Co;er!ece Ten/enc of parallel path# of e5!al /!ration to /ela the completion of the mile#tone 'here the
meet
Cot/!ec$ P'a Planne/ action #tep# to (e ta,en if an i/entifie/ ri#, occ!r#% &e%g% /eveloping alternative activit
Page %0 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
-certa/t$ #e5!ence#)
An !ncommon #tate of nat!re3 characteri"e/ ( the a(#ence of an information relate/ to a /e#ire/
o!tcome%
Wor:aro1# <nplanne/ re#pon#e to negative ri#, event# &re5!ire# to (e impacte/ ( the ri#, fir#t)
E=0ecte# Moetar$ 4a'1e R Pro(a(ilit C .onetar 0mpact &!#e/ in Deci#ion Tree Anal#i#)
R/s: E;et A /i#crete occ!rrence that ma affect the project for (etter or 'or#e% After a ri#, event3 the project
manager4# role i# to rea##e## the ri#, ran,ing% The ri#, o'ner i# re#pon#i(le to ta,e action 'hen an
i/entifie/ ri#, occ!r#%
R/s: Tr/!!er A #mptom of ri#,G in/irect manife#tation of act!al ri#, eventG o!tp!t of ri#, i/entificationG
e1ample i# poor morale
R/s: Port%o'/o 6i#, /ata a##em(le/ for the management of the project
-t/'/t$ T2eor$ Techni5!e that characteri"e# an in/ivi/!al4# 'illingne## to ta,e ri#,
Ses/t/;/t$ Aa'$s/s
R/s: A1#/tor
R/s: To'erace
Place# a val!e on the impact to the project plan ( a/j!#ting a #ingle project varia(leG #imple#t
form of anal#i#
6ole i# to inve#tigate the effectivene## of the ri#, o'ner &'hich can ca!#e potential conflict 'ith
ri#, o'ner)
6i#, Ta,er3 6i#, A/ver#e3 6i#, Ne!tralG if o! ,no' the tolerance of the #ta,ehol/er#3 o! can
/etermine ho' the might react to /ifferent #it!ation an/ ri#, event#% Vo! !#e thi# information to
help a##ign level# of ri#, on each 'or, pac,age%
Res0oses to R/s:
A;o/#ace
(e'/"/at/oEa<ate"e
t(
Eliminating ca!#e eliminate# ri#,% Can (e /one ( changing the Project Plan or protecting project
o(jective# from it# impact%
M/t/!at/o
(re#1ct/o(
6e/!ce the E1pecte/ .onetar 8al!e% Float can (e !#e to mitigate potential ri#,#
Tras%er Deflect or #hare &eg% 0n#!rance3 'arrantie#)
Acce0tace Accept or retain con#e5!ence#% * tpe#K .cti@e Acceptance &/evelop a contingenc plan) or Pa&&i@e
Acceptance &no action)%
N1"<ers to Ko&
Cost Est/"atesO
Or/er of .agnit!/e
&(allpar, e#timate)
=*7O I97O
B!/get =$>O I*7O
Definitive =7O I$>O
$ #igma 6:%-O
* #igma ;7%7O
- #igma ;;%9O
6 #igma ;;%;;O
The range of an e#timate 'ith the #malle#t range i# the lea#t ri#,%
Doc1"etat/o
R/s: Maa!e"et P'a 8 'o!l/ mo#t li,el (e /evelope/ /!ring #cope planning pha#e of the #cope management proce##%
Dec/s/o Tree Aa'$s/s = $% Ta,e# into acco!nt f!t!re event# in tring to ma,e /eci#ion to/a
*% 0t calc!late# E.8 in more comple1 #it!ation# -% 0nvolve# m!t!al e1cl!#ivit
9a'' <ac: P'a E Specific action# that 'ill (e ta,en if the contingenc plan i# not effective%
Page %2 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter 72 8 PROC-REMENT Maa!e"et
Project Maa!e"et Tea" E 0# re#pon#i(le to help tailor the contract to the #pecific nee/# of the Project%
Proc1re"et Processes Re0et/t/o = +hen the project o(tain# pro/!ct# an/ #ervice# &project #cope) from o!t#i/e the
performing organi"ation3 the proce##e# from #olicitation planning &Section $*%*) thro!gh contract clo#eo!t &Section $*%6)
'o!l/ (e performe/ once for each pro/!ct or #ervice item%
Costs = Direct co#t# are co#t# inc!rre/ for the e1cl!#ive (enefit of the project &e%g%3 #alarie# of f!ll=time project #taff)% 0n/irect
co#t#3 al#o calle/ overhea/ co#t#3 are co#t# allocate/ to the project ( the performing organi"ation a# a co#t of /oing
(!#ine## &e%g%3 #alarie# of corporate e1ec!tive#)%
Proc1re"et Doc1"ets 8 Common name# for /ifferent tpe# of proc!rement /oc!ment# incl!/eK 0nvitation for Bi/ &0FB)3
6e5!e#t for Propo#al &6FP)3 6e5!e#t for ?!otation &6F?)3 ten/er notice3 0nvitation for Negotiation3 an/ Contractor 0nitial
6e#pon#e% Proc!rement /oc!ment# are rigoro!# eno!gh to en#!re con#i#tent3 compara(le re#pon#e# (!t fle1i(le eno!gh to
allo' #eller #!gge#tion# for (etter 'a# to #ati#f the re5!irement#% Seller i# allo'e/ to propo#e alternative #ol!tion in a
#eparate propo#al%
0t ha# $% 0nformation for #eller# *% Contract SO+ -% Propo#e/ term# an/ con/ition# of the contract &Legal B B!#ine##)
Pro0osa' = technical approach3 B/#B Te#er a# 31otat/o E price
Proc1re"et Maa!e"et P'a E De#cri(e# ho' proc!rement 'ill (e manage/ till contract clo#!re% 0t incl!/e# Tpe Of
contract3 'ho prepare# in/epen/ent e#timate#3 #tan/ar/i"e/ proc!rement /oc!ment#3 Con#traint# an/ a##!mption#3
i/entifing #eller li#t etc%
Cotract SOW E Develope/ from Scope Statement3 +BS an/ +BS Dictionar /e#cri(e# proc!rement item in #!fficient
/etail to allo' pro#pective #eller# to /etermine if the are capa(le of provi/ing it%
Cotract SOW T$0es E $% Performance *% F!nctional -% De#ign
0T3 @igh=tech3 6 B D or Project# never /one (efore E Performance B F!nctional
Con#tr!ction3 E5!ipment or P!rcha#e = De#ign
B/##er Co%ereces E Al#o calle/3 a# Contactor Conference#3 8en/or Conference# an/ Pre=Bi/ Conference# are meeting#
'ith pro#pective #eller# prior to preparation of (i/ or propo#al3 en#!re# clear an/ common !n/er#tan/ing of proc!rement
nee/#%
Proc1re"et Doc1"et Pac:a!e E B!er prepare/ formal re5!e#t #ent to each #eller an/ i# the (a#i# !pon 'hich a #eller
prepare# a (i/ for the re5!e#te/ pro/!ct#3 #ervice or re#!lt%
Proc1re"et Doc1"ets
$% 6e5!e#t For Propo#alJTen/er &6FP3 6FT ) E 6e5!e#t# for Price an/ Detaile/ Propo#al
*% 0nvitation for Bi/J6e5!e#t for Bi/ &0FB3 6FB) E One Price
-% 6e5!e#t for ?!otation E Price ?!ote per item
Cotract E S!(ject# covere/ incl!/e 6e#pon#i(ilitie#3 a!thoritie#3 la' an/ term#3 technical an/ management approache#3
financing3 #che/!le3 pament# an/ price% Contract negotiation# concl!/e 'ith a /oc!ment that can (e #igne/ ( (oth (!er
an/ #eller3 that i# contract% The final contract can (e a revi#e/ offer ( the #eller or co!nter offer ( the (!er%
Se'ect Se''ers 8 Too's & Tec2/31es
7. We/!2t/! S$ste" 8 N!meric +eight to each criteria3 rating #eller#3 #election (a#e/ on total 'eight
2. *#e0e#et Est/"ates 8 calle/ FSho!l/=Co#tH 3 prepare/ ( proc!ring organi"ation%
.. Scree/! S$ste" 8 E#ta(li#h minim!m performance re5!irement for one or more criteria an/ !#e $ B * metho/#
4. Cotract Ne!ot/at/o 8 Project .anager ma not (e the lea/ negotiator3 P. team ma (e pre#ent /!ring
negotiation# for provi/ing an clarification of project4# technical an/ management re5!irement#%
A. Se''er Rat/! S$ste"s
C. E=0ert J1#!"et
). Pro0osa' E;a'1at/os tec2/31es 8 <#e #ome E1pert j!/gment an/ eval!ation criteria to rate an/ #core propo#al#%
Page %7 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Cotract Maa!e"et P'a E Li#t# /oc!mentation3 /eliver an/ performance re5!irement# that the (!er an/ #eller m!#t
meet% The plan cover# the contract a/mini#tration activitie# thro!gho!t the life of the contract% Part of P.P%
Cotract A#"//strat/o E En#!re# the #eller meet# the performance re5!irement# of the contract% Beca!#e of legal
con#i/eration# man organi"ation# treat contract a/mini#tration a# a #eparate a/mini#trative f!nction from the project
organi"ation% Contract a/mini#tration incl!/e# application of the appropriate project management proce##e# to the contract!al
relation#hip#&#) an/ integration of the o!tp!t# from the#e proce##e# into overall management of the project%
Pa$"et S$ste" E <#!all han/le/ ( acco!nt# paa(le ##tem of the (!er% 0t incl!/e# revie'# B approval# ( P. team%
C'a/"s A#"//strat/o E Conte#te/ Charge# &claim#3 Di#p!te# or appeal#) are tho#e 'here (!er an/ #eller cannot agree% 0f
(oth partie# /o not re#olve a claim it i# han/le/ accor/ing to the re#ol!tion proce/!re# e#ta(li#he/ in the contract% Contract
cla!#e# can involve ar(itration or litigation an/ can (e invo,e/ prior or after contract clo#!re%
Recor#s Maa!e"et S$ste" E Set of proce/!re# an/ a!tomation tool# that are con#oli/ate/ a# part of P.0S to manage
contract /oc!mentation an/ recor/#%
Or!a/@at/o Process Assets &After Contract A/mini#tration) E
$% Corre#pon/ence E 0n a//ition to /oc!mentation3 it i# a recor/ of all the 'ritten an/ oral comm!nication%
*% Pament Sche/!le# an/ 6e5!e#t#
-% Seller Performance eval!ation /oc!mentation
PMP 10#ates E Proc!rement .anagement Plan an/ Contract .anagement Plan%
Proc1re"et A1#/t E 6evie' of proc!rement proce##e# from Plan p!rcha#e# to Contract a/mini#tration% Aim# to i/entif
#!cce##e# an/ fail!re#%
a contract3 an agreement3a &u:contract3 a purcha&e order3 or a memorandum o under&tanding%
B1$er(G/;e Or#er (????PO???????????? Se''er
Se''er ????*;o/ce?????? B1$er (Pa$ or#er(
Contract a/mini#tration al#o ha# a financial management component% Pament term# #ho!l/ (e /efine/ 'ithin the contract
an/ m!#t involve a #pecific lin,age (et'een #eller progre## ma/e an/ #eller compen#ation pai/%
Contract clo#eo!t i# #imilar to a/mini#trative clo#!re &/e#cri(e/ in Section $>%4) in that it involve# (oth pro/!ct verification
&+a# all 'or, complete/ correctl an/ #ati#factorilY)
A/mini#trative clo#eo!t &!p/ating of recor/# to reflect final re#!lt# an/ archiving of #!ch information for f!t!re !#e)%
Contract i"e. A complete #et of in/e1e/ recor/# #ho!l/ (e prepare/ for incl!#ion 'ith the final project recor/#
+hen P62# involve #ignificant proc!rement3 partic!lar attention m!#t (e pai/ to archiving of financial recor/#%
7G.4 A#"//strat/;e C'os1re (*tera'(D!eerat/!B !at2er/!B a# #/sse"/at/! /%or"at/o
to %or"a'/@e a 02ase or 0roject co"0'et/o.
Cotract C'oseo1tDco"0'et/o a# sett'e"et o% t2e cotractB /c'1#/! reso'1t/o o% a$ o0e /te"s.
&E1ternal )
Common format# for performance report# incl!/e (ar chart# &al#o calle/ Aantt chart#)3 S=c!rve#3 hi#togram#3 an/ ta(le#%
Project Proc1re"et Maa!e"et = the proce##e# re5!ire/ to ac5!ire goo/# an/ #ervice# from o!t#i/e the performing
organi"ation%
Ma:e or B1$ Dec/s/o E it i# generall (etter to /o the 'or, o!r#elf if !#ing an o!t#i/e compan mean# o! have to t!rn
over highl confi/ential proprietar /ata to other compan%
Cotract T$0es a# R/s: 7. 9/=e# Pr/ce 2. Cost?Re/"<1rsa<'e ..T/"e & Mater/a'
Cost P'1s Perceta!e o%
Cost (CPPC(
No vali/ for fe/eral contract#
Cost P'1s 9/=e# 9ee
(CP99(
<#e/ for re#earch an/ /evelopment contract# &'hich generall have lo' level of /etail in the
#cope)G fi1e/ fee can change if there i# a change to the contract &!#!all thro!gh change
or/er#)% The ri#, re#t# 'ith the (!er% Thi# i# the mo#t common co#t reim(!r#a(le contract%
Cost P'1s *cet/;e 9ee B!er an/ #eller #hare in #aving# (a#e/ on pre/etermine/ O#G long performance perio/# an/
Page %3 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
CP*9( #!(#tantial /evelopment an/ te#t re5!irement# &incentive to the ven/or to perform on or
ahea/ of time)
In Co&t p"u& contractL the on"! irm igure i& the ee
9/=e# Pr/ce P'1s *cet/;e
9ee (9P*(
@igh=val!e project# involving long performance perio/#
9/r" 9/=e# Pr/ce (99P( 6ea#ona(l /efinite #pecification# &e%g% SO+)% Shift ri#, to #eller% Aoo/ 'hen /elivera(le i#
not a core competenc% Fi1e/ Price &FP) i# the mo#t common tpe of contract in the 'orl/%
T/"e & Mater/a' (T&M( Aoo/ if the (!er 'ant# to (e in f!ll control an/Jor the #cope i# !nclearJnot /etaile/ or 'or,
ha# to #tart 5!ic,l% Profit factor into the ho!rl rate%
9/=e# Pr/ce A&ar# 9ee F(on!#H to the #eller (a#e/ on performance &e%g% $>>D I $>D for ever /e#ignate/
incremental 5!alit level reache/%
9/=e# Pr/ce Ecoo"/c Pr/ce
A#j1st"et (9PEPA(
Allo' Price increa#e if the contract i# for m!ltiple ear#
P1rc2ase Or#er A form of contract that i# normall !nilateral an/ !#e/ for #imple commo/it p!rcha#e#% 0t i#
#imple#t tpe of fi1e/ price contract an/ i# !#!all !nilateral&Signe/ ( one part in#tea/ of
(ilateral)
Cotract t$0e 4s R/s: FP E FP0F E FPAF E FPEPA E TB. E CP0F E CPAF E CPFF = CPPC
Fi1e/ Price E TB. = Co#t 6eim(!r#a(le
B!er4# ri#, from lo' to high
Seller4# ri#, from high to lo'
E'e"ets o% a Cotract
Offer A##ent to certain term# ( (oth partie#
Acceptance Agreement3 'ritten or #po,en
Con#i/eration Something of val!e
Legal Capacit A(le to contract
Legal P!rpo#e No violation of p!(lic polic
Sta!es o% Cotract
Ne!ot/at/o
Protocol 0ntro/!ction#
Pro(ing 0/entif concern#3 #trength#3 'ea,ne##e#
Scratch (argaining Act!al (argaining
Clo#!re Po#ition# #!mme/ !p
Agreement Doc!menting
S0ec/%/cat/o = preci#e /e#cription of a ph#ical item3 proce/!re3 or #ervice% The SO+ #!pplement# the #pecification in
/e#cri(ing 'hat m!#t (e /one to complete the project%
Pr/;/t$ = legal relation#hip that e1i#t# (et'een an contracting partie# &e%g% if compan FAH hire# FBH an/ FBH #!(contract to
FCH3 FCH i# not legall (o!n/ ( anthing FAH can #aG the pri@it! i# 'ith FBH)
Wa/;er = a part can relin5!i#h right# that it other'i#e ha# !n/er the contract% Fore(earance can mat!re into 'aiver%
9orce Maje1re E Act of Ao/3 Floo/#3 Fire etc
*#e"/%/cat/o E Lia(ilit3 'ho i# lia(le
Reta/a!e E 'ithhol/ing of f!n/# !n/er contract% Amo!nt of mone !#!all 7O to $>O 'ithhel/ form each pament% Thi#
mone i# pai/ 'hen 'or, i# complete%
Warrat$ = a##!rance of the level of 5!alit to (e provi/e/
A contract e#s (K
S!cce##f!l performance
.!t!al agreement La#t t'o are *ermination
Breach of contract
Page %$ o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Ter"s a# Co#/t/os E the project manager m!#t !phol/ the Term# an/ Con/ition# of the contract3 even if it meet# the
nee/# of the project3 it ha# to al#o meet the re5!irement of the contract%
L/31/#ate# #a"a!es =
Cotract Cotro' S$ste" ;s Project Cotro' S$ste" E the (oth incl!/e proce/!re#% The contract control ##tem re5!ire#
more /oc!mentation an/ more #ignoff%
Wor: A1t2or/@at/o S$ste"s E can (e !#e/ to coor/inateJcontrol 'hat time an/ #e5!ence 'or, i# /one% 0t help# 'ith
integrating ta#,# into a 'hole%
Per%or"ace Sco0e o% Wor: E /e#cri(e# the performance E not the f!nctionalit== re5!ire/ ( the c!#tomer
*#e0e#et Est/"ate E mo#t concern 'ith co#t#3 comparing co#t e#timate# 'ith in=ho!#e e#timate# or 'ith o!t#i/e
a##i#tance &part of So!rce Selection)
Proc1re"et A1#/t E #tr!ct!re/ revie' that fl!#h o!t i##!e#3 an/ #et=!p le##on# learne/% @elp# en#!re pro(lem# are re#olve/
for f!t!re project#% 0/entif #!cce##e# an/ fail!re# that 'arrant tran#fer to other proc!rement#%
Bee%/c/a' E%%/c/ec$ E 'hen the 'or, i# (eing !#e/ for the inten/e/ p!rpo#e an/ ha# (een certifie/
Terminating contract for Co;e/ece E if a project i# terminate/ (efore it i# complete3 the level of e1tent of completion
#ho!l/ (e e#ta(li#he/ an/ /oc!mente/%
Mater/a' Breac2 E Breach #o large that it ma not (e po##i(le to complete the 'or,%
So'e So1rce (ot S/!'e So1rce)E Onl one #eller3 it might (e a compan that o'n# a patent%
Cotract/!
Cetra'/@e# Decetra'/@e#
P .ore economical P Project .anager ha# more control
P Ea#ier to Control P Contracting per#onnel are more familiar 'ith project
P @igher /egree of #peciali"ation
&e1perti"e)
P .ore fle1i(le an/ a/apta(le to project nee/#
P Or/er# can (e con#oli/ate/ ? D!plication of contracting effort#
? .a (ecome a (ottlenec, ? @igher co#t#
? Le## attention to #pecial nee/# ? No #tan/ar/ policie#
Ne!ot/at/! Tact/cs
Dea/line Strategic Dela
S!rpri#e 6ea#oning Together
Limite/ A!thorit +ith/ra'al
.i##ing .an <nrea#ona(le
Fair an/ 6ea#ona(le S!gge#ting Ar(itration
Fait Accompli &A /one /eal)
D/%%erece Bet&ee Cotract C'oseo1t a# A#"/ C'os1re
$% Contract Clo#!re come# fir#t *% AC i# /one at en/ of each pha#e or project3 CC i# /one onl once at the en/ of Contract
-%AC E Le##on# learne/ CC E Proc!rement a!/it 4% AC E Le## Formal CC E .ore Formal%
Page (' o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
C2a0ter 7. 8 Pro%ess/oa' Res0os/</'/t/es
Ro1t/e Go;er"et 9ee (Tras%er 9ee( E onl government official can collect ro!tine government fee# &thi# i# not a (ri(e)
Co"0a$ Po'/c/es = 0t i# the project manager4# profe##ional re#pon#i(ilit to en#!re that compan policie# are follo'e/
/!ring the project%
Co0$r/!2t 'a&s E /o not violate
E"0'o$ee "/sta:e = 'hen a team mem(er ma,e# a mi#ta,e#3 allo' him to #ave face an/ to fi1 the pro(lem% Tr to 'or,o!t
an i##!e (efore e#calating% E1ceptionK if it i# not con#i/ere/ a project relate/ i##!e &e%g% hara##ment)3 it #ho!l/ (e reporte/
/irectl to the emploee4# manager%
Do not ma,e illegal pament#3 report theft#
Co"0a$ a# C1sto"erQs *terest = profe##ional re#pon#i(ilit re5!ire# the inve#tigation of an in#tance# 'here the
legitimate intere#t# of the c!#tomer ma (e compromi#e/% 0f #!ch compromi#e i# fo!n/3 action m!#t (e ta,en% Protect
o!r compan4# intere#t#
B1#!et ta"0er/! = pre#enting anthing (e#i/e# o!r original e#timate to allocate more to the (!/get i# inacc!rate an/ call#
into 5!e#tion o!r competence an/ integrit a# project manager &e%g% if a c!#tomer a#, to e#timate Fpe##imi#ticallH3 o!
#ho!l/ a// a# a l!mp #!m contingenc f!n/ to han/le project ri#,#)
R/!2ts = /o not /o (!#ine## 'ith a co!ntr 'here there i# a clear violation of the f!n/amental right# &e%g% non=/i#criminating
treatment)%
Page (1 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
POSS*BLE E+AM ,-EST*ONS
Scope Questions
+h i# a caref!l an/ acc!rate nee/# anal#i#
importantY
To ma,e #!re c!#tomer or #ta,ehol/er e1pectation# can (e i/entifie/ an/
#ati#fie/%
@o' i# a change control (oar/ !#e/Y Can
there (e more than oneY
To approve or reject change re5!e#t# accor/ing to re#pon#i(ilitie# /efine/
an/ agree/ !pon ( ,e #ta,ehol/er#% .!ltiple CCB# ma (e !#e/ on large
project#%
+hat i# the p!rpo#e of the project charterY
@o' /oe# it (enefit the project managerY
To formall /oc!ment the e1i#tence of the project3 incl!/ing the (!#ine##
nee/ that the project 'a# !n/erta,en to a//re## an/ the pro/!ct
/e#cription% 0t provi/e# the project manager 'ith the a!thorit to appl
organi"ational re#o!rce# to project activitie#%
+hat i# the Delphi Techni5!eY A foreca#ting techni5!e !#e/ to gather informationG it relie# on gathering
e1pert opinion#% <#!all goe# three ro!n/#% O(j%K Aain con#en#!# of e1pert
opinion#%
+hat i# the p!rpo#e of the #cope management
planY
To /e#cri(e ho' project #cope 'ill (e manage/ an/ ho' #cope change 'ill
(e integrate/ into the project%
+hat i# the p!rpo#e of the +BS /ictionarY To provi/e intere#te/ partie# 'ith 'or, pac,age /e#cription# an/ other
planning information #!ch a# #che/!le /ate3 co#t (!/get#3 an/ #taff
a##ignment# for each +BS element%
+hat i# the :> ho!r r!leY Each ta#, #ho!l/ (e (ro,en /o'n into 'or, pac,age# that re5!ire no more
than :> ho!r# to complete%
+hat i# the /ifference (et'een #cope
verification an/ 5!alit controlY
Scope verification i# primaril concerne/ 'ith acceptance of the 'or,
re#!lt#G 5!alit control i# primaril concerne/ 'ith the correctne## of the
'or, re#!lt#%
+hat are the three #tep# involve/ in .BOY &$) E#ta(li#h !nam(ig!o!# an/ reali#tic o(jective#
&*) Perio/icall eval!ate 'hether project o(jective# are (eing achieve/
&-) Act on the re#!lt# of the eval!ation%
+hen #ho!l/ #cope verification occ!rY At the en/ of the project%
HR Questions
+hich are the five metho/# of managing
conflict i# recommen/e/Y +hY
Pro(lem SolvingJconfrontation (eca!#e (oth partie# can (e f!ll #ati#fie/ if
the 'or, together to fin/ a #ol!tion that #ati#fie# (oth their nee/#%
+hat are the three tpe# of project interface#
that #erve a# inp!t# to the organi"ational
planning proce##% +hen can the occ!rY
&$) Organi"ational interface#
&*) Technical interface#
&-) 0nterper#onal interface#
The can occ!r #im!ltaneo!#l%
+hat i# .cAregor4# Theor TY +hat i#
management4# role in thi# approachY
Tra/itional approachK 'or,er# are #elf=centere/3 la"3 lac,ing am(ition%
.anager# organi"e the element# of the pro/!ctive enterpri#e in the intere#t
of economic end&%
+hat i# .cAregor4# theor VY +hat i#
management4# role in thi# approachY
+or,er# are not ( nat!re re#i#tant to organi"ational nee/#G the are 'illing
an/ eager to accept re#pon#i(ilitie# an/ are concerne/ 'ith #elf=gro'th an/
f!lfillment% .anager# #ho!l/ tr to create an environment 'here 'or,er#
can achieve their o'n goal#%
+hat i# an organi"ational (rea,/o'n #tr!ct!re
&OBS)Y
A #pecific tpe of organi"ational chart that #ho'# 'hich !nit# are
re#pon#i(le for 'hich 'or, item#
+hat i# the p!rpo#e of a re#o!rce Aantt chartY 0t i/entifie# 'hen a partic!lar re#o!rce i# or 'ill (e 'or,ing on a partic!lar
ta#,
Doe# the matri1 form of project organi"ation
facilitate or complicate project team
/evelopmentY
0t complicate# team /evelopment (eca!#e team mem(er# are acco!nta(le to
(oth a f!nctional manager an/ a project manager%
Name three major form# of project
organi"ational #tr!ct!re%
F!nctional3 .atri13 an/ Projecti"e/
+hat i# the e1pectanc theorY 0t hol/# that people ten/ to (e highl pro/!ctive an/ motivate/ if the
Page (2 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Scope Questions
+h i# a caref!l an/ acc!rate nee/# anal#i#
importantY
To ma,e #!re c!#tomer or #ta,ehol/er e1pectation# can (e i/entifie/ an/
#ati#fie/%
@o' i# a change control (oar/ !#e/Y Can
there (e more than oneY
To approve or reject change re5!e#t# accor/ing to re#pon#i(ilitie# /efine/
an/ agree/ !pon ( ,e #ta,ehol/er#% .!ltiple CCB# ma (e !#e/ on large
project#%
(elieve their effort# 'ill lea/ to #!cce##f!l re#!lt# an/ the 'ill (e re'ar/e/
for their #!cce##%
+hat i# pro(lem #olvingJconfrontationY A//re##ing conflict /irectl ( getting the partie# to 'or, together to /efine
the pro(lem3 collect information3 /evelop an/ anal"e alternative#3 an/
#elect the mo#t appropriate alternative%
Aive three e1ample# of hgiene factor# in
@er"(erg4# theor of motivation% @o' /o the
affect motivation%
Pa3 attit!/e of #!pervi#or3 an/ 'or,ing con/ition#%
Poor hgiene ma /e#tro motivation3 (!t improving hgiene factor# in not
li,el to increa#e motivation% .otivator# are an opport!nit to achieve an/
e1perience #elf=act!ali"ation%
+ho i# re#pon#i(le for a//re##ing in/ivi/!al
performance pro(lem#Y
Senior an/ f!nctional management
De#cri(e the /ifference (et'een a 'ea, matri1
an/ a #trong matri1%
+ea, matrice# are #imilar to f!nctional organi"ation#% Strong matrice# are
#imilar to projecti"e/ organi"ation# &'ith (alance of po'er tippe/ to'ar/
the project manager)
+hat i# a projecti"e/ organi"ationY One in 'hich a #eparate3 f!nctional organi"ation i# e#ta(li#he/ for each
project% Per#onnel are a##igne/ on a f!ll=time (a#i#%
Project manager4# concern i# that the team ma not (e foc!#e/ on
completing the project &team loo,# for ne' man/ate or trie# to e1ten/ the
length of the project)% Accor/ing to P.03 the (igge#t pro(lem in
A/mini#trative Clo#!re i# retaining team mem(er# !ntil clo#!re of the
project%
Communications Questions
+hat i# a project ['ar room[Y +hat i# it#
primar (enefitY
A #ingle location for the team to get together for an p!rpo#e% 0t provi/e# a
repo#itor for project artifact#3 recor/#3 an/ !p=to=/ate #che/!le# an/ #tat!#
report#% 0t give# an i/entit to the project team%
De#cri(e the #i1 part# of a Comm!nication#
.anagement Plan%
&$) +hat information 'ill (e collecte/
&*) @o' the information 'ill (e collecte/
&-) @o' an/ to 'hom the information 'ill (e /i#tri(!te/
&4) +hen the information 'ill (e comm!nicate/
&7) @o' to o(tain information (et'een reg!lar comm!nication#
&6) @o' the Comm!nication# Plan 'ill (e !p/ate/ thro!gh the project
+hat i# variance anal#i#Y Comparing act!al project re#!lt# to planne/ or e1pecte/ re#!lt# in term# of
co#t3 #che/!le3 #cope3 5!alit3 an/ ri#,%
+hat are #i1 action# project manager# #ho!l/
ta,e to en#!re effective project team
comm!nication#Y
&$) Be an effective comm!nicator
&*) Be a comm!nication# e1pe/itor
&-) Avoi/ comm!nication# (loc,er#
&4) <#e a tight matri1
&7) @ave a project 'ar room
&6) .a,e meeting# effective
+hat i# active li#teningY Li#tening in 'hich the recipient i# attentive an/ a#,# for clarification of
am(ig!o!# me##age#
+hat i# major ca!#e of conflict 'ith f!nctional
manager#Y
Sche/!le#
+hat i# mo#t /iffic!lt conflict to /eal 'ithY Per#onalit conflict#
+hat i# earne/ val!e anal#i#Y @o' i# it !#e/
in performance reportingY
An anal#i# that integrate# co#t an/ #che/!le mea#!re#% 0t i# !#e/ to help
the project management team a##e## project performance%
+hat i# the tool for !#e/ for comm!nication
planningY
Sta,ehol/er anal#i#
Page (% o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Communications Questions
+hat i# a project ['ar room[Y +hat i# it#
primar (enefitY
A #ingle location for the team to get together for an p!rpo#e% 0t provi/e# a
repo#itor for project artifact#3 recor/#3 an/ !p=to=/ate #che/!le# an/ #tat!#
report#% 0t give# an i/entit to the project team%
De#cri(e the #i1 part# of a Comm!nication#
.anagement Plan%
&$) +hat information 'ill (e collecte/
&*) @o' the information 'ill (e collecte/
&-) @o' an/ to 'hom the information 'ill (e /i#tri(!te/
&4) +hen the information 'ill (e comm!nicate/
&7) @o' to o(tain information (et'een reg!lar comm!nication#
&6) @o' the Comm!nication# Plan 'ill (e !p/ate/ thro!gh the project
+hat i# variance anal#i#Y Comparing act!al project re#!lt# to planne/ or e1pecte/ re#!lt# in term# of
co#t3 #che/!le3 #cope3 5!alit3 an/ ri#,%
+hat are #i1 action# project manager# #ho!l/
ta,e to en#!re effective project team
comm!nication#Y
&$) Be an effective comm!nicator
&*) Be a comm!nication# e1pe/itor
&-) Avoi/ comm!nication# (loc,er#
&4) <#e a tight matri1
&7) @ave a project 'ar room
&6) .a,e meeting# effective
+hat i# the mo#t important characteri#tic for a
project managerY
A(ilit to 'or, 'ell 'ith other#
+hat factor ha# the greate#t effect on the
projectW# comm!nication re5!irement#Y
The projectW# organi"ational #tr!ct!re
+hat i# the primar con/ition lea/ing to
conflict in (oth the 'ea, an/ #trong matri1
organi"ation#Y
Am(ig!o!# j!ri#/iction#% The e1i#t 'hen t'o or more partie# have relate/
re#pon#i(ilitie#3 (!t their 'or, (o!n/arie# an/ role /efinition# are !nclear%
+hen i# a project con#i/ere/ clo#e/Y +hen the archive i# complete/% All project /oc# goe# into the archive#G thi#
i# the la#t thing to create (efore relea#ing the team%
Time Questions
+hat i# the critical pathY The longe#t path thro!gh the net'or, 'hich repre#ent# the #horte#t amo!nt
of time in 'hich the project can (e complete/%
+hat i# cra#hingY Ta,ing action to /etermine ho' to o(tain the greate#t amo!nt of /!ration
compre##ion for the lea#t incremental co#tG generall increa#e# co#t%
+hat i# fa#t trac,ingY Compre##ing the #che/!le ( overlapping activitie# that 'o!l/ normall (e
/one in #e5!enceG ma re#!lt in re'or, an/ increa#e/ ri#,G logical
relation#hip# are mo/ifie/
@o' /oe# re#o!rce leveling 'or,Y
B !#ing po#itive float availa(le on non=critical path#3 #che/!le (
#moothing or leveling pea,# an/ valle# of re#o!rce !tili"ation
+hat i# activit /!ration e#timatingY A##e##ing the n!m(er of 'or, perio/# li,el to (e nee/e/ to complete each
activit
+hat i# a /!mm activitY One that con#!me# no time or re#o!rce#G it #ho'# onl /epen/enc
+hat i# #lac, or floatY Free floatY Amo!nt of time that an activit can (e /elae/ 'itho!t /elaing project%
Free float i# the amo!nt of time an activit can (e /elae/ 'itho!t /elaing
the earl #tart of the ne1t activit
+hat i# lagY 6e5!ire/ 'aiting time (et'een activitie#
Cost Questions
+hat i# life ccle co#tingY Concept of incl!/ing ac5!i#ition3 operating3 maintenance3 an/ /i#po#al
co#t#G total co#t of o'ner#hip
+hich of the follo'ing incl!/e# an a!/itG
A/mini#trative Clo#!re or Contract Clo#!reY
Contract Clo#!re incl!/e# an a!/it%
+hat i# [chart of acco!nt#[Y Co/ing #tr!ct!re !#e/ to report financial information in general le/ger%
Co/e of acco!nt# i# n!m(ering of +BS element#
+hat are co#t acco!nt#Y The repre#ent the (a#ic level at 'hich project performance i# mea#!re/
Page (( o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
Cost Questions
an/ reporte/%
Risk Questions
Aenerall #pea,ing3 in 'hat project pha#e are
ri#, an/ opport!nit greater than the amo!nt at
#ta,e ( the 'i/e#t marginY
0nitiation
De#cri(e the /ifference (et'een an internal
ri#, an/ an e1ternal ri#,%
An internal ri#, i# !n/er the control or infl!ence of the project teamG
e1ternal i# (eon/ control or infl!ence%
+hat i# p!rpo#e of a ri#, management planY
+hat #ho!l/ it incl!/eY
To /oc!ment the proce/!re# that #ho!l/ (e !#e/ to manage ri#, thro!gho!t
the project% 0t #ho!l/ incl!/e the ri#, i/entification an/ ri#, 5!antificationG
ho' contingenc plan# 'ill (e implemente/G ho' re#erve# 'ill (e allocate/%
+hat i# a re#erveY A provi#ion in the project plan to mitigate co#t an/Jor #che/!le ri#,%
.anagement re#erve# are for F!n,no'n !n,no'n#H an/ contingenc
re#erve# are for F,no'n !n,no'n#H%
+hat are the t'o mo#t common tpe# of
management re#erve#Y @o' are the !#e/Y
Co#t an/ Sche/!le3 !#e/ to re/!ce the chance of overr!n# in either area
+hen i# the highe#t ri#, impact generall
occ!rY
D!ring 0mplementation an/ Clo#e=o!t = the Amo!nt at Sta,e i# high tho!gh
ri#, ha# /ecrea#e/% 6i#, i# highe#t /!ring 0nitiation an/ Planning%
+ho i# !ltimatel re#pon#i(le for i/entifing
an/ managing ri#,Y
Project manager
Vo! are fin/ing it /iffic!lt to eval!ate the e1act
co#t con#e5!ence# of ri#,#% Vo! #ho!l/K
Eval!ate them on a 5!alitative (a#i#%
0n 'hat circ!m#tance 'o!l/ o! have to
!p/ate the 6i#, 6e#pon#e PlanY
0f a ri#, occ!r# an/ ha# a greater impact on the project than 'hat 'a#
anticipate/% &part of 6i#, .onitoring an/ Control)
+hat #ho!l/ (e /one after competingJ!p/ating
the 6i#, 6e#pon#e PlanY
A// ta#,# to the +BS
@o' /o o! a//re## !n,no'n ri#,#Y B appling a general contingenc (a#e/ on pa#t e1perience
+hat i# a ,no'n=!n,no'n ri#,Y 6i#, that can (e i/entifie/ a# po##i(l happening &e%g% Floo/ if a (!#ine## i#
locate/ in a floo/ "one)
Quality Questions
+hat are control limit# a# !#e/ in control
chart#Y
Control limit# /e#cri(e the nat!ral variation of a proce##% .&&igna:"e cau&e
i# a point o!t#i/e the control limit#
Define [,ai"en[Y Contin!o!# improvement% Small improvement# in pro/!ct# or proce/!re#
to re/!ce co#t# an/ en#!re con#i#tenc of performance of pro/!ct or #ervice%
+hat i# gol/=platingY Aiving the c!#tomer more than 'hat 'a# re5!ire/% 0t ha# no val!e%
+hat i# the effect of #ample #i"e on the
#tan/ar/ /eviationY
+henever #ample #i"e increa#e#3 the #tan/ar/ /eviation /ecrea#e#%
+hat i# the 6!le of SevenY 0f #even or more o(#ervation# in a ro' occ!r on the #ame #i/e of the mean3
even tho!gh 'ithin control limit#3 the #ho!l/ (e inve#tigate/ a# an
a##igna(le ca!#e%
+hat i# 2!#t=0n=TimeY An inventor control approach that attempt# to re/!ce 'or, =in=proce##
inventor &Decrea#ing 0nventor co#t to >)G there i# no e1tra #toc, ,ept in
re#erve
+hat i# meant ( the co#t of 5!alitY Co#t of conormance an/ co#t of nonconormance
@o' are ca!#e an/ effect /iagram# !#e/Y The #ho' ho' vario!# ca!#e# an/ #!( ca!#e# relate to create potential
pro(lem#% After the#e are i/entifie/3 corrective action can (e ta,en%
+hat i# the principal p!rpo#e of the ?!alit
.anagement PlanY
To /e#cri(e ho' the project management team 'ill implement it# 5!alit
polic
+hat i# a Pareto DiagramY A (ar chart in 'hich /ata are arrange/ in /e#cen/ing or/er of importance%
0t p!t# i##!e# into an ea#il !n/er#too/ frame'or,%
+hat i# the !n/erling concept of a Pareto
DiagramY
A relativel #mall n!m(er &*>O) of ca!#e# 'ill tpicall pro/!ce a large
majorit &:>O) of the pro(lem# or /efect#%
Page (0 o 46 La&t 5pdated
1';2;12
PMI Exam Study Notes Sajid Jambagi
+ho i# !ltimatel re#pon#i(le for 5!alitY The in/ivi/!al% The project manager ha# o@era"" re#pon#i(ilit%
Procurement Questions
+hat i# ma,e or (! anal#i#Y A techni5!e !#e/ to /etermine 'hether a pro/!ct can (e pro/!ce/ co#t
effectivel ( the organi"ation%
+hat are contract incentive#Y 0n/!cement# provi/e/ ( the (!er to the contractor in an attempt to ring
the o(jective# an/ intere#t# of the contractor in line 'ith tho#e of the (!erG
po#itive an/ negative% <#!all co#t effective
+hat i# a (i//erW# conferenceY .eeting# 'ith pro#pective #eller# to en#!re that the have a clear3 common
!n/er#tan/ing of the proc!rementG hel/ (efore #eller# prepare their
propo#al#%
+hat i# part of the contract /oc!mentY Propo#al3 Scope of +or,3 Term# an/ Con/ition# &'hich #ho!l/ (e the re#!lt
of a ri#, anal#i#)3 general provi#ion3 #pecial provi#ion# &'hich ta,e#
prece/ence over general provi#ion#)
+hat /o o! /o if a #eller /oe# not perform
accor/ing to the contractY
Ta,e action% &$) Contact #eller an/ a#, 'hat4# going on% &*) let #eller ,no'
he i# in /efa!lt &e%g% /efa!lt letter)%
Integration Questions
Le##on# learne/ are complete/ (Y Project team
+hat are the major con#traint# on a projectY 6efer# to the Tr/0'e Costra/tsK Co#t3 Time3 ?!alit3 along 'ith c!#tomer
#ati#faction an/ #cope of 'or,%
+hen man change# are ma/e to a project3
'hat #ho!l/ a project manager /oY
.a,e change a# nee/e/3 (!t maintain a #che/!le (a#eline &(a#eline i# there
to /etermine ho' the project i# progre##ing)
+hat i# the p!rpo#e of a Project PlanY $% A!i/e the project e1ec!tion
*% Doc!ment project planning a##!mption
-% Doc!ment project planning /eci#ion# regar/ing alternative# cho#en
4% Facilitate comm!nication# among #ta,ehol/er#
7% Define ,e management revie'
6% Provi/e a (a#eline for progre## mea#!rement an/ project control
Vo! are a ne' project manager% 0t i# (e#t to
rel on YY to improve o!r chance# of #!cce##Y
@i#torical information
STRATEG !"R #ARI"$S TPES "! Q$ESTI"%S&
R7O FW2at 2as t2e 0roject "aa!er 9ORGOTTEN to #oS>
a) /etermine 'hat proce## the are referring to
() /etermine if an#'er choice# areJ#ho!l/ (e inp!tJo!tp!tJtool# &activitie#)
c) /etermine 'hich inp!tJo!tp!tJtool the 5!e#tion i# loo,ing for
/) #elect the one mi##ing
R2O FW2at /s t2e BEST t2/! to #oS>
The correct an#'er #ho!l/ re#olve the !n/erling pro(lem%
R. FT2e 0roject "aa!er "1st <e MOST care%1' to E W2/c2 /s t2e MOST /"0ortatS>
The ea#ie#t 'a to /eal 'ith the#e 5!e#tion# i# to loo, for the choice that 'ill have the highe#t impact on the project%
R4 T/0O 6o&e;er acc1rate as&er c2o/ce areB 0/c: t2e oe t2at as&er t2e 31est/o.
RA T/0O Ko& 0ro<'e" so';/! 0rocesses &e%g% for a changeK &$) Eval!ate impact of the change 'ith the team3 &*) /etermine
option an/ &-) go to management or c!#tomer%)
Page (2 o 46 La&t 5pdated
1';2;12

You might also like