Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Abstract--In a new competitive environment, it becomes

possible for third parties to access transmission networks. Key


information used to determine how much power can be
transferred through the network is known as Available Transfer
Capability or ATC. Generally, ATC is calculated based on the
severest case with some safety margin reserved for any
uncertainty in the near future. However, without considering the
probabilistic nature of the power system, it becomes a question
whether ATC is reasonable in practice or not. This paper
proposes a probabilistic approach to cope with this problem. By
the probabilistic method, a characteristic of the transfer capability
can be obtained through its probability density function. The
objective of this research is to provide realistic information on the
actual ability of the network that may be an alternative choice for
system operators. The advantages of this proposed method are
illustrated by an application to a modified IEEE 118-bus system.

Index Terms-- Power System, Deregulation, Total Transfer
Capability (TTC), Probabilistic, Uncertainty, Risk Analysis
I. INTRODUCTION
n a present open access transmission system, accurate and
flexible information is needed to provide non-discriminatory
access from all participants. Available Transfer Capability
(ATC) is one key parameter that indicates an ability of power
systems to reliably increase a transferred power between two
zones or two points. According to North American Electric
Reliability Council (NERC)s definition, ATC depends on
several parameters, i.e. Total Transfer Capability (TTC),
Transmission Reliability Margin (TRM), sum of existing
transmission commitments and Capacity Benefit Margin
(CBM). Mathematically, ATC is defined as TTC minus base-
flow, TRM and CBM. Although TRM and CBM are important
parts of ATC, they can be considered independent from TTC
evaluation [14].
Currently, the ATC used in almost all utilities around the
world is based on a deterministic method. With appropriate
system conditions assumed, many sets of transfer capabilities
are calculated based on N-1 contingencies. The worst case--or
minimum value--of transfer capability in conjunction with
some safety margin to handle uncertainties in the near future is
defined as the ATC. In general, this method seems appropriate
and efficient in managing usage of the transmission system.
However, because it fails to consider the probabilistic nature of

A. Yokoyama is a professor at Department of Electrical Engineering,
University of Tokyo, J APAN (e-mail: yokoyama@syl.t.u-tokyo.ac.jp).
K. Audomvongseree is a student at Department of Electrical Engineering,
University of Tokyo, J APAN (e-mail: ukulyos@syl.t.u-tokyo.ac.jp).
the power system, the obtained ATC may be too conservative
and therefore lead to a costly and inefficient use of a system
resource. This paper proposes a probabilistic approach to
evaluate total transfer capability to cope with this kind of
problem. By using the probabilistic method, a probability
density function (p.d.f) or distribution of the related TTC is
obtained [1]. This proposed information provides an alternative
choice for transmission providers (TPs) or ISOs to allow them
to flexibly choose an appropriate TTC, and then ATC, under
their criteria to match with a real time economic signal.
This paper is organized in the following sequence. In
section II, the probabilistic nature of TTC calculation is
discussed. In section III, a reference of algorithm for TTC
calculation used in this paper is given. Section IV proposes the
risk analysis concept for considering an appropriate TTC.
Then, applications of the proposed probabilistic method to a
modified IEEE 118-bus system are presented in section V.
Finally, conclusions are provided in section VI.
II. PROBABILISTIC NATURE OF TTC CALCULATION
In TTC calculation, generally, the maximum transfer
capability of many scenarios will be evaluated due to the N-1
contingencies. The minimum one of these candidates is set to
be the TTC of a specified path. However, this technique may
not be appropriate in some practical systems. One reason is
that a probability of an occurrence of the worst case may be
very small and may not occur in any specified lead-time. This
results in the too conservative and inefficient use of network
resources. The other reason, in contrast to the first one, is that
in a system that contains a large number of equipment, the N-1
contingencies may not be enough to cover all possible
scenarios occurring in the near future. For example, assume
that one power system has 1000 transmission lines and each
line has 0.1% unavailability [12]-[13]. The probabilities in
cases of no-line outage, one-line outage and two-line outage
are shown respectively as follows:

No-line outage : 3677 . 0 ) 999 . 0 (
1000
=
One-line outage : 3681 . 0 ) 001 . 0 ( ) 999 . 0 ( 1000
999
=
Two-line outage : 1840 . 0 ) 001 . 0 ( ) 999 . 0 ( C
2 998
2
1000
=

From the above example, we can see that the N-1 criterion
covers only 73.58% of the overall possible events which may
not be enough. Therefore, situations with more than one
equipment outage, (N-2, N-3 or more criteria) are also
significant and cannot be neglected. For these purposes, many
researches using a probabilistic approach based on Monte
Risk based TTC Evaluation
by Probabilistic Method
K. Audomvongseree, and A. Yokoyama, Member, IEEE
I
0-7803-7967-5/03/$17.00 2003 IEEE
Paper accepted for presentation at 2003 IEEE Bologna Power Tech Conference, June 23th-26th, Bologna, Italy

Carlo simulation have been proposed [2]-[3], [15]-[16]. In this
simulation method many network conditions are sampled.
Then, the maximum transfer capability is calculated for each
scenario. However, because of time consuming limitations,
Monte Carlo simulation is not adopted in this paper. Rather, a
state selection method[12] is used. An appropriate contingency
level defined as the numeric amount of equipment that fails or
is in the outage state at the same time used in this method
depends on characteristics of each system. Nevertheless, N-2
contingencies criterion is used in this paper. The reason for this
decision is that generally TTC is calculated for a short lead-
time, more than N-2 contingencies might rarely occur.
A probabilistic approach to TTC proposed in this paper
starts from identification of all scenarios comprising their
system condition and probability obtained from N-2
contingencies. Then, at each scenario, the maximum transfer
capability is calculated. After performing this task for all
contingencies, the obtained data containing maximum transfer
values and their related probability is used to form a
probability distribution. This distribution is used to describe a
probabilistic nature of TTC for the specified path and is a vital
tool used in considering the appropriate TTC proposed in this
paper. A detailed explanation of the utilization of probabilistic
TTC is discussed in section IV.
III. TTC EVALUATION
TTC is a maximum amount of power for a given set of
system conditions that can be transferred from one location
known as a source to another location known as a sink without
any violations of system constraints. To calculate this amount,
this research formulates the problem by introducing a load
parameter, , to the load at the sink- bus while the source-bus
is considered as a system slack.


p 0 L
Sink
L
K P P + = (1)

q 0 L
Sink
L
K Q Q + = (2)

where is a load parameter
P
L
and Q
L
are real and reactive load at the sink-bus,
K
p
and K
q
are load multipliers related to power factor

To calculate the maximum transferred power, load
parameter, , should be maximized subject to power flow
equations and a set of security constraints. This is a kind of
optimization problems. However, it will be time consuming if
we solve this problem directly using an optimal power flow
method (OPF). Generally, the occurrence of simultaneous
violation in considering maximum transfer capacity is rarely
occurred. The limiting condition of the transferred power in
each scenario usually comes from only one security constraints.
Therefore, if we know what the limiting constraint is, we can
calculate the maximum transferred power by just solving that
constraint together with the power flow equation.
A method used in this research for calculating TTC is
divided into two steps, Prediction and Calculation [17].
Prediction uses a linear estimation concept [8]-[18] to identify
an active constraint that limits the transferred power.
Calculation uses the information from the prediction step to
augment that active constraint into the power flow equation to
calculate an accurate TTC.
Details methodology of these two concepts can be found in
reference 8.
IV. PROPOSED APPROACH AND RISK ANALYSIS
A. Probability density function of maximum transfer capability
As it is stated earlier, considering only cases based on N-1
contingency may not be enough. Consequently, rather N-1, this
paper will also consider contingency cases obtained from N-2
criteria. All cases considered here are only the contingencies
related to the unavailability of transmission line. The
unavailability of generators should not be taken into account
for the purpose of TCC calculation. This is because TCC is
defined based on a particular base-case. However, any
occurrences of contingencies concerning generator will cause
the generations and demand to be re-dispatched. As a result,
the base-case condition will be changed. The effect of these
system condition changes should be handled by an introduction
of TRM, not by TTC.

G1
G2
L1
1
2 3
4
L2
L3
L4
Source
Sink

Fig. 1: Model Power System

A concept of the proposed probabilistic approach can be
described using the following example. Assume that the
maximum transferred power of a transaction from bus 1 to bus
3 of a small power system shown in Fig. 1 is considered. From
a statistical record, transmission lines are assumed to have 9%,
7%, 5% and 3% unavailability respectively. From these values,
we can evaluate the probability for each event by the following
formula [12]-[13]:




=
Available k
k
Outage j
j
) FOR 1 ( FOR ) X ( P (3)

where X is an interested event
j is a set of outage elements
k is a set of available elements

After the algorithm described in section III is applied to all
events related only to transmission line outage contingencies
obtained from N-2 rule, the maximum transfer capability and
their event probability calculated using (3) is shown in Table 1.
The keyword Base Case shown in the table means there is no
outage element in that event. L1 means only transmission
line number 1 fails. L1, L2 means both transmission lines fail
in that event.

Table 1: Maximumtransfer capability and their probability fromN-2 rule
Event
No.
Contingency Probability
MaximumTransfer
Capability (MW)
1 Base Case 0.779865 100
2 L1 0.077130 102
3 L2 0.058700 96
4 L3 0.041046 94
5 L4 0.024120 85
6 L1, L2 0.005805 95
7 L1, L3 0.004059 93
8 L1, L4 0.002385 89
9 L2, L3 0.003089 93
10 L2, L4 0.001815 84
11 L3, L4 0.001269 83

To construct the p.d.f used for describing their probabilistic
nature, all data related to the maximum transfer capability
shown in Table 1 is divided into multiple sections. Seven
sections of equal width are used in this example. The
probability of each section is evaluated by accumulating the
probability of all events relating to that section. Then each
probability is normalized to yield a sum of unity. The p.d.f. of
the maximum transfer capability, for this example, is illustrated
in Fig. 2. The numerical details are also shown in Table 2.

80 85 90 95 100 105
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
Maximum Transfer Capability
P
r
o
b
a
b
i
l
i
t
y
(MW)

Fig. 2: Probability density function of maximumtransfer capability

Table 2: Probability density function of maximumtransfer capability
MaximumTransfer Capability (MW)
(Average point of an interval)
Probability
83.00 0.003086
86.17 0.024137
89.33 0.002387
92.50 0.048229
95.67 0.064551
98.83 0.780425
102.00 0.077185

By the deterministic method, due to N-1 contingencies, the
TTC will be set to 85 MW. However, from this example, we
can see that this situation having approximately 2.41%
probability hardly occurs. This is why the deterministic TTC
obtained from the worst case among N-1 contingencies is
thought to be very conservative, and it provides motivation to
consider increasing this value, TTC, beyond 85 MW. In
addition, because the ATC also has some reserved margins,
TRM and CBM, the TTC does not need to be that strict value.
B. Risk Analysis
If we conclude that utilization of the TTC obtained from the
deterministic method is inefficient, it becomes a question how
much it should be used. This might be answered by considering
risk analysis. The concept is that the higher value you use the
greater risk you get. Consider the p.d.f. from Fig. 2. The
overall area under this curve is one. If we consider any value of
the maximum transfer value, TTC
j
, we can define an associated
risk of curtailment, a probability that the maximum transfer
capability is less than TTC
j
, as follows:

x ) x ( f ) TTC ( t Cultailmen of Risk
j
TTC
x
j

=
= (4)

where f(x) is a p.d.f. of the maximum transfer capability
x is the amount of the maximum transfer capability.

The easiest way to determine the optimal TTC is to define a
prescribed risk level [4]. If one would accept a risk of 5%, then
the TTC would be 92.26 MW. However, a more reasonable
method should include a consideration of an optimum between
benefit and risk in a monetary viewpoint [19]. Benefit and risk
used in this analysis cannot be defined uniquely. They depend
on the objective and structure of each power system. In this
paper, we show only some examples of benefit and risk
functions. Nevertheless, it should be noted that these functions
can differ depending upon decisions of ISOs or TPs.
1) Benefit function:
In this section, we propose a wheeling benefit index which
represents a merit when using transferred power x more than
the deterministic TTC. For example, this index is an income
corresponding to the average benefit power as shown below:

) TTC x ( g ) x ( B
istic min er det
= (5)

where g(z) is wheeling benefit function
2) Risk function:
The risk when wheeling the power x more than the
deterministic TTC can be evaluated from the concept of outage
cost [6], [7], [20] and others. Because there are many possible
outage conditions, the risk function can be defined as follow:

=
=
x
s
s ) s ( f ) s , x ( h ) x ( R (6)

where h(x,s) is monetary loss function
s is a dummy variable relating to the transferred
power
3) Determination of the appropriate TTC:
To find an appropriate TTC, the total benefit function which
is determined from benefit minus risk functions has to be
maximized. At an optimal point, a derivative of this function
will be zero that gives:


dx
) x ( dR
dx
) x ( dB
= (7)

Because R(x) which has a discrete-p.d.f. is hard to
differentiate, equation (7) will be approximated with a
numerical method to be (8).

) x ( R ) x x ( R ) x ( B ) x x ( B
1 n 1 n 1 n 1 n
+ = + (8)

With (8), the appropriate TTC will be evaluated by a search
algorithm starting at the deterministic TTC. Then the transfer
capability will be increased (may increase with the same step
length as section width of p.d.f.) and the benefit and risk will
be calculated. At the beginning, generally, an increment of
benefit is greater than an increment of risk. Our goal is to find
the point where both increments are equal. However, with a
search algorithm, this is hard to be done. Therefore the process
will be continuously done until we find the point where the
increase in benefit is not greater than the increase in risk. After
that, an interpolation technique may be applied to find a more
accurate solution.
V. NUMERICAL EXAMPLE
In this section, the proposed probabilistic method is applied
to the modified IEEE 118-bus system. It is called a modified
test system because probabilistic data related to transmission
line failure and repair rates is assumed. The failure rate is
assumed to have a value which is proportional to its line length
and the repair rate is assumed to have a value depending upon
its type. All contingencies that have to be taken into account
for each interested path contain 172 cases from N-1 and 29,313
cases from N-2 contingencies. Although TTC of this test
system were calculated in numerous possible paths, only
probabilistic TTC of one path is illustrated. The source and
sink of this path are buses 69 and 51 respectively. A single line
diagram of the IEEE 118-bus test system is shown as Fig 3.

G
1 2
3
5
4
G
6 7
G
G
G
8
9
10
11 12 13
14 15
G
G
16
17 18 19
20
G G
21
22
23 24
25
G
G
26
G
G
27
28
30
29
31
G
G
32
33
34
35
36
G
G
37
38
39
40
G
41 42
G
43 44
45
46
G
47
48
49
G
50
51
52
53 54
G
56
55
57
G G
58
59
G
60
61
62
G
G
63
64
65
66
G
G
68
69
67
G
70
71
72
73
G
G
G
74
75
G
118
76
77
G
G
78
79
80
81
82
G
117
116
G
113
G
114
115
83
84
85
G
G
G
86 87
88
89
90
91
92
G G
G 93
94
95
96
100
97
98
99
G
G
102
101
103
104
105
106
107
G
G
G
G
108
109 110
G
G
G
112
111

Fig. 3: Single line diagramof the IEEE 118-bus system

In this test system, the probability in the base case that all
equipment is in service is about 0.1338. The probability of an
event having one and two outage lines is 0.2572 and 0.4871
respectively. These probability results support us to consider
more contingency cases than only in the N-1 rule.
The TTC calculations for all 29,486 cases of this path are
done with a method mentioned in section III. The probabilistic
result is shown below. All calculations are conducted on a 1.6
GHz personal computer using a program developed on
MatLab. The simulation time for all calculations is 32 minutes
56 seconds which is approximately 0.067 seconds each case.
30 35 40 45 50 55
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
Maximum Transfer Capability
P
r
o
b
a
b
i
l
i
t
y
(MW)

Fig. 4: Probability density function of maximumtransfer capability

Table 3: Probability density function of maximumtransfer capability: f(x)
MaximumTransfer Capability (Average point of an interval)
Real power (MW) Reactive power (MVar)
Probability
31.70 14.92 0.000013
33.16 15.60 0.000306
33.89 15.95 0.000185
34.62 16.29 0.000299
36.07 16.98 0.000111
37.53 17.66 0.000307
38.26 18.01 0.000041
38.99 18.35 0.001337
39.72 18.69 0.007949
40.45 19.04 0.013475
41.18 19.38 0.000455
41.91 19.72 0.000418
42.64 20.07 0.010879
43.37 20.41 0.000690
44.10 20.75 0.000768
44.83 21.10 0.007725
45.56 21.44 0.006374
46.29 21.78 0.019922
47.02 22.13 0.184269
47.75 22.47 0.718564
48.48 22.81 0.007427
49.21 23.16 0.017726
49.94 23.50 0.000212
50.67 23.84 0.000020
51.40 24.19 0.000012
52.86 24.88 0.000516

The deterministic TTC obtained from considering only N-1
rule is 39.56 MW which is equivalent to an approximately
0.4719% in risk of curtailment according to (23). It can be seen
that this risk value is very small. If we accept the risk of 5%,
then the TTC would be 45.04 MW.
To evaluate the appropriate TTC by cost analysis, we
assume the benefit and risk functions as follows:

Wheeling benefit function: x 65 ) 1 e ( 250 x 80 ) x ( g
x 02 . 0
+ = $/hr
Monetary loss function: 1561 s 6 . 0 ) s x ( 500 ) s , x ( h
2
+ = $/hr

From these assumed functions, we can construct the benefit
and risk functions as follows:

2571 x 65 ) 1 e ( 250 ) 56 . 39 x ( 80 ) x ( B
) 56 . 39 x ( 02 . 0
+ + =

$/hr

[ ] s ) s ( f ) 1565 s ( 6 . 0 ) s x ( 500 ) s , x ( R
x
s
2

=
+ = $/hr

With the proposed algorithm described in Fig. 3, we found
that when the transferred power is 44.10 MW the increment of
benefit and risk are 14.92 and 13.48 $/hr respectively. And the
increment of benefit begins to be less than that of risk when the
transferred power is 44.83 MW. At this point the increments of
benefit and risk are 14.98 and 15.65 $/hr respectively. With the
interpolation technique shown in Fig. 5, the appropriate TTC
where benefit and risk are equal can be calculated by (9),
yielding the optimal TTC of 44.60 MW.


)) x ( dR ) x ( dB ( )) x ( dB ) x ( dR (
) x x ( )) x ( dR ) x ( dB (
x TTC
1 1 2 2
2 2 1 1
1
+

+ = (9)

TTC x
1
x
2
dR(x
1
)
dR(x
2
)
dB(x
1
)
dB(x
2
)
TTC
*
Incremental cost ($/MW)

Fig. 5: Interpolation technique to calculate the optimal TTC

Relationships among benefit, risk and total benefit as
functions of TTC are shown in Fig. 6. It can be seen that the
benefit function increases linearly whereas, at the beginning,
the risk is gradually increase. But when the transferred power
exceeds 46.29 MW, it rapidly increases because the risk of
curtailment becomes very high. Furthermore, the optimal TTC
is not a point where the benefit equals to the risk but is the
point that both increments are equal. At this point, 44.60 MW,
the total benefit is at its maximum.
41 42 43 44 45 46 47 48
0
20
40
60
80
100
120
140
160
Maximum Transfer Capability (MW)
M
o
n
e
t
a
r
y

u
n
i
t

(
$
)
Benefit
risk
Total Benefit

Fig. 6: Relations among benefit, risk and total benefit as the functions of TTC
V. CONCLUSION
This paper proposes a probabilistic approach to determine
the appropriate TTC. A state selection with N-2 contingency
level is used to generate considered events. In each event, a
maximum transfer capability considering AC network and
stability constraints is computed. Then the probabilistic nature
of TTC is formulated through probability density function.
From this method, it is shown that the deterministic TTC which
is calculated using the worst case of N-1 rule might be too
conservative. It motivates us to increase TTC beyond this
value. There are two methods proposed in this paper to
consider the increasing in TTC. One is to define a prescribed
risk level. Other is to consider the optimum between benefit
and risk. To show the advantages of this proposed method, the
application to a modified IEEE 118-bus system will be done. It
has been concluded that this proposed method is helpful for
operator to trade off between benefit and risk in the new
competitive environment.
VI. REFERENCES
Periodicals:
[1] A.M. Leite da Silva, J .G.C. Costa, L.A.F. Manso, G.J . Anders,
Transmission Capacity: Availability, Maximum Transfer and
Reliability, IEEE Trans. on Power Systems, vol. 17, pp. 843-849, Aug.
2002
[2] A.M. Leite da Silva, J .W. Marangon Lima, and G.J . Anders, Available
transmission capability-sell firm or interruptible?, IEEE Trans. on
Power Systems, vol. 14, pp. 1299-1305, Nov. 1999
[3] J .C.O Mello, A.C.G. Melo, and S. Granville, Simultaneous transfer
capability assessment by combining interior point methods and Monte
Carlo simulation, IEEE Trans. on Power Systems, vol. 12, pp. 436-742,
May 1997
[4] Vijay Vittal, J ames D. McCalley and Hua Wan, Increasing Thermal
Rating by Risk Analysis, IEEE Trans. on Power Systems, vol. 14, pp.
815-828, Aug. 1999
[5] Wei-J en Lee, Lin C.H., Swift K.D., Wheeling charge under a deregulated
environment, IEEE Transactions on Industry Applications, vol 37, pp.
178 -183, J an/Feb 2001
[6] K.K. Kariuki, R.N. Allan, Applications of customer outage costs in
system planning, design and operation, IEE Proc.-Gener. Transm.
Distrib., vol. 143, pp. 305-312, J uly 1996
[7] L. Goel and R. Billinton, A Procedure for Evaluating Interrupted Energy
Assessment Rates in an Overall Electric Power System, IEEE Trans. on
Power Systems, vol. 6, pp.1396- 1403, Aug., 1991
[8] Greene, S., Dobson, I., Alvarado, F.L., Sensitivity of transfer capability
margins with a fast formula, IEEE Transactions on Power Systems, vol.
17, pp. 34 -40, Feb 2002
[9] G. Hamoud, Assessment of Available Transfer Capability of
Transmission Systems, IEEE Trans. on Power Systems, vol. 15, pp. 27-
32, Feb. 2000
[10] M.D. Ilic, Y.T.Yoon, and A.Zobian, Available transfer capacity (ATC)
and its value under open access, IEEE Trans. on Power Systems, vol.
12, pp. 636-645, May. 1997
[11] Y. Xiao, Y.H. Song and Y.Z.Sun, A hybrid stochastic approach to
available transfer capability evaluation, IEE Proc.-Gener. Transm.
Distrib., vol. 148, pp. 420-426, September 2001

Books:
[12] R. Billinton and R.N.Allan, Reliability Evaluation of Power Systems,
Pitman, London, 1984.
[13] R. Billinton and R.N.Allan, Reliability Evaluation of Engineering
Systems Concepts and Techniques, Plenum Press, New York, 1992.

Technical Reports:
[14] Transmission Transfer Capability Task Force, Available Transfer
Capability Definitions and Determination, North American Electric
Reliability Council, Princeton, New J ersey, J une 1996.

Papers from Conference Proceedings:
[15] B. Corniere, L. Martin, S. Vitet, N. Hadjsaid and A.G. Phadke,
Assessment of the congestion cost and the risk of curtailment associated
with available transfer capability (ATC), in Proc. 2000 IEEE Power
Engineering Society Winter Meeting, pp. 891 -896
[16] A.B. Rodrigues and M.G. Da Silva, Solution of simultaneous transfer
capability problemby means of Monte Carlo simulation and primal-dual
interior-point method, in Proc. 2000 International Conference on
Power System Technology, PowerCon, pp. 1047 -1052
[17] K. Audomvongseree and A. Yokoyama, Application of AC equivalent
to Total Transfer Capability Evaluation using Two-Step Method, in
Proc. 2002 International Conference on Power System Technology,
PowerCon, pp. 383-387
[18] De Tuglie, E., Dicorato, M., La Scala, M., Bose, A., Multiple criteria
decision making methodology based on a probabilistic evaluation of
ATC for congestion management in Proc. 2001 IEEE Power
Engineering Society International Conference on Power Industry
Computer Applications, PICA, pp. 362 -367
[19] Y. Shimizu and A. Yokoyama, Risk-based Assessment of Available
Transmission Capability in Power System, in Proc. 2000 International
Conference on Probabilistic Method Applies to Power Systems, PMAPS
[20] K. Audomvongseree, B. EUA-Arporn and A. Yokoyama, Reliability
Worth Evaluation for Distribution SystemPlanning and Operation using
Improved Actual Performance Data, in Proc. 2002 IEEE Power
Engineering Society Transmission and Distribution Asia Pacific Conf.,
pp. 74-79













































VIII. BIOGRAPHIES
Akihiko Yokoyama was born in Osaka, J apan
in 1956. He received BS, MS and Dr. Eng all
fromthe University of Tokyo in 1979, 1981 and
1984, respectively. He has been with Department
of Electrical Engineering, University of Tokyo
since 1984 and currently a professor in charge of
Power System Engineering. He was a visiting
research fellow at University of Texas, Arlington
and University of California, Berkley during
1987-1989. He is now a member of IEEE and
CIGRE.

Kulyos Audomvongseree was born in Bangkok,
Thailand, in 1977. He graduated B.Eng. and
M.Eng. in the field of electrical engineering from
Chulalongkorn University, Bangkok, Thailand in
1998 and 2000 respectively. He is now pursuing
a Ph.D. in electrical engineering at University of
Tokyo, J apan. His interested topics include
Power System Planning and Operation,
Reliability Assessment, Probabilistic Method and
Power SystemDeregulation.

You might also like