M&E Outstanding Work
M&E Outstanding Work
AIRPORT
SYRIAN ARAB REPUBLIC
Dated: 09/12/09
M&E Testing & Commissioning
KEMJ 10/28/2009
2 Public Address 10/27/2009
11/14/2009
Palmac
6 Plumbing Services 10/28/2009 11/3/2009
Construction
11/3/2009
11/17/2009
11/19/2009
11/21/2009
Meridian
7 Fire Protection Services 11/3/2009 11/23/2009
Engineering
Meridian
7 Fire Protection Services 11/3/2009
Engineering
11/10/2009
10 Networking System 11/9/2009
KLIA INFORMATIK
06 - 07/01/10
11/11/2009
11 Flight Information Display System, FIDS 11/12/2009
11/16/2009
KLIA Info
8 CCTV Image focusing and joystick at control room mulfunction. 0% 0%
9 CCTV Additional 3 nos CCTV camera / DVR / Monitor 0% 0%
Rectification work for all existing AHU as requested by
10
SCAA :
11 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
12 ACMV b) Duct insulation for existing ductworks 0% 0%
G3-1
13 c) Motor changed/fan inspected 90% 10%
a) Hot & Chilled Water Pipes Insulation for existing
14 0% 0%
pipes
AHU
15 ACMV b) Duct insulation for existing ductworks 0% 0%
G3-2
16 c) Motor changed/fan inspected 90% 10%
17 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
18 ACMV b) Duct insulation for existing ductworks 100% 0%
GT-1
19 c) Motor changed/fan inspected 90% 10%
20 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
21 ACMV b) Duct insulation for existing ductworks 100% 0%
GT-2
22 c) Motor changed/fan inspected 90% 10%
23 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
24 ACMV b) Duct insulation for existing ductworks 100% 0%
C1W
25 c) Motor changed/fan inspected 90% 10%
26 a) Hot Water Pipes Insulation for existing pipes 0% 10%
AHU
27 ACMV b) Duct insulation for existing ductworks 100% 0%
C4E
28 c) Motor changed/fan inspected 100% 0%
29 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
30 ACMV b) Duct insulation for existing ductworks 100% 0%
K6W
31 Pathfinder c) Motor changed/fan inspected 100% 0%
32 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
33 ACMV b) Duct insulation for existing ductworks 0% 20%
I6E
34 c) Motor changed/fan inspected 90% 10%
35 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
36 ACMV b) Duct insulation for existing ductworks 100% 0%
K7W
37 c) Motor changed/fan inspected 90% 10%
38 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
39 ACMV b) Duct insulation for existing ductworks 100% 0%
I6W
40 c) Motor changed/fan inspected 90% 10%
41 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
42 ACMV b) Duct insulation for existing ductworks 100% 0%
I5E
43 c) Motor changed/fan inspected 90% 10%
44 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
45 ACMV b) Duct insulation for existing ductworks 100% 0%
K6E
46 c) Motor changed/fan inspected 90% 10%
47 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
48 ACMV b) Duct insulation for existing ductworks 0% 0%
E4E1
49 c) Motor changed/fan inspected 90% 10%
50 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
51 ACMV b) Duct insulation for existing ductworks 0% 0%
D7E
52 c) Motor changed/fan inspected 90% 10%
53 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
54 ACMV b) Duct insulation for existing ductworks 0% 0%
C5W
55 c) Motor changed/fan inspected 0% 90%
56
Pathfinder a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
57 ACMV b) Duct insulation for existing ductworks 0% 0%
E7E-1
58 c) Motor changed/fan inspected 0% 90%
59 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
60 ACMV b) Duct insulation for existing ductworks 0% 0%
E7E-2
61 c) Motor changed/fan inspected 50% 40%
62 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
63 ACMV b) Duct insulation for existing ductworks 0% 0%
E6E
64 c) Motor changed/fan inspected 90% 10%
65 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
66 ACMV b) Duct insulation for existing ductworks 0% 0%
E2E
67 c) Motor changed/fan inspected 90% 10%
68 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
69 ACMV b) Duct insulation for existing ductworks 0% 0%
G4W-1
70 c) Motor changed/fan inspected 0% 0%
71 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
72 ACMV b) Duct insulation for existing ductworks 0% 0%
G4W-2
73 c) Motor changed/fan inspected 90% 10%
74 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
75 ACMV b) Duct insulation for existing ductworks 0% 0%
ZE-1
76 c) Motor changed/fan inspected 10% 90%
77
Pathfinder a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
78 ACMV b) Duct insulation for existing ductworks 0% 0%
ZE-2
79 c) Motor changed/fan inspected 10% 90%
80 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
81 ACMV b) Duct insulation for existing ductworks 0% 0%
G4-1
82 c) Motor changed/fan inspected 90% 10%
83 a) Hot Water Pipes Insulation for existing pipes 0% 0%
AHU
84 ACMV b) Duct insulation for existing ductworks 0% 0%
G4-2
85 c) Motor changed/fan inspected 90% 10%
86 Existing FCU unit at 1st floor transit area (4 nos):
87 ACMV b)Rectify all duct work due to poor air distribution. 0% 0%
88 c)To install grille/diffuser/flexible duct at Departure Gates 0% 0%
89 ACMV To add splitter/damper at sick bay duct branch out. 0% 0%
91 ACMV Pressure test for chilled water and hot water system. 50% 0%
101 Civil work High mast, edge light and airfield signage installation. 0% 0%
106 Civil work Car park water ponding rectification work. 100% 0%
111 Civil work Manhole at arrival carousal to be air tight type. 100% 0%
112 Civil work Painting at arrival rentaining wall and external void. 87% 0%
Completed work.
Work in progress (WIP)
Notes:
1. Zink sheet for hot & chilled water pipe delivered to site not enough.
PARK AND PARKING APRON AT DAMASCUS INTERNATIONAL AIRPORT
Meb had notified GCEC that MSB shall be VO to the Mobilazation of kitlite
contract. Meb is awaiting acknowledgement from GCEC expected on 23/12/09 in
T&C completed with comment on echo phenomenon in anticipation that balance
1st Inspection concourse area. GCEC advised Meb to treat the echo material like conduit
2nd Inspection problem. (including additional light
T&C completed but final approval subject to documents to arrive / clear by
22/12/09)
submission conforming to the specification.
T&C completed but final approval subject to the
documents submission conforming to the specification.
MEB had written to Airport Director request for fix line
for testing. MEB to coordinate with airport maintenance
team for this line. Letter sent
T&C completed with comment on damages and defective
fittings due to public rough handling.
HR & Pyrogen
T&C of Hose reel & Pyrogen system completed. T&C of
FA 1st T&C Fire Alarm System in progress
FA 2nd T&C GCEC require original catalogue submission for all fire
protection devices installed at site especially for FA
FA 3rd T&C panel. Catalogue under compilation & target to submit
12/12/09. HQ to assist getting JVK to justify:
FA 4th T&C
1) PC based graphic central control system
2) Fault isolator
1st T&C First inspection at server room has been carried out.
Second inspection at access point in the ground area
pending due to inspector do not have workpass. Target to
2nd T&C carry out on 6 January 2010.
T&C completed with general comment on cleanliness of
1st T&C the monitors and replacement of some burn mark
2nd T&C monitors.
Target physical inspection on Mid Dec 2009 and official
inspection around Mid Jan 2009.
As-Off: 12/8/2009
Daily work progress
Remarks
Completed
0% No confirmation from SCAA. Please advice.
GCEC advised no to connect main electrical system to
0% the new essential supply until the "type tested" issue
KEMJ workers demob on
resolved.
2/12. HQ is arranging for
0% Please advise. Kitlite to mob tentative on
23/12/09 subject to the full
T&C completed but final approval subject to documents
0% delivery of conduit and light
submission conforming to the specification.
fittings / accessories.
65% Awaiting material from supplier Wassem.
0% HQ to order 4 nos hot water tanks.
Beam detector arrived on 8/12/09. Worker went back TKH to assist getting next
0%
without permission on 6/12/09. from Meridian.
0%
0%
100%
0%
0%
100%
0%
100%
100%
0%
100%
100%
0% Fabrication of hot water jacket completed.
100%
100%
10% Sourcing zink sheet from
local in progress. Current
100% stock 600 out of 2000 meter
100%
0% Dismantle of existing jacket completed.
100%
100%
0% Dismantle of existing jacket completed.
20% Dismantle of existing insulation completed.
100%
0% Dismantle of existing jacket completed.
100%
100%
0% Dismantle of existing jacket completed.
100%
100%
0% Dismantle of existing jacket completed.
100%
100%
0% Dismantle of existing jacket completed.
100%
100%
0% Dismantle of existing jacket completed.
0% Dismantle of existing insulation completed.
100%
0% Dismantle of existing jacket completed.
0% Dismantle of existing insulation completed.
100%
0% Dismantle of existing jacket completed.
0% Dismantle of existing insulation completed.
90% Test run in progress.
0% Dismantle of existing jacket completed.
0% Dismantle of existing insulation completed.
90% Test run of airflow in progress.
0% Dismantle of existing jacket completed.
0% Dismantle of existing insulation completed.
90% Test run in progress.
0% Fabrication of hot water jacket completed.
0% Dismantle of existing insulation completed.
100%
0% Fabrication of hot water jacket completed.
0% Dismantle of existing insulation completed.
100%
0% Fabrication of hot water jacket completed. Sourcing zink sheet from
local in progress. Current
0% Dismantle of existing insulation completed.
stock 600 out of 2000 meter
0% Motor on site.
0% Fabrication of hot water jacket completed.
0% Dismantle of existing insulation completed.
100%
0%
0%
100% Test run in progress.
0%
0%
100% Test run in progress.
0%
0%
100%
0%
0%
100%
0%
0%
0%
100%
0%
0%
0% 8/25/2009
0% TBA TBA
0% TBA TBA
0% TBA TBA
0% TBA TBA
100% completed
95% 12/15/2009
100% completed
0% TBA TBA
0% TBA TBA
100% completed