1. The City of Hartford performed a special review of activities related to the proposed Hartford Municipal Office Building project after receiving an inquiry.
2. The review found that invoices totaling $149,000 were approved for payment prior to the approval and execution of the related contract. Additionally, a final vendor report was issued in April 2014 prior to contract approval in May 2014.
3. The review recommends that the Department of Development Services ensure contracts and purchase orders are approved and executed before vendors provide services or invoices are approved for payment in the future.
Original Description:
Order of events
Original Title
t Ford Municipal Office Building Special Review Memorandum Final
1. The City of Hartford performed a special review of activities related to the proposed Hartford Municipal Office Building project after receiving an inquiry.
2. The review found that invoices totaling $149,000 were approved for payment prior to the approval and execution of the related contract. Additionally, a final vendor report was issued in April 2014 prior to contract approval in May 2014.
3. The review recommends that the Department of Development Services ensure contracts and purchase orders are approved and executed before vendors provide services or invoices are approved for payment in the future.
1. The City of Hartford performed a special review of activities related to the proposed Hartford Municipal Office Building project after receiving an inquiry.
2. The review found that invoices totaling $149,000 were approved for payment prior to the approval and execution of the related contract. Additionally, a final vendor report was issued in April 2014 prior to contract approval in May 2014.
3. The review recommends that the Department of Development Services ensure contracts and purchase orders are approved and executed before vendors provide services or invoices are approved for payment in the future.
To: Distribution From: H. Patrick Campbell, Chief Auitor HPC Telephone: !"0.#$#.99$1 Subject: Special %e&ie' of Purchasin( an )inancial Acti&ities %elatin( to the Propose Hartfor *unicipal +ffice ,uilin( As a result of an in-uir. 'e recei&e re(arin( the timin( of purchasin(/financial ata an reports relatin( to the propose Hartfor *unicipal +ffice ,uilin( 0H*+,1, 'e performe a special re&ie' of relate acti&ities. 2he follo'in( is a timeline of actions an acti&ities relatin( to the propose H*+,. 3o&ember 1, 2014 5n&itation to respon %)% 67 $4"4 for +ne 8o&ernment Center7 *unicipal +ffice ,uilin( 2his %e-uest for 9ualifications 0%)91 in&ites 9ualifie %esponents to submit proposals escribin( in etail their technical, mana(erial an financial -ualifications to esi(n, e&elop an structure financin(, an mana(e the operation of a municipal office builin(. 2he response ate an time is December 2, 2014 at 2700 p.m. 3o&ember 20, 2014 Section 27 Scope of :ork ; %e&ise 11/20/2014 +ne 8o&ernment Center7 *unicipal +ffice ,uilin( %e-uest for 9ualifications %)%6 $4"4 December 2, 2014 Proposal for the Cit. of Hartfor %)P 6< $4"4 +ne 8o&ernment Center *unicipal +ffice ,uilin( ; 8ilbane, =C= Architecture, C> Properties ??C Proposal to pro&ie Phase 1 ser&ices for the e&elopment, financin(, esi(n, construction an mana(ement of a *unicipal +ffice ,uilin( for the Cit. of Hartfor. December 1", 2014 %)9 6$4"4 Selection Committee %atin( )orm an )inal Selection December 1!, 2014 INTERDEPARTMENTAL MEMORANDUM A'ar letter to 8ilbane. 2he follo'in( terms an conitions are in the letter. 2his a'ar is contin(ent to @@+ Certification, taA status, final scopin(/pricin( an form of Contract. Do not initiate 'ork until a contract has been eAecute. )ebruar. ", 2014 )irst raft of contract. *arch 24, 2014 5n&oices for pa.ment submitte b. C> Properties ??C for B49#,000. Pai as follo's7 5n&oice 6"04 B1"$,""# Date *arch 24, 2014 Appro&e for Pa.ment April 4, 2014 Pai =une 2, 2014 5n&oice 6"0$ B1"$,""# Date April 1#, 2014 Appro&e for Pa.ment *a. 2!, 2014 Pai =une 2, 2014 5n&oice 6"0! B1"$,""" Date *a. ", 2014 Appro&e for Pa.ment *a. 2!, 2014 Pai Au(ust 1!, 2014 April 2014 H*+, Hartfor, C2 ; 2he Stu. of the Hartfor *unicipal +ffice ,uilin( >olume 1 C>, =C= Architecture, 8ilbane *a. 19, 2014 Contract Appro&al *a. 20, 2014 Contract @Aecution *a. 29, 2014 Purchase +rer 62014$21!C00, C> Properties ??C, B49#,000 for Architectural Ser&ices, Professional %e&ie' %esults 2 >arious tests of the abo&e transactions an ocumentation an re&ie's of relate operations isclose the follo'in(7 1. +ne in&oice totalin( B1"$,""# 'as appro&e for pa.ment b. Department of De&elopment Ser&ices mana(ement prior to the appro&al an eAecution of the contract. 5t shoul be note that all three pa.ments relatin( to this contract 'ere actuall. pai after the contract eAecution ate. 2. All three in&oices totalin( B49#,000 'ere appro&e for pa.ment b. Department of De&elopment Ser&ices mana(ement prior to the issuance of the relate purchase orer for the ser&ices pro&ie. 5t shoul be note that all three in&oices 'ere not actuall. pai until after the contract 'as eAecute. 4. 2he final &enorDs report H*+, Hartfor, C2 2he Stu. for the Hartfor *unicipal +ffice ,uilin( >olume 1 ate April 2014 'as issue prior to the appro&al an eAecution of the contract an purchase orer for relate ser&ices. 4. As note abo&e, the final &enorDs report 'as issue in April 2014 e&en thou(h the Procurement Ser&ices Enit a'ar letter inicate FDo not initiate 'ork until a contract has been eAecute.G 2he contract 'as not eAecute until *a. 29, 2014. Ser&ices shoul not be pro&ie b. &enors an in&oices shoul not be appro&e for pa.ment prior to the appro&al an eAecution of applicable contracts an purchase orers. :e recommen that Department of De&elopment Ser&ices mana(ement take action to ensure that contracts an purchase orers are appro&e an eAecute before an. ser&ices are pro&ie b. &enors an in&oices are appro&e for pa.ment in the future. :e re&ie'e this matter 'ith 2. Deller, Director, Department of De&elopment Ser&ices, 'ho informe us that he 'as not a'are that this occurre until 'e brou(ht it to his attention. 2. Deller also inicate an assure us that he has since establishe proceures an controls to pre&ent this from occurrin( in the future. Distribution7 Cit. Council *embers 5nternal Auit Commission *embers A. Clou, Cit. 2reasurer 2. Deller, Director, Department of De&elopment Ser&ices D. Hill, Chief +peratin( +fficer ?. A. %alls, Actin( Director, )inance Department P. Se(arra, *a.or 4