This weekly progress report summarizes the activities of an engineering student team working on a project to design and build a mousetrap vehicle. It details what each team member accomplished over the past week, including attending meetings, conducting research, drafting designs, and brainstorming criteria. Goals for the coming week are outlined for finalizing the vehicle design, drawing plans, and completing waste minimization plans and evaluation criteria. The report concludes with questions for the project managers and a checklist to identify any teamwork issues.
This weekly progress report summarizes the activities of an engineering student team working on a project to design and build a mousetrap vehicle. It details what each team member accomplished over the past week, including attending meetings, conducting research, drafting designs, and brainstorming criteria. Goals for the coming week are outlined for finalizing the vehicle design, drawing plans, and completing waste minimization plans and evaluation criteria. The report concludes with questions for the project managers and a checklist to identify any teamwork issues.
This weekly progress report summarizes the activities of an engineering student team working on a project to design and build a mousetrap vehicle. It details what each team member accomplished over the past week, including attending meetings, conducting research, drafting designs, and brainstorming criteria. Goals for the coming week are outlined for finalizing the vehicle design, drawing plans, and completing waste minimization plans and evaluation criteria. The report concludes with questions for the project managers and a checklist to identify any teamwork issues.
This weekly progress report summarizes the activities of an engineering student team working on a project to design and build a mousetrap vehicle. It details what each team member accomplished over the past week, including attending meetings, conducting research, drafting designs, and brainstorming criteria. Goals for the coming week are outlined for finalizing the vehicle design, drawing plans, and completing waste minimization plans and evaluation criteria. The report concludes with questions for the project managers and a checklist to identify any teamwork issues.
Engineering Foundations: Principles and Communications 100
Semester 2, 2013Weekly Progress Report
A copy of this report is to be uploaded prior to your project meeting and a printed copy presented to your manager in class.
WEEKLY PROGRESS REPORT
COMPANY NAME: ALDNOAH TECHNOLOGY DATE: 19/8/2014
ACTIVITY LOG:
Team Member: Ngu Leon Weiy Attend Group Meeting 1.0hr Done Learn Google Sketchup 1.0hr Done Draft Procedures for constructing mousetrap vehicle 2.0hr Done
Team Member: Lee Che Keat Attend Group Meeting 1.0hr Done Learn Google Sketchup 2.0hr Done Draft the design of the mousetrap vehicle 2.5hr Done Research on the information of the mousetrap vehicle 1.0hr Done
Team Member: Kelvin Lu J ack Lee Attend Group Meeting 1.0hr Done Do research on waste minimisation plan ( string and mousetrap) 2.0hr Done Brainstorm tender evaluation criteria 1.0hr Done
Team Member: Rebecca Wong Attend group meeting 1.0hr Done Learn Google SketchUp 1.0hr Done Draft the design of the mousetrap vehicle 0.5hr Done Research on the information of the mousetrap vehicle 0.5hr Done
Team Member: Kurniawan Koeswadi Attend Group Meeting 1.0hr Done Brainstorm waste minimisation plan for chopsticks and CD-rom 2.0hr Done Brainstorm tender evaluation criteria 1.5hr Done
Team Member: Mable Siaw Yiyee Attend Group Meeting 1.0hr Done Do research for waste minimisation plan ( balloon, MDF board and bottle cap) 2.0hr Done Brainstorm tender evaluation criteria 1.0hr Done
A-14 GOALS:A detailed list of what each team member is responsible for next week and when it will be done.
Team Member: Ngu Leon Weiy Finalize the procedures for constructing mousetrap vehicle 27 August Search for supplier of materials 23 August
Team Member: Lee Che Keat Finalize the design of the mousetrap vehicle 23 August Draw the mousetrap vehicle from front and rear views 24 August
Team Member: Kelvin Lu J ack Lee Finalize waste minimisation plan for string and mousetrap 27 August Finalize tender evaluation criteria 27 August
Team Member: Rebecca Wong Finalize the design of the mousetrap vehicle 24 August Draw the mousetrap vehicle from side views 22 August
Team Member: Kurniawan Koeswadi Finalize waste minimisation plan for chopsticks and CD-rom 27 August Finalize tender evaluation criteria 27 August
Team Member: Mable Siaw Yiyee Finalize waste minimisation plan for balloon, bottle cap and MDF board 27 August Finalize tender evaluation criteria 27 August
QUESTIONS FOR MANAGERS:
What if the solutions for waste minimisation plan cannot be found for certain materials? Do we need to provide places to buy the materials in the specification? Do we need to account the price of tools in our budget?
TEAMWORK DYNAMICS: Tick or highlight ALL the problems your team has had this week. Dont be afraid of doing this as every team has problems. Having a small professional disagreement now will avoid a massive argument later in the project.
Team member sick Team member not completing allocated tasks Imbalance in task allocations Non-responsive team member Team member trying to do all the work Team member having to do all the work Mismatch of expectations amongst team Mismatch of ambition amongst team members Team member unhappy with team performance Other