Professional Documents
Culture Documents
PDD 8MW Cabulig River Minihydroelectric Power Project
PDD 8MW Cabulig River Minihydroelectric Power Project
y
= Factor expressing the percentage of time when low-cost/must-run power
units are on the margin in year y
EG
m,y
= Net quantity of electricity generated and delivered to the grid by power unit
m in year y (MWh)
EG
k,y
Net quantity of electricity generated and delivered to the grid by power unit
k in year y (MWh)
EF
EL,m,y
= CO
2
emission factor of power unit m in year y (tCO
2
/MWh)
EF
EL,k,y
= CO
2
emission factor of power unit k in year y (tCO
2
/MWh)
m = All grid power units serving the grid in year y except low-cost/must-run
power units
k = All low-cost/must run grid power units serving the grid in year y
Y = The relevant year as per the data vintage chosen
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
17
2) Determination of EF
EL,m,y
There are three (3) options to determine the emission factor of each
power unit m. Option A2 is used. Under Option A2, the emission factor of each power unit is
resolved based on the CO
2
emission factor of the fuel type used and the efficiency of the power unit,
as follows:
(4)
Where,
EF
EL,m,y
= CO
2
emission factor of power unit m in year y (tCO
2
/MWh)
EF
CO2,m,i,y
= Average CO
2
emission factor of fuel type i used in power unit m in year y
(tCO
2
/GJ)
m,y
= Average net energy conversion efficiency of power unit m in year y (ratio)
m = All power units serving the grid in year y except low-cost/must-run power units
y = The relevant year as per the data vintage chosen
Build Margin (BM) Emission Factor
According to the Baseline Methodology, the Build Margin (BM) emissions factor is defined as the
generation-weighted average emission factor of a sample group of power units m that consists of either:
(1) the 5 most recently built power plants, or (2) the most recently built power plants accounting for 20%
of all power generation, whichever groups annual generation is greater. Power plants that are registered
as CDM projects are excluded from the sample group m.
To calculate the Build Margin, the most recently built power plants that account for 20% of the total
power generation in the Mindanao Grid is applied using the Ex-ante approach (Option 1 in the Tool to
calculate the emission factor for an electricity system, Ver. 2.0, page 15). For the first crediting period,
the Build Margin Emission Factor (EF
BM,y
) is calculated based on the most recent information available
on units already built (as of 2007) at the time of PDD submission for validation.
The formula applied to the selected sample is:
(5)
Where,
EF
grid,BM,y
= Build margin CO2 emission factor in year y (tCO2/MWh)
EG
m,y
= Net quantity of electricity generated and delivered to the grid by power unit m
in year y (MWh)
EF
EL,m,y
= CO
2
emission factor of power unit m in year y (tCO
2
/MWh)
m = Power units included in the build margin
y = Most recent historical year for which power generation data is available
Combined Margin (CM) Emission Factor
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
18
The combined margin emission factor is determined as follows:
(6)
Where,
EF
grid,CM,y
= Combined margin CO
2
emission factor in year y (tCO
2
/MWh)
EF
grid,OM,y
= Operating margin CO
2
emission factor in year y (t CO
2
/MWh) = EF
grid,OM-adj,y
EF
grid,BM,y
= Build margin CO
2
emission factor in year y (t CO
2
/MWh)
w
OM
= Weighting of operating margin emissions factor (%)
w
BM
= Weighting of build margin emissions factor (%)
The key information and data used in determining the baseline emissions are taken from the following
sources:
Since data of the amount of fuel consumed (in a mass or volume unit) by relevant power sources are
not available in the Philippines, it has to be established indirectly by calculating it from electricity
produced and assuming realistic net energy conversion (NEC) efficiencies;
As plant-specific efficiency data is not publicly available, the net energy conversion (NEC)
efficiencies or default efficiency factors for power plants are adopted from Annex 1 of the Tool to
calculate the emission factor for an electricity system, Version 2, EB 50, page 25.
Information on the cohort of plants in the Mindanao Grid and their respective annual net electricity
generation (MWh) for the last 3 years is provided by the National Power Corporation, TRANSCO,
and the Philippine Department of Energy (PDoE). Information on capacity additions to the grid over
the most recent years is obtained from the Power Planning Department of the PDoE;
Mindanao system load data from 2005 2007 is provided by the Systems Operations Department of
the National Transmission Corporation (TRANSCO);
CO
2
emission factors for the various fuel types used by power plants connected to the Mindanao grid
are taken from the 2006 IPCC Guidelines for National Greenhouse Gas Inventories, using the
lower limit values at 95% confidence interval.
B.6.2. Data and parameters that are available at validation:
Data / Parameter: Carbon Emission Factor (CEF
electricity,y
)
Data unit: Tons of CO
2
/MWh
Description: CO
2
emissions intensity of the electricity displaced
Source of data used: Official statistics. Department of Energy
Value applied: 0.6489
Justification of the
choice of data or
description of
measurement methods
and procedures
actually applied :
The CEF
electricity,y
is calculated according to the equations given in the Tool to
calculate the emission factor for an electricity system, Ver. 2.0, based on fuel
consumption and electricity generation data for plants connected to the grid,
provided by Philippine Official Statistics.
Any comment: CEF calculation approach is described in Section B.6.3 on Ex-ante calculation
of emission reductions. Additional data is provided in Annex 3 on Baseline
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
19
Information.
B.6.3 Ex-ante calculation of emission reductions:
The ex-ante emission reductions values and calculations are given in Table 8. Details of the calculations
are provided in Annex 3.
Table 8. Summary of emission reductions calculations.
Parameter Formula Value Unit
EF
grid,OM-adj,y
Eqs. 2 & 3 provided in Section B.6.1 0.6651 tCO
2
e/MWh
EF
grid,BM,y
Eq. 4 provided in Section B.6.1 0.6328 tCO
2
e/MWh
EF
grid, y
Eq. 5 provided in Section B.6.1 0.6489 tCO
2
e/MWh
ER
y
Eq. 1 provided in Section B.6.1 31,962 tCO
2
e
B.6.4 Summary of the ex-ante estimation of emission reductions:
Table 9. Ex ante emission reduction estimations for first 7-year crediting period.
Year
18
Estimation of
project activity
emissions
(tons of CO
2
e)
Estimation of
baseline
emissions (tons of
CO
2
e)
Estimation of
leakage
(tons of CO
2
e)
Estimation of
overall emission
reductions
(tons of CO
2
e)
2011 0 21,308 0 21,308
2012 0 31,962 0 31,962
2013 0 31,962 0 31,962
2014 0 31,962 0 31,962
2015 0 31,962 0 31,962
2016 0 31,962 0 31,962
2017 0 31,962 0 31,962
2018 0 10,654 0 10,654
Total 0 223,736 0 223,736
B.7 Application of a monitoring methodology and description of the monitoring plan:
B.7.1 Data and parameters monitored:
Data / Parameter: EG
y
Data unit: MWh
Description: Net Electricity supplied by the project activity to the grid
Source of data to be used: Mindanao Energy Systems, Inc.
Value of data 49,253
Description of
measurement methods
and procedures to be
Hourly measurement and monthly recording of net electricity supplied to the
grid.
18
For the Project the year will run from 1 May to 30 April, the first year of the first crediting period being 1May 2011 30
April 2012, and the last year of the first crediting period being 1May 2017 30 April 2018.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
20
applied:
QA/QC procedures to be
applied:
Electricity supply will be monitored and double checked by means of
electricity sales receipts.
Any comment: Electricity figure is ex-ante estimate; actual production will be monitored.
Data / Parameter: A
PJ
Data unit: m
2
Description: Area of the reservoir measured in the surface of the water, after the
implementation of the project activity, when the reservoir is full
Source of data to be used: Mindanao Energy Systems, Inc.
Value of data 67,000
Description of
measurement methods
and procedures to be
applied:
Measured from topographical surveys, maps, satellite pictures, etc.
QA/QC procedures to be
applied:
Reservoir area will be monitored on a yearly basis.
Any comment: --
Data / Parameter: Cap
PJ
Data unit: kW
Description: Installed capacity of the hydro power plant after the implementation of the
project activity
Source of data to be used: MINERGY Project Site
Description of
measurement methods
and procedures to be
applied:
Determine the installed capacity based on recognized standards
QA/QC procedures to be
applied:
--
Monitoring frequency: Yearly
Any comment: Per reference to ACM 0002 by AMS I.D.; this parameter is included as it is
used to calculate power density as a function of the capacity of generation
divided by the reservoir area, with the result noted on page 7 as a power
density of 119 W/ m
2
, accordingly, well above the threshold of 4 W/ m
2
,
The project, as designed, is 8 MW installed capacity but at the time of
validation project procurement has not yet occurred; thus the exact
turbine/generator rating is not known ex-ante but will be approximately
8MW within recognized standards which would in no event reduce the
power density of the project below the 4 W/ m
2
threshold.
B.7.2 Description of the monitoring plan:
The monitoring methodology follows the AMS I.D. (V. 15, EB 50, October 2009) definition, which
states: The monitoring shall consist of metering the electricity generated by the renewable energy
technology. However, for more accuracy and to be consistent with the Tool to calculate the emission
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
21
factor for an electricity system, Ver. 2.0 the emission factor will be calculated ex-ante and will remain
fixed for the first 7-year crediting period.
No special monitoring equipment is needed. Endesa Carbono will provide Minergy with a Monitoring
Plan and pre-programmed spreadsheets such that the Project sponsor will only need to collect the
information as described and apply the formulas as instructed in the Monitoring Plan. TRANSCO and
the PDoE will be the data providers for the annual ex-ante calculation of the Projects ERs. The
designated project staff will confirm these data with their own records, which they will cross check with
sales receipts.
All data collected as part of the monitoring will be archived at least for 2 years after the end of the last
crediting period.
The integrity and credibility of the electric meters shall be overseen and guaranteed by the Energy
Regulatory Commission (ERC) under the guidelines stipulated in Chapter 9 (Grid Revenue Metering
Requirements)
19
of the Philippine Grid Code of 2001.
B.8 Date of completion of the application of the baseline and monitoring methodology and the
name of the responsible person(s)/entity(ies)
The Baseline and monitoring methodology were completed on March 23, 2010 by:
Francisco Fernndez-Asn
Endesa Carbono
E-mail: francisco.asin@endesacarbono.com
Website: www.endesacarbono.com
Endesa Carbono is not a participant of the project.
SECTIO C. Duration of the project activity / crediting period
C.1 Duration of the project activity:
C.1.1. Starting date of the project activity:
11/06/2009
C.1.2. Expected operational lifetime of the project activity:
The Project is expected to have an operational lifetime of 30 years.
19
http://www.doe.gov.ph/Downloads/Final_Grid_Code.pdf
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
22
C.2 Choice of the crediting period and related information:
C.2.1. Renewable crediting period
C.2.1.1. Starting date of the first crediting period:
5/1/11 (May 1, 2011) or the date of registration with the EB, whichever is latest
C.2.1.2. Length of the first crediting period:
Seven (7) years with the option of two renewal periods.
C.2.2. Fixed crediting period:
C.2.2.1. Starting date:
N/A
C.2.2.2. Length:
N/A
SECTIO D. Environmental impacts
D.1. If required by the host Party, documentation on the analysis of the environmental impacts
of the project activity:
An Environmental Impact Assessment (EIA) Study conducted in March 2006 provided a comprehensive
assessment of the projects environmental and socio-economic impacts. The report also identified the
environmentally critical issues and the corresponding measures adopted by the Project Developer. The
results are summarized in the table below.
Table 10. Summary of Environmental Impacts and Mitigation Measures
Environmental
Parameters /
Issues
Impact Description Mitigation measures
Impacts during Construction
Surface
hydrology
High
Fluctuation in river
discharge between the
intake and the tailrace;
changes in river
morphology by increased
erosion and sedimentation.
Ensure minimum ecological
flow downstream of the river
diversion.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
23
Natural hazards High Erosion and slope instability
resulting from removal of
vegetation due to
construction of access roads
and related infrastructure.
Strict compliance to codes of
practice in road construction;
apply landslide mitigation
measures.
Soil and water
quality
Low to
Moderate
Contamination of soil and
water resulting from
construction waste material
such as chemicals, oil, and
other solid waste.
Implement best practice in
hazardous and solid waste
management; identify different
types of solid and liquid wastes
from construction activities and
ensure proper treatment of waste
material to prevent pollution.
Environmental Impacts
Flooding Low Reservoir inundation and
sedimentation
Proper site selection and design
of the intake; implement proper
maintenance of dam and weir
Aquatic Biota Low Changes in fish population
and habitat downstream that
could result from modifying
the natural flow of water.
Maintain good water quality and
provide for minimum ecological
flow of water (not less than
0.41m
3
/s).
Terrestrial
Wildlife and
Vegetation
Low Loss of terrestrial and
wetland habitats and
resources
Preservation of natural forest,
promote vegetation and erosion
control
Socio-Economic Impacts
Land ownership Low Right-of-way (ROW) during
construction of the project
and its access roads.
Conform to government policies
on land acquisition and provide
compensation for any
disruptions or disturbances that
may result from the
implementation of the Project.
Resettlement Moderate Possible influx of people
resulting from increased
opportunities for
employment and creation of
access roads
Accommodate qualified
personnel with priority given to
the Indigenous People
community and local residents
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
24
D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
Environmental law in the Philippines requires all projects to prepare an Environmental Impact
Statement
20
(EIS) Study for the Department of the Environment and Natural Resources (DENR) before
an approval and an Environment Compliance Certificate (ECC) could be issued. However, according to
a Memorandum of Agreement signed between DENR and Department of Energy (DOE), mini-hydro
projects with rated capacities between 1 to 10 megawatts, or with less than twenty (20) million cu. m.
water impoundment, need not secure an EIS but instead, submit an Initial Environmental Examination
(IEE), which is a simplified version of an EIS
21
.
Rather than fulfilling the minimum requirement of presenting an IEE, the project developer sought to
fully comply with the EIS system by submitting a credible environmental impact assessment (EIA) due to
the environmental sensitivity of the project. Some of the conclusions that can be drawn from the EIA are
as follows:
Although the overall rating on environmental and social impact is low to moderate, the Project is still
considered to be environmentally sound and socially acceptable;
During construction, there will likely be environmental impacts resulting from civil works, use of
heavy machinery, and increased human activity which could result to adverse changes in the
environment and induce natural hazards such as erosion and landslides;
During construction and operation, there will likely be impacts due to solid and liquid waste
disposal;
There is a perceived social impact from in-migration or influx of people from neighboring towns or
municipalities as a result of employment opportunities being offered by the project activity that could
stir up undue competition and unrest between local residents and immigrant workers.
In general, the proposed projects impacts do not detrimentally affect environmentally sensitive areas.
The Project Developer has given due consideration to all possible adverse environmental and social
impacts of the Project and has committed to adopt mitigation measures as well as implement an
Environmental Management program involving the following plans, which will be monitored throughout
the construction, operation, and abandonment phases of the project:
Reforestation Plan: Every tree cut or removed due to construction activity will have to be
compensated for by planting a replacement tree. A management plan for clearing of vegetation
and reforestation will be prepared. The plan shall establish the protection of vegetation along the
river banks and its environs. Cutting of hardwood species will be avoided as much as possible,
and these trees will have to be clearly identified prior to initiation of construction activities.
20
http:// www.emb.gov.ph/laws/environmental%20impact%20assessment/PD%201586.doc
21
http://www.doe.gov.ph/pecr2005/petroleum/PETROLEUM%20jpg/4.0%20FISCAL-
LEGAL/4.2%20LAWS%20AD%20ISSUACES/4.2b%20LAWS_CIRCULARS/4.2b.13%20%20PD1586.pdf
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
25
Watershed Management and Protection Plan: Includes activities such as reforestation,
bamboo planting, agroforestry, assisted natural regeneration, erosion control and protection
system especially for significant flora and fauna in the area.
Construction/contractors Environmental Program: Implement careful engineering, planning,
and supervision program to ensure proper management of excavation materials, river and
drainage crossings, and reduction of nuisances such as dust, noise, and traffic.
Social Development Plan: Includes programs for education, environmental, health, labor and
infrastructure development of the community
Disaster Preparedness Plan: Covers the installation of a flood warning device that would be
activated during abnormally high flows; and a
Monitoring Plan: Proper implementation of the mitigation measures and enhancement plan
mentioned earlier. The plan will cover the different phases of the project from construction to
operation and maintenance.
In accordance with Presidential Decree No. 1586 and Department Administrative Order No. 2003-30, an
Environmental Impact Statement was submitted to the Department of Environment and Natural
Resources Region 10 office in Macabalan, Cagayan de Oro City on March 2006. An Environmental
Compliance Certificate [ECC 10(43)08 01-22 4596-4010] was subsequently issued on 22 January 2008.
The ECC signifies that the project has given careful consideration to its environmental impacts and that
due mitigation measures will be carried out in effect.
SECTIO E. Stakeholders comments
E.1. Brief description how comments by local stakeholders have been invited and compiled:
Documents provided by the Project Developer reveal that the stakeholders process was initiated around
September 2005 with the Project Developer conferring with representatives of the host community
(Baranggay Plaridel) to endorse and allow the development of the hydropower resource along the
Cabulig River for power generation. Coordination and consultations continued during the conduct of the
Environmental Impact Assessment (EIA) in 2006.
The stakeholder process involved not only the communities surrounding the Project but also the
indigenous cultural communities in the area and the National Commission on Indigenous Peoples
(NCIP), which is responsible in enforcing the Indigenous Peoples Right Act (IPRA)
22
. The Indigenous
Peoples Reform Act (IPRA) requires that a Free and Prior Informed Consent (FPIC) from the local tribal
leaders be secured before an endorsement from the NCIP can be issued. A certificate of FPIC signifies
the consensus of all members of the indigenous peoples community in accordance with their respective
customary laws and practices, given freely without any external manipulation, coercion and in a process
and language understandable to the community. In order to obtain the FPIC, coordination with the NCIP
for all stakeholder consultations was undertaken as follows:
Table 11. Summary of consultative meetings for the 8 MW Cabulig River Mini-hydro Power Project.
Date/Venue Activity Scope/Agenda Attendees / Composition
22
http://www.sipo.gov.cn/sipo/ztxx/yczyhctzsbh/zlk/gglf/200509/P020060403599030158748.pdf
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
26
07 May 2007
CEPALCO
Office, Cagayan
de Oro City
(CDO)
Pre-FPIC
Conference
Pre-consultative meeting Conference to
discuss matters relating to Minergys
application for hydro power plant located at
Plaridel, Claveria, Misamis Oriental.
16 persons / IP
representatives, Natl
Commission on Indigenous
People Free & Prior
Informed Consent (NCIP-
FPIC) Team, Project
Developer
21-22 May
2007 Plaridel
Tribal Hall,
Plaridel,
Claveria
Community
consultative
assembly
Consultative meeting Presentation of
proposed hydropower project, its socio-
economic benefits, and mitigation measures
by the project developer as mandated by the
Indigenous Peoples Republic Act (IPRA)
Law.
21 persons / Community
Consultative Assembly,
NCIP Team, and the Project
Developer
23-24 May
2007 Plaridel
Tribal Hall,
Plaridel,
Claveria
Consensus
building
Consultative meeting Consensus
building on the project sponsors
responsibilities and commitments as well as
the individual and community demands of
the stakeholders.
Community Consultative
Assembly, NCIP Team, and
the Project Developer
08 Jun 2007
Dynasty Court
Hotel, CDO
Decision
meeting
Consultative meeting Project developers
response to demands of stakeholders and
drafting of Memorandum of Agreement
(MOA).
21 persons / IP Community
representatives, NCIP Team,
and the Project Developer
06 Aug 2007 &
10 Aug 2007
Dynasty Court
Hotel, CDO
Consultative meeting Forum for
stakeholders and project developer to
provide comments to the draft MOA.
IP Community
representatives, NCIP Team,
and the Project Developer
15 Aug 2007
Grand Caprice,
Limketkai,
CDO
MOA
signing
Consultative meeting MOA signing
61 persons / IP Community
representatives, NCIP Team,
and the Project Developer
The Memorandum of Agreement between the proponent and the IP community covers the results of all
the consultative meetings conducted. The MOA between the indigenous peoples group, the NCIP and
the proponent is proof that due account was taken in response to the issues and concerns raised during
the consultative meetings.
E.2. Summary of the comments received:
In the course of the consultation meetings conducted with the stakeholders, some concerns were raised
regarding the Project:
Possible impacts of water level rise to the plants along the river banks
Land titling and ancestral domain
Livelihood and employment opportunities for local residents, particularly the IP community
Supply of basic services such as water, electricity, education and health services
Infrastructure and road access
Emergency preparedness measures
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
27
The following comments summarize the issues and concerns raised by the local community during the
consultation activities:
Table 12. Summary of stakeholder comments.
Issues and Concerns Proponents Response
On the nature of assistance and benefits
CEPALCO could provide with regards to the
ancestral domain process
The project developer will provide all social and
economic benefits covered under Republic Act
8371 (the Indigenous Peoples Right Act). The
project developer recognizes the rights of the
Indigenous Peoples (IPs) to their Ancestral
Domain and has requested to conduct further
consultative meetings with the NCIP to ensure the
realization of these rights and corresponding
benefits, subject to the provisions and limitations
defined in the IPRA Law.
On the issue regarding methods of assessment and
valuation in case of crop damage
The assessment of crop damage as a direct or
indirect result of the project will be based on an
economic valuation scheme currently being
adopted by the local government.
On the request regarding special assessment and
valuation for primary crops such as coconut and
banana
The local government will also take into account
asset losses, income reduction and reconstruction
costs during the damage assessment for these
staple crops. Subject to provisions and limitations
under the IPRA law, this would result to a higher
compensation compared to its original assessed
value for the affected landowners.
On the nature of assistance the project developer
could provide to land owners directly or indirectly
affected by the project, e.g. areas affected by
increase in water level or inundation attributed to
dam construction
Environmental mitigation measures will be
strictly enforced to ensure the well-being of the
affected communities. Financial assistance and
just compensation will also be provided by the
project developer.
On the issue of compensation to owners whose
lots are occupied by CEPALCOs transmission
line posts
Lot owners will be recompensed or their lots
leased.
On the nature of assistance and benefits
MINERGY could provide with regards to the
ancestral domain process
In terms of financial assistance to facilitate the
conduct of the social preparation, MINERGY has
committed to provide 100,000 pesos as a
counterpart contribution.
On the issue of crop damage as a result of hazards
brought about by the project
Aside from the strict implementation of mitigation
measures to minimize natural hazards, MINERGY
is committed to pay for crop damages that are
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
28
directly or indirectly attributed to the project,
subject to provisions and limitations of the IPRA
law.
On the issue of educational assistance
The project developer will provide educational
benefits and related financial assistance to
qualified dependents from the IP community.
On the issue of medical assistance and health
program
In cases of emergency, IP community
beneficiaries can avail of the clinical facility and
services provided by MINERGY for its workers
during construction period. The project developer
will also establish a health program for the benefit
of the IP community.
On the suggestion to include the Tribal Chieftain
in the committee in charge of hiring people for the
company to give priority to IPs in the area
This suggestion is duly noted and will be strongly
considered by the project developer. The project
developer is fully commited to help promote
social and economic well-being by initiating and
facilitating new livelihood and energy project
proposals to the Department of Energy (DOE) and
NCIP on behalf of the IP community.
Taking into account all the comments received, the local government, IP communities and the NCIP
expressed their overall support to the implementation of the Project.
E.3. Report on how due account was taken of any comments received:
All the comments and requests received in the course of conducting the stakeholder consultations were
duly noted. These served as the basis for the provisions contained within the Memorandum of
Agreement between the proponents and the people of Plaridel and Claveria. Listed below are the
documents to signify how due account was taken of the comments received:
FPIC report dated November 5, 2007
NCIP Provincial Officer endorsement of CEPALCO/MINERGY FPIC Report to the NCIP
Regional Director dated November 9, 2007
NCIP Regional Director endorsement of CEPALCO/MINERGY FPIC Report to the NCIP
Central Office dated March 31, 2008
Certification from the Local Government Unit of Claveria recognizing implications of the
CEPALCO project issued on April 18, 2007 at Claveria, Misamis Oriental signed by Mayor Paul
Douglas Calingin
Certification from the Local Government Unit of Jasaan recognizing implications of the
CEPALCO project issued on March 29, 2007 at Jasaan, Misamis Oriental signed by Mayor
Redentor Jardin
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
29
Resolution from the Barangay of Plaridel (Resolution No. 08S-2008) allowing MINERGY to
develop the mini-hydro project along the Cabulig River
Resolution from the Town of Claveria (Resolution Nos. 108 & 109) endorsing the development
and implementation of the proposed mini-hydro project along the Cabulig River
NCIP Certificate of Compliance issued on June 30, 2008
Memorandum of Agreement issued on August 30, 2007
Documentation of proceedings of all consultation meetings conducted (minutes, photos,
attendance)
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
30
Annex 1
COTACT IFORMATIO O PARTICIPATS I THE PROJECT ACTIVITY
Organization: Mindanao Energy Systems, Inc.
Street/P.O.Box: Emerald Avenue
Building: 8F Strata 100 Building
City: Ortigas Complex, Pasig City
State/Region: Metro Manila
Postfix/ZIP:
Country: Philippines
Telephone: +6326311581
FAX: +6326348149
E-Mail:
URL:
Represented by: William U. Lim
Title: Senior Vice-President
Salutation: Mr.
Last Name: Lim
Middle Name: U.
First Name: William
Department:
Mobile:
Direct FAX:
Direct tel:
Personal E-Mail: wulminergy@cepalco.com.ph
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
31
Annex 2
IFORMATIO REGARDIG PUBLIC FUDIG
The Project has not received any type of public funding or public financial help.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
32
Annex 3
BASELIE IFORMATIO
According to the latest version of the AMS I.D. methodology (V. 15, EB 50, October 2009), for a system
where not all generators use exclusively fuel oil and/or diesel fuel, the baseline is described as the kWh
produced by the renewable generating unit multiplied by an emission coefficient (measured in kg
CO2e/kWh) calculated in a transparent and conservative manner as:
(a) A combined margin (CM) consisting of the average of the operating margin (OM) and the
build margin (BM), according to the procedures prescribed in the Tool to calculate the
emission factor for an electricity system, Ver. 2.0 or,
(b) The weighted average emissions (in kg CO2e/kWh) of the current generation mix, wherein
data of the year in which project generation occurs must be used.
The combined margin approach (Option A) is chosen. The estimated anthropogenic emissions were
calculated for the Project, applying the following 6-step process:
Step 1 Identify the relevant electricity systems.
Step 2 Choose whether to include off-grid power plants in the project electricity system (optional).
Step 3 Selection of Method to determine the Operating Margin.
Step 4 Calculation of the Operating Margin (OM) emission factor according to selected method.
Step 5 Identify the group of power units to be included in the build margin (BM).
Step 6 Calculation of the Build Margin (BM) emission factor.
Step 7 Calculation of the Combined Margin (CM) emission factor.
Step 1 Identify the relevant electric power system.
According to the Philippine Grid Code
23
, there are 3 national grids in the country: Luzon, Visayas and
Mindanao grids. The Luzon and Visayas Grids are physically linked by a submarine cable. The
Mindanao Grid remains to be isolated from the 2 other grids and, therefore, electricity is neither exported
nor imported to and from the island
24
.
The project is located in the province of Misamis Oriental in Mindanao Island. The spatial extent of the
project boundary includes the project site and all power plants physically connected to the Mindanao
Grid. Therefore, the emission factors which would be determined shall be applicable for the Mindanao
Grid.
Step 2 Choose whether to include off-grid power plants in the project electricity system
This step is optional and allows project participants to calculate the operating margin and build margin
emission factors by considering only grid power plants in the calculations (Option I) or by considering
both grid power plants and off-grid power plants in the calculations (Option II). The OM and BM
23
http://www.doe.gov.ph/Downloads/Final_Grid_Code.pdf , page 121
24
http://www.ngcp.ph/gridmap/2k6gridmap.pdf
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
33
emission factors will therefore be calculated based on data from grid-connected power plants only
(Option I).
Step 3 Selection of Method to determine the Operating Margin (OM)
Any of the four procedures to calculate the OM can be chosen, but the restrictions in using the Simple
OM and the Average OM methods were taken into account.
As explained in Section B.6.1., the Simple Adjusted Operating Margin method was selected out of the
four options for the OM because it constitutes the only methodological choice for which data is available
for the Project. The Dispatch Data Analysis OM cannot be applied because detailed dispatch data is not
publicly available. The Simple OM method cannot be used since low cost, must-run resources constitute
more than 50% of total grid generation in Mindanao (see Table A3-1)
Table A3-1. Mindanao Grid Power Generation by Source from 2003 to 2007.
2003 2004 2005 2006 2007
Oil based 1,713,692 1,915,799 2,319,927 1,671,619 1,478,868
Natural gas - - - - -
Coal - - - 476,245 1,570,872
Hydro 3,989,013 4,261,525 4,028,352 4,419,049 3,971,927
Geothermal 861,016 909,815 892,863 845,660 867,308
Solar - - 1,517 1,376 1,309
Wind - - - - -
total 6,563,721 7,087,139 7,242,659 7,413,949 7,890,284
Total LC/MR 4,850,029 5,171,340 4,922,732 5,266,085 4,840,544
% LC/MR 73.89% 72.97% 67.97% 71.03% 61.35%
Data supplied by the DOE in Philippines
Mindanao Total Energy Generation (MWh)
In terms of data vintage, the Ex-ante option is chosen, i.e. a 3-year generation-weighted average, based on
the most recent data available at the time of submission of the CDM-PDD to the DOE for validation,
without requirement to monitor and recalculate the emissions factor during the first crediting period.
Step 4 Calculation of the Operating Margin (OM) emission factor according to selected method
As explained in Section B.6.1, the Simple Adjusted OM approach is selected, following the ex-ante
option. The simple adjusted OM is calculated as the generation-weighted average CO
2
emissions per unit
net electricity generation (tCO
2
/MWh) of all generating power plants serving the system based on the net
electricity generation and a CO
2
emission factor of each power unit and where the power plants / units
are separated in low-cost/must-run power sources and other power sources (Equation 3). A 3-year data
vintage from 2005 to 2007 is used to determine the Lambda,
y
, in Equation 3, calculated as follows:
y
= (7)
Step 4-1a. Plot a Load Duration Curve
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
34
Collect chronological load data (typically in MW) for each hour of the year y, and sort the load
data from the highest to the lowest MW level. Plot MW against no. of hours in the year, in
descending order.
2005 Mindanao Grid System Load
-
200
400
600
800
1,000
1,200
1,400
1 1001 2001 3001 4001 5001 6001 7001 8001
Hours
M
W
Load curve
Figure A3-1. 2005 load duration curve for the Mindanao grid.
2006 Mindanao Grid System Load
-
200
400
600
800
1,000
1,200
1,400
1 1001 2001 3001 4001 5001 6001 7001 8001
Hours
M
W
Load curve
Figure A3-2. 2006 load duration curve for the Mindanao grid.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
35
2007 Mindanao Grid System Load
-
200
400
600
800
1,000
1,200
1,400
1 1001 2001 3001 4001 5001 6001 7001 8001
Hours
M
W
Load curve
Figure A3-3. 2007 load duration curve for the Mindanao grid.
Step 4-1b. Collect power generation data from each power plant/unit
Calculate the total annual generation (in MWh) from low-cost/must-run power plants (i.e.
k
EG
k,y
).
Table A3-2. Annual net electricity generation of all power plants connected to the Mindanao Grid.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
36
2005 2006 2007
Source
Net Electricity
Generation
Net Electricity
Generation
Net Electricity
Generation
MWh MWh MWh MWh
COAL - 432,898 1,409,947 1,842,845
1 Mindanao Coal NPC - 432,898 1,409,947 1,842,845
OIL-BASED 2,146,328 1,535,456 1,340,816 5,022,600
2 PB104 NPC 8,720 59,804 66,306 134,830
3 Gen Santos (SPPC) NPC 244,380 192,635 174,933 611,948
4 Western Mindanao Power Corp. NPC 401,229 224,667 157,146 783,043
5 Mindanao Energy Systems PDOE 771 845 385 2,001
6 Cotabato Light PDOE 155 242 93 491
7 Davao Light PDOE 1,401 1,699 4,445 7,545
8 Power Barge 117 NPC 629,006 490,024 402,607 1,521,637
9 Power Barge 118 NPC 676,179 528,054 497,945 1,702,179
10 NMPC II NPC 120,037 5,205 - 125,242
11 NMPC I (Iligan Diesel Plant) NPC 64,450 32,282 36,953 133,685
GEOTHERMAL 844,460 802,872 824,717 2,472,049
12 Mindanao I (Mt. Apo) NPC 423,174 396,507 413,398 1,233,079
13 Mindanao II (Mt. Apo) NPC 421,286 406,365 411,319 1,238,970
HYDRO 4,011,354 4,401,620 3,954,714 12,367,689
14 Agus 1 Unit 1 & 2 NPC 258,769 295,548 267,307 821,624
15 Agus 2 NPC 683,289 740,343 607,706 2,031,337
16 Agus 4 NPC 753,332 817,941 713,740 2,285,013
17 Agus 5 NPC 280,905 299,142 248,550 828,597
18 Agus 6 NPC 1,028,414 1,122,358 969,405 3,120,176
19 Agus 7 NPC 209,780 229,990 192,413 632,183
20 Agusan NPC 1,582 - - 1,582
21 Pulangi 4 NPC 747,492 844,948 905,061 2,497,501
22 Bubunawan PDOE 24,523 24,474 22,215 71,212
23 Talomo HEPP PDOE 23,270 26,876 28,317 78,463
SOLAR 1,517 1,376 1,309 4,202
24 Solar Photovoltaic PDOE 1,517 1,376 1,309 4,202
TOTAL Mindanao 7,003,659 7,174,223 7,531,503 21,709,385
TOTAL Low Cost / Must Run 4,857,331 5,205,869 4,780,740 14,843,940
TOTAL NOT LC/ MR 2,146,328 1,968,354 2,750,763 6,865,445
*Note: NPC - National Power Corporation, PDOE - Philippine Department of Energy
Power Plant
Total Generation
(2005-2007)
As hydro, geothermal and solar power sources are considered to be low cost / must run (shaded
blue in Table 3-2), total generation from these plants for 2005, 2006, and 2007 are 4,857,331
MWh, 5,205,869 MWh, and 4,780,740 MWh, respectively. The total generation from these
plants from 2005 to 2007 amount to 14,843,940 MWh.
Step 4-1c. Fill load duration curve
Plot a horizontal line across the load duration curve such that the area under the curve (MW
times hours) equals the total generation (in MWh) from lowcost/must-run power plants/units
(i.e.
k
EG
k,y
).
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
37
2005 Mindanao Grid System Load
-
200
400
600
800
1,000
1,200
1 1001 2001 3001 4001 5001 6001 7001 8001
Hours
M
W
Load curve
LC/MR curve
Figure A3-4. Fill curve (horizontal line) with low-cost/must-run generation (MWh) for 2005.
2006 Mindanao Grid System Load
-
200
400
600
800
1,000
1,200
1 1001 2001 3001 4001 5001 6001 7001 8001
Hours
M
W
Load curve
LC/MR curve
Figure A3-5. Fill curve (horizontal line) with low-cost/must-run generation (MWh) for 2006.
2007 Mindanao Grid System Load
-
200
400
600
800
1,000
1,200
1 1001 2001 3001 4001 5001 6001 7001 8001
Hours
M
W
Load curve
LC/MR curve
Figure A3-6. Fill curve (horizontal line) with low-cost/must-run generation (MWh) for 2007.
Step 4-1d. Determine the number of hours for which low-cost/must-run sources are on the
margin in year y.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
38
First, locate the intersection of the horizontal line plotted in Step (iii) and the load duration curve
plotted in Step (i). The number of hours (out of the total of 8760 hours) to the right of the
intersection is the number of hours for which low-cost/must-run sources are on the margin. If the
lines do not intersect, then one may conclude that low-cost/must-run sources do not appear on the
margin and y is equal to zero. Lambda (
y
) is then calculated by using Equation 7.
Lambda (
y
)
2005 2006 2007
0.0040 0.0191 0.0023
Lambda (
y
)
AVE
= 0.0084
The next step is to calculate the Simple Adjusted OM emission factor using Equation 3. In the Mindanao
grid, low-cost/must-run power sources k constitute hydro, geothermal, and solar resources, wherein
emissions from these sources are considered zero. Thus, Eq. 3 is further simplified into:
(8)
Table A3-3 below illustrates how the OM emission factor for the Mindanao grid is computed.
Table A3-3. Calculations to determine Operating Margin power plants.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
39
Source
MWh % TJ/GWh TJ tCO2/TJ tCO2
1 Mindanao Coal NPC 1,842,845 39.0% 3.60 17,010.88 89.5 1,522,473
2 PB104 NPC 134,830 39.0% 3.60 1,244.59 72.6 90,357
3 Gen Santos (SPPC) NPC 611,948 37.5% 3.60 169.99 72.6 12,341
4 Western Mindanao Power Corp. NPC 783,043 37.5% 3.60 7,517.21 72.6 545,749
5 Mindanao Energy Systems PDOE 2,001 37.5% 3.60 19.21 72.6 1,395
6 Cotabato Light PDOE 491 37.5% 3.60 4.71 72.6 342
7 Davao Light PDOE 7,545 37.5% 3.60 72.43 72.6 5,258
8 Power Barge 117 NPC 1,521,637 37.5% 3.60 14,607.71 72.6 1,060,520
9 Power Barge 118 NPC 1,702,179 37.5% 3.60 16,340.91 72.6 1,186,350
10 NMPC II NPC 125,242 37.5% 3.60 1,202.33 72.6 87,289
11 NMPC I (Iligan Diesel Plant) NPC 133,685 37.5% 3.60 1,283.38 72.6 93,173
12 Mindanao I (Mt. Apo) NPC 1,233,079 - - -
13 Mindanao II (Mt. Apo) NPC 1,238,970 - - -
14 Agus 1 Unit 1 & 2 NPC 821,624 - - -
15 Agus 2 NPC 2,031,337 - - -
16 Agus 4 NPC 2,285,013 - - -
17 Agus 5 NPC 828,597 - - -
18 Agus 6 NPC 3,120,176 - - -
19 Agus 7 NPC 632,183 - - -
20 Agusan NPC 1,582 - - -
21 Pulangi 4 NPC 2,497,501 - - -
22 Bubunawan PDOE 71,212 - - -
23 Talomo HEPP PDOE 78,463 - - -
24 Solar Photovoltaic PDOE 4,202 - - -
TOTAL Mindanao 21,709,385 4,605,248
TOTAL Low Cost / Must Run 14,843,940
TOTAL NOT LC/ MR 6,865,445
* Note: NPC - National Power Corporation, PDOE - Philippine Department of Energy
** Efficiencies are Default efficiency factors for power plants (Annex 1) in Tool to calculate the emission factor for an electricity system_V2
*** CO2 emission factors taken from Table 2.2 of Chapter 2 of Vol. 2 (Energy) of the 2006 IPCC Guidelines on National GHG Inventories
using the lower limits of the 95% confidence intervals for diesel and sub-bituminous coal
CO2 Emissions
Power Plant
Total Generation
(2005-2007)
Plant
Efficiency**
Conversion
Factor
Fuel
Consumption
CO2 Emission
Factor of fuel***
Applying the Lambda (
y
)
AVE
of 0.0084 to Eq. 8, the Simple Adjusted OM emission factor results to:
EF
grid,OM-adj,y
= (1- 0.0084) x 0.6708 tCO
2
e/MWh
= 0.6651 tCO
2
e/MWh
Step 5 Identify the group of power units to be included in the build margin (BM).
To determine the group of power plants that would be included in the Build Margin calculation,
reference is made to information provided by the PDOE on the most recent plants that have been added
to the Mindanao grid, as of end 2007. From this group of power plants and in accordance with the
Baseline Methodology procedure, the Build Margin will be calculated using either as:
(a) The set of five power units that have been built most recently, or
(b) The set of power capacity additions in the electricity system that comprise 20% of the system
generation (in MWh) and that have been built most recently.
The Build Margin is established using Option (b) or the set of power capacity additions in the electricity
system that comprise 20% of the system generation (in MWh) and that have been built most recently.
The BM emission factor is calculated ex ante based on the most recent information available at the time
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
40
of PDD submission (Option 1 of Step 5 in the Tool to calculate the emission factor for an electricity
system, Ver. 2.0). The year in which information is available for this group of plants is 2007.
Based on the analysis of the most recently built power plants connected to the Mindanao Grid, the net
electricity generation for 5 most recent additions (Table 3-4) represents about 25.37% (or more than
20%) of the total generation of the Mindanao Grid in 2007. In addition, the list of Build Margin power
plants does not include any project that is registered as a CDM activity.
Table A3-4. Build Margin power plants.
Plant ame
Date
Commissioned
Plant
Classification
et Electricity
Generated
Units Year - MWh
Source PDOE PDOE PC
Mindanao Coal 2006 Coal 1,409,947
PB104 2005 Diesel Barge 66,306
Solar 2004 Solar 1,309
Bubunawan 2001 Hydro 22,215
Mt Apo II 1999 Geothermal 411,319
Total Generation of recent plants 1,911,096
Total Generation of Mindanao Grid (2007) 7,531,503
% of Total Generation 25.37%
Step 6 Calculate the Build Margin (BM) Emission Factor
The emission factor for the Build Margin is therefore calculated using Option A2 for determining the
Simple OM emission factor and following Equation 4 in the following manner:
Table A3-5. Calculation of the Build Margin.
A B C D=(A/1000)/B*C E F=D*E
2007
Net Electricity
Generation
Plant
Efficiency**
Conversion
Factor
Fuel
Consumption
CO
2
Emission
Factor of
fuel***
CO
2
Emissions
NPC, PDOE
Default plant
eff. factors
Calculated IPCC 2006 Calculated
MWh % TJ/GWh TJ tCO2/TJ tCO2
1 Mindanao Coal 2006 1,409,947 39.0% 3.6 13,015 89.5 1,164,833
2 PB104 2005 66,306 39.0% 3.6 612 72.6 44,435
3 Solar Photovoltaic 2004 1,309
4 Bubunawan 2001 22,215
5 Mindanao II (Mt. Apo) 1999 411,319
1,911,097 13,627 1,209,269
BM = Total F/Total A
BM = 0.6328
* Data provided by the Power Planning Group of the Philippine Department of Energy
** Efficiencies are Default efficiency factors for power plants (Annex 1) in Tool to calculate the emission factor for an electricity system_V2
*** CO2 emission factors taken from Table 2.2 of Chapter 2 of Vol. 2 (Energy) of the 2006 IPCC Guidelines on National GHG Inventories using the
lower limits of the 95% confidence intervals for diesel and sub-bituminous coal
MOST RECENT POWER PLANTS BUILT IN MINDANAO*
Power Plant
Date
Commissioned
TOTAL Most Recent Plants
The BM emission factor for the Mindanao grid is 0.6328 tCO
2
e/MWh.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
41
Step 7 Calculate the Combined Margin (CM) emission factor
The Baseline Emission Factor was calculated as a Combined Margin (CM) emission factor using
Equation 5, which is the simple average of the OM and the BM. All margins are expressed in
tCO
2
/MWh.
CM = 0.5*OM + 0.5*BM (9)
CM = 0.5*(0.6651) + 0.5*(0.6328) = 0.6489 tCO
2
/MWh
The resulting Baseline Emission Factor is 0.6489 tCO
2
e/MWh, and will remain fixed for the first
crediting period.
Calculate the Projects Emission Reductions
As detailed in Section B.6.1., the Project itself does not lead to any GHG emissions. Furthermore, no
equipment was transferred to the project from another project, so leakage is also considered to be zero.
Therefore, the estimated annual project emission reductions are calculated follows:
ER
y
= BE
y
PE
y
LE
y
= BE
y
0 0
ER
y
= BE
y
Estimated Annual ERs = Estimated Baseline Emissions = CM x (Est. Annual Generation in MWh)
= 0.6489 tCO
2
/MWh x 49,253 MWh
= 31,962 tCO
2
for the first crediting period
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
42
Annex 4
MOITORIG IFORMATIO
TABLE OF COTETS
I. Background information
II. Purpose of the Monitoring Plan
III. Use of the Monitoring Plan by the Operator
IV. Organizational, Operational and Monitoring Obligations
A. Obligations of the Operator
B. Emissions Reductions Calculation Procedure and Required Spreadsheets
V. Annexes
The ERCP Organizational Structure and Quality Assurance and Control Procedure
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
43
I. Background Information
The proposed project is a run-of-river hydropower plant, located in northern Plaridel within the
municipality of Claveria, province of Misamis Oriental, about 30 kilometers northeast of Cagayan de Oro
City in Mindanao Island. The plant will have an nominal installed capacity of 8.0 MW and a projected
yearly average generation of 49.253 Gigawatt hours (GWh). The purpose of the 8 MW Cabulig River
Mini-Hydroelectric Power Project is to produce clean renewable energy by harnessing the waters of the
Cabulig River to generate electricity. As a run-of-river hydropower project, the project activity does not
produce GHG emissions; on the contrary, it will therefore help to reduce the Philippines overall GHG
emissions since the project activity displaces fossil fuel-based electricity generation that would have
emitted additional carbon dioxide. The resulting power will be exported to the Mindanao grid via
interconnection with the distribution lines of the Cagayan Electric Power and Light Company, Inc.
(CEPALCO) located in Barangay Natubo, Jasaan, Misamis Oriental. By doing so, the Project is
expected to displace 223,736 tons of carbon dioxide equivalent (tCO
2
e) in the first 7-year crediting
period, generating an equivalent amount of certified emission reductions (CERs).
Because the existing Project equipment is neither transferred to another activity nor comes from another
activity, there is no need to monitor leakage since leakage in this Project is zero. The project boundary is
the area of the concession where the facilities of the project are located. As the power generated by the
facility will reach the Mindanao grid via interconnection with CEPALCOs distribution line and
substation, the Mindanao Grid is included in the projects boundary.
The baseline methodology and monitoring methodology for the 8 MW Cabulig River Mini-Hydroelectric
Power Project is in accordance with the approved small-scale project methodology AMS I.D., which is
applicable to renewable electricity generation for a grid. The Projects baseline methodology and
monitoring methodology use the most recent version (V. 15, EB 50, October 2009). As per procedures
prescribed in AMS I.D. and the Tool to calculate the emission factor for an electricity system, Ver. 2.0
a simple adjusted OM analysis was used to calculate the operating margin, and the Build Margin (BM)
was calculated based on the generation-weighted average emission factor of the most recently built
power plants accounting for 20% of all power generation; the Mindanao grid Emission Factor (EF) for
the project is the Combined Margin (CM) emission factor and was calculated as the simple average of
the OM and BM. This EF is calculated on an ex-ante basis and will remain fixed for the first crediting
period.
II. Purpose of the Monitoring Plan
The CDM defines monitoring as the systematic surveillance of a projects performance by measuring and
recording performance-related indicators relevant to the project activity. This report presents the
Monitoring Plan (MP) for the Project. The MP defines a standard against which the performance in
terms of the Projects ERs will be monitored and verified, in conformance with all relevant requirements
of the CDM of the Kyoto Protocol. Both the Baseline and the MP are subject to verification procedures.
III. Use of the Monitoring Plan by the Project Operator
The MP identifies key performance indicators of the Project and sets out the procedures for metering,
monitoring, calculating and verifying the ERs generated by the Project annually. Adherence to the
instructions in the MP is necessary for the project operator
25
(the Operator) to successfully measure and
25
Mindanao Energy Systems, Inc. (MIERGY)
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
44
track the impact of the Project, and to prepare all data required for the periodic audit and verification
process that must be undertaken to confirm the attainment of the corresponding ERs.
The MP can be updated and adjusted to meet operational requirements. The Verifier approves such
modifications during the process of initial or periodic verification. In particular, any shifts in the
baseline scenario may lead to such amendments, which may be mandated by the Verifier. Amendments
may also be necessary as a consequence of new circumstances that affect the ability to monitor ERs, as
described here, or to accommodate new or modified CDM rules.
IV. Organizational, Operational and Monitoring Obligations
A. Obligations of the Operator
Monitoring performance of the Project requires the fulfilment of operational data collection and
processing obligations by the project operator (the Operator) throughout the crediting period of the
Project. The Operator is obligated to ensure that sufficient and accurate information is available to
calculate ERs in a transparent manner, and that adequate information is collected and maintained to
facilitate successful verification of accounted ERs.
Key responsibilities: The ERCP Organizational Structure dictates that the ERCP Manager will be
responsible for performing the ERCP (monthly), and the MP Steering Committee will be responsible for
supervising the ERCP Managers monitoring work (monthly). The ERCP Manager will report to the MP
Steering Committee (monthly), and the ERCP Manager and MP Steering Committee will coordinate in
reporting to the DOE at Verification.
Training of monitoring personnel: The team established in the ERCP Organizational structure, and
composed of the MP Steering Committee and the ERCP Management will be trained by Endesa Carbono
in a one day workshop on a comprehensive set of tools and knowledge required to implement the
monitoring plan. The training on the MP and associated responsibilities will build the capability of the
MP Steering Committee and the ERCP Management to replicate, on an ex-post basis, an equivalent
process that has been demonstrated in this PDD for an ex-ante emissions avoidance calculation. All
relevant staff will be provided with a comprehensive set of tools and knowledge required to implement
the monitoring plan, including: (a) accurate monitoring of the performance and output characteristics of
the plant to record and keep accurate data; (b) incorporation of these data sets into spread sheets pre-
prepared by Endesa Carbono, and (c) consistently calculating verifiable CERs as a function of measured
plant output against a the calculated emission factor that serves as a recognized proxy for emissions
displaced from the grid.
Equipment Required: Adequate computer services and file storage are required, and maintenance of
computers and data contained therein are described under the following section. Aadequate metering
and logging equipment will be procured for measuring electricity generation by the plant, and net levels
of electricity dispatched for sale to the grid. As explained in section B.7.2 of the PDD, no other special
monitoring equipment is needed for this project. Procedures for maintenance and installation of
equipment will be performed in accordance with manufacturer specifications of equipment and under the
guidance of Philippine Grid Code of 2001. Meter calibration, as specified in Chapter 9 (Grid Revenue
Metering Requirements), Section 9.4 (Metering Equipment Testing and Maintenance), Item 9.4.2 (Meter
Testing and Calibration) of the aforementioned Grid Code, shall be conducted at least once a year. All
measurements, data gathering, record keeping, and procedures for dealing with possible monitoring data
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
45
adjustments will be performed in specific consideration of the data gathering requirements of the MP and
as determined as adequate for meeting the baseline and monitoring requirements described in baseline
methodology AMS I.D. (V. 15) and the Tool to calculate the emission factor for an electricity system
(Ver. 2.0).
Data Collection and Integration: It is required that the Operator calculate the Projects ERs based on
most recent available information, following the ERCP presented in this report. The Operator must
gather and process information needed to monitor ERs. The Operator shall supply, install, operate and
maintain a metering system to measure the net level of electricity delivered to CEPALCO and sold to the
grid. The metering system shall be installed at the agreed point of delivery where the net power and
electricity exported to CEPALCO shall be measured. CEPALCO may install and maintain a check meter,
adjacent to the revenue meter of MINERGY to serve as monitoring meter and as back-up billing meter in
case the Operators billing meter is not available.
The metering system shall consist of bi-directional revenue meter, instrument transformers with an
accuracy class of 0.3% or better, lightning protection and all interconnecting cables, wires and associated
devices and protections. Both Minergy and CEPALCO meters will have the following specifications:
a) Type: kV2c+
b) Current Class: Class 20A (transformer rated)
c) Meter Form: Form 48A (bottom connection)
d) Accuracy Class as per ANSI C12.20: 0.3
e) Meter Construction: 3 element, 4 wire
f) Service: 3 phase, 4 wire (wye)
MIERGY-CEPALCO Current Metering and Invoicing Set-up
Every 25th of the month, a meter reading is jointly conducted by MINERGY and CEPALCO official
representatives to verify the actual quantity of electricity delivered to CEPALCO. The accuracy of the
meter reading data gathered are then confirmed through signing of the meter billing form by both parties
before the same is sent to MINERGY Accounting Department for the preparation of billing invoice. Final
review of the correctness of the inputted data is undertaken before copies are sent to CEPALCO.
Payment is collected within 30 days after the issuance of billing invoice.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
46
MINERGY
Revenue Meter
CEPALCO
Check Meter
Gen 1
Power
Meter
CEPALCO
34.5kV Line
Power
Meter
Gen 2
Auxilliary
MINERGY
Revenue Meter
CEPALCO
Check Meter
Gen 1
Power
Meter
CEPALCO
34.5kV Line
Power
Meter
Gen 2
Auxilliary
MINERGY
Revenue Meter
CEPALCO
Check Meter
Gen 1
Power
Meter
CEPALCO
34.5kV Line
Power
Meter
Gen 2
Auxilliary
Figure A4-1. Project operators proposed metering scheme.
From a pre-determined monthly billing schedule, a meter reading will be jointly conducted by the
Operator and CEPALCO official representatives to verify the actual quantity of electricity delivered to
CEPALCO. The accuracy of the meter reading data gathered are then confirmed through signing of the
meter billing form by both parties. A final review of the correctness of the net electricity measured is
done before a billing invoice is sent to CEPALCO.
Data gathering and processing should be done monthly by the Operator, as follows:
Monthly Data collection
Table A4-1: Monthly Data Collection: Division of Labor
I. Electricity distributor
final client(s)
(Data Provider)
Provide the Project Operator with written proof of the Projects
hourly generation purchased/sold.
Frequency: Monthly
II. Grid Operator
(Data Provider)
Provide the Project Operator with written proof of the Projects
hourly generation registered.
Frequency: Monthly
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
47
III. Project Operator
(Data Processor)
Directly measure the electricity generated following the Tool to
Calculate the Emission Factor for an Electricity System and
AMS. I.D.
Perform the monthly calculation of ERs following the ERCP.
Keep receipt of sales of electricity.
Prepare and submit the annual report of the total project ERs to
the DOE.
Establish the necessary agreements with the Grid Operator and
final clients to assure that they all provide a monthly written
report of the Projects hourly generation registered/bought.
Source: Endesa Carbono
On an annual basis, the project sponsor shall summarize from its record keeping on CERs the annual
generation and tons of CO2 displaced by the operation of the project, the number of employees (part-time
and full-time) engaged in the project operation, approximate taxes paid to National and/or local
jurisdictions, and, on a qualitative basis, shall summarize any other infrastructure, economic,
employment, social, or other benefits that can be attributed to the project.
As the primary purpose of Verification is independent inspection and validation of ERs actually achieved
by the Project, the ERCP Management will seek to establish and maintain a strong and efficient
relationship with the Verifier, i.e. the Designated Operational Entity (DOE), in order to ensure a
dependable and transparent outcome. In doing so, the ERCP Management will:
provide all necessary monitoring information about ERs to facilitate the verification work
and cooperate with the DOE on all data requests and questions;
during the crediting period, always take into account requests by the CDM Executive Board
and conduct preparatory work for the Verification to obtain high quality results and
efficiency; and,
ensure that ERCP Management and ERCP Steering Committee review all monitoring reports
before they are transmitted to the DOE.
It is believed that the monitoring approach presented in this MP will result in an accurate yet
conservative calculation of ERs. However some uncertainties, especially errors in the data monitoring
and processing system, may result in a discrepancy between the monitored ERs and the verified ERs.
The Operator is expected to prevent such errors and the verification audits are expected to uncover any
possible errors. As CERs can only be granted ex-post verification, there is a significant internal incentive
for the Operator to perform all steps related to data collection and calculations as accurately as possible.
Procedures for review of reported results data and internal audits: quality control and inspection
procedures are established in the ERCP to ensure monitoring accuracy. Such procedures will include,
but will not be limited to, the following:
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
48
Spreadsheets will be reviewed during yearly consolidation of monthly calculations;
Corrective actions will be taken in the case of malfunction or breakdowns, or simply for more
accurate monitoring and reporting;
An internal audit will be performed by the ERCP Steering Committee once a year to see if the
MP has been performed according the guidelines established in the PDD; and,
A project performance review will be performed every year, in accordance with the PDD.
Independent verification of monitoring results and achievement of the ERs as calculated in the PDD is a
critical outcome for all CDM projects. The ERCP Management should work closely with the DOE to
assure a dependable and transparent outcome, and to that end they will follow the procedures below for
project performance reviews and corrective actions:
Keep efficient contact with the DOE who verifies the Projects ERs;
Provide all necessary monitoring information about the ERs to facilitate the verification work;
During the crediting period, always take into account requests by the CDM Executive Board and
conduct preparatory work for the verification to obtain high quality results and efficiency;
The monitoring report should be reviewed by the ERCP Steering Committee before verification;
and,
The projects management and operators also should cooperate to answer all questions raised by
DOE during the Verification process.
All data will be archived for a period of 2 years from the end of the crediting period
Upon detecting a problem or being informed of a discrepancy, ERCP Management will take immediate
action to rectify it. Should CEPALCO as customer fail to provide adequate information, the ERCP
Steering Committee will file a claim with CEPALCO to obtain the information. If a major investment is
required, the ERCP Management will notify the ERCP Steering Committee to ask MINERGYs
management to invest in the monitoring personnel or/and equipment.
B. Emissions Reductions Calculation Procedure and Required Spreadsheets
The ERCP is the basic instrument for gathering, recording and processing information that will result in
the measured ERs. The Project Operator shall consider the Projects ERCP as a manual. The ERCP
should contain: (i) data gathered from the Grid Operator information system, and (ii) data processed by
the Project Operator. All data processing should be done using Excel software. The ERCP is designed
for monthly and yearly calculation, based on final monthly Grid Operator reports and monthly recording
and continuous recording of the meters installed. Entering the data monthly in the required spreadsheets
will provide the opportunity to review formulas, minimize errors and have data readily available for the
DOE at any time during the year.
For effective data management, Endesa Carbono will provide the Project Developer with an MP and pre-
programmed spreadsheets such that the Project Developer will only need to collect the information as
described and apply the formulas as instructed in the MP.
The Project Operator will calculate the ERs on the basis of the MP, following the ERCP. Calculations
will follow AMS I.D. (V. 15, EB 50, October 2009) to calculate ERs from electricity displacement when
the Project provides electricity to the grid due to the plant efficiency improvement.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
49
There will only be one spreadsheet to be reviewed by the DOE, namely Cabulig ERs at yearly period in
question.xls. However, as the DOE may require preliminary calculations, the staff person designated
as the ERCP Manager should keep the name of the files, and every time he/she works on the files, should
follow by the date when the latest adjustment was made. Doing so would allow old versions to be saved
on disk and kept as a record to show to the Verifier, if the need arises.
When the ER calculation for the month is completed, the files should be named Cabulig ERs at month
in question.xls in order to differentiate drafts from final monthly calculations. Likewise, after the
calculation of the ERs of the last month of the year, the file name should be changed to Cabulig ERs at
yearly period in question.xls.
Worksheet 2 should contain historical data as it was provided by the Grid Operator, on a CD or in email,
arranged in months of the electricity actually delivered to the grid before the project activity
implementation. The ERCP Manager should not manipulate this data other than to copy and paste it
from the file in which it was handed. The CD or e-mail through which the data came from the provider
should also be kept as proof for the DOE
Spreadsheet 2, Cabulig ER at yearly period in question.xls will be composed of two worksheets:
Worksheet# 1: Original Data from Grid operator, Worksheet# 2: Organized Data, Processed Data and
Result.
Worksheet 1 should contain data as it was provided by the Grid Customer, on a CD or in email, arranged
in months of the electricity actually delivered to the grid. The ERCP Manager should not manipulate this
data other than to copy and paste it from the file in which it was handed. The CD or e-mail through
which the data comes from the provider should also be kept as proof for the DOE.
For Worksheet 2, the ERCP Manager should put in one column per month the monthly project
generation. In this same Worksheet, the ERCP Manager should calculate monthly ERs in tCO
2
e by
multiplying the generation in MWh times 0.6489 tCO
2
e/MWh (the Baseline Emissions Factor for the
Mindanao Grid calculated ex-ante as described in Annex 3) and which will be used for the first 7-yr
crediting period. Rounding off is not necessary when calculating monthly ERs since the monthly
calculation is only for measuring progress. At the end of the year, the ERCP Manager should sum up the
resulting monthly ERs from electricity displacement to obtain the yearly project ERs from electricity
displacement ready for Verification. Resulting yearly ERs from electricity displacement must be
rounded off to the nearest integer. Once the calculation of yearly ERs from electricity displacement is
completed in the Cabulig ERs at December.xls
26
, this file should become Cabulig ERs at yearly
period in question.xls.
Worksheet 2 also allows the ERCP Manager to calculate the cumulative generation and cumulative ERs
from electricity displacement throughout the year and be aware of the progress of the Projects
environmental benefits accrued due to ERs from electricity displacement.
The ERCP Quality Control and Organizational Structure can be seen in the annex section of this MP.
26
December is the last month of the year, for the MP.
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
50
V. Annexes
The ERCP Organizational Structure and Quality Assurance and Control Procedure
Monitoring plan (MP) Emissions Reductions Calculation Procedure (ERCP)
ERCP Organizational Structure
MP Steering Committee
WILLIAM U. LIM
Seniot Vice-President
ERCP Management
ROALD ZARAGOZA
Asst. Vice-President
PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03
CDM Executive Board
51
Monitoring Plan (MP)
Emissions Reductions Calculation Procedure (ERCP)
Quality Control for Electricity Displacement
The Project Operator will perform monthly recording and check calibration of electric meters periodically. Only
one person will be responsible for the ERCP: Mr. Ronald Zaragoza.
Quality of Data Collection:
Data: Monthly generation from Grid Operator from provider, remaining information from the
Project Operator.
Format: Summarized in Excel.
Frequency: Monthly
Quality of Data Processing:
Original Data
Organized Data
Entered Data
Processed Data
Results
Quality of Data Storage:
Prevent Excel version problems by updating Excel software packages every year in PCs used for
the ERs calculations
Keep all data for 2 years after the first crediting period, i.e. for a total of 9 years
Assign a password to Excel spreadsheets used for the ERCP
Save the document with the last date in which an alteration was made so that old versions are
kept on disc
Keep all written documentation in a folder that will be provided to the DOE together with the
data collected in Excel
Quality of Data Delivery:
Provide to the DOE the e-mails/CDs through which Data Provider delivered the original data
Provide to the DOE the sales receipts
Provide to the DOE evidence of all calculations made showing all preliminary versions of
spreadsheets saved on disc.
Monthly calculations involve 5 data points.
All must be recorded and manipulated in Excel
with records of data points and electricity sales
receipts.
Yearly consolidation of monthly calculations.