Professional Documents
Culture Documents
Draw Control at Koffiefontein Mine
Draw Control at Koffiefontein Mine
Draw Control at Koffiefontein Mine
Introduction
The Koffiefontein Diamond Mine is located in the south-
west portion of the Free State, 137 km south-west of
Bloemfontein and 107 km south-east of Kimberley. Mining
of the kimberlite pipe commenced in 1878, but ceased
several times from 1892 to 1913 and from 1919 to 1931 due
to World War I. It reopened in 1970 as an opencast
operation and converted to an underground operation in
1981 with the development of levels 27 to 60. Due to the
downturn in the diamond market, the mine closed in 1982.
In 1987 the mine re-opened with a sub-level open-stope
mining method, but the mining method was immediately
converted to the blast hole open stoping, compound-ring
method
1
.
Koffiefontein mine is a low grade, marginal mine and the
forecasted ore dilution due to pit sidewall failures when
extracting the kimberlite pipe to lower levels resulted in an
investigation into an alternative mining method. Reducing
the waste influx to the underground drawpoints is vital to
ensure a viable future when deepening the mining
operations. It was appreciated at the start of the blast hole
open stoping that early waste dilution would be a problem,
but the method enabled the mine to get production, and
hence revenue, quickly. If a block cave or front cave was
started instead, the build up period would have delayed the
production start-up and the required initial capital
investment was considered too high. Blast hole open
stoping on the 37 Level was later replaced by sub-level
caving in an attempt to cut off the increasing quantities of
waste rock reporting to the drawpoints from the open pit.
The susceptibility to slope failures demanded a revision
of the mining method at depths below 37 Level. Several
mining methods were evaluated and front caving provided a
technically sound, financially viable option.
Figure 1 shows a diagrammatic section through the mine.
Front caving was selected above other methods for
technical and financial merits. The front cave layout
constitutes two levels with 4 m wide by 4.2 m high tunnels
spaced at 15 m centres. The upper level, 48 Level, acts as
the main undercut level. The lower level, 49 Level, is the
main extraction level and lags the upper level by 12 to 24 m.
HANNWEG, L.A. and VAN HOUT, G.J. Draw control at Koffiefontein Mine. 6th International Symposium on Mine Mechanization and Automation, South
African Institute of Mining and Metallurgy, 2001.
Draw control at Koffiefontein Mine
L.A. HANNWEG* and G.J. VAN HOUT
*De Beers Consolidated Mines Limited, Koffiefontein, Free State, South Africa