This document provides a work package for installing new 13.8kV cables serving a new autoclave switchgear. It details 17 steps for safely installing termination kits on the cables in an existing 13.8kV switchgear, including deenergizing and grounding sections of the switchgear, installing barricades and danger signs, and testing for absence of voltage before and after the work. Sketches and a schedule are also included to coordinate the work between construction and plant personnel over multiple days.
This document provides a work package for installing new 13.8kV cables serving a new autoclave switchgear. It details 17 steps for safely installing termination kits on the cables in an existing 13.8kV switchgear, including deenergizing and grounding sections of the switchgear, installing barricades and danger signs, and testing for absence of voltage before and after the work. Sketches and a schedule are also included to coordinate the work between construction and plant personnel over multiple days.
This document provides a work package for installing new 13.8kV cables serving a new autoclave switchgear. It details 17 steps for safely installing termination kits on the cables in an existing 13.8kV switchgear, including deenergizing and grounding sections of the switchgear, installing barricades and danger signs, and testing for absence of voltage before and after the work. Sketches and a schedule are also included to coordinate the work between construction and plant personnel over multiple days.
PROJECT No. : WORK PACKAGE No. : WORK PACKAGE GENERATED DATE
PACKAGE No. : 4333-EI-001 WORK PACKAGE TITLE: SHEET 13.8Kv Cable installation 1 of 1 WORK PACKAGE GENERATED BY: AREA(S) WHERE WORK IS TO BE PERFORMED: APPROVED BY SCHEDULE CONSTRUCTION PROJECT ACTIVITY ID: NAME: DATE: SCHEDULED DURATION: SAFETY ACTUAL DURATION: NAME: DATE: SCHEDULED START DATE: ACTUAL START DATE: PLANT NAME: SCHEDULED FINISH DATE: DATE: ACTUAL FINISH DATE: PLANT NAME: DATE: I. OBJECTIVE
The objective of this package is to detail the safe installation of the new 13.8Kv cables serving the new #9 Autoclave switchgear. This package will not "Electrically" connect the new cables to the existing switch. The Termination of the cables to the existing switch will not be performed until all downstream work has been completed. A separate work package will be issued prior to terminating the cables to the existing 13.8Kv switch
II. SAFETY
A. When working in substation the adjacent #7 gear will be DEENERGIZED.
B. Testing for absence of voltage shall be performed each time prior to the commencement of work. This means that each time you leave the work area upon returning to perform work you MUST re-verify that the equipment is deenergized.
C. During absence of voltage only parties involved directly in the exercise, with Proper PPE, will be allowed within 15' of task.
Per Project Schedule 249739995.xls.ms_office DETAILED JOB PLAN ( work package # 4333-EI-001 ) STEP ACTION TIME PLANT MK 1 Plant / Construction: Supervision to review work package and demonstrate concurrence with plan by signing cover sheet. Date 2 Construction: Verify that all equipment and miscellaneous materials are on-site and identified for use in this package. Date 3 Construction: Erect barricades around New transformer on roof of the #9 Autoclave finishing building 4 Construction: Erect barricades around existing 13.8Kv switchgear. (subs 6,7 & 8 ) 5 Plant: Install Danger signs on the following Compartments: 1. Incoming feeder #7 2. Substation #6 Upper compartment 3. Substation #8 Upper compartment (switching side) 4. Substation #8 Lower compartment (switching side) 5. Substation #8 Lower compartment (outgoing side) 6. Substation #7 Upper compartment (switching side) 7. Substation #7 Lower compartment (switching side) 8. Substation #7 Lower compartment (outgoing side) 6 Plant: Close #7 feeder switches on sub-stations #7 & #8. 7 Plant: Open #8 feeder switches to sub-stations #7 & #8. Apply locks on switches to maintain them in the open position. 8 Construction: Place locks on locked #8 feeder Switches. 9 Plant: Open feeder #8 Breakers A & B at Building 50. Rack breakers out and apply locks to breakers or rack-in rails. 10 Construction: Place locks on locked #8 feeder Breaker. INITIALS Page2 of 6 DETAILED JOB PLAN ( work package # 4333-EI-001 ) STEP ACTION TIME PLANT MK INITIALS 11 Construction: Test for absence of voltage in Substation #6 outgoing compartment and feeder #8 buss located above substation #6 outgoing compartment. USE PROPER PPE! Beehive Hood Nomex Voltage Rated Gloves 12 Construction: Verify that grounds are properly installed in substation #6 outgoing compartment. 13 Construction: Verify that grounds are properly installed in feeder #8 incoming compartment. 14 Construction: Install termination kits. 15 Construction: Clean-up and remove all materials from compartment. 16 Construction: Remove locks on #8 Feeder breaker and #8 feeder switches. 17 Construction: Inform plant that work is completed. Installation of Cable term kits complete Page3 of 6 SKETCH SHEET #5 PROJECT No. : 4333 WORK PACKAGE No. : WORK PACKAGE GENERATED DATE PACKAGE No. : EI-3 1/10/2000 SHEET 1 of 1 AREA(S) WHERE WORK IS TO BE PERFORMED: 4333-EI-001 Existing 13.8Kv Switchgear On roof of 162 Building WORK PACKAGE TITLE: 13.8 Kv CABLE Installation Jerry Hamilton WORK PACKAGE GENERATED BY: 12 11 12 11 12 11 12 11 12 11 7 8 7 8 12 11 7 8 SUB-STATION #5 INCOMING FEEDER #7 SUB-STATION #6 SUB-STATION #8 SUB-STATION #7 SWITCH ORIENTATION FOR SUB #6 Cable Term Kit INSTALLATION SKETCH SHEET #5 PROJECT No. : 4333 WORK PACKAGE No. : WORK PACKAGE GENERATED DATE PACKAGE No. : EI-3 1/10/2000 SHEET 1 of 1 AREA(S) WHERE WORK IS TO BE PERFORMED: 4333-EI-001 Existing 13.8Kv Switchgear On roof of 162 Building WORK PACKAGE TITLE: 13.8 Kv CABLE Installation Jerry Hamilton WORK PACKAGE GENERATED BY: 12 11 12 11 12 11 12 11 12 11 7 8 7 8 12 11 7 8 INCOMING FEEDER #7 SUB-STATION #6 SUB-STATION #8 SUB-STATION #7 DANGER SIGNS FOR SUB #6 Cable Term Kit INSTALLATION DANGER HIGH VOLTAGE DANGER HIGH VOLTAGE DANGER HIGH DANGER HIGH DANGER HIGH VOLTAGE DANGER HIGH VOLTAGE SKETCH SHEET #5 PROJECT No. : 4333 WORK PACKAGE No. : WORK PACKAGE GENERATED DATE PACKAGE No. : EI-3 1/10/2000 SHEET 1 of 1 AREA(S) WHERE WORK IS TO BE PERFORMED: 4333-EI-001 Existing 13.8Kv Switchgear On roof of 162 Building WORK PACKAGE TITLE: 13.8 Kv CABLE Installation Jerry Hamilton WORK PACKAGE GENERATED BY: 12 11 12 11 12 11 12 11 SUB-STATION #7 SUB-STATION #8 SUB-STATION #6 INCOMING FEEDER #8 DANGER SIGNS FOR SUB #6 Cable Term Kit INSTALLATION DANGER HIGH VOLTAGE DANGER HIGH VOLTAGE DANGER HIGH VOLTAGE DANGER HIGH VOLTAGE DANGER HIGH DANGER HIGH VOLTAGE DANGER HIGH VOLTAGE