Professional Documents
Culture Documents
Laguna LBNO GM Presentation 4.3.11 r2 PDF
Laguna LBNO GM Presentation 4.3.11 r2 PDF
Slide 1
RHYAL ENGINEERING
Contents
Slide 2
RHYAL ENGINEERING
Rhyal Engineering
Formed in 1998 with an experienced tank construction
management team and workforce
Slide 3
RHYAL ENGINEERING
Past Projects
Aviation Fuel Storage Tanks Isle of Grain Terminal, UK
Slide 4
RHYAL ENGINEERING
Past Projects
Aviation Fuel Storage Tanks Isle of Grain Terminal, UK
Slide 5
RHYAL ENGINEERING
Past Projects
Aviation Fuel Storage Tanks Isle of Grain Terminal, UK
Slide 6
RHYAL ENGINEERING
Past Projects
Bio-ethanol Storage Tanks Kingsbury Terminal, UK
Slide 7
RHYAL ENGINEERING
Past Projects
Bio-ethanol Storage Tanks Kingsbury Terminal, UK
Slide 8
RHYAL ENGINEERING
Past Projects
Typical Access Restrictions Pembroke Refinery, UK
Slide 9
RHYAL ENGINEERING
Past Projects
Typical Access Restrictions Pembroke Refinery, UK
Slide 10
RHYAL ENGINEERING
Past Projects
Storage Tank and Vessels Nitrogen Sphere
Slide 11
RHYAL ENGINEERING
Past Projects
Storage Tank and Vessels Crude Oil Tank
Slide 12
RHYAL ENGINEERING
Past Projects
Storage Tank and Vessels LNG Tanks
Slide 13
RHYAL ENGINEERING
Involvement with LAGUNA
Slide 14
RHYAL ENGINEERING
Cryogenic Tank Construction
Slide 15
RHYAL ENGINEERING
LNG Tank Construction Sequence
Install foundation, slip-form cast outer
concrete shell walls
Slide 16
RHYAL ENGINEERING
LNG Tank Construction Sequence
Roof structure & plates kingpost method
Temporary
Kingpost
Slide 17
RHYAL ENGINEERING
LNG Tank Construction Sequence
Roof structure & plates blown roof method
Phase 1 Construct roof at floor level
Temporary
Kingpost
Slide 18
RHYAL ENGINEERING
LNG Tank Construction Sequence
Roof structure & plates blown roof method
Phase 2 Raise roof with air cushion
Slide 19
RHYAL ENGINEERING
LNG Tank Construction Sequence
Roof structure & plates blown roof method
Phase 2 Raise roof with air cushion
Slide 20
RHYAL ENGINEERING
LNG Tank Construction Sequence
Roof structure & plates blown roof method
Slide 21
RHYAL ENGINEERING
LNG Tank Construction Sequence
Complete concrete surround
Slide 22
RHYAL ENGINEERING
LNG Tank Construction Sequence
Install & weld outer tank shell & floor liner
Slide 23
RHYAL ENGINEERING
LNG Tank Construction Sequence
Lay insulation and temp sensors
Slide 24
RHYAL ENGINEERING
LNG Tank Construction Sequence
Install & weld inner tank floor & shell
Slide 25
RHYAL ENGINEERING
LNG Tank Construction Sequence
Install piping, hydrostatic test and insulate
Slide 26
RHYAL ENGINEERING
Slide 27
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Full containment concrete-steel type tanks
Completed 2008
Storage capacity 160,000m3 per tank
Slide 28
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Slip forming the concrete walls
Slide 29
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Installing King post
Slide 30
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Roof construction transport petals from storage
Slide 31
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Roof construction lifting petals into position
Slide 32
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Roof construction lifting petals into position
Slide 33
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Roof construction erecting infill structure
Slide 34
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Roof construction erecting roof plates
Slide 35
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Erecting and welding outer tank shell liner
Slide 36
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Outer tank floor, insulation and inner tank floor
Slide 37
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Inner tank shell erection and welding
Slide 38
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Inner tank shell erection and welding
Slide 39
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Installing internal tank piping
Slide 40
RHYAL ENGINEERING
Dragon LNG - Milford Haven, UK
Installing internal tank piping
Slide 41
RHYAL ENGINEERING
LNG Tank Build - Milford Haven, UK
Tank complete ready for hydro test
Slide 42
RHYAL ENGINEERING
Slide 43
RHYAL ENGINEERING
LAGUNA Project Challenges
At present we believe the three main tank construction
challenges are:
Location
Construction methodology
Construction costs
Slide 44
RHYAL ENGINEERING
LAGUNA Project Challenges - Location
Slide 45
RHYAL ENGINEERING
LAGUNA Project Challenges - Location
Slide 46
RHYAL ENGINEERING
LAGUNA Project Challenges - Methodology
Proven above ground construction methods can be
transferred and adapted to below ground working
Slide 47
RHYAL ENGINEERING
LAGUNA Project Challenges - Cost
Slide 48
RHYAL ENGINEERING
LAGUNA Project Challenges - Cost
Slide 49
RHYAL ENGINEERING
Slide 50