Instruction & Change Order Procedure 10
Instruction & Change Order Procedure 10
FOR
INDICATIVE FIELD REVISION INSTRUCTION &
CHANGE ORDER PROCEDURE
FOR
HINDUSTAN PETROLEUM CORPORATION LTD.
VISAKH REFINERY
DHT PROJECT
TEIL JOB NO. : 6261
DOCUMENT NO. : CEP - 307
01.06.09
Rev.
no.
Issue Date
Description
UCM
PRK
SSV
ORDER PROCEDURE
Sheet 2 of 10
Revision History
Rev.
Date
01.06.09
Description
For Bid Enquiry
ORDER PROCEDURE
Sheet 3 of 10
CONTENTS
Page
1.0
1.1
1.2
General
Intent
Definitions
2
2
2
2.0
2.1
2.2
2.3
2.4
2.5
2.6
3
3
3
4
4
4
5
3.0
3.1
3.2
3.2.1
3.2.2
3.2.3
3.2.4
Change orders
General conditions of change orders ..
Change order handling .
Request for change order .
Approval of change order by owner
Execution of change order
Change order status report ..
5
5
6
6
7
8
8
Annexure (1)
Annexure (2)
Annexure (3)
Annexure (4)
Annexure (5)
Annexure (6)
Annexure (7)
Annexure (8)
1.0
General
1.1
Intent
ORDER PROCEDURE
Sheet 5 of 10
The intent of this procedure is to define the methods of preparation, control and
issue of field revision instructions to the respective construction contractors /
subcontractors and procedure to carryout change orders.
The requirements of this procedure are to be applied to all field revision instructions
to be issued to the construction contractors / subcontractors, whether originated at
the home office or the site office.
1.2
Definitions
In this procedure, the following words and expressions are used, and they have the
respective meanings hereby assigned to them, except where the context otherwise
requires:
(1)
ERI are TEIL internal documents and as such are not normally issued
to any construction contractors / subcontractors.
(2) "FRI" means a Field Revision Instruction which is prepared by the Field
Engineering group of site office, and is generated either from an ERI issued from
home office or the needs recognized at the work site. A FRI shall be issued to the
construction contractor / subcontractor as an instruction for the works.
(3) "OWNER" means M/s. HINDUSTAN PETROLEUM CORPORATION LTD., and
includes its personal representatives, its successors and permitted assigns.
(4) "PMC" means a M/s. TOYO ENGINEERING INDIA LIMITED who is Project
Management Consultant engaged by the OWNER for the project management
of PLANT.
(5) "LSTK CONTRACTOR: / Bidder / Contractor ' means any third party agency
whose services are obtained by OWNER for supply, execution and/or erection
of units/facilities covered under PMCs Scope of services.
(6)
"PLANT" means the process units and facilities associated with the project for
which PMC is to provide services under this contract.
(7)
(8)
"Site office" means the LSTK CONTRACTORs site office established and
operated at the work site for the execution of the construction works.
ORDER PROCEDURE
Sheet 6 of 10
ISSUED : 01.06.2009
DOC.No. CEP - 307
2.1
Modify the ERI as necessary to suit the existing conditions of the site, in which
case, one (1) copy of the modified ERI is to be forwarded to the H.O. stating the
reasons for, or the cause of the change or modification to original ERI.
(2)
Prepare FRI using the standard format, for issue to the construction contractor /
subcontractor (if required, by re-drafting),
(3)
(4)
Issue the FRI to the document controller for registration and distribution to the
concerned site office departments and the construction contractors /
subcontractors concerned.
(2)
(3)
ORDER PROCEDURE
Sheet 7 of 10
Issue the FRI to the document controller for registration and distribution to the
concerned site office departments and the construction contractors /
subcontractors concerned.
Distribution of FRI
The document controller, upon receipt of the FRI, shall:
(1)
Assign a discrete reference number, and record and register the subjects of the
FRI.
(2)
Distribute its copies to the concerned site office departments and, as applicable,
to the owner.
(3)
Prepare the transmittal form and three (3) copies of the FRI for RCM signature,
and subsequently issue to the construction contractors / subcontractors
concerned.
Upon receipt of FRI, both the discipline construction engineer and the QC inspector
shall:
Append one (1) copy to each of the relevant drawings, specifications and/or any
other related technical document that the FRI amends or revises, in the respective
departmental bound drawing files or folders.
2.4
Revision of FRI
When any further changes or revisions are required for the same part of the works
for which a FRI has previously been issued, the FRI shall be revised and re-issued to
the construction contractors / subcontractors concerned.
2.5
Registration of FRI
The document controller shall register all FRI to record the following information:
(1)
(2)
(3)
(4)
(5)
ORDER PROCEDURE
Sheet 8 of 10
ISSUED : 01.06.2009
DOC.No. CEP - 307
(6)
Appended as Annexure (4) is a sample, standard layout of the register for FRI which
in this example is specifically for piping revisions.
2.6
Numbering of FRI
The numbering system used for identification of the respective FRI shall be as
follows and the category of works given on the FRI is indicated by two (2) letters as
below:
PI P&ID; PP - Plot plan;
TK - Tank; EL - Electrical;
PN - Piping (*)
CV Civil / building;
IN - Instrumentation;
SS - Structural steel;
EQ - Equipment, (*)
*Note (1) : If a FRI is required for revisions of insulation works or painting works,
then such FRI shall be categorized as follows:
- Insulation or painting applied to Equipment
- Insulation or painting applied to Piping
EQ
PN
A sequential number is to be allocated for each category of the works starting 001.
For example, the first FRI raised for piping works would be numbered thus:
FRI - PN - 001 (and sequentially onward for each FRI raised within piping category).
Note (2) : This numbering system is for reference only.
This numbering
identification system can differ from site to site depending upon the
specific job requirement.
3.0
Change orders
3.1
(3)
The contract price of the contract will be adjusted only by a change order.
(4)
LSTK CONTRACTOR 's Project Manager (PM) is responsible for handling all
change orders with assistance of the Project Engineer (PE) in Home office and
LSTK CONTRACTOR Site In-charge in Site office.
ORDER PROCEDURE
Sheet 6 of 10
ISSUED : 01.06.2009
DOC.No. CEP - 307
3.2
Annexure (5) hereto, appends the standard form to be used as the request for
change order.
(3)
ORDER PROCEDURE
Sheet 7 of 10
(2)
A serial reference number, assigned for the change order, and a description
of the change involved,
The total number of man-hours allotted for the preparation of the change
order.
The required completion date for the preparation of the change order.
Annexure (6) hereto, appends the standard forms to be used in the submittal of the
change order for approval.
(3)
ORDER PROCEDURE
Sheet 8 of 10
ISSUED : 01.06.2009
DOC.No. CEP - 307
The change order must be approved in writing by owner within specified period
by way of a project change authorization, to permit the execution of the change
in work.
Project change authorization for change order approval / disapproval is
appended as Annexure (7) hereto.
3.2.3 Execution of change order
The execution of change order follows after the approval of the change order by
owner.
On receipt of authorization by owner to proceed with the change, LSTK
CONTRACTOR project group shall arrange for the details of the change order and
change authorization to be distributed to the Site In charge and all concerned groups
with in LSTK CONTRACTOR home office.
3.2.4 Change order status report
The project group and the site field engineering group shall update and maintaining
the change order status report with all relevant informations like :
(1)
(2)
(3)
Annexure (8) appends a standard format for the change order status report.