Professional Documents
Culture Documents
RAB-Gang Way DMG V Tahap II Value
RAB-Gang Way DMG V Tahap II Value
RAB
26,710,000,000.00
26,710,115,639.17
(115,639.17)
No
1
2
3
4
5
6
7
8
9
10
11
12
Bahan / Material
Pekerja
Tukang
Kepala Tukang
Mandor
Tukang Las
Operator
Mekanik
Juru Ukur
Juru Gambar
Surveyor
Pembantu Surveyor
Tukang Selam
Satuan
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Harga Satuan
(Rp.)
46,200.00
60,500.00
66,000.00
66,000.00
66,000.00
93,500.00
77,000.00
66,000.00
66,000.00
77,000.00
55,000.00
110,000.00
42,000.00
55,000.00
60,000.00
60,000.00
60,000.00
85,000.00
70,000.00
60,000.00
60,000.00
70,000.00
50,000.00
100,000.00
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
30
31
32
33
34
35
36
37
38
39
40
41
Bahan / Material
Semen PC 50 Kg/zak
Pasir Beton
Batu Pecah 2-3
Pasir Urug
Tanah Timbunan
Sirtu
Base Course
Batu Kali
Batu Belah 150 - 200 kg/unit
Batu Belah 300 - 500 kg/unit
Besi Beton
Kawat Beton
Pipa Baja 406.12 mm t = 12 mm
Pipa Baja 812.8 mm t = 14 mm
Pipa Baja 812.8 mm t = 16 mm
Pipa Baja 1400 mm t = 19 mm
Baja Profil dan Plat
Fender V500, L=2000 mm + angker (Hot dip Galvanized)
Electrode
Oxigen
Acetelyn
Pasir Kuarsa
Cat Anti Karat Untuk Baja
Kayu Kelas I
Kayu Kelas II
Kayu Perancah
Multipleks t = 12 mm
Geotextile
Olie
Solar
Paku
Air
Beton Readymix K-300
Beton Readymix K-250
Beton Readymix K-175
Beton Readymix K-Bo
Beton Material Grout
Karung
Air Kerja
Minyak Bekisting
Paving Block
Wiremesh D10
Satuan
zak
m3
m3
m3
m3
m3
m3
m3
m3
m3
kg
kg
kg
kg
kg
kg
kg
Unit
kg
tabung
tabung
kg
kg
m3
m3
m3
lbr
m2
Liter
Liter
kg
m3
m3
m3
m3
m3
m3
lbr
m3
Liter
Liter
m2
Harga Satuan
(Rp.)
63,390.00
126,780.00
142,628.00
116,215.00
52,825.00
123,611.00
153,193.00
126,780.00
158,475.00
211,300.00
7,811.00
15,515.00
9,660.00
9,660.00
9,660.00
9,660.00
19,661.00
21,130,000.00
31,695.00
126,780.00
158,475.00
291.00
145,523.00
3,169,500.00
2,641,250.00
2,535,600.00
168,512.00
25,356.00
30,000.00
8,200.00
15,848.00
792.00
749,100.00
721,600.00
666,600.00
635,800.00
998,800.00
5,283.00
5,283.00
5,283.00
95,085.00
74,210.00
60,000.00
120,000.00
135,000.00
110,000.00
50,000.00
117,000.00
145,000.00
120,000.00
150,000.00
200,000.00
7,300.00
14,500.00
9,660.00
9,660.00
9,660.00
9,660.00
18,375.00
20,000,000.00
30,000.00
120,000.00
150,000.00
275.00
137,741.00
3,000,000.00
2,500,000.00
2,400,000.00
159,500.00
24,000.00
30,000.00
8,200.00
15,000.00
750.00
681,000.00
656,000.00
606,000.00
578,000.00
908,000.00
5,000.00
5,000.00
5,000.00
90,000.00
70,241.40
No
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Bahan / Material
Satuan
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Harga Satuan
(Rp.)
439,900.00
510,500.00
581,900.00
763,900.00
1,057,100.00
1,288,900.00
556,400.00
661,400.00
241,400.00
407,900.00
423,900.00
480,900.00
309,900.00
220,900.00
90,900.00
62,600.00
41,400.00
103,800.00
28,500.00
374,000.00
33,600.00
Sewa / Bln
50,000,000.00
60,000,000.00
70,000,000.00
100,000,000.00
150,000,000.00
200,000,000.00
80,000,000.00
100,000,000.00
20,000,000.00
40,000,000.00
45,000,000.00
50,000,000.00
35,000,000.00
20,000,000.00
10,000,000.00
9,000,000.00
3,000,000.00
10,000,000.00
2,500,000.00
40,000,000.00
2,500,000.00
Persiapan
Mobilisasi
Upah
Bahan Umum
Tiang Pancang
Besi beton
Beton
Peralatan
Sub Pancang (yg tdk pakai analisa)
Sub Pek Sipil
Sub Pek Gedung
Indeks INASA (diluar analisa)
1.0500
1.0500
1.1000
1.0565
1.0000
1.0700
1.1000
1.0500
1.0500
1.1250
1.1250
1.0300
1.05
1.05
1.11
1.10
1.12
1.11
1.13
1.06
NFA
747,000.00
717,000.00
667,000.00
614,000.00
Jayamix
Estimasi
Estimasi
Jayamix
6.75
187.5
FA
681,000.00
656,000.00
606,000.00
578,000.00
Sewa/Jam
262,500.00
315,000.00
367,500.00
525,000.00
787,500.00
1,050,000.00
420,000.00
525,000.00
105,000.00
210,000.00
236,250.00
262,500.00
183,750.00
105,000.00
52,500.00
47,250.00
15,750.00
52,500.00
13,125.00
210,000.00
13,125.00
HP
BBM/Jam
(liter)
160.00
180.00
200.00
220.00
250.00
220.00
120.00
120.00
120.00
180.00
170.00
200.00
110.00
100.00
37.50
15.00
25.00
50.00
15.00
160.00
20.00
20.00
22.50
25.00
27.50
31.25
27.50
15.00
15.00
15.00
22.50
21.25
25.00
13.75
12.50
4.69
1.88
3.13
6.25
1.88
20.00
2.50
BBM/Jam
(Rp.)
164,000.00
184,500.00
205,000.00
225,500.00
256,250.00
225,500.00
123,000.00
123,000.00
123,000.00
184,500.00
174,250.00
205,000.00
112,750.00
102,500.00
38,437.50
15,375.00
25,625.00
51,250.00
15,375.00
164,000.00
20,500.00
Operator
13,357.14
11,000.00
9,428.57
13,357.14
13,357.14
13,357.14
13,357.14
13,357.14
13,357.14
13,357.14
13,357.14
13,357.14
13,357.14
13,357.14
-
Total
439,857.14
510,500.00
581,928.57
763,857.14
1,057,107.14
1,288,857.14
556,357.14
661,357.14
241,357.14
407,857.14
423,857.14
480,857.14
309,857.14
220,857.14
90,937.50
62,625.00
41,375.00
103,750.00
28,500.00
374,000.00
33,625.00
Keterangan
Solar Umum
Solar Industri
Bensin
4500
8200
4500
No
1
2
3
4
5
6
7
8
9
10
11
12
Bahan / Material
Pekerja
Tukang
Kepala Tukang
Mandor
Tukang Las
Operator
Mekanik
Juru Ukur
Juru Gambar
Surveyor
Pembantu Surveyor
Tukang Selam
Satuan
Harga Satuan
(Rp.)
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
46,200.00
60,500.00
66,000.00
66,000.00
66,000.00
93,500.00
77,000.00
66,000.00
66,000.00
77,000.00
55,000.00
110,000.00
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Bahan / Material
Semen PC 50 Kg/zak
Pasir Beton
Batu Pecah 2-3
Pasir Urug
Tanah Timbunan
Sirtu
Base Course
Batu Kali
Batu Belah 150 - 200 kg/unit
Batu Belah 300 - 500 kg/unit
Besi Beton
Kawat Beton
Baja Profil dan Plat
Electrode
Oxigen
Acetelyn
Kayu Perancah
Multipleks t = 12 mm
Olie
Solar
Paku
Air
Beton Readymix K-300
Beton Readymix K-Bo
Minyak Bekisting
Paving Block
Wiremesh D10
Satuan
Harga Satuan
(Rp.)
zak
m3
m3
m3
m3
m3
m3
m3
m3
m3
kg
kg
kg
kg
tabung
tabung
m3
lbr
Liter
Liter
kg
m3
m3
m3
Liter
Liter
m2
63,390.00
126,780.00
142,628.00
116,215.00
52,825.00
123,611.00
153,193.00
126,780.00
158,475.00
211,300.00
7,811.00
15,515.00
19,661.00
31,695.00
126,780.00
158,475.00
2,535,600.00
168,512.00
30,000.00
8,200.00
15,848.00
792.00
749,100.00
635,800.00
5,283.00
95,085.00
74,210.00
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Bahan / Material
Satuan
Harga Satuan
(Rp.)
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
Jam
510,500.00
581,900.00
1,288,900.00
556,400.00
241,400.00
407,900.00
423,900.00
480,900.00
309,900.00
220,900.00
90,900.00
62,600.00
41,400.00
103,800.00
28,500.00
374,000.00
33,600.00
Luar Atas
Luar Bawah
Luar Atas
Luar Bawah
Samping
Tengah
Luar Atas
Luar Bawah
Luar Atas
Luar Bawah
Samping
Tengah
Luar Atas
Luar Bawah
Luar Atas
Luar Bawah
Samping
Tengah
Samping
Tengah
Luar Atas
Luar Bawah
Luar Atas
Luar Bawah
Samping
Tengah
p Tipe - 1 (7 m x 8 m x 1.6 m)
1.00
Tulangan
BJ
Panjang
Jumlah
Total
Panjang
Total
Berat
D22-150
2.984
11.20
54.00
604.80
1,804.72
D22-150
2.984
10.00
54.00
540.00
1,611.36
D22-150
2.984
10.20
48.00
489.60
1,460.97
D22-150
2.984
9.00
48.00
432.00
1,289.09
D22-150
2.984
30.00
12.00
360.00
1,074.24
D22-150
2.984
9.60
48.00
460.80
1,375.03
D22-150
2.984
2.40
96.00
230.40
687.51
Dibulatkan
Total Pembesian
Jumlah Pile = 1
Volume Beton
Rasio Besi/m3
1.05 Rasio Besi/m3
9,302.92
9,302.92
89.60
103.83
109.02
Bekisting
Volume Beton
Rasio Bekisting/m3
103.75
89.60
1.16
1.00
BJ
Panjang
Jumlah
Total
Panjang
Total
Berat
D22-150
2.984
11.20
54.00
604.80
1,804.72
D22-150
2.984
10.00
54.00
540.00
1,611.36
D22-150
2.984
10.20
48.00
489.60
1,460.97
D22-150
2.984
9.00
48.00
432.00
1,289.09
D22-150
2.984
30.00
12.00
360.00
1,074.24
D22-150
2.984
9.60
48.00
460.80
1,375.03
D22-150
2.984
2.40
96.00
230.40
687.51
Dibulatkan
Total Pembesian
Jumlah Pile = 1
Volume Beton
Rasio Besi/m3
1.1 Rasio Besi/m3
9,302.92
9,302.92
89.60
103.83
114.21
Bekisting
Volume Beton
Rasio Bekisting/m3
103.75
89.60
1.16
1.00
BJ
Panjang
Jumlah
Total
Panjang
Total
Berat
D22-150
2.984
6.70
24.00
160.80
479.83
D22-150
2.984
5.50
24.00
132.00
393.89
D22-150
2.984
6.70
24.00
160.80
479.83
D22-150
2.984
5.50
24.00
132.00
393.89
D22-150
2.984
14.00
12.00
168.00
501.31
D22-150
2.984
5.10
24.00
122.40
365.24
D22-150
2.984
2.40
48.00
115.20
343.76
Dibulatkan
Total Pembesian
Jumlah Pile = 1
Volume Beton
Rasio Besi/m3
1.05 Rasio Besi/m3
Bekisting
Volume Beton
Rasio Bekisting/m3
2,957.74
2,957.74
19.60
150.91
158.45
103.75
19.60
5.29
p Tipe - 4 (4 m x 8 m x 1.6 m)
Tulangan
1.00
BJ
Panjang
Jumlah
Total
Panjang
Total
Berat
D22-150
2.984
11.20
28.00
313.60
935.78
D22-150
2.984
10.00
28.00
280.00
835.52
D22-150
2.984
7.20
54.00
388.80
1,160.18
D22-150
2.984
6.00
54.00
324.00
966.82
D22-150
2.984
26.40
12.00
316.80
945.33
D22-150
2.984
9.60
28.00
268.80
802.10
D22-150
2.984
2.40
84.00
201.60
601.57
Dibulatkan
Total Pembesian
Jumlah Pile = 1
Volume Beton
Rasio Besi/m3
1.05 Rasio Besi/m3
6,247.30
6,247.30
51.20
122.02
128.12
Bekisting
Volume Beton
Rasio Bekisting/m3
103.75
51.20
2.03
1.00
BJ
Panjang
Jumlah
Total
Panjang
Total
Berat
D22-150
2.984
11.20
28.00
313.60
935.78
D22-150
2.984
10.00
28.00
280.00
835.52
D22-150
2.984
7.20
54.00
388.80
1,160.18
D22-150
2.984
6.00
54.00
324.00
966.82
D22-150
2.984
26.40
12.00
316.80
945.33
D22-150
2.984
9.60
28.00
268.80
802.10
D22-150
2.984
2.40
84.00
201.60
601.57
Dibulatkan
Total Pembesian
Jumlah Pile = 1
Volume Beton
Rasio Besi/m3
1.05 Rasio Besi/m3
Bekisting
Volume Beton
Rasio Bekisting/m3
6,247.30
6,247.30
51.20
122.02
128.12
103.75
51.20
2.03
kg
kg
m3
kg/m3
kg/m3
m2
m3
m2/m3
kg
kg
m3
kg/m3
kg/m3
m2
m3
m2/m3
kg
kg
m3
kg/m3
kg/m3
m2
m3
m2/m3
kg
kg
m3
kg/m3
kg/m3
m2
m3
m2/m3
kg
kg
m3
kg/m3
kg/m3
m2
m3
m2/m3
Jenis Pekerjaan
Harga Satuan/Lump Sum
NO
URAIAN PEKERJAAN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
SATUAN
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
52,500,000.00
52,500,000.00
78,750,000.00
157,500,000.00
2,100,000.00
1,050,000.00
5,250,000.00
4,200,000.00
1,050,000.00
525,000.00
525,000.00
525,000.00
2,625,000.00
525,000.00
525,000.00
TOTAL
=
=
Jenis Pekerjaan
Harga Satuan/Bulan
NO
I
II
III
URAIAN PEKERJAAN
SATUAN
519,750,000.00
JUMLAH (Rp.)
52,500,000.00
52,500,000.00
78,750,000.00
315,000,000.00
2,100,000.00
2,100,000.00
5,250,000.00
4,200,000.00
1,050,000.00
1,575,000.00
525,000.00
525,000.00
2,625,000.00
525,000.00
525,000.00
519,750,000.00
47,107,500.00
JUMLAH (Rp.)
PERALATAN
1 Theodolite
2 Waterpass
3 Alat bantu
Sub total
Bln
Bln
ls
8.00
8.00
1.00
1,050,000.00
787,500.00
157,500.00
8,400,000.00
6,300,000.00
157,500.00
14,857,500.00
TENAGA KERJA
1 Surveyor
2 Pembantu surveyor
Sub total
org
org
150.00
300.00
77,000.00
55,000.00
11,550,000.00
16,500,000.00
28,050,000.00
8.00
8.00
367,500.00
157,500.00
2,940,000.00
1,260,000.00
4,200,000.00
BAHAN BANGUNAN
1 Kayu dan bambu
2 Paku, Cat, Meni
Sub total
ls
ls
TOTAL
47,107,500.00
Jenis Pekerjaan
Harga Satuan/Lump Sum
NO
URAIAN PEKERJAAN
1 Instalasi Listrik
2 Instalasi Air Kerja
SATUAN
Ls
Ls
5,250,000.00
3,150,000.00
Jumlah
=
=
URAIAN PEKERJAAN
SATUAN
bln
bln
2,625,000.00
2,100,000.00
Jumlah
=
=
URAIAN PEKERJAAN
SATUAN
Rp.
VOLUME
bln
bln
=
=
URAIAN PEKERJAAN
Jumlah
2,625,000.00
2,100,000.00
984,375.00
2,625,000.00
3,609,375.00
JUMLAH (Rp.)
984,375.00
2,625,000.00
3,609,375.00
Jenis Pekerjaan
Harga Satuan/Ls
1 Direksi Keet
4,725,000.00
JUMLAH (Rp.)
Keselamatan Kerja
Jumlah
NO
5,250,000.00
3,150,000.00
4,725,000.00
Jenis Pekerjaan
Harga Satuan/Bulan
NO
JUMLAH (Rp.)
8,400,000.00
Jenis Pekerjaan
Harga Satuan/Bulan
NO
8,400,000.00
SATUAN
m2
Direksi Keet
Rp.
VOLUME
787,500.00
787,500.00
JUMLAH (Rp.)
787,500.00
787,500.00
=
=
Jenis Pekerjaan
Harga Satuan/Lump Sum
NO
URAIAN PEKERJAAN
1 Administrasi
2 Asbuilt Drawing
3 Dokumentasi
SATUAN
Ls
Ls
Bln
8,400,000.00
7,875,000.00
210,000.00
Jumlah
=
=
URAIAN PEKERJAAN
BAHAN
1 Besi Beton
2 Kawat Beton
SATUAN
Pembesian
Rp.
VOLUME
kg
kg
UPAH
1 Pekerja
2 Mandor
Hari
Hari
ALAT
1 Bar Bender/Bar Cutter
2 Genset
3 Alat bantu
Jam
Jam
Ls
8,045.33
310.30
8,355.63
0.0143
0.0029
46,200.00
66,000.00
660.66
191.40
0.0020
0.0010
1.00
852.06
33,600.00
90,900.00
25.00
9,390.79
=
=
Jenis Pekerjaan
Harga Satuan/m3
URAIAN PEKERJAAN
BAHAN
1 Beton Readymix K-300
SATUAN
m3
1.03
749,100.00
Jumlah Bahan
B
UPAH
1 Pekerja
2 Mandor
Hari
Hari
0.9091
0.2273
46,200.00
66,000.00
Jumlah Upah
C
1
2
3
4
ALAT
Concrete Vibrator
Air Compressor
Concrete Pump
Alat bantu
Jam
Jam
Jam
Ls
0.1250
0.0500
0.0833
1.00
28,500.00
103,800.00
374,000.00
2,500.00
Jumlah Alat
Jumlah
67.20
90.90
25.00
183.10
Jumlah
JUMLAH (Rp.)
7,811.00
15,515.00
Jumlah Bahan
Jumlah Alat
NO
9,390.79
1.03
0.02
Jumlah Upah
C
8,400,000.00
7,875,000.00
1,680,000.00
17,955,000.00
Jenis Pekerjaan
Harga Satuan/Kg
NO
JUMLAH (Rp.)
870,981.92
JUMLAH (Rp.)
771,573.00
771,573.00
42,000.42
15,001.80
57,002.22
3,562.50
5,190.00
31,154.20
2,500.00
42,406.70
870,981.92
URAIAN PEKERJAAN
A
1
2
3
4
5
6
BAHAN
Kayu Perancah
Multipleks t = 12 mm
Paku
Minyak Bekisting
Klem Baja, Baut dll
Baja Profil dan Plat
1
2
3
4
UPAH
Pekerja
Tukang
Kepala Tukang
Mandor
=
=
SATUAN
VOLUME
m3
lbr
kg
ltr
Ls
kg
0.0560
0.1910
0.3500
0.2000
1.0000
2.58
Rp.
HARGA SATUAN (Rp.)
2,535,600.00
168,512.00
15,848.00
5,283.00
25,000.00
19,661.00
Jumlah Bahan
Hari
Hari
Hari
Hari
0.8000
0.2667
0.2667
0.1333
ALAT
1 Perahu Kerja
2 Alat Bantu
Ls
Ls
46,200.00
60,500.00
66,000.00
66,000.00
1.0000
1.0000
10,000.00
5,000.00
=
=
URAIAN PEKERJAAN
1
2
3
4
5
BAHAN
Kayu Perancah
Multipleks t = 12 mm
Paku
Minyak Bekisting
Klem Baja, Baut dll
1
2
3
4
UPAH
Pekerja
Tukang
Kepala Tukang
Mandor
SATUAN
m3
lbr
kg
ltr
Ls
0.0250
0.1910
0.6000
0.4000
1.0000
2,535,600.00
168,512.00
15,848.00
5,283.00
7,500.00
Jumlah Bahan
Hari
Hari
Hari
Hari
0.5000
0.1667
0.1667
0.0833
46,200.00
60,500.00
66,000.00
66,000.00
Jumlah Upah
ALAT
1 Alat Bantu
2 Scaffolding
Ls
m2
1.0000
1.0000
191,378.46
JUMLAH (Rp.)
63,390.00
32,181.11
9,508.80
2,113.20
7,500.00
114,693.11
23,100.00
10,085.35
11,002.20
5,497.80
49,685.35
2,000.00
25,000.00
Jumlah Alat
Jumlah
10,000.00
5,000.00
350,999.57
Jenis Pekerjaan
Harga Satuan/m2
36,960.00
16,135.35
17,602.20
8,797.80
15,000.00
Jumlah
141,990.17
32,181.11
5,546.80
1,056.60
25,000.00
50,729.54
79,495.35
Jumlah Alat
NO
JUMLAH (Rp.)
256,504.22
Jumlah Upah
C
350,999.57
2,000.00
25,000.00
27,000.00
191,378.46
Jenis Pekerjaan
Harga Satuan/ton
Volume
NO
URAIAN PEKERJAAN
SATUAN
VOLUME
211,623.21
JUMLAH (Rp.)
BAHAN
1
2
3
Jumlah Bahan
B
1
2
3
4
UPAH
Pekerja
Pembantu surveyor
Mandor
Operator
Hari
Hari
Hari
Hari
0.2000
0.2000
0.1000
0.2000
46,200.00
55,000.00
66,000.00
93,500.00
9,240.00
11,000.00
6,600.00
18,700.00
45,540.00
439,900.00
556,400.00
73,331.33
92,751.88
Jumlah Upah
C
ALAT
1 Crane Kap. 25 Ton
2 Hammer Diesel 4.5 Ton + Leader
Jam
Jam
0.1667
0.1667
Jumlah Alat
166,083.21
Jumlah
211,623.21
=
=
=
Jenis Pekerjaan
Harga Satuan/ton
Volume
NO
URAIAN PEKERJAAN
SATUAN
Pengukuran
Rp.
VOLUME
JUMLAH (Rp.)
BAHAN
1
2
3
Jumlah Bahan
B
1
2
3
4
UPAH
Pekerja
Pembantu surveyor
Mandor
Operator
Hari
Hari
Hari
Hari
0.2500
0.2500
0.1250
0.2500
ALAT
1 Crane Kap. 40 Ton
2 Hammer Diesel 4.5 Ton + Leader
3 Ponton Service
Jam
Jam
Jam
0.2000
0.2000
0.2000
11,550.00
13,750.00
8,250.00
23,375.00
56,925.00
581,900.00
556,400.00
1,288,900.00
116,380.00
111,280.00
257,780.00
Jumlah Alat
Jumlah
46,200.00
55,000.00
66,000.00
93,500.00
Jumlah Upah
542,365.00
485,440.00
542,365.00
Jenis Pekerjaan
Harga Satuan/buah
NO
A
URAIAN PEKERJAAN
BAHAN
1 Oxigen
2 Acetelyn
SATUAN
tabung
tabung
0.2000
0.2000
126,780.00
158,475.00
Jumlah Bahan
UPAH
1 Pekerja
2 Mandor
3 Tukang
Hari
Hari
Hari
1.0000
0.2500
0.2500
1
2
3
4
ALAT
Mesin Las
Genset
Crane Kap. 35 Ton
Alat Bantu
Jam
Jam
Jam
Ls
0.2500
0.2500
0.0667
1.0000
46,200.00
16,500.00
15,125.00
77,825.00
62,600.00
90,900.00
510,500.00
5,000.00
15,650.00
22,725.00
34,033.33
5,000.00
77,408.33
Jumlah
212,284.33
Jenis Pekerjaan
Harga Satuan/buah
=
URAIAN PEKERJAAN
BAHAN
1 Oxigen
2 Acetelyn
SATUAN
tabung
tabung
Rp.
VOLUME
0.2000
0.2000
126,780.00
158,475.00
Jumlah Bahan
UPAH
1 Pekerja
2 Mandor
3 Tukang
Hari
Hari
Hari
1.0000
0.5000
0.5000
1
2
3
4
5
ALAT
Mesin Las
Genset
Crane Kap. 40 Ton
Ponton Service
Alat Bantu
Jam
Jam
Jam
Jam
Ls
0.2500
0.2500
0.0833
0.1667
1.0000
JUMLAH (Rp.)
25,356.00
31,695.00
57,051.00
46,200.00
33,000.00
30,250.00
109,450.00
62,600.00
90,900.00
581,900.00
1,288,900.00
5,000.00
15,650.00
22,725.00
48,472.27
214,816.67
5,000.00
Jumlah Alat
Jumlah
473,164.94
46,200.00
66,000.00
60,500.00
Jumlah Upah
25,356.00
31,695.00
46,200.00
66,000.00
60,500.00
Jumlah Alat
NO
JUMLAH (Rp.)
57,051.00
Jumlah Upah
C
212,284.33
306,663.94
473,164.94
Jenis Pekerjaan
=
Harga Satuan/kg
NO
A
=
URAIAN PEKERJAAN
BAHAN
1 Baja Profil dan Plat
2 Pengecatan
SATUAN
Kg
Kg
1.0000
1.0000
19,661.00
3,380.80
Jumlah Bahan
UPAH
1 Pekerja
2 Mandor
3 Tukang
Hari
Hari
Hari
0.0640
0.0080
0.0320
1
2
3
4
5
ALAT
Mesin Las
Genset
Crane Kap. 35 Ton
Ponton Service
Alat Bantu
Jam
Jam
Jam
Jam
Ls
0.0150
0.0100
0.0029
0.0020
1.0000
46,200.00
66,000.00
60,500.00
2,956.80
528.00
1,936.00
5,420.80
62,600.00
90,900.00
510,500.00
1,288,900.00
250.00
939.00
909.00
1,458.57
2,577.80
250.00
Jumlah Alat
6,134.37
Jumlah
34,596.97
=
=
Jenis Pekerjaan
Harga Satuan/kg
NO
URAIAN PEKERJAAN
SATUAN
8,755.79
JUMLAH (Rp.)
BAHAN
1 Pengecatan
Kg
1.0000
3,380.80
Jumlah Bahan
19,661.00
3,380.80
23,041.80
Jumlah Upah
C
JUMLAH (Rp.)
UPAH
1 Pekerja
2 Mandor
3 Tukang
Hari
Hari
Hari
0.0267
0.0033
0.0133
1
2
3
4
ALAT
Mesin Las
Genset
Crane Kap. 35 Ton
Alat Bantu
Jam
Jam
Jam
Ls
0.0150
0.0100
0.0020
1.0000
Jumlah Alat
Jumlah
3,380.80
46,200.00
66,000.00
60,500.00
1,233.54
217.80
804.65
2,255.99
62,600.00
90,900.00
510,500.00
250.00
939.00
909.00
1,021.00
250.00
Jumlah Upah
C
3,380.80
3,119.00
8,755.79
Jenis Pekerjaan
Harga Satuan/kg
NO
A
=
URAIAN PEKERJAAN
BAHAN
1 Baja Profil dan Plat
2 Pengecatan
SATUAN
Kg
Kg
Rp.
VOLUME
1.0000
1.0000
19,661.00
3,500.00
Jumlah Bahan
UPAH
1 Pekerja
2 Mandor
3 Tukang
Hari
Hari
Hari
0.0640
0.0080
0.0320
1
2
3
4
5
ALAT
Mesin Las
Genset
Crane Kap. 35 Ton
Ponton Service
Alat Bantu
Jam
Jam
Jam
Jam
Ls
0.0150
0.0100
0.0040
0.0025
1.0000
19,661.00
3,500.00
23,161.00
2,956.80
528.00
1,936.00
5,420.80
62,600.00
90,900.00
510,500.00
1,288,900.00
250.00
939.00
909.00
2,042.00
3,222.25
250.00
Jumlah Alat
Jumlah
JUMLAH (Rp.)
46,200.00
66,000.00
60,500.00
Jumlah Upah
35,944.05
7,362.25
35,944.05
Jenis Pekerjaan
Harga Satuan/m3
Volume
=
=
NO
A
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting Pile Cap (Bahan)
3 Pembesian (Bahan)
SATUAN
m3
m2
kg
1.0000
2.0000
103.0300
771,573.00
256,504.22
8,355.63
Jumlah Bahan
UPAH
1 Beton K-300 (Upah)
2 Bekisting Pile Cap (Upah)
3 Pembesian (Upah)
m3
m2
kg
1.0000
2.0000
103.0300
ALAT
1 Beton K-300 (Alat)
2 Bekisting Pile Cap (Alat)
3 Pembesian (Alat)
m3
m2
kg
57,002.22
79,495.35
852.06
1.0000
2.0000
103.0300
42,406.70
15,000.00
183.10
Harga Satuan/m3
Volume
=
=
URAIAN PEKERJAAN
SATUAN
JUMLAH (Rp.)
BAHAN
1 Beton K-300 (Bahan)
m3
1.0000
771,573.00
771,573.00
2 Pembesian (Bahan)
3 Plat Beton
kg
kg
285.3600
35.3250
8,355.63
19,661.00
2,384,362.58
694,524.83
Jumlah Bahan
3,850,460.41
UPAH
1 Beton K-300 (Upah)
m3
1.0000
57,002.22
57,002.22
2 Pembesian (Upah)
kg
285.3600
852.06
243,143.84
Jumlah Upah
C
42,406.70
30,000.00
18,864.79
2,540,514.15
Jenis Pekerjaan
57,002.22
158,990.70
87,787.74
91,271.49
Jumlah
771,573.00
513,008.44
860,880.56
303,780.66
Jumlah Alat
NO
JUMLAH (Rp.)
2,145,462.00
Jumlah Upah
C
2,540,514.15
m3
300,146.06
ALAT
1 Beton K-300 (Alat)
m3
1.0000
42,406.70
42,406.70
2 Pembesian (Alat)
kg
285.3600
183.10
52,249.42
Jumlah Alat
Jumlah
94,656.12
4,245,262.59
Jenis Pekerjaan
Harga Satuan/m3
NO
A
=
URAIAN PEKERJAAN
BAHAN
1 Beton Readymix K-Bo
SATUAN
Rp.
VOLUME
m3
1.03
635,800.00
Jumlah Bahan
B
UPAH
1 Pekerja
2 Mandor
Hari
Hari
0.5000
0.1250
ALAT
1 Concrete Vibrator
2 Air Compressor
3 Alat bantu
Jam
Jam
Ls
46,200.00
66,000.00
0.1250
0.0333
1.00
28,500.00
103,800.00
1,000.00
=
URAIAN PEKERJAAN
SATUAN
m3
Rp.
VOLUME
1.20
126,780.00
Jumlah Bahan
B
UPAH
1 Pekerja
2 Mandor
Hari
Hari
1.0000
0.2500
ALAT
1 Alat bantu
Ls
46,200.00
66,000.00
1.00
Jumlah
JUMLAH (Rp.)
152,136.00
46,200.00
16,500.00
62,700.00
5,000.00
Jumlah Alat
219,836.00
152,136.00
Jumlah Upah
C
3,562.50
3,456.54
1,000.00
694,243.04
Jenis Pekerjaan
Harga Satuan/m3
BAHAN
1 Batu Kali
23,100.00
8,250.00
8,019.04
Jumlah
654,874.00
31,350.00
Jumlah Alat
NO
JUMLAH (Rp.)
654,874.00
Jumlah Upah
C
694,243.04
5,000.00
5,000.00
219,836.00
Harga Satuan/m3
Volume
=
=
NO
A
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting Pile Cap (Bahan)
3 Pembesian (Bahan)
SATUAN
m3
m2
kg
1.0000
2.0000
109.0186
771,573.00
256,504.22
8,355.63
Jumlah Bahan
UPAH
1 Beton K-300 (Upah)
2 Bekisting Pile Cap (Upah)
3 Pembesian (Upah)
m3
m2
kg
1.0000
2.0000
109.0186
57,002.22
79,495.35
852.06
Jumlah Upah
ALAT
1 Beton K-300 (Alat)
2 Bekisting Pile Cap (Alat)
3 Pembesian (Alat)
m3
m2
kg
1.0000
2.0000
109.0186
42,406.70
15,000.00
183.10
Harga Satuan/m3
Volume
=
=
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting Pile Cap (Bahan)
3 Pembesian (Bahan)
UPAH
1 Beton K-300 (Upah)
2 Bekisting Pile Cap (Upah)
3 Pembesian (Upah)
SATUAN
m3
m2
kg
VOLUME
1.0000
2.0000
114.2099
771,573.00
256,504.22
8,355.63
m3
m2
kg
1.0000
2.0000
114.2099
57,002.22
79,495.35
852.06
Jumlah Upah
ALAT
1 Beton K-300 (Alat)
2 Bekisting Pile Cap (Alat)
3 Pembesian (Alat)
m3
m2
kg
1.0000
2.0000
114.2099
JUMLAH (Rp.)
771,573.00
513,008.44
954,295.97
2,238,877.41
57,002.22
158,990.70
97,313.72
313,306.64
42,406.70
15,000.00
183.10
Jumlah Alat
Jumlah
42,406.70
30,000.00
19,961.30
Jumlah Bahan
57,002.22
158,990.70
92,890.37
2,596,751.61
Jenis Pekerjaan
2,195,500.32
92,368.00
Jumlah
771,573.00
513,008.44
910,918.88
308,883.29
Jumlah Alat
NO
JUMLAH (Rp.)
42,406.70
30,000.00
20,911.84
93,318.54
2,645,502.59
Jenis Pekerjaan
Harga Satuan/m3
Volume
=
=
NO
A
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting Pile Cap (Bahan)
3 Pembesian (Bahan)
SATUAN
m3
m2
kg
1.0000
2.0000
158.4504
771,573.00
256,504.22
8,355.63
Jumlah Bahan
UPAH
1 Beton K-300 (Upah)
2 Bekisting Pile Cap (Upah)
3 Pembesian (Upah)
m3
m2
kg
1.0000
2.0000
158.4504
57,002.22
79,495.35
852.06
Jumlah Upah
ALAT
1 Beton K-300 (Alat)
2 Bekisting Pile Cap (Alat)
3 Pembesian (Alat)
m3
m2
kg
1.0000
2.0000
158.4504
42,406.70
15,000.00
183.10
Harga Satuan/m3
Volume
=
=
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting Pile Cap (Bahan)
3 Pembesian (Bahan)
UPAH
1 Beton K-300 (Upah)
2 Bekisting Pile Cap (Upah)
3 Pembesian (Upah)
SATUAN
m3
m2
kg
VOLUME
1.0000
2.0000
128.1185
771,573.00
256,504.22
8,355.63
m3
m2
kg
1.0000
2.0000
128.1185
57,002.22
79,495.35
852.06
Jumlah Upah
ALAT
1 Beton K-300 (Alat)
2 Bekisting Pile Cap (Alat)
3 Pembesian (Alat)
m3
m2
kg
1.0000
2.0000
128.1185
JUMLAH (Rp.)
771,573.00
513,008.44
1,070,510.83
2,355,092.27
57,002.22
158,990.70
109,164.65
325,157.57
42,406.70
15,000.00
183.10
Jumlah Alat
Jumlah
42,406.70
30,000.00
29,012.27
Jumlah Bahan
57,002.22
158,990.70
135,009.25
3,060,955.50
Jenis Pekerjaan
2,608,534.36
101,418.97
Jumlah
771,573.00
513,008.44
1,323,952.92
351,002.17
Jumlah Alat
NO
JUMLAH (Rp.)
42,406.70
30,000.00
23,458.50
95,865.20
2,776,115.04
Harga Satuan/m3
Volume
=
=
NO
A
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting Pile Cap (Bahan)
3 Pembesian (Bahan)
SATUAN
m3
m2
kg
1.0000
2.0000
128.1185
771,573.00
256,504.22
8,355.63
Jumlah Bahan
UPAH
1 Beton K-300 (Upah)
2 Bekisting Pile Cap (Upah)
3 Pembesian (Upah)
m3
m2
kg
1.0000
2.0000
128.1185
57,002.22
79,495.35
852.06
Jumlah Upah
ALAT
1 Beton K-300 (Alat)
2 Bekisting Pile Cap (Alat)
3 Pembesian (Alat)
m3
m2
kg
1.0000
2.0000
128.1185
42,406.70
15,000.00
183.10
=
=
URAIAN PEKERJAAN
SATUAN
m3
1.20
123,611.00
Jumlah Bahan
B
UPAH
1 Pekerja
2 Mandor
Hari
Hari
0.1000
0.0250
46,200.00
66,000.00
Jumlah Upah
C
1
2
3
4
ALAT
Motor Grader
Mesin Gilas
Water Tank Truck
Alat bantu
Jam
Jam
Jam
Ls
0.0167
0.0250
0.0125
1.00
423,900.00
309,900.00
220,900.00
1,500.00
Jumlah Alat
Jumlah
57,002.22
158,990.70
109,164.65
42,406.70
30,000.00
23,458.50
2,776,115.04
Jenis Pekerjaan
Harga Satuan/m3
BAHAN
1 Sirtu
2,355,092.27
95,865.20
Jumlah
771,573.00
513,008.44
1,070,510.83
325,157.57
Jumlah Alat
NO
JUMLAH (Rp.)
173,691.08
JUMLAH (Rp.)
148,333.20
148,333.20
4,620.00
1,650.00
6,270.00
7,079.13
7,747.50
2,761.25
1,500.00
19,087.88
173,691.08
Jenis Pekerjaan
Harga Satuan/m3
NO
A
URAIAN PEKERJAAN
BAHAN
1 Tanah Timbunan
SATUAN
m3
1.20
52,825.00
Jumlah Bahan
B
UPAH
1 Pekerja
2 Mandor
Hari
Hari
0.0800
0.0200
1
2
3
4
ALAT
Motor Grader
Mesin Gilas
Water Tank Truck
Alat bantu
Jam
Jam
Jam
Ls
46,200.00
66,000.00
0.0167
0.0125
0.0167
1.00
423,900.00
309,900.00
220,900.00
500.00
=
URAIAN PEKERJAAN
SATUAN
m3
Rp.
VOLUME
1.20
153,193.00
Jumlah Bahan
B
UPAH
1 Pekerja
2 Mandor
Hari
Hari
0.1000
0.0250
46,200.00
66,000.00
Jumlah Upah
C
1
2
3
4
ALAT
Motor Grader
Mesin Gilas
Water Tank Truck
Alat bantu
Jam
Jam
Jam
Ls
0.0167
0.0250
0.0125
1.00
423,900.00
309,900.00
220,900.00
1,500.00
Jumlah Alat
Jumlah
7,079.13
3,873.75
3,689.03
500.00
83,547.91
Jenis Pekerjaan
Harga Satuan/m3
BAHAN
1 Base Course
3,696.00
1,320.00
15,141.91
Jumlah
63,390.00
5,016.00
Jumlah Alat
NO
JUMLAH (Rp.)
63,390.00
Jumlah Upah
C
83,547.91
209,189.48
JUMLAH (Rp.)
183,831.60
183,831.60
4,620.00
1,650.00
6,270.00
7,079.13
7,747.50
2,761.25
1,500.00
19,087.88
209,189.48
Jenis Pekerjaan
Harga Satuan/m3
NO
A
URAIAN PEKERJAAN
BAHAN
1 Pasir Urug
SATUAN
m3
1.20
116,215.00
Jumlah Bahan
B
UPAH
1 Pekerja
2 Mandor
Hari
Hari
0.0800
0.0200
46,200.00
66,000.00
Jumlah Upah
JUMLAH (Rp.)
139,458.00
139,458.00
3,696.00
1,320.00
5,016.00
ALAT
1 Mesin Gilas
2 Water Tank Truck
3 Alat bantu
Jam
Jam
Ls
0.0250
0.0167
1.00
309,900.00
220,900.00
2,500.00
Jumlah Alat
Jumlah
7,747.50
3,689.03
2,500.00
13,936.53
158,410.53
Jenis Pekerjaan
Harga Satuan/m3
NO
A
URAIAN PEKERJAAN
BAHAN
1 Paving Block
SATUAN
m3
#REF!
Rp.
VOLUME
1.05
95,085.00
Jumlah Bahan
B
UPAH
1 Pekerja
2 Mandor
Hari
Hari
0.2667
0.0333
JUMLAH (Rp.)
99,839.25
99,839.25
46,200.00
66,000.00
Jumlah Upah
116,858.59
12,321.54
2,197.80
14,519.34
ALAT
1 Alat bantu
Ls
1.00
2,500.00
Jumlah Alat
Jumlah
2,500.00
2,500.00
116,858.59
Jenis Pekerjaan
Harga Satuan/m3
NO
A
Pengadaan material dan pemasangan batu armour ukuran 150 - 200 Kg/unit
=
URAIAN PEKERJAAN
BAHAN
1 Batu Belah 150 - 200 kg/unit
SATUAN
m3
Rp.
VOLUME
1.20
158,475.00
Jumlah Bahan
B
UPAH
1 Pekerja
2 Mandor
Hari
Hari
0.2667
0.0667
46,200.00
66,000.00
Jumlah Upah
ALAT
1 Dump Truck
2 Excavator
3 Alat bantu
Jam
Jam
Ls
0.2000
0.0400
1.00
241,400.00
407,900.00
5,000.00
Jumlah Alat
Jumlah
276,489.74
JUMLAH (Rp.)
190,170.00
190,170.00
12,321.54
4,402.20
16,723.74
48,280.00
16,316.00
5,000.00
69,596.00
276,489.74
Jenis Pekerjaan
Harga Satuan/m3
NO
A
Pengadaan material dan pemasangan batu armour ukuran 300 - 500 Kg/unit
=
URAIAN PEKERJAAN
BAHAN
1 Batu Belah 300 - 500 kg/unit
SATUAN
m3
Rp.
VOLUME
1.20
211,300.00
Jumlah Bahan
B
UPAH
1 Pekerja
2 Mandor
Hari
Hari
0.2667
0.0667
46,200.00
66,000.00
Jumlah Upah
ALAT
1 Dump Truck
2 Excavator
3 Alat bantu
Jam
Jam
Ls
0.2000
0.0667
1.00
241,400.00
407,900.00
5,000.00
Jumlah Alat
Jumlah
350,770.67
JUMLAH (Rp.)
253,560.00
253,560.00
12,321.54
4,402.20
16,723.74
48,280.00
27,206.93
5,000.00
80,486.93
350,770.67
Jenis Pekerjaan
Harga Satuan/m3
Volume
NO
A
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting (Bahan)
3 Pembesian (Bahan)
SATUAN
m3
m2
kg
1.0000
1.5000
150.0000
771,573.00
256,504.22
8,355.63
Jumlah Bahan
UPAH
1 Beton K-300 (Upah)
2 Bekisting (Upah)
3 Pembesian (Upah)
m3
m2
kg
1.0000
1.5000
150.0000
ALAT
1 Beton K-300 (Alat)
2 Bekisting (Alat)
3 Pembesian (Alat)
m3
m2
kg
57,002.22
79,495.35
852.06
1.0000
1.5000
150.0000
42,406.70
15,000.00
183.10
2,806,099.78
Jenis Pekerjaan
Harga Satuan/m3
Volume
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting (Bahan)
3 Pembesian (Bahan)
=
=
#REF!
SATUAN
VOLUME
m3
m2
kg
Rp.
UPAH
1 Beton K-300 (Upah)
2 Bekisting (Upah)
3 Pembesian (Upah)
m3
m2
kg
1.0000
1.5000
150.0000
771,573.00
256,504.22
8,355.63
1.0000
1.5000
150.0000
57,002.22
79,495.35
852.06
Jumlah Upah
ALAT
1 Beton K-300 (Alat)
2 Bekisting (Alat)
3 Pembesian (Alat)
m3
m2
kg
1.0000
1.5000
150.0000
JUMLAH (Rp.)
771,573.00
384,756.33
1,253,344.50
2,409,673.83
57,002.22
119,243.03
127,809.00
304,054.25
42,406.70
15,000.00
183.10
Jumlah Alat
Jumlah
2,806,099.78
m3
Jumlah Bahan
B
42,406.70
22,500.00
27,465.00
92,371.70
Jumlah
57,002.22
119,243.03
127,809.00
304,054.25
Jumlah Alat
NO
771,573.00
384,756.33
1,253,344.50
2,409,673.83
Jumlah Upah
C
JUMLAH (Rp.)
42,406.70
22,500.00
27,465.00
92,371.70
2,806,099.78
Jenis Pekerjaan
Harga Satuan/m3
Volume
NO
A
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting (Bahan)
3 Pembesian (Bahan)
=
=
#REF!
SATUAN
VOLUME
m3
m2
kg
Rp.
1.0000
1.5000
125.0000
771,573.00
256,504.22
8,355.63
Jumlah Bahan
UPAH
1 Beton K-300 (Upah)
2 Bekisting (Upah)
3 Pembesian (Upah)
m3
m2
kg
1.0000
1.5000
125.0000
57,002.22
79,495.35
852.06
Jumlah Upah
ALAT
1 Beton K-300 (Alat)
2 Bekisting (Alat)
3 Pembesian (Alat)
m3
m2
kg
1.0000
1.5000
125.0000
42,406.70
15,000.00
183.10
=
=
=
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting (Bahan)
3 Wiremesh D10
SATUAN
m3
m2
m2
1.0000
1.5000
7.0000
771,573.00
114,693.11
74,210.00
Jumlah Bahan
UPAH
1 Beton K-300 (Upah)
2 Bekisting (Upah)
3 Pembesian (Upah)
m3
m2
m2
1.0000
1.5000
7.0000
57,002.22
49,685.35
2,128.53
Jumlah Upah
ALAT
1 Beton K-300 (Alat)
2 Bekisting (Alat)
3 Pembesian (Alat)
m3
m2
m2
1.0000
1.5000
7.0000
57,002.22
119,243.03
106,507.50
42,406.70
22,500.00
22,887.50
1,698,379.19
JUMLAH (Rp.)
771,573.00
172,039.67
519,470.00
1,463,082.67
57,002.22
74,528.03
14,899.69
146,429.94
42,406.70
27,000.00
851.41
Jumlah Alat
Jumlah
2,200,783.08
2,571,330.03
Jenis Pekerjaan
Harga Satuan/m3
Volume
771,573.00
384,756.33
1,044,453.75
87,794.20
Jumlah
JUMLAH (Rp.)
282,752.75
Jumlah Alat
NO
2,571,330.03
m3
42,406.70
40,500.00
5,959.88
88,866.58
1,698,379.19
Jenis Pekerjaan
Harga Satuan/m3
Volume
NO
A
=
=
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting (Bahan)
3 Wiremesh D10
SATUAN
m3
m2
m2
1.0000
1.5000
7.0000
771,573.00
114,693.11
74,210.00
Jumlah Bahan
UPAH
1 Beton K-300 (Upah)
2 Bekisting (Upah)
3 Pembesian (Upah)
m3
m2
m2
1.0000
1.5000
7.0000
ALAT
1 Beton K-300 (Alat)
2 Bekisting (Alat)
3 Pembesian (Alat)
m3
m2
m2
57,002.22
49,685.35
2,128.53
1.0000
1.5000
7.0000
42,406.70
27,000.00
851.41
=
=
=
URAIAN PEKERJAAN
SATUAN
480,375.73
m3
HARGA SATUAN (Rp.)
JUMLAH (Rp.)
BAHAN
1 Batu Kali
2 Semen PC 50 Kg/zak
3 Pasir Beton
m3
zak
m3
1.2000
3.0000
0.4900
126,780.00
63,390.00
126,780.00
Jumlah Bahan
UPAH
1 Pekerja
2 Tukang
3 Mandor
Hari
Hari
kg
0.6667
0.3333
0.2500
46,200.00
60,500.00
66,000.00
Jumlah Upah
42,406.70
40,500.00
5,959.88
1,698,379.19
Jenis Pekerjaan
Harga Satuan/m3
Volume
57,002.22
74,528.03
14,899.69
88,866.58
Jumlah
771,573.00
172,039.67
519,470.00
146,429.94
Jumlah Alat
NO
JUMLAH (Rp.)
1,463,082.67
Jumlah Upah
C
1,698,379.19
m3
ALAT
1 Concrete Mixer
Jam
0.2000
Jumlah
404,428.20
30,801.54
20,164.65
16,500.00
67,466.19
42,406.70
Jumlah Alat
152,136.00
190,170.00
62,122.20
8,481.34
8,481.34
480,375.73
Jenis Pekerjaan
Harga Satuan/m3
Volume
=
=
NO
A
URAIAN PEKERJAAN
BAHAN
1 Beton K-300 (Bahan)
2 Bekisting Pile Cap (Bahan)
3 Pembesian (Bahan)
SATUAN
m3
m2
kg
Beton bertulang (K-300, U32) pile cap dan sbg pondasi kolom
penyangga selter, 18 unit, dim.1600x1200x1200
2,887,691.66
Rp.
41.00 m3
VOLUME
1.0000
2.0000
140.0000
771,573.00
256,504.22
8,355.63
Jumlah Bahan
UPAH
1 Beton K-300 (Upah)
2 Bekisting Pile Cap (Upah)
3 Pembesian (Upah)
m3
m2
kg
1.0000
2.0000
140.0000
ALAT
1 Beton K-300 (Alat)
2 Bekisting Pile Cap (Alat)
3 Pembesian (Alat)
m3
m2
kg
57,002.22
79,495.35
852.06
1.0000
2.0000
140.0000
42,406.70
15,000.00
183.10
2,887,691.66
Jenis Pekerjaan
Harga Satuan/m3
Volume
=
=
URAIAN PEKERJAAN
1
2
3
4
BAHAN
Beton K-300 (Bahan)
Bekisting Pile Cap (Bahan)
Pembesian (Bahan)
Angkur
UPAH
1 Beton K-300 (Upah)
2 Bekisting Pile Cap (Upah)
3 Pembesian (Upah)
SATUAN
ALAT
1 Beton K-300 (Alat)
2 Bekisting Pile Cap (Alat)
3 Pembesian (Alat)
JUMLAH (Rp.)
m3
m2
kg
Ls
1.0000
3.5000
128.7875
1.00
771,573.00
191,378.46
8,355.63
250,000.00
Jumlah Bahan
771,573.00
669,824.61
1,076,100.70
250,000.00
2,767,498.31
m3
m2
kg
1.0000
3.5000
128.7875
57,002.22
79,495.35
852.06
57,002.22
278,233.73
109,734.68
m3
m2
kg
1.0000
3.5000
128.7875
444,970.63
42,406.70
15,000.00
183.10
Jumlah Alat
Jumlah
3,330,956.63
m3
Jumlah Upah
C
42,406.70
30,000.00
25,634.00
98,040.70
Jumlah
57,002.22
158,990.70
119,288.40
335,281.32
Jumlah Alat
NO
771,573.00
513,008.44
1,169,788.20
2,454,369.64
Jumlah Upah
C
JUMLAH (Rp.)
42,406.70
52,500.00
23,580.99
118,487.69
3,330,956.63
URAIAN PEKERJAAN
UNIT
Pekerjaan Persiapan
Mobilisasi dan Demobilsasi
Pengukuran dan Positioning
Direksi Keet beserta kelengkapannya
Pagar Pengaman Proyek
Instalasi listrik, penerangan dan air kerja
a. Instalasi listrik dan air kerja
b. Biaya pemakaian listrik dan air kerja
6 Keselamatan Kerja
7 Administrasi, As built drawing dan Dokumentasi
1
2
3
4
5
VOLUME
HARGA SATUAN
(Rp.)
Ls
Ls
m2
m'
1.00
1.00
36.00
160.00
519,750,000.00
47,107,500.00
787,500.00
150,000.00
519,750,000.00
47,107,500.00
28,350,000.00
24,000,000.00
Ls
Bln
Bln
Ls
1.00
8.00
8.00
1.00
8,400,000.00
4,725,000.00
3,609,375.00
17,955,000.00
8,400,000.00
37,800,000.00
28,875,000.00
17,955,000.00
712,237,500.00
Kg
m
unit
unit
unit
unit
Kg
180.00
6.00
12.00
6.00
6.00
140.00
211,623.21
212,284.33
262,500.00
744,432.50
182,310.00
30,385.00
38,092,177.80
1,273,705.98
3,150,000.00
4,466,595.00
1,093,860.00
4,253,900.00
52,330,238.78
Kg
m
unit
unit
unit
unit
Kg
m2
1,650.00
55.00
110.00
55.00
55.00
18,800.00
580.00
542,365.00
473,164.94
567,000.00
1,792,715.00
717,086.00
30,385.00
846,443.58
894,902,250.00
26,024,071.70
62,370,000.00
98,599,325.00
39,439,730.00
571,238,000.00
490,937,275.00
2,183,510,651.70
m3
m3
m3
m3
m3
m3
unit
unit
26.87
3.01
3.62
27.47
41.20
80.71
28.00
3.00
2,540,514.15
4,245,262.59
694,243.04
219,836.00
45,000.00
56,250.00
1,931,250.00
31,981,500.00
68,263,615.21
12,778,240.40
2,513,159.80
6,038,894.92
1,854,000.00
4,539,937.50
54,075,000.00
95,944,500.00
246,007,347.83
m3
m3
m3
m3
m3
m3
unit
unit
89.60
97.28
78.40
102.40
224.00
55.26
9.00
8.00
2,596,751.61
2,645,502.59
3,060,955.50
2,776,115.04
2,776,115.04
4,245,262.59
31,981,500.00
18,726,945.00
232,668,944.26
257,354,491.96
239,978,911.20
284,274,180.10
621,849,768.96
234,593,210.72
287,833,500.00
149,815,560.00
unit
2.00
23,950,590.00
47,901,180.00
unit
2.00
20,859,045.00
41,718,090.00
unit
22.00
1,456,935.00
32,052,570.00
2,430,040,407.19
Sub Total
B
1
2
3
4
5
6
7
Tiang Pancang dan Assesoriesnya (Pondasi kolom penyangga gangway dan ESR, laut)
1 Pengadaan Tiang pancang 812,3 mm, t=14 mm ( w = 276 kg/m') (TA.2011)
2 Pemancangan tiang pancang dia. 812,3 mm
3 Pemotongan tiang pancang, setting dan penyambungan
Penyambungan tiang pancang setiap 12m
4 Ring pelat Dia=1200mm, t= 12 mm ( w = 59 kg/unit)
5 Pelat penutup tiang dia. 812,3 mm, t= 6mm ( w = 23,6 Kg/unit)
6 Bracing pengaku tiang pancang H 300 x 300 x 10/15 (w=94Kg/m')
7 Pengadaan dan Pemasangan Selimut Tiang Pancang (Pelindung Karat, PE Cover)
Sub Total
D
1
2
3
4
5
6
7
8
JUMLAH HARGA
(Rp.)
No
URAIAN PEKERJAAN
F
1
2
3
4
5
6
7
8
9
10
11
12
13
14
UNIT
m3
m3
m3
m3
m2
m2
m3
m3
m3
m
m3
unit
unit
m
VOLUME
5,756.00
1,279.00
1,066.00
127.50
2,050.00
525.00
87.75
1,409.89
600.00
10.00
82.00
30.00
120.00
75.00
HARGA SATUAN
(Rp.)
173,691.08
83,547.91
209,189.48
158,410.53
116,858.59
16,102.13
2,806,099.78
276,489.74
350,770.67
45,000.00
480,375.73
225,000.00
309,375.00
84,375.00
Sub Total
G
1
2
3
4
5
6
7
8
Tiang Pancang dan Assesoriesnya (Abutment ESR dan Kolom Penyangga Gangway)
Pengadaan Tiang pancang 812,8 mm, t=14 mm ( w = 276 kg/m') (TA. 2011)
Pemancangan tiang pancang dia. 812.8 mm
Pemotongan tiang, setting
Penyambungan tiang pancang setiap 12m
Ring pelat Dia=1200mm, t= 12 mm ( w = 59 kg/unit)
Pelat penutup tiang dia. 812.3 mm, t= 6mm ( w = 24 Kg/unit)
Bracing pengaku tiang pancang H 300 x 300 x 10/15 (w=94 Kg/m')
Base plate dan angkur untuk post guard rail ( w= 12Kg/unit )
1
2
3
4
5
6
7
8
9
10
Kg
m
unit
unit
unit
unit
Kg
unit
60.00
2.00
4.00
2.00
2.00
348.00
12.00
542,365.00
473,164.94
567,000.00
1,792,715.00
729,240.00
30,385.00
364,620.00
32,541,900.00
946,329.88
2,268,000.00
3,585,430.00
1,458,480.00
10,573,980.00
4,375,440.00
55,749,559.88
m3
m3
unit
unit
m
Kg
m3
m3
m3
m3
27.00
2.00
1.00
2.00
15.00
750.00
20.00
5.00
20.00
15.00
2,806,099.78
4,245,262.59
31,981,500.00
1,367,325.00
607,700.00
35,535.00
2,571,330.03
694,243.04
209,189.48
173,691.08
Sub Total
I
999,765,856.48
106,857,776.89
222,995,985.68
20,197,342.58
239,560,109.50
8,453,615.63
246,235,255.70
389,820,119.53
210,462,402.00
450,000.00
39,390,809.86
6,750,000.00
37,125,000.00
6,328,125.00
2,534,392,398.83
Sub Total
H
JUMLAH HARGA
(Rp.)
75,764,694.06
8,490,525.18
31,981,500.00
2,734,650.00
9,115,500.00
26,651,250.00
51,426,600.60
3,471,215.20
4,183,789.60
2,605,366.20
216,425,090.84
Kg
2 Pengadaan, pabrikasi pengecatan dan pemasangan konstruksi kolom penyangga (TA. 2011)
Kg
3 Pengadaan, pabrikasi konstruksi gangway (tanpa pengecatan dan pemancangan) (TA. 2011)
Kg
Pengadaan, pabrikasi kontruksi kolom penyangga (tanpa pengecatan dan pemasangan) (TA.
4 2011)
Kg
5
6
7
8
9
Kg
Kg
m3
m2
m2
120,739.000
26,638.000
38.00
363.00
727.00
8,755.79
8,755.79
1,698,379.19
178,190.00
87,550.00
1,057,165,328.81
233,236,734.02
64,538,409.22
64,682,970.00
63,648,850.00
m2
220.00
unit
53.00
918,760.00
393,750.00
202,127,200.00
20,868,750.00
1,706,268,242.05
No
URAIAN PEKERJAAN
J
1
2
3
4
5
6
7
8
9
UNIT
Kg
Kg
Kg
Kg
m3
m2
m2
m2
unit
VOLUME
37,302.00
146,823.00
43,800.00
88.00
735.00
1,593.00
245.00
50.00
HARGA SATUAN
(Rp.)
34,596.97
8,755.79
35,944.05
1,698,379.19
178,190.00
87,550.00
918,760.00
393,750.00
Sub Total
K
Kg
150,000.00
34,596.97
5,189,545,500.00
5,189,545,500.00
Kg
Kg
Kg
Kg
Kg
Kg
3,600.00
1,169.00
3,600.00
36,050.00
56,135.00
129,780,000.00
65,621,815.00
129,780,000.00
unit
unit
set
1,290,536,174.94
1,285,551,355.17
1,574,349,390.00
149,457,368.72
130,969,650.00
139,467,150.00
225,096,200.00
19,687,500.00
4,815,114,788.83
36,050.00
325,181,815.00
Sub Total
M
JUMLAH HARGA
(Rp.)
Kg
Kg
Kg
Kg
Kg
Kg
22,000.00
5,500.00
25,000.00
610.00
1,130.00
56,135.00
45,835.00
34,505.00
29,458.00
34,505.00
1,234,970,000.00
252,092,500.00
862,625,000.00
17,969,380.00
38,990,650.00
unit
unit
unit
unit
set
titik
m3
m2
2,406,647,530.00
No
N
URAIAN PEKERJAAN
UNIT
Shelter
Pengadaan dan pemasangan konstruksi baja termasuk pengecatan
Pemancangan tiang pancang dia. 400 mm pondasi selter, 18 titik @ 30 m
Pemotongan tiang pancang
Penyambungan tiang pancang
Ring pelat Dia=700mm, t= 12 mm ( w = 24.5 kg/unit)
Pelat penutup tiang dia. 400 mm, t= 6mm ( w = 6 Kg/unit)
Bracing pengaku tiang pancang H 300 x 200 x 8/12 (w=57Kg/m')
Beton bertulang (K-300, U32) pile cap dan sbg pondasi kolom penyangga selter, 18 unit,
5 dim.1600x1200x1200
1
2
3
4
VOLUME
HARGA SATUAN
(Rp.)
JUMLAH HARGA
(Rp.)
Kg
m
Unit
Unit
Unit
Unit
Kg
540.00
18.00
36.00
18.00
18.00
897.75
125,000.00
150,000.00
250,000.00
744,432.50
182,310.00
30,385.00
67,500,000.00
2,700,000.00
9,000,000.00
13,399,785.00
3,281,580.00
27,278,133.75
m3
41.00
2,887,691.66
118,395,358.06
m3
unit
m3
m2
m2
2.00
18.00
54.00
419.00
450.00
3,330,956.63
618,750.00
1,698,379.19
85,000.00
178,190.00
6,661,913.26
11,137,500.00
91,712,476.26
35,615,000.00
80,185,500.00
unit
11.00
9,290,250.00
102,192,750.00
Pengadaan dan pemasangan jendela Tipe-2 dim. 2800x2200mm (rangka alumunium + Kaca dan
12 assesoriesnyuan)
unit
9.00
9,290,250.00
83,612,250.00
Pengadaan dan pemasangan jendela Tipe-3 dim. 2800x1500mm(rangka alumunium + Kaca dan
13 assesoriesnyau)
unit
10.00
6,423,750.00
64,237,500.00
Pengadaan dan pemasangan jendela Tipe-4 dim.2200x900mm (rangka alumunium + Kaca dan
14 assesoriesnya)
unit
2.00
3,177,000.00
6,354,000.00
Pengadaan dan pemasangan jendela Tipe-5 dim.1625x900mm (rangka alumunium + Kaca dan
15 assesoriesnya)
unit
2.00
2,420,156.25
4,840,312.50
Pengadaan dan pemasangan jendela Tipe-6 dim. 1100x500mm (rangka alumunium + Kaca dan
16 assesoriesnya)
unit
2.00
1,085,625.00
2,171,250.00
Pengadaan dan pemasangan pintu double dim.3100x2100 (rangka alumunium + Kaca dan
17 assesoriesnya)
unit
2.00
9,802,125.00
19,604,250.00
m2
500.00
618,750.00
309,375,000.00
m2
m2
unit
m2
m2
set
set
500.00
540.00
6.00
132.00
122.00
1.00
1.00
120,937.50
163,928.57
393,750.00
106,875.00
106,875.00
1,968,750.00
151,875,000.00
60,468,750.00
88,521,428.57
2,362,500.00
14,107,500.00
13,038,750.00
1,968,750.00
151,875,000.00
unit
1.00
16,875,000.00
16,875,000.00
6
7
8
9
10
18
19
20
21
22
23
24
25
26
Pengadaan dan pemasangan Aluminium Komposit Panel PVDF (tebal 4 mm, Al.koil 0,3 mm )
termasuk rangkam dan sealant
Pengadaan dan pemasangan kalsiboard termasuk finishing dan pengecatan
Pengadaan dan pemasangan atap corrugated metal roof termasuk perlengkapannya
Pengadaan dan pemasangan pintu PVC untuk toilet termasuk perlengkapannya
Pekerjaan dinding pasangan bata merah termasuk plesteran, acian dan pengecatan
Pengadaan dan pemasangan dinding keramik 20X20 cm di toilet
Pekerjaan plumbing dan sanitari, termasuk kloset duduk, keran dan perelngkapan lainnya
Pekerjaan elektrikal termasuk jaringan listrik, lampu dan perlengkapan lainnya
Pekerjaan bangunan septic tank (beton bertulang) dim. 2000x2000x3000mm termasuk
kelengkapannya
Sub Total
1,408,472,237.40
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
PEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V
PELABUHAN PENYEBERANGAN MERAK - TAHAP II
TA. 2012
No
A
B
C
D
E
F
G
H
I
J
K
L
M
N
URAIAN PEKERJAAN
BIAYA (Rp.)
Pekerjaan Persiapan
Tiang Pancang dan Assesoriesnya (Pondasi kolom penyangga gangway, darat)
Tiang Pancang dan Assesoriesnya (Pondasi kolom penyangga gangway dan ESR, laut)
Pekerjaan beton dan pelengkapnya (Pondasi kolom penyangga gangway, darat)
Pekerjaan beton dan pelengkapnya (Pondasi kolom penyangga gangway, laut)
Pekerjaan reklamasi dan revetmen
Tiang Pancang dan Assesoriesnya (Abutment ESR dan Kolom Penyangga Gangway)
Pekerjaan beton dan pelengkapnya (Abutment dan Appron ESR)
Konstruksi Gangway dan Kolom Penyangga ( 267 m, bagian darat )
Konstruksi Gangway dan Kolom Penyangga ( 200 m, bagian laut )
Konstruksi Baja Apron ESR (Elevated Side Ramp)
Movable Gangway
Elevated Side Ramp
Shelter
712,237,500.00
52,330,238.78
2,183,510,651.70
246,007,347.83
2,430,040,407.19
2,534,392,398.83
55,749,559.88
216,425,090.84
1,706,268,242.05
4,815,114,788.83
5,189,545,500.00
325,181,815.00
2,406,647,530.00
1,408,472,237.40
Sub Total I
PPN 10%
TOTAL
PEMBULATAN
24,281,923,308.34
2,428,192,330.83
26,710,115,639.17
26,710,115,639.00
Terbilang :
Dua Puluh Enam Milyar Tujuh Ratus Sepuluh Juta Seratus Lima Belas Ribu Enam Ratus Tiga Puluh Sembilan Rupiah
Kepala
No
Bab B
2
3
4
PROSENTASE DARI
HARGA TOTAL
PENAWARAN
(%)
URAIAN PEKERJAAN
0.16%
0.01%
0.01%
3.69%
0.11%
0.26%
Bab D
3
0.01%
Bab H
8
0.01%
Bab C
2
3
4.25%
Kepala
DN
(2)
TKDN
% KDN
(5)
Barang / Jasa Rp
Gabungan %
(7)
(8)
Barang
I
II
22,703,598,293.29
-
22,703,598,293.29
-
100.00%
#DIV/0!
22,703,598,293.29
-
85.00%
0.00%
22,703,598,293.29
22,703,598,293.29
100.00%
22,703,598,293.29
85.00%
667,752,890.98
667,752,890.98
100.00%
667,752,890.98
2.50%
934,854,047.37
1,736,157,516.55
667,752,890.98
934,854,047.37
1,736,157,516.55
667,752,890.98
100.00%
100.00%
100.00%
934,854,047.37
1,736,157,516.55
667,752,890.98
3.50%
6.50%
2.50%
4,006,517,345.88
4,006,517,345.88
100.00%
4,006,517,345.88
15.00%
26,710,115,639.17
26,710,115,639.17
100.00%
26,710,115,639.17
100.00%
Jasa
III
IV
V
VI
Kepala
0
0
0
0
0
0
0
0
0
0
0
5.12051E+11
RUPIAH
26,710,115,639
26,710,115,639
26,710,115
26,710
26
710
115
639
0
26
7
10
1
15
6
39
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
Satu
Dua
Tiga
Empat
Lima
Enam
Tujuh
Delapan
Sembilan
Sepuluh
Sebelas
Dua Belas
Tiga Belas
Empat Belas
Lima Belas
Enam Belas
Tujuh Belas
Delapan Belas
Sembilan Belas
Dua Puluh
Dua Puluh Satu
Dua Puluh Dua
Dua Puluh Tiga
Dua Puluh Empat
Dua Puluh Lima
Dua Puluh Enam
Dua Puluh Tujuh
Dua Puluh Delapan
Dua Puluh Sembilan
Tiga Puluh
Tiga Puluh Satu
Tiga Puluh Dua
Tiga Puluh Tiga
Tiga Puluh Empat
Tiga Puluh Lima
Tiga Puluh Enam
Tiga Puluh Tujuh
Tiga Puluh Delapan
Tiga Puluh Sembilan
Empat Puluh
Empat Puluh Satu
Empat Puluh Dua
Empat Puluh Tiga
Empat Puluh Empat
Empat Puluh Lima
Empat Puluh Enam
Empat Puluh Tujuh
Empat Puluh Delapan
Empat Puluh Sembilan
Seratus
Lima Belas
Ribu
Enam Ratus
Tiga Puluh Sembilan
Rupiah
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
Lima Puluh
Lima Puluh Satu
Lima Puluh Dua
Lima Puluh Tiga
Lima Puluh Empat
Lima Puluh Lima
Lima Puluh Enam
Lima Puluh Tujuh
Lima Puluh Delapan
Lima Puluh Sembilan
Enam Puluh
Enam Puluh Satu
Enam Puluh Dua
Enam Puluh Tiga
Enam Puluh Empat
Enam Puluh Lima
Enam Puluh Enam
Enam Puluh Tujuh
Enam Puluh Delapan
Enam Puluh Sembilan
Tujuh Puluh
Tujuh Puluh Satu
Tujuh Puluh Dua
Tujuh Puluh Tiga
Tujuh Puluh Empat
Tujuh Puluh Lima
Tujuh Puluh Enam
Tujuh Puluh Tujuh
Tujuh Puluh Delapan
Tujuh Puluh Sembilan
Delapan Puluh
Delapan Puluh Satu
Delapan Puluh Dua
Delapan Puluh Tiga
Delapan Puluh Empat
Delapan Puluh Lima
Delapan Puluh Enam
Delapan Puluh Tujuh
Delapan Puluh Delapan
Delapan Puluh Sembilan
Sembilan Puluh
Sembilan Puluh Satu
Sembilan Puluh Dua
Sembilan Puluh Tiga
Sembilan Puluh Empat
Sembilan Puluh Lima
Sembilan Puluh Enam
Sembilan Puluh Tujuh
Sembilan Puluh Delapan
Sembilan Puluh Sembilan
1
2
26,710,115,639.00
26,710,115,639
Dua Puluh Enam Milyar Tujuh Ratus Sepuluh Juta Seratus Lima Belas Ribu Enam Ratus Tiga Puluh Sembilan Rupiah
2.67E+10
URAIAN PEKERJAAN
UNIT
Pekerjaan Persiapan
Mobilisasi dan Demobilsasi
Pengukuran dan Positioning
Direksi Keet beserta kelengkapannya
Pagar Pengaman Proyek
Instalasi listrik, penerangan dan air kerja
a. Instalasi listrik dan air kerja
b. Biaya pemakaian listrik dan air kerja
6 Keselamatan Kerja
7 Administrasi, As built drawing dan Dokumentasi
1
2
3
4
5
ESTIMASI
KUANTITAS
HARGA SATUAN
(Rp.)
Ls
Ls
m2
m'
1.00
1.00
36.00
160.00
519,750,000.00
47,107,500.00
787,500.00
150,000.00
Ls
Bln
Bln
Ls
1.00
8.00
8.00
1.00
8,400,000.00
4,725,000.00
3,609,375.00
17,955,000.00
Sub Total
B
1
2
3
4
5
6
7
Tiang Pancang dan Assesoriesnya (Pondasi kolom penyangga gangway dan ESR, laut)
1 Pengadaan Tiang pancang 812,3 mm, t=14 mm ( w = 276 kg/m') (TA.2011)
2 Pemancangan tiang pancang dia. 812,3 mm
3 Pemotongan tiang pancang, setting dan penyambungan
Penyambungan tiang pancang setiap 12m
4 Ring pelat Dia=1200mm, t= 12 mm ( w = 59 kg/unit)
5 Pelat penutup tiang dia. 812,3 mm, t= 6mm ( w = 23,6 Kg/unit)
6 Bracing pengaku tiang pancang H 300 x 300 x 10/15 (w=94Kg/m')
7 Pengadaan dan Pemasangan Selimut Tiang Pancang (Pelindung Karat, PE Cover)
Sub Total
D
1
2
3
4
5
6
7
8
JUMLAH HARGA
(Rp.)
Kg
m
unit
unit
unit
unit
Kg
180.00
6.00
12.00
6.00
6.00
140.00
100,000.00
100,000.00
250,000.00
669,989.25
164,079.00
27,346.50
Kg
m
unit
unit
unit
unit
Kg
m2
1,650.00
55.00
110.00
55.00
55.00
18,800.00
580.00
350,000.00
100,000.00
275,000.00
1,613,443.50
645,377.40
27,346.50
550,000.00
4,019,935.50
984,474.00
3,828,510.00
8,832,919.50
88,739,392.50
35,495,757.00
514,114,200.00
638,349,349.50
m3
m3
m3
m3
m3
m3
unit
unit
26.87
3.01
3.62
27.47
41.20
80.71
28.00
3.00
2,540,514.15
4,245,262.59
694,243.04
219,836.00
40,000.00
35,000.00
1,738,125.00
28,783,350.00
m3
m3
m3
m3
m3
m3
unit
unit
89.60
97.28
78.40
102.40
224.00
55.26
9.00
8.00
2,596,751.61
2,645,502.59
3,060,955.50
2,776,115.04
2,776,115.04
4,245,262.59
28,783,350.00
16,854,250.50
259,050,150.00
134,834,004.00
unit
2.00
21,555,531.00
43,111,062.00
unit
2.00
18,773,140.50
37,546,281.00
unit
22.00
1,311,241.50
28,847,313.00
503,388,810.00
48,667,500.00
86,350,050.00
135,017,550.00
No
URAIAN PEKERJAAN
F
1
2
3
4
5
6
7
8
9
10
11
12
13
14
UNIT
m3
m3
m3
m3
m3
m3
m3
m3
m3
m
m3
unit
unit
m
ESTIMASI
KUANTITAS
5,756.00
1,279.00
1,066.00
127.50
2,050.00
525.00
87.75
1,409.89
600.00
10.00
82.00
30.00
120.00
75.00
HARGA SATUAN
(Rp.)
173,691.08
83,547.91
209,189.48
158,410.53
116,858.59
12,500.00
2,806,099.78
276,489.74
350,770.67
40,000.00
450,000.00
200,000.00
275,000.00
75,000.00
Sub Total
G
1
2
3
4
5
6
7
8
Tiang Pancang dan Assesoriesnya (Abutment ESR dan Kolom Penyangga Gangway)
Pengadaan Tiang pancang 812,8 mm, t=14 mm ( w = 276 kg/m') (TA. 2011)
Pemancangan tiang pancang dia. 812.8 mm
Pemotongan tiang, setting
Penyambungan tiang pancang setiap 12m
Ring pelat Dia=1200mm, t= 12 mm ( w = 59 kg/unit)
Pelat penutup tiang dia. 812.3 mm, t= 6mm ( w = 24 Kg/unit)
Bracing pengaku tiang pancang H 300 x 300 x 10/15 (w=94 Kg/m')
Base plate dan angkur untuk post guard rail ( w= 12Kg/unit )
Kg
m
unit
unit
unit
unit
Kg
unit
60.00
2.00
4.00
2.00
2.00
348.00
12.00
150,000.00
100,000.00
250,000.00
1,613,443.50
656,316.00
27,346.50
328,158.00
Sub Total
H
1
2
3
4
5
6
7
8
9
10
1
2
3
3,226,887.00
1,312,632.00
9,516,582.00
3,937,896.00
17,993,997.00
m3
m3
unit
unit
m
Kg
m3
m3
m3
m3
27.00
2.00
1.00
2.00
15.00
750.00
20.00
5.00
20.00
15.00
2,806,099.78
4,245,262.59
28,783,350.00
1,230,592.50
546,930.00
31,981.50
2,571,330.03
694,243.04
209,189.48
173,691.08
Sub Total
I
JUMLAH HARGA
(Rp.)
28,783,350.00
2,461,185.00
8,203,950.00
23,986,125.00
63,434,610.00
Kg
Kg
Kg
Pengadaan, pabrikasi kontruksi kolom penyangga (tanpa pengecatan dan pemasangan) (TA.
4 2011)
Kg
5
6
7
8
9
Kg
Kg
m3
m2
m2
120,739.000
26,638.000
38.00
363.00
727.00
8,806.50
8,806.50
1,698,379.19
160,371.00
78,795.00
1,063,288,003.50
234,587,547.00
m2
220.00
unit
53.00
826,884.00
350,000.00
181,914,480.00
58,214,673.00
57,283,965.00
1,595,288,668.50
No
URAIAN PEKERJAAN
J
1
2
3
4
5
6
7
8
9
UNIT
Kg
Kg
Kg
Kg
m3
m2
m2
m2
unit
ESTIMASI
KUANTITAS
37,302.00
146,823.00
43,800.00
88.00
735.00
1,593.00
245.00
50.00
HARGA SATUAN
(Rp.)
29,200.50
8,806.50
29,200.50
3,000,000.00
160,371.00
78,795.00
826,884.00
350,000.00
Sub Total
K
Pengadaan dan pemasangan lampu red flash, kabel dan assesoriesnya (1 set@ 2 unit)
e.
Pengadaan dan pemasangan kabel listrik (power supply) termasul konduit dan
f. assesoriesnya
g. Pengadaan dan pemasangan tiang lampu, lampu dan kabel jaringannya
3 Pekerjaan Sipil Lainnya
a. Pelat Lantai kendaraan t = 250 mm (beton bertulang, K500)
b. Rumah mesin (4 m x 4 m)
Sub Total
117,872,685.00
125,520,435.00
202,586,580.00
Kg
150,000.00
29,200.50
4,380,075,000.00
4,380,075,000.00
Kg
Kg
Kg
Kg
Kg
Kg
3,600.00
1,169.00
3,600.00
32,445.00
50,521.50
116,802,000.00
59,059,633.50
116,802,000.00
unit
unit
set
1,089,237,051.00
1,292,996,749.50
1,278,981,900.00
4,107,195,400.50
32,445.00
292,663,633.50
Sub Total
M
JUMLAH HARGA
(Rp.)
Kg
Kg
Kg
Kg
Kg
Kg
22,000.00
5,500.00
25,000.00
610.00
1,130.00
50,521.50
41,251.50
31,054.50
26,512.20
31,054.50
1,111,473,000.00
226,883,250.00
776,362,500.00
16,172,442.00
35,091,585.00
unit
unit
unit
unit
set
titik
m3
m2
2,165,982,777.00
No
N
URAIAN PEKERJAAN
UNIT
Shelter
Pengadaan dan pemasangan konstruksi baja termasuk pengecatan
Pemancangan tiang pancang dia. 400 mm pondasi selter, 18 titik @ 30 m
Pemotongan tiang pancang
Penyambungan tiang pancang
Ring pelat Dia=700mm, t= 12 mm ( w = 24.5 kg/unit)
Pelat penutup tiang dia. 400 mm, t= 6mm ( w = 6 Kg/unit)
Bracing pengaku tiang pancang H 300 x 200 x 8/12 (w=57Kg/m')
Beton bertulang (K-300, U32) pile cap dan sbg pondasi kolom penyangga selter, 18 unit,
5 dim.1600x1200x1200
1
2
3
4
ESTIMASI
KUANTITAS
HARGA SATUAN
(Rp.)
Kg
m
Unit
Unit
Unit
Unit
Kg
540.00
18.00
36.00
18.00
18.00
897.75
475,000.00
100,000.00
250,000.00
669,989.25
164,079.00
27,346.50
m3
41.00
2,500,000.00
m3
unit
m3
m2
m2
2.00
18.00
54.00
419.00
450.00
2,500,000.00
550,000.00
3,500,000.00
85,000.00
160,371.00
unit
11.00
3,388,000.00
Pengadaan dan pemasangan jendela Tipe-2 dim. 2800x2200mm (rangka alumunium + Kaca
12 dan assesoriesnyuan)
unit
9.00
3,388,000.00
unit
10.00
2,310,000.00
Pengadaan dan pemasangan jendela Tipe-4 dim.2200x900mm (rangka alumunium + Kaca dan
14 assesoriesnya)
unit
2.00
1,089,000.00
Pengadaan dan pemasangan jendela Tipe-5 dim.1625x900mm (rangka alumunium + Kaca dan
15 assesoriesnya)
unit
2.00
804,375.00
Pengadaan dan pemasangan jendela Tipe-6 dim. 1100x500mm (rangka alumunium + Kaca dan
16 assesoriesnya)
unit
2.00
302,500.00
Pengadaan dan pemasangan pintu double dim.3100x2100 (rangka alumunium + Kaca dan
17 assesoriesnya)
unit
2.00
3,580,500.00
18
m2
500.00
350,000.00
19
20
21
22
23
24
25
m2
m2
unit
m2
m2
set
set
500.00
540.00
6.00
132.00
122.00
1.00
1.00
150,000.00
175,000.00
350,000.00
95,000.00
95,000.00
1,750,000.00
35,000,000.00
unit
1.00
15,000,000.00
6
7
8
9
10
Pengadaan dan pemasangan Aluminium Komposit Panel PVDF (tebal 4 mm, Al.koil 0,3 mm )
termasuk rangkam dan sealant
Pengadaan dan pemasangan kalsiboard termasuk finishing dan pengecatan
Pengadaan dan pemasangan atap corrugated metal roof termasuk perlengkapannya
Pengadaan dan pemasangan pintu PVC untuk toilet termasuk perlengkapannya
Pekerjaan dinding pasangan bata merah termasuk plesteran, acian dan pengecatan
Pengadaan dan pemasangan dinding keramik 20X20 cm di toilet
Pekerjaan plumbing dan sanitari, termasuk kloset duduk, keran dan perelngkapan lainnya
Pekerjaan elektrikal termasuk jaringan listrik, lampu dan perlengkapan lainnya
Pekerjaan bangunan septic tank (beton bertulang) dim. 2000x2000x3000mm termasuk
26 kelengkapannya
Sub Total
JUMLAH HARGA
(Rp.)
12,059,806.50
2,953,422.00
24,550,320.38
72,166,950.00
111,730,498.88
PERHITUNGAN PEMBESIAN
1
2
3
18-D 25
D13 - 75
Plat t = 9 mm
II.2
1
2
16- 13
10 - 100
PILE CAP
SEGMEN I
No.
Tulangan
Luar
D19-200
Dalam
D19-200
Samping
D19-200
Begel tengah
D19-200
Penahan Fender
Trapesium
D19-200
Horizontal (mengelilingi)
D19-200
Horizontal Atas
D19-200
SEGMEN I'
SEGMEN II
No.
Tulangan
Luar
D19-200
Dalam Atas
D19-200
D19-200
Bawah
D19-200
Begel tengah
D19-200
SEGMEN II'
SEGMEN III
No.
Tulangan
Luar
D19-200
Dalam
D19-200
Samping
D19-200
Begel tengah
D19-200
Penahan Fender
Trapesium
D19-200
Horizontal (mengelilingi)
D19-200
Horizontal Atas
D19-200
Samping
Fender
Bawah
Multipleks
V=
V=
V=
(17.5+3.5+3.5+2+4.5+2+1.5+2+4.5+2+3.5+3.5)*1.5
((1.5*1.5)+(1.1*1.5*2)+(1.5*2))*3
(3.5*3.5)*2+(1.5*4.5*2)+(1.5*3.5)
1.00
Panjang
3.980
1.042
3.05
2.24
Jumlah
18.00
29.33
Total
Panjang
Total
Berat
54.90
65.61
218.50
68.37
terpisah
Dibulatkan
Total Pembesian
Jumlah Pile = 1
Volume Beton Isi Tiang
Rasio Besi/m3
1 Rasio Besi/m3
286.87
286.87
1.01
285.36
285.36
kg
kg
m3
kg/m3
kg/m3
1.00
Panjang
1.578
0.617
Dibulatkan
3.00
2.71
Jumlah
16.00
25.00
Total
Panjang
Total
Berat
48.00
67.70
75.74
41.77
Total Pembesian
Jumlah Pile = 1
Volume Beton Selimut Tiang
Rasio Besi/m3
1.05 Rasio Besi/m3
117.52
117.52
0.72
164.06
172.27
Bekisting
Volume Beton Selimut Tiang
Rasio Bekisting/m3
7.95 m2
0.72 m3
11.10 m2/m3
BJ
Panjang
Jumlah
Total
Panjang
kg
kg
m3
kg/m3
kg/m3
Total
Berat
2.250
10.00
19.00
190.00
427.50
2.250
10.00
19.00
190.00
427.50
2.250
14.00
9.00
126.00
283.50
2.250
1.90
57.00
108.30
243.68
2.250
7.40
9.00
66.60
149.85
2.250
5.20
9.00
46.80
105.30
2.250
4.50
3.00
13.50
30.38
BJ
Panjang
Total Pembesian
1,667.70 kg
Total Pembesian
1,667.70 kg
Jumlah
Total
Panjang
Total
Berat
2.250
6.00
24.00
144.00
324.00
2.250
10.00
9.00
90.00
202.50
2.250
4.50
18.00
81.00
182.25
2.250
4.50
9.00
40.50
91.13
2.250
1.90
24.00
45.60
102.60
BJ
Panjang
Total Pembesian
902.48 kg
Total Pembesian
902.48 kg
Jumlah
Total
Panjang
Total
Berat
2.250
10.00
9.00
90.00
202.50
2.250
6.00
19.00
114.00
256.50
2.250
10.00
9.00
90.00
202.50
2.250
1.90
19.00
36.10
81.23
2.250
7.40
9.00
66.60
149.85
2.250
5.20
9.00
46.80
105.30
2.250
4.50
3.00
13.50
30.38
Total Pembesian
1,028.25 kg
6,168.60 Kg
39.38 m3
Pengurang
Dibulatkan
Volume II
Volume III
Volume IV
Volume V
Volume Beton Pile Cap
Rasio Besi/m3
1.15 Rasio Besi/m3
21.00
4.50
7.09
(3.11)
68.86
89.59
103.03
3.5+3.5+2+4.5+2+1.5+2+4.5+2+3.5+3.5)*1.5
5)+(1.1*1.5*2)+(1.5*2))*3
5)*2+(1.5*4.5*2)+(1.5*3.5)
5/7
5/7
5/7
5/7
5/7
5/7
5/10
6/12
5/7
5/7
5/7
6/12
Jumlah
20.00
16.00
16.00
12.00
20.00
4.00
6.00
2.00
8.00
4.00
4.00
2.00
75.00
25.65
43.25
=
Rasio Multipleks/m3
Type
m3
m3
m3
m3
m3
kg/m3
kg/m3
Luas
Pot
0.0035
0.0035
0.0035
0.0035
0.0035
0.0035
0.0050
0.0072
0.0035
0.0035
0.0035
0.0072
143.90 m2
2.09 m2/m3
Panjang
1.40
1.00
1.10
0.80
0.70
1.20
1.80
1.80
0.90
0.75
1.10
0.75
Volume
(m3)
0.10
Kayu dalam utk precast
0.06
Kayu dalam utk precast
0.05
0.02
0.05
0.03
0.03
0.01
0.02
0.01
7.712
0.112 m3/m3
PERHITUNGAN PEMBESIAN
1
2
3
32-D 25
D12 - 200
Plat t = 9 mm
Tulangan
Luar
D13-200
Vertikal
D16-200
Samping
D16-200
D16-200
Tulangan
Luar
D13-200
Vertikal
12-D25
Luar
D13-200
Vertikal
12-D25
#REF!
SEGMEN I
No.
Tulangan
Luar
D16-150
Atas
10-D25
Samping
D16-150
Bawah
10-D25
Begel Horizontal
D13-400
Begel Vertical
D13-25
Samping
Bawah
Multipleks
V=
V=
(1.5+1.5)*6.2
2.8*6.2
3
4
5
6
7
8
9
10
Total Volume Kayu Pile Cap
#REF!
No.
Tulangan
Luar
D13-100
Atas
10-D25
Samping
D16-150
Bawah
10-D25
8-D25
Begel Horizontal
D13-250
Begel Vertical
D13-25
WF dudukan bekisting
Plat Klem
1
2
WF 200x100x5,5x8 mm
Plat Clamp Cincin t = 12 mm
lebar 25 cm
Samping
Bawah
Multipleks
V=
V=
(2*2.8)+(3*2)+(2.8*2)+(3*2)
2.8*5.8
#REF!
No.
Besi Plat
1
2
Pengurang Lingkaran
1.00
BJ
Panjang
3.980
0.888
4.05
4.24
Jumlah
32.00
14.75
Total
Panjang
Total
Berat
129.60
62.56
515.81
55.55
terpisah
Dibulatkan
Total Pembesian
Jumlah Pile = 1
Volume Beton Isi Tiang
Rasio Besi/m3
1.05 Rasio Besi/m3
571.36
571.36
4.54
125.82
132.11
kg
kg
m3
kg/m3
kg/m3
1.00
BJ
Panjang
Jumlah
Total
Panjang
Total
Berat
1.042
9.80
32.00
313.60
326.77
1.560
7.45
41.00
305.45
476.50
1.560
7.45
4.00
29.80
46.49
1.560
2.50
15.00
37.50
58.50
Dibulatkan
Total Pembesian
Jumlah Pile = 1
Volume Beton Precast
Rasio Besi/m3
1.05 Rasio Besi/m3
908.26
908.26
8.03
113.09
118.75
Bekisting
Volume Beton Precast
Rasio Bekisting/m3
103.75 m2
8.03 m3
12.92 m2/m3
1.00
BJ
Panjang
Jumlah
kg
kg
m3
kg/m3
kg/m3
Total
Panjang
Total
Berat
1.042
2.60
32.00
83.20
86.69
3.980
8.05
12.00
96.60
384.47
1.042
2.60
32.00
83.20
86.69
3.980
Dibulatkan
8.05
12.00
96.60
Total Pembesian
Jumlah Pile = 1
Volume Beton Pengisi Precast
Rasio Besi/m3
1.05 Rasio Besi/m3
384.47
942.32
942.32
8.44
111.63
117.21
Bekisting
Volume Beton Pengisi Precast
Rasio Bekisting/m3
kg
kg
m3
kg/m3
kg/m3
4.00 m2
8.44 m3
0.47 m2/m3
BJ
Panjang
Jumlah
Total
Panjang
Total
Berat
1.578
9.00
42.00
378.00
596.48
3.980
6.82
10.00
68.20
271.44
1.578
6.82
20.00
136.40
215.24
3.980
6.82
10.00
68.20
271.44
1.042
3.20
32.00
102.40
106.70
1.042
1.80
32.00
57.60
60.02
Total Pembesian
Dibulatkan
1,521.32 kg
1,521.32
26.04
58.42
67.19
Kg
m3
kg/m3
kg/m3
18.60
17.36
Dibulatkan
Type
5/7
5/7
5/7
5/7
=
Rasio Multipleks/m3
2.5 Rasio Multipleks/m3
Jumlah
20.00
16.00
16.00
12.00
Luas
Pot
0.0035
0.0035
0.0035
0.0035
35.96 m2
1.38 m2/m3
3.45 m2/m3
Panjang
1.40
1.00
1.10
0.80
Volume
(m3)
0.10
Kayu dalam utk precast
0.06
Kayu dalam utk precast
5/7
5/7
5/10
6/12
5/7
5/7
5/7
6/12
20.00
4.00
6.00
2.00
8.00
4.00
4.00
2.00
0.0035
0.0035
0.0050
0.0072
0.0035
0.0035
0.0035
0.0072
0.70
1.20
1.80
1.80
0.90
0.75
1.10
0.75
0.05
0.02
0.05
0.03
0.03
0.01
0.02
0.01
3.213
BJ
Panjang
Jumlah
Total
Panjang
0.123 m3/m3
Total
Berat
1.042
10.10
59.00
595.90
620.93
3.980
8.80
10.00
88.00
350.24
1.578
17.60
28.00
492.80
777.64
3.980
8.80
10.00
88.00
350.24
3.980
6.95
8.00
55.60
221.29
1.042
3.20
24.00
76.80
80.03
1.042
2.30
45.00
103.50
107.85
Total Pembesian
Dibulatkan
21.33
7,850.00
Dibulatkan
Pemakaian
2,508.21 kg
6
5.60
2
0.10
12
0.01
2,508.21
31.50
79.63
95.55
Kg
m3
kg/m3
kg/m3
256.00
39.55
295.55
31.50
9.38
10.32
5.16
kg
kg
kg
m3
kg/m3
kg/m3
kg/m3
23.2
16.24
=
Rasio Multipleks/m3
39.44 m2
1.25 m2/m3
Dibulatkan
Type
5/7
5/7
5/7
5/7
5/7
5/7
5/10
6/12
5/7
5/7
5/7
6/12
Jumlah
20.00
16.00
16.00
12.00
20.00
4.00
6.00
2.00
8.00
4.00
4.00
2.00
Luas
Pot
0.0035
0.0035
0.0035
0.0035
0.0035
0.0035
0.0050
0.0072
0.0035
0.0035
0.0035
0.0072
3.13 m2/m3
Panjang
Volume
(m3)
1.40
1.00
1.10
0.80
0.70
1.20
1.80
1.80
0.90
0.75
1.10
0.75
0.10
Kayu dalam utk precast
0.06
Kayu dalam utk precast
0.05
0.02
0.05
0.03
0.03
0.01
0.02
0.01
3.213
0.102 m3/m3
1.00
BJ
Panjang
Lebar
m
Volume
m3
Total
Berat
7,850.00
5.60
0.25
0.02
131.84
7,850.00
2.00
2.00
0.05
376.80
(0.02)
(145.01)
7,850.00
Total Pembesian
363.63 kg
4,545,358.45
Rasio Bekisting
Selimut Tiang 609 mm
Keliling Luar
Panjang (coba)
Luas
2.542 m'
1.000 m'
2.542 m2
Volume
Luas Luar
Luas Dalam
Selisih
Panjang (coba)
0.514
0.291
0.223
1.000
Volume / 1 m'
0.223 m3
Rasio Bekisting
m2
m2
m2
m'
11.410 m2/m3
Misal P = 1.5 m
Klem
Rasio Klem
3.812 m2
2.000 Buah
0.525 Buah / m2
Keliling Luar
Panjang (coba)
Luas
3.170 m'
1.000 m'
3.170 m2
Volume
Luas Luar
Luas Dalam
Selisih
Panjang (coba)
0.800
0.514
0.286
1.000
Volume / 1 m'
0.286 m3
Rasio Bekisting
m2
m2
m2
m'
11.100 m2/m3