Professional Documents
Culture Documents
The Use of CPM in Construction Five
The Use of CPM in Construction Five
The Use of CPM in Construction Five
C ! 2 & ?
V
w
c : ;
C
9
C
Z
n
C
W
tn
O
-
Q
C
W
O C
N 2
o
o
Q
0
..
n z
m
m
-
o
o
O
-
*
4
FIGURE 5-1
56
C
4
C P H 1 1 AUTOMATED
CONTROL SYSTEM
LAMOl
FRO H?NC.ER R E N N A T I O N
K E ACTI
~
VITY S T A T U S R E P O R T
S E W E Y C E = TIWGET
~ORK-WEEK= 5
DUMMIES NO
FINISHED
NO
AS OF 1 5 D E C 7 5
P R E D I C T E D COMPLETION
P G F
.........
'1561
01381
01590
q1577
02000
TRACE
'73C".
KE t
0 3 0 0 0 KEY
0 3 0 0 0 KFV
KEY
)3"?
03000 KEY
AC EA
DESCR I P T I ON
S k I T C H GEAR I N S T A L L E D
HAWGER ROOFED
H A G E R F IRCPRnOFEO
1ST F L Q OFFICE D9YE
PR'3JECT COPPLE TF
OCCURANCE
DATE
TARGET
DATE STATUS
PREVICUS
T R E N 0 OCCURANCE
PS D F 1 5 C E C 7 5
A L L PROJECT STATLS REPORT
................
FRCJECT
ANAHB W A R E H O C S E
PREOICTEO
COMPLETICh
DATE
TARGET
DATE
STATUS
1N
CPL-OAYS
PNARBO STORAGE C C
3DMAR76
1l O C T 7 5
-171
AWCAN A M E R l C d N P H O l C C A l C F F I C E B L D G
25PPt76
25SEP76
122
UP
-141
STEADY
ID
.......
NAME
CHASH D F F I C E / S T C F A G E
CUWIL
COLLINSMFG
C l - E S A P E P K E A S W R E IM:
~ILSCRBLDG
DAABT D A V I S PBBATOIR
Ui
PACE
1
SEO = P R C J E C T
ObWAR O A V I S CO'4PAN,
CRlNK C A V I S
MPREkfOLSE
ICE R l F K
MGFiK6 MhiKEY H O U S E
REGIONAL ZCC
U S M N WANAGEMENT T P A l N I N G CENTER
USARTWT
lOJAN70
Z2AUG75
2 2 JUL76
2OJUL76
19MAR77
15MlR77
IOJUh76
-2
TREN0
OWN
DOWN
15M4Y76
-1 4
-2 6
OOih
31SEP77
31SEP77
STEAOY
250CT76
30CCT76
-5
STEAOY
lbFEe77
lSFEB77
-1
STEPDY
USPAV F O B # P A V I L I C N
18DEC77
I O F Ee78
53
VAMAC V A H O S P I T A L A C D I T I O N C A C A L I S L A N O
15FEB76
2 5 FE876
10
ZYTRO Z Y T R C h I N C 3 F F I C E 4 P R C C E S S I N G C E N T E R
IOJUN70
24JAN76
-137
UP
UP
STEAOY
DOlh
PERIODS
1N
TREN)
PREVIOLS
COMP
DATE
DATE O F
LAST
UPOATE
AS O F l S D E C 7 5
TROURL ED PROX.U.-SJA.TUf-
CPM 11 AUTCCATED C C N T R a S I S T E M
fEPUlr. .
PR EC I C T E D
COMPLETION
DATE
W m - A N A f l R C STilf!AE
I;IL
30 PAR76
TARGET
DATE
11MT35
O B T A I N ROOF STEEL
---
. . .. ....-
STATUS
IN
CAL-DAYS
.-
TREN0
.?m-.
D
- - . --.P W 10M
1N
TREM
PACE
--
qF0 r
PR EV I O U S
COMP
DATE
PPnlFCT
DATE ff
LAS1
UPDAU
DAYAR D A V I S COMPANI b A R E M U S E
10JUN76 15MAY76
E X 1 M S O N R Y VES1 H A L L L I P T 1
W D E R S L A B PLBG SOUTH H U F
ZYTRO ZYTRON I N C O F F I C E # P R U E S C I N G C W T E R
LATH 8 PLASTER
- 4TH
10JUh76
FLR
2UAN76
-26
DWN
2WAY76
30NOV75
-137
OOYN
28MAY76
15DECTS
-. F l N l S H
DATE
%
Y'
Vi
0 1 3 8 0 CL391
C 1 3 9 1 C1414
01414 01422
01422- 0 1 4 3 5
1,1437 2 1 4 4 1
'21441 0 1 4 4 6
0 1 4 4 8 '21454
'1454 C145F
01450 01464
01464 01467
C 1 5 i l C1507
01511 01515
0 1 5 2 0 C1522
0 1 5 2 5 01 5 3 5
01535 01565
01569 01572
0157201577
CI5770157B
0157601<19S
0 1 5 5 5 C2000
8..2(Ci. 0 3 0 0 C
01%7 0141 7
01431 01449
C14b5 C1457
0 1 4 9 8 C1508
01435 01442
' 145L 2145E
01467 01471
01502 0 1 5 9 0
L1512 L1517
0152E e 1 5 3 1
01532 01540
01544 C1548
.--0 1.5 2 .4-0 1..5.-3 .5.
L A T t OCF
MTL STUOS 1ST FLR YEST
L b 1 H CFF
HTL STUOS 1ST F L P EdST
LATH CFF
MTL STUDS ZYD FLR YEST
LATH
CFF
HTL '!LOS
ZYD- FLR EAST
FLECT CFF
CT3hDUl T 1ST FLR YEST
ELECT CFF
C C K I U I T 1ST FLR EAST
ELECT CFF
COhDUIT ZND F L P WFST
L E C 1 CFF
CONDUIT 2YD FLP EAST
IYSUL CFF
IPJSULATICN I S T FLR WEST
2 I h S-U L CFF
I"1SULATION 1ST FLR EAST
1 FLBG
CFF
PLCC F I K T U R E S 1ST FLk EAST
5 TPART CCF
T C I L E T P b R T I T l O N 5 1 S T FLR EAST
5 l P A R T CFF
TOILET PARTI TIONS 2NC FLG hEST
5 l P d R T CFF
T31LET PARTI T l O h S 2 h C FLR EbST
2 I A C C ' CFF
TOILET ACCESSOIES 2PD F L P EPST
1 G<--_
CFF
CLEANUP I S T FLR YEST2 CC
CFF
CLEANUP 1 5 1 FLR EAST
3CC
CFF
CLEANUPZNOFLRhEST
4CC
CFF
CLEANJF2NI)FLREAST
5 CC
PUhCH L I ST WHOLE BLCG
O KEY
PRTJECT COCPLETE
1 5lOE..PER
E X T ~ R ~ ! O ~ ~ I D l ~ G
. ..
-.
5 SFPNK
TE S 1 SPR INKL ERS
1 PLBG
CFF
PLBG F I X T U P E S I S T FLR wEST
1 l P A R T I P A R T T O I L E T P A d T I TIONS 1ST FLR YEST
1 PECH CFF
h P l / C H I L L O UATER L I h E S
1 PECH CFF
EXkALSTS
2 I h S U L CFF
I N S U L A T I C N 2NO-FLk YEST
_ -5 CC
CFF
COLNTERS
1 FLBG
CFF
PLBG F I X T U P E S ZNC FLP h E S 1
1 ELECT T F F
C E l L l N G L I G H T S 1 S T FLR WtST
1 CECH CFF
G R l L L E S l C l F F U S E R S I S T FLP hEST
2 FLP
CFF
FLCORING I S T FLR UEST
2
1ACCZ
CFF
TOILET
ACCESSORIES
2LO
- .- . .-.--- ---- -- ..-F L R YEST
1
1
2
1
1
1
1
1
2
EARLY
START
EARLY
FINISk
RE L
START
PE L
FINISH
RFL K
.
..
i90EC75
BOEC.7'
310EC75
OZJAN76
&JAN76
07JAN76
14JAY7t
21 JA h 7 6
2AJAN76
30JAN76
%?FE876
30~~~7521bKI
31UEC75 2 4 h O V 7 5
0 2 J A h 7 6 25hOV75
0 6 J A N 7 t 27hOV75
.07JAN76 OlCEC75
!4JAN76 02DEC75
2 1 J A N 7 6 09CEC75
2 B J A N 7 6 16DEC75
3 0 J a N 7 t 230Ec<
O2FEB76 i 5 D E C 7 5
5 4 F E B 7 6 26OEC75
.~
24NOV75
I75
-26
25NOV75 - 2 0
27NOV75 - 2 6
01DEC75 - 2 6
020EC75 -26
090EC-r5 .._y=
160EC75 - 2 6
23CEC
7 5 - 2 6250EC75 -26
260EC75 - 2 6
3OOEC75 - 2 6
26CEC75
06JAN76
08JAN76
08JAN7C
15JAN76
ibJAN7t
15JAY76
21JAN76
29OEC75
OBJAk76
15JAN76
09JAN76
lbJAN76
19JAti7-6
21JAh76
23JAN76
2 4 h O V 7 5 25NOV75 - 2 4
OCCEC75 OBOEC75 - 2 3
OBCEC75 1 5 0 E C 7 5 - 2 3
OBCEC75 090CC75.-.-&315CEC75 1 6 0 E C 7 5 - 2 3
lbOEC75-~17CEC75 - 2 3
17DEC75 19CEC75 - 2 3
190EC75 230EC75 -23
up later in time than their "Relative" counterparts. It is for this reason that a
Relative Report does not refer to LATE START or LATE FINISH.
Note in Figure 5-5 that the float field is headed RFL which stands for
RELATIVE FLOAT. RFL is calculated by subtracting EARLY START from
RELATIVE START, and when the revised project schedule has been
lengthened in any way, it will be a negative number. For this reason, some
CPM users when referring to float calculated in this manner will erroneously
cal1 it "Negative Float." This practice should be avoided since if the revised
project schedule is less in time than the original, the RFL value will be positive.
It doesn't make much cense to cal1 it negative when it can be either.
The Control Monitor Phase can, of course, produce revised versions of the
Resource Reports and the Cash Flow Analyses described in the chapter on the
Scheduling Phase. The,only difference in these revised versions is that they
project resource and cash positions for the work remaining as of the monitor
date.
COST STATUS REPORTS
The CPM user naturally wants to know the time status of his project, but in
addition, he wants to know its Cost Status. The Control Monitor Phase
produces a report that indicates just how the project looks from a "cost"
standpoint.'
This report which is called the Cost Status Report is prepared in the
following fashion:
As described in Chapter 4, the contractor must first prepare cost estimates
for each of the activities in the project. Then, for activities that have been
completed, as shown in the MONITOR Report, appropriate costs can be
calculated. This gives the contractor an ESTIMATED COST TO DATE. This
estimated cost is then a yardstick against which the contractor can compare
the ACTUAL COST TO DATE for that articular phase of work. The actual
costs are relatively easily collected. Anyone who keeps books can determine
his actual costs. CPM, however, gives him at any time during the progress of
the project an estimate of the cost for the work reported as complete so that
effective comparisons can be made. With this report the contractor does not
have to wait until the end of the project to discover the "status" of his costs.
The process of Cost Status Report creation can best be explained with a
sample project. Consider that the arrow diagram below represents a project for
which periodic Cost Status Reports were desired.
The first step necessary to be taken would be the definition of the costs
involved per activity. Assume that the table in Figure 5-6 describes the costs
estimated for the completion of each activity. This could be prepared any time
prior to the production of a Cost Status Report, and it could have been revised
at any time.
The entries in this table merely indicate how much money should have been
spent for various categories (types) of expense when each activity had been
finished. For example, when ~ c t i v i t yA is finished, the contractor will owe
somebody $488.10 for bulldozer expenses, $135.00 for general labor, and
$100.00 for engineering expenses. When B is finished, $1,085.30 will be owed
for concrete, $309.10 for concrete labor and $80.00 for general labor. The costs
for al1 activities in the project are similarly described.
The second input is information a.bout which activities have been finished.
Notice in Figure 5-1 that the Marked-up Schedule indicates clearly what
activities are completed. This is, thus, a good source of this second input.
Suppose that at the time a Cost Status Report was desired for the project
described above, activities A, B, C, D, C and I had been finished. With this
information, the ESTIMATED COST TO DATE for the various categories
types) of expense can be calculated.
Activity
3
4
4
4
8
9
D
F
G
56-
6
4
E
P
6 -
78-
10
12
Category
Expense
48 - Bulldozer
46 - Gen. Labor
73 - Engineering
15 - Concrete
$ 488.10
16 - Concrete Labor
46 - General Labor
51 - Excavation
73 - Engineering
10 - Architect
309.10
80.00
1,955.10
190.30
100.00
(No Expense)
478.35
1,009.90
195.00
1,800.00
75.00
50.00
1,800.00
205.60
22 - Carpenter
18 - Lurnber
46 - General Labor
38 - Masonry Contract
10 - Architect
73 - Engineering
38 - Masonry Contract
46 - General Labor
135.00
100.00
1,085.30.
(No Expense)
15 - Concrete
975.00
16 - Concrete Labor
255.00
46 - General Labor
185.00
90.00
9-
11
46 - General Labor
10-
13
22 - Carpenter
195.00
18 - Lurnber
555.30
11-
10
15 - Concrete
16 - Concrete Labor
11-
12
46 - General Labor
12-
13
L
O
1,907.00
655.00
195.00
(No Expense)
FIGURE 5-6
64
If Activity A is finished, the project should have cost $488.10 for catetory 48
- Bulldozer, $135.00 for General Labor, category 46, and $100.00 for
TABLE A
Category
10 ARCHITECT
15 CONCRETE
16 CONCRETE LABOR
38 MSNRY CONTRACT
46 GENERAL LABOR
48 BULLDOZER
51 EXCAVATION
73 ENGlNEERlNG
TOTAL FOR THE PROJECT
TABLE B
Category
10 ARCHITECT
15 CONCRETE
16 CONCRETE LABOR
38 MSNRY CONTRACT
46 GENERAL LABOR
48 BULLDOZER
51 EXCAVATION
73 ENGlNEERlNG
TOTAL FOR THE PROJECT
$8,248.50
Per Cent
Spent
Est. Total
Cost
Est. Cost
l o Date
10 ARCHITECT
15 CONCRETE
16 CONCRETE LABOR
38 MSNRY CONTRACT
46 GENERAL LABOR
48 BULLDOZER
51 EXCAVATION
73 ENGlNEERlNG
This information is valuable in and by itself because it indicates how much
activity has been accomplished cost-wise. However, if the contractor supplies
information about how much was actually spent for concrete, for general labor
and for al1 other items of expense, he can find out whether or not he is "on
schedule" in terms of cost.
As a project proceeds, the contractor collects bills, invoices and so forth as
part of his normal bookkeeping procedures. These at any particular point in
time are ACTUAL COSTS TO DATE. If these actual costs are known, two
additional items of information can be calculated and placed in the Cost Status
Report. The DOLLAR DIFFERENCE is the result when the ESTIMATED COST
TO DATE for a category is subtracted from that category's ACTUAL COST
TO DATE. The DEVlATlON for a category is the ratio of actual costs to
CategOv
10 Architect
15 Gancrete
16 Concrete
Labor
38 Masonry
Contract
46 Gen. Labor
48 Bulldozer
51 Excavation
73 Engineering
~ost
57
27
$ 175.00
25
1,219.10
100
39
100
100
85
3,600.00
1,085.60
488.10
1,955.10
340.30
Est. Cost
l o Date
h t u a l Cost
l o Date
Deviation
3,967.30
In the project that has been used as a sample for the Cost Status Report, the
ACTUAL COST TO DATE entries must be assumed. Assuming the actual
costs indicated, the completed Cost Status Report based upon activities
reported as finished and on actual costs collected would look like Table D.
This report tells the contractor what is the cost status for al1 categories of
expense defined by him. The final Cost Status Report contains the information
described above as well as summary type data for the entire project. The
completed Cost Status Report for the project described above is shown in
Figure 5-7 on the following page.
The Cost Status Report, because it indicates how much money is being
spent in relation to what was expected, is a very valuable report. The project
manager can tell from this report which areas of expense need investigation,
which estimates perhaps need revision, and how he is doing in general as far
as his costs are concerned.
There are variations on the report shown here as a sample. One can include,
as part of the Cost Status Report, information about the cost of change orders
or other revisions or separate the labor costs from the material costs just to
mention only two.
One question that always arises about the procedure described above
concerns itself with activities that have started but have not yet been
completed. At the time the Cost Status Report is desired, activities in this sort
of circumstances are assumed to be "on schedule," and their costs are
"pro-rated" according to how many days they have been in progress relative
to their schedule duration. To illustrate: if Activity E were a six-day activity that
had been reported as STARTED three days before the "effective date" of the
Cost Status Report, the Cost Status Report would have included only half
(316) of the costs involved for that activity.
Total Estimated
Revised Estimate
Cost To Complete
Categoiy
Number
Name
15.069.05
14.975.15
6.810.55
Budget
Amount
Est. Cost
To Date
Act. Cost
To Date
Ddlar
Difer.
8.248.50
8.164.60
83.90
Deviation
Architect
Concrete
Concrete
Labor
Masonry
Contract
Gen. Labor
Bulldozer
Excavation
Engineering
400.60
527.35
1955.00
260.00
FIGURE 5-7
20.00
39.25
O
30.30
Over .95
1 .O8
.99
Over .89
PAGE
P? E V
OUCGET
01374
01408
' 141
U1417
01417
' 1431
0 1 4 1 7 SPFUK
Cl5l'; SPF'JK Y c Q
( 1 5 1 '
SPrVK "6
U 1 4 3 1 SPFYK
0 2 4 9 9 Sf0hC br5
L l i t 9 SPEUC
PCT
THlS
PCT
SPfiIhKL'QS w i T k i H I f q
I ' J S T A L L F::AP T.L.dK5
I:iCT/TFST
FY-lP P . C T Z L f 5
S F 2 I N K L C Q S F O C V d3l- 1 %
5 P F l h K L C g S C C A V cGl- 1N
T E S T SCKT 4KL E!;S
THI
5 d P P L I C A T I J a FARNEU
A CCUST
EAHLED
27
,-
d
4
L
"
U J C
.<
i i
L.
!VI
3
'
,
--
-4
-0-
22,-
~ K d L ~ r 7 L d u V 8 P l d i d d l
> d , a , ~
. n + f i o t - ~ - > ~ <
7 n~d .h J . s . a
< 3 ~ 2 a , ~ - i . . ~ a 1 ,>dc r; 9 - ~ - i ; - a c . < a
. x V d O U & A 3 1 - 2 7
x ' x l i l a U . 1 m r l > . ~ . . ' I + , -
Y G
FIGURE 5-9
contractor and the sub was for $117,471.20 when al1 his work was completed.
the ratio of that amount to what had been agreed to between the contractor
and the owner ($133,490.00) is 88 %. This ratio would be the factor applicable
to the amounts earned for that sub, and the result of such factoring would
justify and support payment to the sub. Figure 5-10 is the backup for payment
to the subcontractor represented t5y the page illustrated.
P A Y M E N DOCUMENTS
~
Many owners use CPM as the initial input to an automated contractor
payment operation. One such organization is the Veterans Administration
whose payment document is illustrated in Figure 5-11. Use of such an
approach has significantly reduced the amount of time necessary for
processing of payments, the result of which is faster payment to the
contractor.
Note in the Payment Document illustrated in Figure 5-11 that a separate
entry is made to accommodate Material-On-Site values. These values are
those that were discussed earlier in this chapter.
C P M II AUTOMATEO
~ n ~ O FBD
l
WNGER R E N [ N * I O N
COST EARNEO REPORT BY TRAOE
AS OF 1 5 0 E C 7 5
TRAOE
ci
v
w
C
AI
= SPRNK
- ..
.-,
CONTROL
sYsTEn
PAGE
.-
TR~DE-.
01374 01417
01408 01519
01410 01519
01417 O1431
01417-02499
61431 01449
ED~EISC
SPRNU
SPRNK M R
SPRNK MER
SPRNK
SPRNKMOS
SPRNK
__
R 1OO
I N.-
PREV
_ _- . _ - -. BUDGET - - PCT
THIS
PCT
AllOLHT
E ~ N E D
un
SPRINKLERS
R G H IN
I N S T A L L FOAM TANKS
I N S T / T E S T F O M NOZZLES
SPRI NKLERS F C A M RGH I N
SPRINKLERS FCAM RtH I N
TEST SPR INKLERS
TOTAL
H)R TRAOE
117,471.20
YA'
PREVIOUS A M W W E A R M D
T H I S APPL I C A T ION EARNED
59
36 8. 0 0
WL TE R I AL
CM S I T E
C.@.
CWAhGF 3 R C PPEV R F P T D S Y U .
C.O.
P R O C F F D 0 9 C P P F V ? E P T O NO.
FIELD CHANGE ne3 P R E V Q C P T Q S Y M .
F I E L 0 P R O C E F 9 ' O C FREV Q E P T 9 SVM.
T I M E E X T E N S I O N S FREV R F P T f l NO.
I S S U E D T H I S P F R 1 0 0 s C O 2 3 CAC FPrl H
I S S U t U TH1 S D E R I ' 7 0 FPn-H 1 CANC)
I S S U E D T U 1 5 PEQICIC FCO-34
I S S U E O T H I S PEQ1!P
FCO-35
I S S U E U T H l Z PF Q l C O F C q - 3 6 C A C FPC R
l S S U E 0 T H I S PERICO PFrl-BICAPIC)
ISSUEO TWIS P F P I C D CC?-q71FPT-K)
I S S U t U T H I S DEQICC FCO-38
ISSUED TU1 S P E R l C r FPq-KICANC i
ISSUEO T H l S P E R I C P F C C - 1 9
ISSUE~T n r s OE~ICO r v M
A 1.3
O TC
110
A 73
1 TO
C R l G l N A L C O Y T R d C 7 AuOUhT
YET CHANGE
CURRENT COb'9ACT
AMGUNT
V A L U E OF WqPK I N P L A C F
TO
12-"1-75
V A L U E CF WCQK I F ( S T b L L E C
CURQFVT PERIOO
V A L U E O F MOQK I N P L A C E
TC
12-37-75
VALUE CF M A T E R 1 4 L O h S I T E
V A L U E OF hOoK N O 1 C O U P L E T E O
E A R Y E O TC C A T E
(12-30-75)
AMOUNT R E T A l N E C (1.7
'30 F l X E D A M C t J N T )
TOTAL PQEV 13US P I V M E Q T 5
PAYHENT T H I S PFR 1 3 0
TOTAL
PAVPE'JT
T C DAT'
FIGURE 5-11