Professional Documents
Culture Documents
Advanatges of The Critical Path Method
Advanatges of The Critical Path Method
Advanatges of The Critical Path Method
FAMADICO
2011
Construction Planning, Scheduling, Estimating
Friday/ 6-9 PM
March
25,
commencing the follow-on work, different areas of the project are at different stages
completion within the sequence of work.
3. On most major construction projects there are essential installations which must
receive extra attention even when these installations are not reflected on the
critical path
4. Timely completion of most projects requires the establishment of flow and
momentum. The speed of the installation of various trades is substantially affected
by the rhythm of a project.
The examples of pragmatic considerations discussed above point out that the
contractor must exercise good judgment in interpreting the information revealed on
a CPM schedule.
Obstacles to use of CPMs
Contractors have historically resisted CPMs, not because they find fault with the
theory, but because of numerous administrative problems. First, it forces the
contractor to study his operation in detail with careful planning of sequences.
Second, since CPM is a logical sequence, and since it details task durations, obvious
errors can easily be spotted. Third, a written schedule puts the contractors
operation on the line for all to see, and what was composed as an estimated
schedule becomes a tool or weapon for self-serving purposes of all involved.
Applications to Claims
More often than not, the CPM schedule will aid the project manager when he must
file claims. A good CPM is worth a thousand pictures and ten thousand letters. CPMs
are recognized by owners, engineers, contracting officers, boards and courts. It is
difficulty to counter the graphic display of delays on a CPM diagram. Once a delay is
plotted on the CPM, its impact can be seen on all subsequent activities. At this
point, the cost and time impacts resulting from a change order, suspension, delay or
disruption can be computed. This is the time to analyze and price all foreseeable
impact for a change order, as it is increasingly more difficult to receive payment for
impact once a change order is negotiated.
Application- Construction of the CPM
A CPM should be drawn up prudently. When the contractor makes up his schedule,
he should be as realistic as possible in planning. 1.) The original schedule in
accordance with the milestone dates in the contract documents. 2.) An earliest
possible finish date. 3.) Formulate method of measureing progress. Set up and
organize activities into measureable packages.
Pitfalls to avoid
These guidelines not only aid good construction management, but also are of great
value for successful claims documentation. Abnormal weather, change orders,
delays, strikes, and other job impacts are plotted on the CPM. Failure to prepare or
use the CPM properly can be cause to invalidate its use in substantiating a claim.
CPM presentation of the job is the single most important factor in determining the
acceptability of the Contractors CPM based claim.