For this co-cabinet scenario, the commissioning is the same with commissioning BTS and
commissioning NodeB separately.
If UsageStatus = Normal is displayed in the query result, the link is normal. Otherwise, the
link is faulty. For example:
Checking the transmission between the BBU and the BSC and the transmission between
the BBU and the RFU
Specify the number of the target link in the Link No. box
If the link is abnormal, check for the related alarm, for example, 1000 LAPD_OML Fault
alarm. Then rectify the fault according to the alarm help.
Confidential Information of Huawei. No Spreading Without Permission
Click Exec, and the result is displayed in the Common Maintenance window, for
example:
Click Exec, and the result is displayed in the Common Maintenance window, for
example:
If the port running status is down, check for the related alarm, for example, 11278 E1/T1
Local Alarm . Then rectify the fault according to the alarm help.
Click Exec, and the result is displayed in the Common Maintenance tab page. For
example:
Click Next to specify a BTS to be loaded. For example: In the following table, only one BTS
named bts3900 to be loaded.
Click Next to specify a BTS to be activated. For example: In the following table, only one
BTS named bts3900 to be activated.
The green color indicates that the board operates normally. The red color indicates that
the board is faulty, and an alarm related to the board exists.
tab to check the board configuration of the BTS
For example:
For example:
Double-click the active alarm that needs to be handled, and the Alarm Detailed
Information dialog box is displayed
For example:
If the alarm can be reported and cleared normally, end the checking task.
Confidential Information of Huawei. No Spreading Without Permission
If the alarm cannot be reported normally, reconnect the related monitoring signal cables.
This describes how to commission the base station in the transmission unavailable scenario.
In the initial phase of the commissioning, the transmission cables between the base station
and the BSC/RNC are not properly connected. The upgrading of the base station software
and downloading of the data configuration file can be implemented on the SMT/LMT on
the base station side. After the downloading and upgrading, you can check the hardware
status through the LEDs. In the later phase of the commissioning, the transmission cable
between the base station and the BSC/RNC is properly connected. You can commission
the base station on the remote maintenance terminal.
Remote Site Maintenance: maintaining the BTS through the LMT on the BSC side
Site Maintenance Terminal: maintaining the BTS by directly connecting the Site
Maintenance Terminal PC to the BBU of the base station through the Ethernet ports
This describes how to set the IP address of the Site Maintenance Terminal PC to the same
network segment as the IP address (192.168.0.72/255.255.255.0) of the BTS.
The site management right refers to the right to set the parameters of a BTS. After a BTS is
powered on, the remote Site Maintenance System obtains the site management right by
default. Before operating the BTS through the Site Maintenance Terminal System, you
must obtain the site management right first.
When operating a BTS through the Site Maintenance Terminal System, pay attention to
the following:
Obtain the site management right before writing data; otherwise, you may not be able to
write data, for example, load a software or activate a software. You can read data from
the BTS without the site management right.
After a BTS is powered on, the remote Site Maintenance System obtains the site
management right by default and performs all operations directly. Before operating the
BTS through the Site Maintenance Terminal System, you must obtain the site management
right first. You cannot operate the BTS through the Site Maintenance Terminal System and
the remote Site Maintenance System at the same time.
After completing the local maintenance, you must release the site management right.
the parameters in the Deploy RXU dialog box, Set Card Type to MRFU, Chain No. to 0,
SFP No. to 0, and Hop No. to 1. These values are taken only as an example in this section
On SMT, the parameter of DEMU cannot be set. The parameters of DEMU and DPMU
are set by default, therefore, no parameter setting is required
Right-click the slot, and choose the board to be configured from the shortcut menu
Set File Name. In the Send Window Size spin box, specify a size. In the Version area,
enter a version number. In the File ID drop-down list box, select DTMU_MAIN , and then
press Start
Repeat the step to load the software of other boards.
In the Version area, enter the version number of the main control board software. In the
File ID drop-down list box, enter the file ID, and then Click OK.
The TMU software activation causes the BTS reset. You are required to obtain the site
management rights, and then activate the software of other boards.
Repeat the step to activate the software of other boards.
Wait for one to two minutes after the software loading is complete. Then, activate the
software.
During the activation of the DRRU board software, if the Site Maintenance Terminal
prompts that software activation failed, check whether the communication between the
BBU and the RRU is normal..
If UsageStatus = Normal is displayed in the query result, the link is normal. Otherwise, the
link is faulty. For example:
If the link is abnormal, check for the related alarm, for example, 1000 LAPD_OML Fault
alarm. Then rectify the fault according to the alarm help.
Click Exec, and the result is displayed in the Common Maintenance window, for
example:
Click Exec, and the result is displayed in the Common Maintenance window, for
example:
If the port running status is down, check for the related alarm, for example, 11278 E1/T1
Local Alarm . Then rectify the fault according to the alarm help.
Click Exec, and the result is displayed in the Common Maintenance tab page. For
example:
Click Next to specify a BTS to be loaded. For example: In the following table, only one BTS
named bts3900 to be loaded.
Click Next to specify a BTS to be activated. For example: In the following table, only one
BTS named bts3900 to be activated.
The green color indicates that the board operates normally. The red color indicates that
the board is faulty, and an alarm related to the board exists.
For example:
The green color indicates that the board operates normally. The red color indicates that
the board is faulty, and an alarm related to the board exists.
For example:
For example:
Double-click the active alarm that needs to be handled, and the Alarm Detailed
Information dialog box is displayed
Note instruction
Font Size: 11
Segment: 3 pound
For example:
In the BSC6900 window, type SET BTSDEMUBP in the Command Input box, and then
press Enter.
Set Board Parameter Configuration Enable to YES. Click Special Alm
SwitchvEnabled to check whether GMDISABLE(Gate Magne) is selected.
Click Special Alarm Switch Valid to check whether the setting of the GMLOW (Gate
Magnetism{Low Level}) is consistent with the actual valid level of the door sensor.
If the alarm can be reported and cleared normally, end the checking task.
If the alarm cannot be reported normally, reconnect the related monitoring signal cables.