MEETING MINUTES

Ithaca Commons Repair & Upgrade Project


Date
04/01/2014

Start
10:00 AM

End
11:00 AM

Purpose
2014 Construction Meeting #1
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction
Power & Construction Group
Verizon
NYSEG Gas

C#2 Utilities, C#3A Surface, C#3B Electric


Next Date
04/08/2014

Next Time
10:00 AM

Prepared By
Jessica Buckley

Location
Commons Project Office - 215 East State St. Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley
Tammy Baker
Susannah Ross (A), Eamonn Hutton (A)
Dan Walker, James Matzat (A)
Ralph Avery, Andy Breznay, Matt Thomas (A), Roberto DeVincentis(A)
Lou Zupan, Joe Lester, Bill Planert, Brian Planert
James Edwards, Dave Comer
Doug Stafford, Jack Barker

Item / Description
1. RFIs
1.1. Any open RFIs at this time
2. SUBMITTALS
2.1. Any pressing submittals to be approved

2.2. Longest lead time items


3. UTILITIES COORDINATION
3.1. NYSEG, Verizon & Storm at Cayuga:
NYSEG prep to relocate gas for
installation of storm btw DMH 4.01 &
DMH 4.02

3.2. Verizon & Tree Pits: Extent of work


required along the south side of E State St
to lower cables; Conflicts in Bank Alley
TBD

Notes

Due

Per MK: PCG is to build lighting to spec;


submittals reqd for each component (see
spec: concrete, steel, etc.)

Barker will notify the project office after


he confirms that NYSEG can cut and cap
gas main; NYSEG needs a few days notice
to coordinate work; City street
interruption would need to be coordinate
if work extends into street; Existing Storm
MH #3 will be surveyed by project team;
Work planned to start 4/7
Edwards can coordinate the lowering of
Verizon conduits on E State St if reqd by
city; Architect analyzing extent of work;
Verizon DB in Bank Alley not expected to
be in conflict with tree pits; P&CG to
determine if centenary poles conflict with
Verizon DB

3.3. Verizon & Water Feature: TBD

Page 1 of 2

04/08

3.4. TTC Alley/Telecom: Discuss plan of


action and variation from FD #6; schedule
test pit; Verizon most likely will have
work to coordinate
3.5. NYSEG Electric & BM Pavilion: Vacri dig
test pit to determine dimensions of
NYSEG DB in the location of the Pavilion
foundation
3.6. NYSEG Gas Main: Replace existing main
on E State St
4. SCHEDULE
4.1. Vacri
4.2. J&R
4.3. P&CG
4.4. NYSEG
5. VAULTS
5.1. Telecom, Water, NYSEG Gas (?):
Coordinate foundation penetrations
when possible; JB will issue survey notes
of property vaults and installation
limitations.
5.2. Vault Infill
6. ELECTRIC
6.1. New Electrical DB
6.2. Temp lighting

7. TELECOM DUCT BANK


7.1. Rebar specifications

Vacri to dig test pit this week; Notify


Dennis Kuhn of test pit; coordinate FD # 6
with EE Root

Tentative start date 4/7/14, waiting on


project funding approval; Taps for 2
services, saddles for 4 service

Start work 04/14

Pending field directive to be issued for


118 and 126 E State St

Temp lighting expected to be completed


by 4/3/14; City to contact NYSEG to
disconnect power to old lighting
foundations
The duct bank is LaBellas standard detail
for heating and shrinkage Engineer to
review and determine possible reduction;
Vacri to propose credit on rebar reduction

ADDITIONAL NOTES: