MOP PM and Testing Genset With Load TOC
MOP PM and Testing Genset With Load TOC
Initial Drafted
by:
Managed
Service TOC DEA
Date:
Reviewed by:
Dhiyaul Falah
Date:
Reviewed by:
Date:
Approved by:
Date:
Revision Record
Date
Revised Version
Change description
Author
V1.0
Table of Contents
1
2
PREREQUISITES..................................................................................................
.....................5
3
SCOPE OF WORK........................................................................................ 7
ROLLBACK OPERATION.............................................................................14
PERSON IN CHARGE.................................................................................15
SUPPORTING DOCUMENTS.......................................................................16
1.1 Schedule
Date : 22 March 2013 to 24 March 2013
Time : 16.00 05:00
1.2 Location
TOC Menara DEA Jakarta
Gedung Menara Dea
Jakarta
2 PREREQUISITES
This section contains information on the personal Health & Safety
Information, tools, equipment, and conditions required for the installation
procedure.
The hazard symbol is common for all three admonitions levels. The three
admonition levels are defined below :
Danger
result in death or
serious injury.
Note : Danger can be accompanied by other symbols
depending on the country
of operation.
Warning
Indicates that there is a potential hazard that could result in
death or injury.
Caution
injury.
2.3 Safety
All Emerson Standard safety methods should be understood and practiced.
Protective goggles, gloves, step ladder, hard Hat and Safety Shoes must be
worn while working on the equipment that present hazard. Extreme care
should be taken to prevent injury from falls.
2.4 Document
Make sure that the following documents are read and understood:
1. MOP preventive maintenance and testing genset with load TOC Menara
DEA
2. Approved WP by AXIS
2.5 Tools
2.6 PPE
Goggles
Leather Gloves
Safety Shoes
3 SCOPE OF WORK
Emerson will test the genset with load at TOC menara DEA by
simulation PLN blackout and genset should supply TOC load
Operation
Preparation Genset# 1
16:00
16:05
16:10
16:15
16:20
16:30
16:35
16:40
16:45
16:50
17:00
20:25
No effect
No effect
No effect
No effect
No effect
No effect
No effect
Testing simulation PLN Blackout and genset should supply TOC Load
00:05
00:10
No effect
Record which genset is set as
prime
Inform NOC that the genset test No effect
will be started. Record the name
of person of NOC, and the time of
notification
00:40
00:40
00:42
00:45
00:47
00:50
10
11
12
Network will be backed-up by UPS and Rectifier while lost power from
PLN or genset for less than 5 seconds.
This is the transfer period of transfer power supplied from main source
(PLN) to Genset
13
7 ROLLBACK OPERATION
Make sure by Checking at AMF/ATS that all load has switch back to
Main Input (PLN)
14
8 PERSON IN CHARGE
Name
Ade
Kurniawan
Ahmad
Jaelani
Dhiyaul
Falah
Rizal
Arif
Ferry
Komaruddin
Yehuda Deo
Company
Emerson
08119205656
Emerson
081586239966
Emerson
08211232151
Emerson
Emerson
Emerson
Emerson
Emerson
083897705626
083897705626
083897705626
083894345026
083873057767
Supervisor
Supervisor
MS TOC DEA Engineer
MS TOC DEA Engineer
MS TOC DEA Engineer
MS TOC DEA Engineer
Power Engineer
Power Engineer
15
9 SUPPORTING DOCUMENTS
16