CMPIC 7 Creating Work Packages (Production Orders)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 24

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

Creating Work Packages (Production Orders)


From Cloudis CMPIC Wiki

Contents
1 Maintain Work Packages
1.1 Creating the work package
1.1.1 Adding Cables to the Work Package
1.1.2 Other useful queries and reports at this stage of the process
1.1.3 Looking at more filters to use for Work Packages
1.1.4 Additional flexibility in creating work packages
1.2 Releasing the work package
1.2.1 Cable cutting, reports, installation management
1.2.1.1 Using Cable Recuts if required at any time.
1.2.2 Print the cable pulling (running) sheet
1.2.3 Record cable installation progress
1.2.4 Look at a progress report
1.2.5 Complete cable pulling progress
2 Query Cables and Work Packages
3 Work Package Release
4 Work Package Release Status
5 Cables on WP affected by Change Control
6 Cables with Reallocated Work Package
7 Reports
7.1 Work Package Detail
7.2 Detailed Cable Schedule
7.3 Segment Report
7.4 Positional Node Analysis
7.5 Schedule of Local Cable Routes
7.6 Production Cable Changes
7.7 Cable Status by Block
7.8 Cable Changes Summary
8 References

Maintain Work Packages


Create and maintain Work Packages (WP) and the criteria used to select cables for the Work Package. From this screen
navigate through to screen to link cables to the WP.
Work packages (sometimes referred to as Production Orders) are the way in which cables are grouped together for installation.
Once grouped together, the cables can then be tracked and managed as a single work package.
There are many criteria that could be used when selecting cables to group together on a work package, but the key thing is that
these work packages can be built up over a period of time, adding more cables as design progresses. So, before installation
starts, you can register the work packages to represent the different stages of the build, then gradually add cables to those work
packages (sequencing the cables as necessary) and then releasing those work packages once installation should begin.
The cables can be grouped together by using one or more of the following criteria:

1 of 24

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

When creating a Work Package, the user adds the selection criteria line by line using as many criteria as are required to filter the
number of cables down to those required on the work package. If, after this filtering, there are more cables eligible for inclusion
on the work package than is desirable then they can be added cable by cable from the filtered list.

Creating the work package


For the following example the cables will be grouped together by ROUTE SEGMENT. A route segment being a hanger, tray,
penetration or other part of the nodal network.
The first thing you need to do decide which segment(s) are to be used as the basis for the Work Package.You may already have
this information from a drawing or, you can use CMPIC to search for relevant segments.
If you go to the Nodal Network > Create Nodal Network screen, using CMPIC searches you can find, for example, just the
penetrations (MCTs) that you are interested in. You can see from the Used boxes which segments have cables on them. If you
double click on one of these segments you will be able to see the list of cables routed on it.
If you make a note of the segment ID(s) from the Create Nodal Network screen you can the use these in the creation of the Work
Package.
The Work Packages themselves are created in the Maintain Work Packages screen which can be found under: Cable Installation
> Cable Work Packages > Maintain Work Packages (see screen shot below)
In the Work Package ID field type an ID for the package.
If you have more than one site at which the Work Package could be carried out, these sites can be created in Library Data and
will then be displayed here. To create sites, first create them in the Library Data > General Data > More > Maintain Sites screen.
Then go into Library Data > Project Configuration screen. In the Build Details tab you need to double click in the Site ID field and
select one by one the sites that you created in Maintain Sites. Give each a priority number to dictate their position in any lists of
values of sites. These sites are now available to add to the Work Package.
Note: You must have at least 1 site defined to be able to create a Work Package
If Installation Teams have been entered in Library Data then the team responsible for this work package can be added by double
clicking in the Installation Team field and selecting as applicable. Teams need to be defined in Reference Data against a type of
ITEAM first, and could represent a team, person or sub-contract company. It is worthwhile adding Teams because CMPIC has a
number of useful reports that can be generated by Team.

2 of 24

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

3 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

When you SAVE the record the date of creation will be populated.

You can also set the Operator field to Equal To or Not Equal To the value that you are entering.

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

This takes you to the associated screen shown below.


Your work package number will be in the top left hand field.

Follow the instructions below.


Use the Green Traffic light icon to retrieve the cables which match the criteria for the work package and have had their routes
approved. Tick the boxes to the right of the cable list to select a few cables to go on the work package. Press the COPY
SELECTED button. This copies the cables into the working area. Press SET POSITION. This gives each cable a position
number. This number normally represents the order that the cables that have been cut are to be wound onto a smaller drum for
carrying to site or on board. The position can be set by: Cable Tag Number, Diameter, Length or Segregation and this criterion is
set using the pull down list. Once set here, position can be modified later by the cable cutting team if need be.

4 of 24

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

5 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

Once you have set the position, click on the Link to Prodn WP button. You will get a message Linked nn cables Close down this
screen by using the EXIT icon on the toolbar. You are now back in the main Work Package screen and you have created a Work
Package with associated cables.
A note about Setting Tape Marks:
If you use Tape Marks to identify the point to which a cable should be pulled e.g. an MCT, then these tape marks can be set by
CMPIC so that the cutting team know the exact point that the mark should be made.
To enable Tape Marks to be set, you need to have the project default setting switched on. This is found in the Production tab in
the Project Configuration screen. You may need to get your system administrator to switch this option on. THIS OPTION NEEDS
TO BE ENABLED BEFORE YOU CREATE ANY WORK PACKAGES IF YOU WANT TO USE TAPE MARKS.
If the project default for "Use tape marks?" is set ON, then when the work package is created, the position of the tape mark must
also be recorded. The tape mark is the distance from a specific cable end to the common segment (hanger, tray or penetration).
This distance is calculated automatically by CMPIC when the user selects which cable end the length should be calculated from.
It can be populated in batch for cables which all originate in the same area. Otherwise you will need to type in the length
manually in the field headed Tape. This will then note on the cutting sheet the length and from which end the tape mark should
be made.

Adding Cables to the Work Package


Once cables have been selected for inclusion on the Work Package and extra cables added at a later date, it's possible that the
position ordering of cables on the Work Package is no longer correct. In the Pos Field it's possible to manually change the value
for position to get cables in the correct order again. To do this, it may be necessary to give cables an artificially high or low
position value, but the Resequence button will then update the Position so that it runs sequentially from 1 to the total number of
cables.
The Query Cables and Work Packages (CMYF04) screen is useful because it can be used to list all cables which have yet to be
allocated to a Work Package. There's also an output to CSV.

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

6 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

General installation notes for the work package should be entered at the top of this screen (see screenshot overleaf), whereas
cable specific installation notes should be entered in the Details field at the bottom of the screen. The Work Packages report
(CMYP/R01) details each work package and includes these instructions.

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

Other useful queries and reports at this stage of the process


1. Segment Report. Lists all cables running through a particular segment. Useful when looking for cables which are all routed
through a particular transit, hanger, tray etc.
2. Positional Node Analysis. Lists all cables which start and/or finish in a particular area. Useful for finding cables to group on
a work package.
3. Work Package Pulling Statistics. Need a norms file for this, or else it will use the defaults, but it will show the estimated
time required to install the selected work packages (and percentage complete as pulling begins).
4. Work Package Progress by Team. Has options for "Work Package not allocated to a team", "Work Package assigned to
team, no progress" etc etc. Very useful because you can see where in the planning process the work package has got to.
You now have a work package with cables on it which we can now take to the cable cutting stage.
Before doing so, however, we should look at other filter criteria that can be used when creating a work package.

Looking at more filters to use for Work Packages


So far we have just looked at using 2 segments (hangers, trays or MCTs for example) as the filter criteria for the cables to be
associated with the work package.
In the case of segments, if you add more than one segment, the filter looks for cables which pass through ALL of the segments
listed. If you refer to the Explain Filter tab on the Work Package creation screen, the filter explanation is: Route Contains
Segment '18929' And '18914' .
If you add even more segment numbers to the filter, these will be included in this same filter and appended with an AND.
In the case of all other filter criteria, the criteria are added as OR.
See screenshot below.

Additional flexibility in creating work packages


Where you are looking to maximise the potential of the installation resource available, it could be that more than one set of
selection criteria for a work package would be useful.
To cater for this possible requirement, you can create up to 10 sets of criteria against which CMPIC will filter and look for eligible
cables.
To do this, you need to be in the Maintain Work Packages screen.

7 of 24

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

8 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

9 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

As explained above, you can create up to 10 sets of filter criteria. This can be useful in keeping each set quite simple and
therefore easily modified.
If you choose to add the filter criteria to just one set, then there is no limit to the number of criteria you can add.

Releasing the work package


Once you are happy that all the cables required have been added to your work package, you need to release the work package
so that it can pass to the next stage of the process.
Go to Cable Installation > Cable Work Packages > Work Package Release
Click on the green traffic light to bring back the Work Packages awaiting release.
Click in the box to the right of the work package you have created, and then click on RELEASE

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

10 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

At this point Work Package Release Status (see below) is a useful screen.
This is useful for:
a) Planning because they can see all the work packages yet to release. b) Stores because they can see all the work packages
which have been released to them but for which they have yet to produce the cutting sheet or, if an asterix is shown at the end of
the row (just after the CS button) this signifies that a cutting sheet has been produced but there are still cables remaining on the
work package which have not yet been published on a cutting sheet. c) Production because they can review the work packages
which they have to install.

This screen shows the status of each work package.


If the work package list is longer than will fit on the one page, you can use the filters Not Released, or Released, no CS (no
cutting sheet created as yet).

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

11 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

As with all CMPIC screens you could also use the Query facility in the Prodn WP column to look for specific groups of records
e.g. %TEST% to retrieve all work package IDs including the string TEST.
Under the Rel? column, you can see which work packages have been released.
Once the work package has been released, you can arrange for the cables on the work package to be cut.

Cable cutting, reports, installation management


Go to Production Module > Cable cutting & pulling > Cable cutting schedule
Use the green traffic light to retrieve your Work Package. Only Released Work Packages will be available.

Refer to training manual section P4 Create Drums to find out how to add available material so that CMPIC can use it.
Initially, all cables listed in the Cutting Schedule have their Drum ID set to TBC (or the no-drum identifier that was defined in
project defaults). You can select drums on a cable by cable basis by double clicking in the Drum No field which gives you the list
of eligible drums (only drums with sufficient length remaining and located at the same site (if relevant) are displayed). This is
useful if a particular drum is required or one which is located in a particular store (for ease of cutting) should be used.
If a cable has been incorrectly assigned to a drum, you can reset its value back to TBC (or the default name for No Drum) and its
length will become available on the originally selected drum for use again.
Alternatively, CMPIC can optimize the use of drums for you. Using the Optimize Drums button will attempt to allocate a drum to
all cables with TBC; it prioritises drums as follows:
1. Any "not normal" drum i.e. Any length which is saved in the Drum Schedule but which is not categorised as a Normal
Drum. (These would include returned lengths, coiled lengths etc. These different categories can be added to your CMPIC
system based on your own requirements).
1. If only normal drums exist they will be chosen in order as follows:
a drum that has already been allocated to another cable on the work package then
a drum that has already been used, but not on this work package then
a completely new drum

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

12 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

Once you have added drum details, you will have material available. If you now double click in the Drum No field you will see
eligible drums listed.

You can select drums from the list cable by cable, or if you click on the Optimize Drums button, CMPIC will allocate drums based
on the selection process outlined on the previous page.

Once drums have been allocated to as many cables as possible, the cutting sheet can be printed using the Print button. This is
the instruction for stores to cut the cable. You can use Check Print which gives a preview of the cutting sheet, without actually
updating any cable dates. The Print All option displays all cables on the work package, with their status (useful for large work
packages).
Click on the Print button, choose Final or For Use option and Preview the report on your screen.
If you now take another look at the Drum Schedule, in the Drum Usage tab you will see that material has been ASSIGNED and
the drum lengths modified.

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

13 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

Now that you have printed the cutting sheet, in the Cutting Schedule screen you will see that the Issued to Store column has
been updated with the date.

The next stage is for someone to add the Date Cut once the cables have been cut and are ready to collect for installation.

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

14 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

As well as populating the Date Cut field, you can also add the name or clock number of the person who cut the cables, and the
location of the coils or lengths. There are also fields for name of the person who collected the cables.
Notes about the cutting process.
The Print option publishes the cutting schedule for all cables on the work package which have not already been issued on a
cutting schedule (or a recut is required).
These reports also include an option to produce a label ident file. If selected, this will produce a CSV file which can then be
submitted to a cable marker system. (The label ident CSV file has fields for: Device to Device, Area to Area, Cable Type,
Segregation, Length, Reeving Point (if used), Cable ID.)
If a cable has been issued on a cutting sheet, so Issued to Store has a date, and stores subsequently discover there is
insufficient length on the drum, or it would be better to use a different drum, the only way to change the drum assigned is to use
Revert Drum. This process is explained overleaf.
Note: the Reeving Point is the ID of the hanger, MCT or tray that is being used as the point to which the cable will be pulled and
which will correspond to the tape mark made on the cable. We refer to the same point as a Pull Point.
Revert Drum is only available for cables which have not yet been cut, but which have an Issued To Store date. Selecting Revert
Drum sets the Drum No back to TBC and releases that cable's hold on the drum length which is reallocated back to the drum for
general use. A new drum can then be assigned to the cable and its cutting sheet printed again.
To Revert the drum, highlight the cable that you want to move to have cut from an alternative drum. Then click on Revert Drum
button.
You will get the alert shown below.

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

15 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

If you OK the alert, then you will be able to double click in the Drum No field and allocate an alternative drum.

Once the drum has been allocated, the Issue to Store field will be blank. To populate this field, you Print the cutting sheet again
using the Final or For Use option.
Useful reports at this stage:
Unallocated Drum report. This gives a list of all cables with a drum number of TBC i.e. no drum assigned, but where there
is a suitable drum available, this is listed. It is a way of checking for cables which haven't yet been assigned a drum, but
there is now material available. There is also an option to only show those cables for which there is no suitable drum
available. This can be used to identify where more stock is required.
Cables Cut Between Dates
Drum Usage History. Useful if you find that a drum is faulty and you need to recall all cables cut from the drum, or if you
just want to see how the material has been called-off. It also shows whether cables have actually been cut or if they are
just reserving the length.
Material Control report.
Using Cable Recuts if required at any time.
If a cable has been cut, then material will have been used from a drum. If a subsequent recut of the cable is required at any time,
then you would need to add a recut. The Query Cable Recuts screen (CMYF12) provides visibility of cables which have been cut
more than once.
To add a Recut, you follow this process:

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

16 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

Note: if you are using Tape Marks.

Adding the recut takes you back to the main Cable Cutting schedule.
To enable CMPIC to allocate and assign cable accordingly, you now need to print a new cutting sheet.

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

17 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

The Cutting Report has details of the cables to cut and has temporary labels which can be cut out and used to identify the
cables.
Cut length - by default this is the design length rounded either up or down (controlled by a project default). However, this figure
can be modified if the installer is certain that a cable would be too long/short otherwise (there is a warning if the cut length is
different to the design length).
Double click in Store Despatch - it will fill in todays date.
If you like, put in the name of the person who collected the cables from store.
SAVE and EXIT
Quick Update is available to populate any of the remaining fields eg. Date Cut and Cut By can be entered once and copied to all
cables which have had their cutting sheet issued.

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

Print the cable pulling (running) sheet


Go to: Production Module > Cable cutting & pulling > Reports > Cable running sheet.
This report gives authority to the installation team to install the cables which have been cut as part of the Work Package you
created.

The report gives installation details for the cables.


Notes:
1. The running sheet (equivalent of Pull Sheet or Pull Card) can be produced even if the cables have not been cut (this is so
sites aren't prevented from raising status to PSP (Pull Sheet Printed) because they are waiting for the arrival of material),
but the running sheet will display an asterix against any cable which does not have a drum assigned (it doesn't actually
have to be cut at that stage).
2. Once cables have been drummed, reprinting the running sheet will display the cable without the asterix. Since the running
sheet is the instruction to install cables, the asterix gives the installer visibility of the cables which will be missing. Some
sites may wish to supply the work package report (CMYR01) with the running sheet, because this shows any additional
installation instructions (if used).
3. Reprinting the running sheet gives the option to exclude any fully installed cables. This is useful if work is progressing in
stages and not all cables can be installed at the same time, so the report just shows those cables not fully installed. If the

18 of 24

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

19 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

cable has been coiled and the point (node) at which it has been left is recorded in CMYF13 Cable Pulling Progress (note
that the project default for Coil Location must be set to Node), then this node is also highlighted when the Reprint option is
chosen.
Other useful reports:
Team Pulling Progress
Work Package Progress by Team
Work Assigned and Completed by team

Record cable installation progress


Go to: Production Module > Cable cutting & pulling > Cable pulling progress by WP
Use the green traffic light to retrieve the list of work packages and scroll down until you find yours.
Tick the box to the right of a cable.

You can set the cable to be Fully or Partially Pulled (installed)

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

20 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

To set a cable as Partially Pulled, tick the box to the right of the cable(s) to be registered as partially pulled.

If you are using Tape Marks


If you are using Tape Marks then clicking on the Set to Tape Mark will fill in the length of cable to the mark.
If you now click on Set to Reeving point, you will be asked at which node the coil should be left.

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

21 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

This is so that when you later reprint the pull sheet for the next shift or the team which will continue the installation, the location of
the coil will be highlighted on the report.
You can now add the Team responsible by double clicking in the Team field.

Click on Continue.
You will see that the status of the cables is now Partially Pulled.
You can return to these cables anytime and pull some more in, or register them as fully pulled.
SAVE and EXIT

Look at a progress report


Go to:Production Module > Cable cutting & pulling > Reports > Progress/Statistics > Work Package Pulling Statistics

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

22 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

Double click in the Work Package field. Select your work package.
Click on PREVIEW.
Take a look at the report which shows details of how much cable has been installed on your work package.
Like many CMPIC reports this data can be output as a .csv file for use in Excel or reporting tools.
Another option you can set up for this report is to link it to your own in-house norms for cable pulling. So if you have estimated
time to pull in a given length of cable (by metre of foot) in a .CSV file then the report will calculate the time needed to complete
the job. These norms are held outside of CMPIC in a location given to CMPIC so that it reads the .CSV when running the report.

Complete cable pulling progress


Go back to the Cable Pulling Progress by WP screen, retrieve your work package and update all cables to be Fully Pulled.
SAVE & EXIT

Query Cables and Work Packages


Shows each cable and associated WP
Using this screen query you can see which cables have been allocated to a Work Package and which have not.
Results of the query can be output as a .csv file.

Work Package Release


Once a WP has been created and is ready for production, this screen is used to release it. Once the WP is released, all cables
on it are released which allows them to have a pull sheet or running sheet created as part of the production process.

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

By checking the boxes to the right of the Work Packages you want to release and then clicking on the Release button, this will
process the Work Package.

Work Package Release Status


This query screen gives a summary of the various Work Package release statuses.

By using the buttons you can see which Work Packages have not been released, or which have been released but have not had
a cutting sheet printed yet.
By clicking on the CS button you can also see cutting sheet information, where this exists.
A red star to the right of the CS button indicates that there are still cables on the WP for which cutting sheets have not yet been

23 of 24

24.04.2014 11:34

Creating Work Packages (Production Orders) - Cloudis CMPIC Wiki

24 of 24

https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

produced.

Cables on WP affected by Change Control


If, by changing the route or other attributes of a cable through Change Control, that cable no longer meets the criteria of the WP
it is on, then it will appear in this screen query. This alerts the user that the cable has been removed from its original WP and is
awaiting reallocation.

Cables with Reallocated Work Package


Shows list of cables which have been subject to reallocation of WP.

Reports
Work Package Detail
Lists by work package the details of cables including length and from which drum cables were (or are to be) cut.

Detailed Cable Schedule


More detailed cable schedule (usually to customer design)

Segment Report
List of cables in each nodal network segment along with cable details.

Positional Node Analysis


Where used, coordinates appear with the node identifiers.

Schedule of Local Cable Routes


List of cables scheduled to or from devices located in a given area.

Production Cable Changes


List of cables which have been changed between two dates. Parameters for type of change.

Cable Status by Block


Where blocks are defined, lists cables within the block by status. Report parameters by block, cable status and whether the
report is for cables which are fully contained within the block or which start and/or end in the block.

Cable Changes Summary


It is possible in CMPIC to create and maintain a list of Design Authorisation Notices (DANs) or Engineering Change Requests
(ECRs). This report prints out changes to cables and devices which are covered by a given DAN or ECR. These DAN/ECR
records are separate and in addition to the CMPIC Change Request raised to reduce the route or termination status of a cable at
PSP and/or TSP.

References
Retrieved from "https://wiki.cloudis.com/mediawiki/index.php?title=Creating_Work_Packages_(Production_Orders)&oldid=4145"
Categories: CMPIC Overview CMPIC FAQ CMPIC Help CMPIC Knowledge Base
This page was last modified on 29 November 2012, at 05:10.
This page has been accessed 89 times.
Copyright Cloudis Ltd 2014

24.04.2014 11:34

You might also like