Professional Documents
Culture Documents
PGU DryScrubberRecycle
PGU DryScrubberRecycle
www.powergenu.com
3.
2.
The design/sizing criteria for a pneumatic recycle ash conveying system will be presented along with the actual layout
of the pneumatic conveying system that utilizes conventional commercially available blower equipment. Todays
dry scrubber power plant projects that burn Powder River
Basin (PRB) coal have substantially increased the quantity
of solids in the flue gas stream to be collected in the baghouse or pulse jet fabric filter (PJFF).
In an effort to fully utilize the un-reacted lime and reduce
operating costs, utilities are recycling a portion of the fly
ash removed in the baghouse/PJFF for re-use in the scrubbing process. As a result, traditional utility-grade fly ash
pneumatic conveying systems are approaching their vacuum
pipe design limits, compromising the traditional high design
allowable margins, and sub-dividing the vacuum conveying
layout into smaller sub-systems and/or combination vacuum/
pressure pneumatic conveying systems. Higher ash generation production/capacities, difficult material characteristics
and lower operating temperatures provide additional design
constraints directly resulting in larger/more complicated
pneumatic conveying systems (i.e. larger equipment, more
pneumatic pipes, fittings and valve stations).
At the same time, the pneumatic conveying system
equipment location and pipe routing must be arranged and
often re-arranged during the design calculation period so
that the total equivalent conveying length (TEL) including
fitting losses, etc is determined to be less than the available TEL calculated length up to and including the vacuum
exhauster losses. This paper explains the methodology
used for developing system design criteria, presents design
constraints, lessons learned and the final system /equipment
2
Initial Studies
AEP operates a large fleet of pulverized coal-fired generating
units and has considerable experience operating and maintaining fly ash removal systems. However, the unique demands of
a Dry FGD system with a PJFF and fly ash recycle had not
been encountered. A design criteria document was prepared
by AEP based on their fly ash removal system experience,
including limited criteria for the recycle ash system based on
technical discussions with vendors, other utilities, etc. This
design criteria document was provided to Shaw to serve as a
starting point to develop the final recycle ash system design
and to prepare a system specification. Although the design
criteria document required some revisions for specific PRB
recycle ash handling methods and higher material quantities,
the document provided basic system criteria as follows:
Vacuum conveying from the PJFF
Conveying design capacity of 2-times production
3-days capacity for the waste ash silo
8-hours capacity for the recycle ash silo
Truck removal from the waste ash silo
Defined the level of redundancy for equipment
Redundancy
A key component for the success of the Fly Ash Removal/
Recycle System (FARRS) system is the level of redundancy
(LOR) required for the project. The LOR required by
www.powergenu.com
System Constraints
The Turk dry scrubber process receives flue gas exiting the
air heater at approximately 290 F. The flue gas contains fly
ash, and is combined in the Spray Dryer Absorber (SDA)
vessels with the finely atomized lime slurry reagent. Residence time in the SDA is nearly 12 seconds, as the moisture
in the slurry is evaporated, lowering the overall temperature
of the flue gas to approximately 170 oF. The flue gas and
solids (fly ash and FGD waste including un-reacted lime)
enter the downstream PJFF where the solids are removed
from the flue gas stream, captured on the fabric filter bags,
and collected in the PJFF hoppers to be removed by the
FARRS.
Specific system constraints encountered for handling
the recycle ash included developing system layouts that
fall within the vacuum limitations, using commercially
available equipment (staying with the OEM design limits),
and dealing with lower recycle ash temperatures, material
moisture, pipe routing, system complexity (two or four piping configurations), maintenance considerations and capital
costs. These constraints have an impact in the final equipment selection and in developing the system design and
arrangement as follows:
1. For this project, several recycle ash mass flow
quantities were provided by the boiler and SDA/
PJFF supplier. They ranged from high lime usage
to high fuel sulfur content. The case studies ranged
from a low (recycle ash) quantity of 56,312 lbs/Hr
to a high (recycle ash) quantity of 191,177 lbs/Hr.
In designing the optimum recycle ash removal system for this project; the highest flow rate value (191,177
lbs/Hr) was used for equipment sizing, pipe sizing/
routing and to identify how to convey the ash from the
outlet of the PJFF hoppers depending on the number of
conveying pipes needed.
2. The PJFF hopper arrangement set the outlet flange of
the hopper at just 4-feet above the top of concrete.
This distance was already pre-determined and given
to Shaw (BOP Engineer) to begin our design. This
distance does not allow adequate vertical space for a
pressure pneumatic conveying system consisting of
3
www.powergenu.com
References
1. Chemical Industries A series of Reference Books and Text
Books Volume 13 Pneumatic and Hydraulic Conveying of
Solids, O. A. Williams (1983).
2.
Acknowledgements:
This course is based on the presentation Dry Scrubber Recycle
Ash Systems: Considerations for Recycle Solids by Dan
Jennings, Material Handling Manager Technical Support,
Shaw Power Group; and Matt Usher PE, Mechanical
Engineer-New Generation Design & Engineering, American
Electric Power, at POWER-GEN International 2008. The
presenters acknowledged the technical contributions made by
United Conveyor Corp. to the approach method sections of
this paper.
www.powergenu.com
Online Completion
Use this page to review the questions and choose your answers. Return to www.powergenu.com and sign in. If you have not previously purchased the program
select it from the Online Courses listing and complete the online purchase. Once purchased the exam will be added to your User History page where a Take
Exam link will be provided. Click on the Take Exam link, complete all the program questions and submit your answers. An immediate grade report will be
provided and upon receiving a passing grade (70%) your Certificate of Completion will be provided immediately for viewing and/or printing. Certificates of
Completion can be viewed and/or printed anytime in the future by returning to www.powergenu.com, sign in and return to your User History Page.
Questions
1. What type of coal is
bituminous coals to PRB have encountered concrete-like ash formation in backpass locations. The list
a. 3.5% to 7.3%
b. 4.5% to 8.3%
c. 5.5% to 9.3%
b. 30 seconds
c. 12 seconds
d. 2 seconds
c. Un-reacted lime
c. 15,000
b. Anhydrous ammonia
b. 13,100
a. 7,500
a. Aluminum oxide
b. Two days
c. Three days
d. Four days
c. Limestone
a. 1.7 to 1
a. Water sluicing
b. Pneumatic
c. Belt conveyor
b. 1.5 to 1
c. 1.3 to 1
a. 140 F
a. 3.7 to 1
b. 150 F
a. 700 feet
b. 4.2 to 1
c. 160 F
b. 1000 feet
c. 5.7 to 1
d. 170 F
c. 1500 feet
www.powergenu.com