Professional Documents
Culture Documents
Detailed Breakdown: Item Details Unit Quantity Rate Total
Detailed Breakdown: Item Details Unit Quantity Rate Total
Detailed Breakdown: Item Details Unit Quantity Rate Total
DETAILED BREAKDOWN
Details
Item
Rate
Total
Unit
Quantity
Professional Fees
Architect / Draftsman Fees for Plans
Engineers Fees
Development Application Fees
(City of Sydney Council)
Construction Certificate
( City of Sydney Council)
Cost of Analysis / Budget
Asbestos report
Delapidation report
Item
Item
Item
Included
1
1
$
$
$
5,000.00 $
5,000.00 $
19,050.00
5,000.00
5,000.00
Item
8,000.00 $
8,000.00
Item
800.00 $
800.00
Item
Item
Item
1
1
1
$
$
$
250.00 $
2,600.00 $
2,300.00 $
250.00
2,600.00
2,300.00
Item
Included
9,480.00
Item
1,480.00 $
1,480.00
Per Day
800
10.00 $
8,000.00
Connection Fees
Electricity Connection Fees
Sewer Connection Fees
Water Connection Fees
Item
Per Connection
Per Connection
Per Connection
Included
1
1
1
$
$
$
$
1,200.00 $
2,000.00 $
900.00 $
4,100.00
1,200.00
2,000.00
900.00
Disconnection Fees
Electricity Disconnection Fees
Sewer Disconnection Fees
Water Disconnection Fees
Item
Per Connection
Per Connection
Per Connection
Included
1
1
1
$
$
$
$
600.00 $
1,200.00 $
600.00 $
2,400.00
600.00
1,200.00
600.00
Site Establishment
Site Office Equipment
Site Office/Shed
Site Toilet
Perimeter fencing
Item
Week
Week
Week
Week
Included
20
20
52
52
$
$
$
$
$
$
$
$
$
30,280.00
3,000.00
7,000.00
10,400.00
9,880.00
1.05
Administration Costs
Signboards
Head Office Administration Costs
General
Item
Item
Percentage
Percentage
Included
5
0.5%
10.0%
$
$
140.00 $
$ 7,000,000.00 $
$ 260,000.00 $
61,700.00
700.00
35,000.00
26,000.00
1.06
Insurances
Professional indemnity insurance
Public Liability Insurance
Contractors all Risk
Item
Percentage
Percentage
Item
Included
10.0%
10.0%
1
$
$
$
$
15,000.00 $
25,000.00 $
1,500.00 $
5,500.00
1,500.00
2,500.00
1,500.00
Item
wk
day
Item
Item
Included
20
20
1
1
$
$
$
$
$
$
$
$
$
34,000.00
24,000.00
5,400.00
4,000.00
600.00
1.00
PRELIMINARIES
1.01
1.02
1.03
1.04
1.07
Traffic Management
1 man Stop and Go Mon - Fri Ord Time
1 man Stop and Go Mon - Sat
Traffic control signage
Traffic Control Plan
150.00
350.00
200.00
190.00
1,200.00
270.00
4,000.00
600.00
1.08
2.00
3.00
Cleaning-up Expenses
Site Cleaning on Completion
Cleaning Site During Construction
Removing of Rubble
Cleaning Building before Occupation
Item
Item
Item
m3
Item
Included
1
1
12
1
DEMOLITION
Demolition of existing commercial brick building
(Including removal & disposal)
Removal of bonded asbestos
Removal of friable asbestos
Air monitoring
Clearance certificate
A and B Class hoarding
Item
Included
item
Rate
item
item
Item
Item
EXCAVATION
Geotechnical engineer report
Allow for Dewatering of rainwater only
Bulk excavate basement to RL 17.30 (29x18x3)
Detail excavation (pads, strip footings)
Tipping of Venm spoil
Truck Haulage
Dust control - wet down spray
4.00
5.00
BASEMENT
Reinforced concrete slab to eng specification
(FFL 17.50)
Concrete block walls
4000mm x 4200mm Steel Roller shutter
Vertical Bike Rack Storage
Garbage waste bins
Bollards
Sump pit
Detention Tank
Ventilation Grills
Concrete wheel stops
Install Strip drainage
$
$
$
$
$
8,400.00
2,000.00
3,000.00
2,400.00
1,000.00
44,200.00
40,000.00 $
40,000.00
$220/m2
$360/m2
1
1
1
$
$
$
3,000.00 $
1,200.00 $
5,000.00 $
3,000.00
1,200.00
5,000.00
Item
Item
Item
Included
1
1
$
$
$
3,000.00 $
5,000.00 $
187,347.20
3,000.00
5,000.00
m3
1566
40.00 $
62,640.00
m3
tonne
Per Load
Item
150
2505.6
208.8
included
$
$
$
160.00 $
22.00 $
180.00 $
24,000.00
55,123.20
37,584.00
Item
Included
2,500.00
Item
2,000.00 $
2,000.00
Item
500.00 $
500.00
Item
Included
290,000.00
m2
376.5
Included
lm
unit
unit
unit
unit
unit
unit
unit
unit
m
144
1
12
6
4
1
1
3
3
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
$
$
$
$
2,000.00
3,000.00
200.00
1,000.00
6.00
GROUND FLOOR
Structural Elements
Suspended slab
Loadbearing walls
Internal walls
Doors
Single door
Double door
Firedoor
Aluminium Sliding doors
Aluminium Windows
Balconies
wrimco sbs membrane
25mm cement screed provide 1:50 fall
Stainless steel handrail on top of steel framed
and FC clad balustrade
Steel framed structure by Structual Eng
Non-slip tiles
Bathrooms
Waterproof wet areas with waterproof
membrane system
Selected floor tiles laid to fall on screed
600mm wide kitchenette bench with s.s sink
Toilet
Shower screen & Shower
Disabled bathrooms
Wide Door (900mm)
Waterproof wet areas with waterproof
membrane system
Selected floor tiles laid to fall on screed
7.00
7.01
7.02
7.03
7.04
m2
lm
lm
Total
Item
Item
Item
PC Item
PC Item
m2
m2
m2
368.3
63
200
17
10
6
2
13
26.09
$
Included
$
350.00 $
462.67
Included
Included
12,071.00
$
Included
$
350.00 $
Included
Included
Included
Included
Included
Included
Included
Included
462.67 $
Included
Included
801,818.00
Included
m
m2
m2
Included
Included
Included
m2
Included
m2
Included
PC Item
Included
PC Item
PC Item
m2
Item
Included
12
1
Included
Included
m2
Included
m2
Included
PC Item
Included
Item
PC Item
PC Item
Included
Included
Included
m2
lm
lm
Total
Item
Item
Item
PC Item
PC Item
m2
m2
m2
328.1
78
134
30
11
9
2
8
10
29.89
128,905.00
Included
Included
35.88
534,545.00
Included
m
m2
Included
Included
114,835.00
13,829.21
7.05
7.06
8.00
8.01
8.02
8.03
8.04
8.05
8.06
Bathrooms
Waterproof wet areas with waterproof
membrane system
Selected floor tiles laid to fall on screed
600mm wide kitchenette bench with s.s sink
Toilet
Shower screen & Shower
Disabled bathrooms
Wide Door (900mm)
Waterproof wet areas with waterproof
membrane system
Selected floor tiles laid to fall on screed
600mm wide kitchenette bench with s.s sink
Stainless Steel handrails
Toilet
Shower rail & Shower
SECOND FLOOR
Structural Elements
Suspended slab
Loadbearing walls
Internal walls
Doors
Single door
Double door
Firedoor
Aluminium Sliding doors
Aluminium Windows
Balconies
wrimco sbs membrane
25mm cement screed provide 1:50 fall
Stainless steel handrail on top of steel framed
and FC clad balustrade
Steel framed structure by Structual Eng
Non-slip tiles
Bathrooms
Waterproof wet areas with waterproof
membrane system
Selected floor tiles laid to fall on screed
600mm wide kitchenette bench with s.s sink
Toilet
Shower screen & Shower
Disabled bathrooms
Wide Door (900mm)
Waterproof wet areas with waterproof
membrane system
Selected floor tiles laid to fall on screed
600mm wide kitchenette bench with s.s sink
Stainless Steel handrails
Toilet
Shower rail & Shower
m2
23.8
Included
m2
Included
m2
Included
PC Item
Included
PC Item
PC Item
m2
Item
1
1
6.94
1
Included
Included
Included
m2
Included
m2
Included
PC Item
Included
Item
PC Item
PC Item
1
1
1
Included
Included
Included
m2
lm
lm
Total
Item
Item
Item
PC Item
PC Item
m2
m2
m2
344
68
87
33
14
8
2
9
8
36.32
$ 1,069,090.00
Included
$
350.00 $ 120,400.00
Included
Included
Included
Included
Included
Included
Included
Included
462.67 $
16,804.17
Included
Included
Included
m
m2
m2
Included
Included
Included
32.63
m2
Included
m2
Included
PC Item
Included
PC Item
PC Item
m2
Item
1
1
6.94
1
Included
Included
Included
m2
Included
m2
Included
PC Item
Included
Item
PC Item
PC Item
1
1
1
Included
Included
Included
9.00
9.01
9.02
9.03
9.04
9.05
9.06
10.00
10.01
10.02
10.03
10.04
THIRD FLOOR
Structural Elements
Suspended slab
Loadbearing walls
Internal walls
Doors
Single door
Double door
Firedoor
Aluminium Sliding doors
Aluminium Windows
Balconies
wrimco sbs membrane
25mm cement screed provide 1:50 fall
Stainless steel handrail on top of steel framed
and FC clad balustrade
Steel framed structure by Structual Eng
Non-slip tiles
Bathrooms
Waterproof wet areas with waterproof
membrane system
Selected floor tiles laid to fall on screed
600mm wide kitchenette bench with s.s sink
Toilet
Shower screen & Shower
Disabled bathrooms
Wide Door (900mm)
Waterproof wet areas with waterproof
membrane system
Selected floor tiles laid to fall on screed
600mm wide kitchenette bench with s.s sink
Stainless Steel handrails
Toilet
Shower rail & Shower
FOUR FLOOR
Structural Elements
Suspended slab
Loadbearing walls
Internal walls
Doors
Single door
Double door
Firedoor
Aluminium Sliding doors
Aluminium Windows
Balconies
wrimco sbs membrane
25mm cement screed provide 1:50 fall
Stainless steel handrail on top of steel framed
and FC clad balustrade
Steel framed structure by Structual Eng
Non-slip tiles
m2
lm
lm
Total
Item
Item
Item
PC Item
PC Item
m2
m2
m2
350
85
115
35
18
9
2
6
10
45.48
$
Included
$
350.00 $
Included
Included
Included
Included
Included
Included
Included
462.67 $
Included
Included
Included
m
m2
m2
Included
Included
Included
29.68
m2
Included
m2
Included
PC Item
Included
PC Item
PC Item
m2
Item
1
1
6.94
1
Included
Included
m2
Included
PC Item
Included
Item
PC Item
PC Item
1
1
1
Included
Included
Included
344
55
80
38
15
9
2
12
9
50.18
122,500.00
21,042.23
Included
Included
m2
m2
lm
lm
Total
Item
Item
Item
PC Item
PC Item
m2
m2
m2
979,999.00
$ 1,069,090.00
Included
$
350.00 $ 120,400.00
Included
Included
462.67 $
Included
Included
Included
m
m2
Included
Included
23,216.78
10.05 Bathrooms
Waterproof wet areas with waterproof
membrane system
Selected floor tiles laid to fall on screed
600mm wide kitchenette bench with s.s sink
Toilet
Shower screen & Shower
10.06 Disabled bathrooms
Wide Door (900mm)
Waterproof wet areas with waterproof
membrane system
Selected floor tiles laid to fall on screed
11.00
11.01
11.02
11.03
11.04
11.05
m2
32.62
Included
m2
Included
m2
Included
PC Item
Included
PC Item
PC Item
m2
Item
1
1
6.94
1
Included
Included
Included
m2
Included
m2
Included
PC Item
Included
Item
PC Item
PC Item
1
1
Included
Included
Included
m2
lm
lm
Total
Item
Item
Item
PC Item
PC Item
m2
m2
m2
138.2
68
30
13
8
4
1
8
1
43.3
$
Included
$
350.00 $
48,370.00
Included
Included
462.67 $
Included
Included
Included
m
m2
m2
Included
Included
Included
11.77
445,454.00
m2
Included
m2
Included
PC Item
Included
PC Item
PC Item
m2
Item
1
1
8.24
1
Included
Included
Included
m2
Included
m2
Included
PC Item
Included
Item
PC Item
PC Item
1
1
1
Included
Included
Included
20,033.61
12.00 ROOF
balcony roof areas -translucent fibre glass
standard roof areas
roof slab areas - reinf conc
insulation
eaves gutter
steel box gutter
downpipe works
safety mesh
13.00 FINISHES
Basement
Line marking
Signposts
Painting
Tiles
Ground Floor
Carpet
Tiles
Painting
First floor
Carpet
Tiles
Painting
Second floor
Carpet
Tiles
Painting
Third floor
Carpet
Tiles
Painting
Fourth floor
Carpet
Tiles
Painting
Fifth floor
Carpet
Tiles
Painting
m2
m2
m2
m2
m2
Item
Item
Item
m
Item
Included
120
141
316
577
1
1
1
316
Included
lm
unit
m2
m2
$
$52.46
$73.00
$300.00
$15.00
$3,000.00
$3,000.00
$10,000.00
$12.00
Included
Included
Included
Included
m2
m2
m2
74.41
m2
m2
m2
138.09
m2
m2
m2
176.31
m2
m2
m2
147.79
m2
m2
m2
161.92
m2
m2
m2
71.31
400
268
174
230
160
60
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
139,835.20
$6,295.20
$10,293.00
$94,800.00
$8,655.00
$3,000.00
$3,000.00
$10,000.00
$3,792.00
14.00 SERVICES
Joinery works
Hydraulic Services
Mechanical Services
Fire Protection Services
Fire Hydrant System
Fire Hose reel System
Automatice Fire sprinkler system
Portable fire extingusher
exit signs
Emergenecy lighting
Smoke Alarms
Fire doors
Mechanical air handling system
Service penetration and control joints
Lift Services
Electrical Installation Services
Item
provisional sum
provisional sum
provisional sum
provisional sum
Included
1
1
1
1
m
unit
m
unit
unit
unit
unit
unit
unit
unit
provisional sum
Included
$50,000.00
$500,000.00
$300,000.00
$200,000.00
Included
Included
Included
Included
Included
Included
Included
Included
Included
Included
$166,600.00
$50,000.00
$500,000.00
$300,000.00
$200,000.00
$166,600.00
$1,327,542.00
living areas
TV outlet
security system
emergency lighting
illuminated exit sign
telephone outlet
ceiling fan
switchboard and meter box
Light, power, conduits
2443
55
57
12
12
57
55
1
1
$316.00
$108.00
$9,010.00
$326.00
$326.00
$120.00
$316.00
$4,000.00
$0.00
Item
Item
Item
Item
3
3
2
1
Included
Included
Included
Included
Ventilation
unit
Included
Electrical
Lighting
Power outlets
Communications
Cabling including conduit
Item
Item
m
m
Plumbing
Toilets
Basins
Sinks
Shower
$ 2,544,142.00
Mechanical
Included
Included
Included
Included
$771,988.00
$5,940.00
$513,570.00
$3,912.00
$3,912.00
$6,840.00
$17,380.00
$4,000.00
$0.00
15.00 LANDSCAPE
15.01
Maintenance
15.03
Garden Areas
Ensure that the mass planting areas have been
excavated to 300mm below finished levels. Rip
to a further depth of 150mm.
Supply and install 300mm soil mix
Soil mix to comprise of one part approved
compost to three parts topsoil
75mm deep river gravel mulch to garden beds
in detention basins
Turfed Areas
Excavate/grade all areas to be turfed to 120mm
below required finished level
Cultivated 150mm Subbase
Install 100 mm depth of imported topsoil
Lay "buffolo" turf rolls
Supply and spread Shieleys No 17 lawn fertilizer
or equiv
Hard Landscapping Areas
Item
Included
Item
Item
5,000.00
1,000.00 $
1,000.00
4,000.00 $
4,000.00
m2
12
49.25 $
591.00
Item
Included
m2
30
Included
Item
Included
m2
30
Included
m2
35
item
Included
m2
m2
m2
Included
Included
Included
item
Included
m2
97
CONTINGENCY:
18.00 $
630.00
80.00 $
7,760.00
TOTAL:
$ 8,287,930.40
3.00%
248,637.91