Professional Documents
Culture Documents
Progress Report of Sport Deptt Dated 13.03.2014 Final
Progress Report of Sport Deptt Dated 13.03.2014 Final
SOCIAL SECTORS
PROGRESS ON REFORMS INITIATIVES DATED: 14-03-2014
S.No
REFORMS
INITIATIVES
2.
SPORTS& TOURISM
2.1
JawanMarakaz
2.2
Sports Stadiums
2.3
Talent Hunt
Programme
2.4
Khanpur Lake
Festival
2.5
Khanpur Water
sports
2.6
TIMELINES
AS OF
NOV 13
Ongoing process
---
01-01-2014 Ferry (Boat) launched in Indus river D.I Khan Cruise/ boat Ready
for inauguration, Minister
in D.I Khan.
Sports requested to give date
and time
REFORMS
INITIATIVES
2.7
Opening of Supat
Lake/Meadows:
2.8
Development of
Gabeen valley as a
tourist resort
2.9
Development of
Kumrat valley as a
tourist resort
2.10
Log huts,
Restaurants and
skiing facilities at
Malamjaba, swat.
2.11
2.12
Introduction of
caravan culture
2.13
Opening of
Batakundi Tourist
Resort
TIMELINES
CURRENT STATUS AS ON 03-02AS OF
2014
NOV 13
01-04-2014 Umbrella PC-I approved by PDWP at
09-10-2013.
PC-II of the scheme was approved
by DDWP on 13-1-2014.
PC-I of the individual scheme is
pending with the C&W Department.
Land acquisition at the district level
is in process.
01-04-2014 Umbrella PC-I approved by PDWP at
09-10-2013.
PC-II of the scheme was approved
by DDWP on 13-1-2014.
PC-I of the individual scheme is
pending with the C&W Department.
Land acquisition at the district level
is in process.
01-04-2014 Umbrella PC-I approved by PDWP at
09-10-2013.
PC-II of the scheme was approved
by DDWP on 13-1-2014.
PC-I of the individual scheme is
pending with the C&W Department.
Land acquisition at the district level
is in process.
01-04-2014 Umbrella PC-I approved by PDWP at
09-10-2013.
PC-II of the scheme was approved
by DDWP on 13-1-2014.
PC-I of the individual scheme is
pending with the C&W Department
01-04-2014 Umbrella PC-I approved by PDWP at
09-10-2013.
PC-II of the scheme was approved
by DDWP on 13-1-2014.
PC-I of the individual scheme is
pending with the C&W Department.
Land acquisition at the district level
is in process.
Draft advertisement for purchase of
two mobile caravan vehicles for
placing in international press is
under preparation and collaboration
with CM Investment Cell.
01-04-2014 Base of the tourist hostel laid
Old huts of C&W transferred to
TCKP are being restored.
Works stopped due to extreme
weather conditions. Work to be
resumed by end of March, 2014.