Professional Documents
Culture Documents
MLTC CATRAM Market Study Container Terminals West and Central Africa
MLTC CATRAM Market Study Container Terminals West and Central Africa
MLTC/CATRAM
Contents
Glossary ................................................................................................................................... 3
Study summary and recommendations .................................................................................... 9
PHASE 1 CURRENT STATUS ........................................................................................... 13
1. Maritime and port analysis........................................................................................... 13
1.1.
1.2.
Types of vessels................................................................................................... 32
1.3.
Ports in detail........................................................................................................ 64
2.2.
Glossary
Maritime agent
Alliance
Port authority
BAF
B/L
Bill of lading: a negotiable contract for the carriage and ownership of goods
transported by sea, clearly stating the nature of the goods, their packaging, net
weight, gross weight, volumes if required, declared value, the sender and the
recipient. These details are attached to the cargo manifest.
BOT
Cabotage
CAF
Car-Carrier
Carrier Haulage
In contrast to Merchant Haulage: control of the land transport pre or postdelivery by the shipowner and not the consignee or his nominated haulage
contractor.
CWA
Liner conference
Consignee
Consortium
Conventional
This refers to freight or traffic which does not use containerisation and
therefore requires traditional handling techniques. Conventional vessels
transport goods which are neither containerised nor capable of being
rolled/driven.
Detention
Port charges
Taxation levied on the vessel or goods at a port to recover the cost of the use
of the port infrastructure. These charges may be applicable to the vessel (paid
by the owner) or goods (paid by the shipper).
TEU
Twenty Feet Equivalent Units for defining the container capacity of a vessel
(also of storage capacity on land, etc.).
Feedering
Charter
A vessel rented out by its owner. In parallel with this, chartering is to hire a
vessel.
Gateway Port
A port in which the majority of the traffic either originates in or is destined for
the hinterland (this is the case for all historical ports).
Hub
A large port where a significant share of the traffic is destined for transhipment.
(hub).
ICD
Interlining/Relay
Tonnage
The registered volume of the vessel used for calculating the taxes applicable to
it, as well as insurance premiums. The unit of measurement is the tonne, equal
to 2,831 m3 (a British measure of 100 cubic feet).
Gross tonnage: the interior volume of a vessel plus the volume of enclosed
space on deck (minus the volume of the double hull and some spaces above
the upper deck and the volume of various equipment which is found on a ship:
kitchens, auxiliary machinery etc.).
Net tonnage: Gross tonnage, minus machinery space, cabins, staff and crew
offices, fuel tanks etc. Anything that does not have a direct commercial
function.
Regular line
Liners terms
Manifest
An on-board document detailing the cargo loaded and unloaded in each port
and its nature, to which the corresponding bills of lading are attached providing
detailed information.
Handling
Freight handler
The handling operator who loads and unloads ships, deals with storage (in the
case of containers) and delivers to transporters (or vice versa).
Tidal range
Merchant Haulage
Nautical mile
Mother ship
Multipurpose
vessel
Knot
IMO
Equipment
Over-Panamax (or
Post-Panamax)
Panamax
A vessel whose width allows it to use the Panama Canal (a width of not more
than 32.3m), or handling equipment capable of dealing with vessels up to
Panamax width.
Yard
Keel
clearance
Minimum depth which must be left below the vessel. This can be up to one
metre, for safety reasons of course, but also to ensure good water flow
beneath the ship. It varies in accordance with local nautical conditions and the
associated risks.
Pool
Deadweight
The difference between the weight of a completely loaded vessel and the
weight of the empty or nearly empty vessel. It is the maximum loading capacity
allowed by international safety regulations.
Reach-stacker
RMG
Route
RTG
Rubber Tyred Gantry, a yard gantry on wheels. Allows for very high density
storage of containers, in blocks of around six wide and up to four or five in
height. Ensures good capacity in ports with only limited ground space. More
efficient in terms of density than reach-stackers or even straddle carriers and
more flexible than RMGs (see above).
Shift
Slot
Slow steaming
Bunkering
Operation providing the fuel necessary for the operation of the ship. Supply of
fuel for boilers or engines in a vessel.
Automatic
spreader
Automatic tool linked to a mobile crane or gantry which grips the container. The
spreader seizes the container via the corner pieces located at the four upper
extremities of the container.
Surcharges
Demurrage
User taxes
THC
Draught
The vertical distance between the waterline and the keel or lowest point of the
ship.
Tramping
Forwarding agent
Works in the port to provide customs clearance of the goods, pays for all the
maritime and port services required for the goods on behalf of the shipper and
in due course re-invoices for these fees. In Europe, most freight forwarders are
also logistics organisers (organising on behalf of the shipper the entire logistics
chain, including land transport).
VLCS/ULCS
Very Large Container Ship or Ultra-Large Container Ship. VLCSs are vessels
with a size of between 7,500 and 10,000 TEU and ULCSs are vessels with a
size of above 10,000 TEU.
Major operators have sufficient services to reach directly all the major ports of the
region with differentiated services at very short intervals. For secondary ports they
use radial feedering (hub and spokes).
Relay operations are outside the range, mainly in the major hubs of the north
(Algeciras, Tangier Med and Las Palmas). As we noted earlier, all Maersk CWA
container services dealing with traffic from Europe and with part of the flow from
Asia, are transhipping at Algeciras and Tangier Med. Delmas has even got two
services at Tangier Med.
In fact, the logic of exchanges between lines implies that they are carried out in
ports on the major intersections between east-west and north-south flows, which
is not the case for any port in CWA.
Geographical constraints, shipowners strategies and the evolution of the size of vessels
have resulted in the establishment of regional hubs and secondary services which make it
possible to have a cascade of services to all coastal ports depending on their nautical
capacity and commercial importance.
Risks linked to the volatility of transhipment traffic
The traffic passing through gateway ports is a function of the traffic flow generated by the
hinterland of the port in question and can be considered captive to a certain extent, provided
the port remains commercially and operationally competitive vis--vis competing ports whose
hinterlands may overlap1.
In cases where multiple ports are in competition, a judgement is ultimately made by the
shipper based on several criteria: cost and quality of passage through the port, cost and
duration of inland transport, maritime transit time, etc.
In contrast, transhipment traffic is controlled by the maritime operator who chooses to serve
a port directly or via a transhipment hub based on commercial and operational criteria:
volume of traffic under consideration, vessel size and capacity of the final destination port,
competition etc.
Transhipment costs are, therefore, the responsibility of the shipowner who considers them an
operational cost and constantly seeks to minimise them. This has an impact on a large
number of parameters: changes in the size or type of vessels operated, changes in the type
of service etc.
Shipowners can very quickly move large volumes of traffic from one hub to another based on
their current strategy and the commercial attractiveness of the various hubs.
Some transhipment ports have seen their traffic gradually fall as new competitors, better
placed geographically or economically, came on the market. This is the case, for example, of
Gioia Tauro, built in 1995 and whose traffic peaked in 2004 at 3.26m TEU before falling
every year, reaching 2.35m TEU in 2011. Over the same period, its closest competitor,
Marsaxlokk (Malta) saw traffic increase from 1.4 to 2.4m TEU. Similarly, Singapore has seen
its position as a major (if not hegemonic) South-East Asian hub challenged by the
1
While acknowledging that competition between ports in West and Central Africa is severely limited by the distances
involved and the poor quality of road and rail infrastructure when available.
10
11
12
Local feeder or cabotage services; in other words services serving several ports on the
West African coast departing from a port in West Africa,
Feeder services departing from a transhipment hub and destined for ports on the West
African coast,
Direct lines serving West Africa departing from northern and southern Europe and the
Mediterranean,
Direct lines serving West Africa departing from Asia,
Direct lines serving West Africa and arriving from North and South America.
For each of these categories, we have distinguished those maritime services operating only
cellular vessels (cc) and other maritime services operating the following types of vessels:
Multipurpose (mp), Roll-on, Roll-off or Ro-Ro (ro), Reefer (ref), Barge Carriers (bg).
Key indicators for the services (source Alphaliner)
13
14
Source: Alphaliner
In total, 16 services are dedicated to regional feedering between ports on the coast of West Africa. Almost half (seven) are from Pointe-Noire.
This is particularly the case for the services operated by Niledutch, Maersk Line and PIL, whereas MSC operates its three services from the port
of San Pedro. To a lesser extent, Abidjan, Luanda, Douala, Cotonou, Walvis Bay and Durban each have a regional feeder service. The current
maritime offer means 24 ports are serviced in West Africa.
15
Source: Alphaliner
16
Source: Alphaliner
Summary of services
Source: Alphaliner
17
Source: Alphaliner
With 18 services, the direct route from northern Europe to West Africa is one of the sectors with the most shipping lines. Taken together, they
represent a total of 102 ports of call serving 31 different ports. It should be noted that the majority of services coming out of the northern range
ports in Europe are from the port of Antwerp (60%).
18
Source: Alphaliner
Concerning the capacity available for full container services, Delmas (CMA-CGM) is the
maritime operator with the largest presence in the northern Europe-West Africa market with
38% of the total capacity. It is closely followed by MSC (29%) and, to a lesser extent, by the
MOL, Hapag Lloyd, Zim partnership (18%) and finally the Dutch shipowner NileDutch (15%).
19
Source: Alphaliner
On services other than full container, Grimaldi has the largest presence. It operates five
services from northern Europe with a fleet of 21 Ro-Ro vessels. The Italian operator is the
only one to use this type of ship. BOCS, EuroAfrica, UAFL and Safmarine also offer services
from Europe, using multipurpose vessels.
Summary of services
Source: Alphaliner
20
Source: Alphaliner
The route between West Africa and ports in southern Europe and the Mediterranean offers a total of 11 direct services. Taken together, they
represent a total of 52 ports of call, serving 23 different ports.
From the Mediterranean, services leave the ports of Valencia in Spain, Fos and Port-Vendres in France and La Spezia, Salerno and Naples in
Italy. Other services from southern Europe are exclusively from Portugal, notably the ports of Lisbon and Leixoes.
21
Source: Alphaliner
With an offer comprising vessels with capacities of between 2,500 and 3,000 TEU, MSC is
the operator with the largest share of the southern Europe/Mediterranean to West Africa
market segment. It is followed by Delmas (CMA-CGM) and to a lesser extent by the
partnership of Zim/COSCO, Lin Lines, Marguisa and Portline.
22
Source: Alphaliner
Operators Grimaldi, Messina and AEL complete the maritime offer on the southern
Europe/Mediterranean to West Africa route. Grimaldi and Messina operate two and three RoRo vessels respectively, while AEL operates four reefer vessels.
Summary of services
Source: Alphaliner
23
Source: Alphaliner
Routes to ports on the West African coast from transhipment hubs comprise a total of 18 services, the majority of them offered by Maersk Line,
the worlds largest shipowner. In total, they represent a total of 47 ports of call in West Africa, serving 22 different ports.
In order of importance, Algeciras (Spain), Tangier Med (Morocco) and Las Palmas (Canary Islands) are the three transhipment hubs involved in
services to West Africa.
24
Source: Alphaliner
Maersk Line and its subsidiary Safmarine have, by far and away, the largest presence in
services to West African ports from a transhipment hub (64%). They offer at least 11
container services from Tangier Med and Algeciras. In total, the offer comprises 53
containerships with a weekly capacity of 20,169 TEU.
MSC is the second largest operator of services from a hub, with 12% of the total available
capacity. Departing from Las Palmas, MSC offers three services with a weekly capacity of
around 3,800 TEU. It is closely followed by the partnership formed by shipowners UASC,
Hanjin and Evergreen which, since 2010, have offered a service from Algeciras with the
particularity of being operated by three containerships with capacities of between 2,000 and
6,000 TEU.
On a smaller scale (9%), CMA-CGM offers, through its subsidiary Delmas, two weekly
services from the port of Algeciras for a capacity of about 2,800 TEU. Finally, the partnership
of MOL, Hapag Lloyd and ZIM provides one weekly service from Algeciras with a capacity of
1,532 TEU.
25
Summary of services
Source: Alphaliner
26
Source : Alphaliner
The maritime container route between West Africa and Asia offers 15 direct services. In total, these represent 59 port calls into 19 ports.
The services currently in place from Asia come in large part from China - 75% of the total direct services - and notably from the ports of Tianjin
and Shanghai. China is followed by India, which has 13% of the services. Finally, Malaysia and South Korea offer one service each.
27
Source: Alphaliner
Maersk Line and CMA-CGM have the largest presence on the Asia to West Africa route, with
respectively 31% and 29% of the total capacity available, including one service operated
jointly. CMA-CGM has three services of its own compared to two for Maersk Line, which
operates larger capacity vessels at a lower frequency.
With 18% of the total capacity, PIL is the third largest operator on the Asia to West Africa
route. It has three services giving a weekly capacity of 5,372 TEU.
NileDutch, the partnership of CSCL, K Line, Hapag Lloyd and NYK and the partnership of
GSL and Evergreen complete the maritime container offer for Asia to West Africa with
respectively 8%, 7% and 7% of the total capacity.
28
Source: Alphaliner
For services other than full container, we find PIL, Maersk Line and Cosco, each of which
runs multipurpose vessels.
Summary of services
Source: Alphaliner
29
Source: Alphaliner
On the routes from North and South America to West Africa there are six direct services. In total, these represent 32 port calls, serving 17 ports.
Of the six services identified, two depart from, or are destined for, South America and four, North America. In South America, the ports of
Buenos Aires, Rio de Janeiro and Santos are served by two services and in North America, the ports of Jacksonville-Savannah and Houston
figure in the majority of services.
With vessels offering a total capacity of 25,200 TEU, the route between the Americas and West Africa has the lowest capacity of the market
segments we have studied.
30
Only one service of the six offered operates container vessels. The five other services are
composed of multipurpose and Ro-Ro vessels.
The capacity of the containerships varies between 1,700 and 1,900 TEU. It should be noted
that out of a total of 28 vessels operating on these routes, only five are containerships.
Source: Alphaliner
Delmas (CMA-CGM) and NileDutch are the only shipowners to offer containerships from
South America.
Maersk Line and UAL operate respectively two and eight multipurpose vessels, departing
from the ports of Houston and Savannah.
Grimaldi and Nordana Line complete the current offer, operating respectively 11 and two RoRo vessels.
Source: Alphaliner
31
Source: BRS
32
The scatter graph above shows both the current and future fleet of containerships2.
Unsurprisingly, there is a positive correlation between vessel size and the draught required
for a port call.
The high and low limits take into account both the maximum draught registered in the ports
of West Africa (namely the ports of Cotonou, Lagos (Apapa Terminal) and San Pedro which
have a draught of 13.5m) and, on the other hand, the minimum draught, which is found in the
port of Douala with 7m. The average draught of all ports in West Africa is 11.3m (blue line).
Thus, if we take into account only the draught of the ship, we can see that accepting ships
with a capacity of less than 2,000 TEU, and part of the fleet with a capacity of between 2,000
and 3,000 TEU, is not a problem for most of the African ports included in this report.
Note on the scatter graphs: Each point on the graph represents one or several ships. Ships
are often constructed as part of a more or less long series. Ships in the same series, sister
ships, have identical characteristics but appear as only one point on the graph, leading to a
bias against the largest series. Some of these series may be relatively large since the same
design developed by a shipyard may be offered to a number of shipowners. For example,
132 ships were built from theCV1100 Plus design, in many different European and Chinese
The orderbook has been taken into account where the information was available in this case for 536 ships on order.
33
Note on these graphs: For better clarity, the categories of vessels that can be
accommodated entirely in a port have been removed from the graphics. This also applies to
classes of ships which cannot be accommodated.
In the case of the port of Abidjan, for example, we deliberately removed from the graph
Feeder vessels (those with a capacity of less than 1,000 TEU) and vessels with a capacity
greater than 6,000 TEU. In fact, all Feeders ships can be accommodated in the port of
Abidjan while no vessel of more than 6,000 TEU is eligible. Therefore, only vessels with a
capacity of between 1,000 and 6,000 TEU are included in the graph. This principle has been
applied for all the ports studied.
Moreover, when the limit relating to the quay length (red line) no longer appears in a graph,
this means that the quay of the port in question is sufficiently long to accommodate all the
ships in the active fleet.
The draught indicated for each port presented in the study corresponds to the permitted
draught.
34
The nautical conditions3 in the port of Dakar allow it to accommodate a very significant
proportion of containerships with a capacity of between 3,000 and 5,099 TEU, and a small
proportion of vessels with a capacity of between 5,100 and 7,999 TEU. The quay is long
enough for all vessels in the active fleet. In comparison with other ports, Dakar is one of the
ports on the coast of West Africa with the best nautical conditions.
The current nautical conditions for the port of Dakar are a draught limited to 13m and a quay length of 660m.
35
The nautical conditions4 for the port of Banjul, notably in terms of draught, remain restrictive
for a proportion of ships between 1,000 and 1,099 TEU. The draught prevents it hosting
ships with a capacity greater than 2,000 TEU. On the other hand, the length of the quay
(300m) is sufficient for the fleet of containerships with a capacity of less than 5,099 TEU, and
a significant proportion of ships with a capacity of between 5,100 and 7,999 TEU.
The current nautical conditions for the port of Banjul are a draught limited to 10m and a quay length of 300m.
36
The limiting factors for the port of Conakry are similar to those for the port of Banjul. Indeed,
nautical conditions5, particularly in terms of draught, remain restrictive for a limited portion of
vessels with a capacity of between 1,000 and 1,099 TEU. In addition, the draught (with some
exceptions) prevents it accommodating ships with a capacity of more than 2,000 TEU. The
quay (270m) is, however, sufficient for the fleet of containerships with a capacity of less than
2,999 TEU, and a significant proportion of vessels with capacities between 3,000 and 7,999
TEU.
The current nautical conditions for the port of Conakry are a draught limited to 10.5m and a quay length of 270m.
37
The nautical conditions6 for the port of Freetown allow it to accommodate a significant
proportion of the Feeder fleet (ships with a capacity of between 0 and 999 TEU), and a
limited proportion of ships with capacities of between 1,000 and 1,999 TEU. The length of the
quay (722m), on the other hand, is sufficient for all the active fleet.
The current nautical conditions for the port of Freetown are a draught limited to 9.5m and a quay length of 722m.
38
The nautical conditions7 for the port of Monrovia allow it to accommodate a very significant
proportion of the fleet with a capacity of between 1,000 and 1,999 TEU, and a limited
proportion of ships with a capacity between 2,000 and 2,999 TEU. However, the length of the
quay is sufficient for all the active fleet.
The current nautical conditions for the port of Freetown are a draught limited to 11m and a quay length of 600m.
39
The nautical conditions8 for the port of San Pedro, notably in terms of draught, prohibit a
proportion of ships with capacities of between 5,100 and 7,999 TEU. In addition, the draught
prevents it accommodating ships with a capacity greater than 8,000 TEU. The quay (325m),
however, is sufficient (with some exceptions) for the entire fleet of containerships with a
capacity of less than 8,000 TEU.
The current nautical conditions for the port of San Pedro are a draught limited to 13.5m and a quay length of 325m.
40
The nautical conditions9 for the port of Abidjan allow it to receive a significant proportion of
containerships with a capacity of between 1,000 and 1,999 TEU. However, the draught of
11.5m limits access to much of the fleet between 2,000 and 3,000 TEU. Beyond 3,000 TEU,
the draught is insufficient. The quay length, though, makes it possible to receive a large
proportion of vessels between 3,000 and 5,099 TEU.
The Abidjan terminal container has a total quay length of 1000m, broken down into several berths. However, the Vidri
Canal prevents access to vessels with a length exceeding 250m. The draught is 12.5m.
41
The nautical conditions10 for the port of Takoradi remain restrictive for a significant proportion
of vessels between 1,000 and 1,099 TEU, particularly in terms of draught. Under 9m, the
entire Feeder fleet (with some exceptions) can access the port.
10
The current conditions for the port of Takoradi are a draught limited to 9m and a quay length of 190m.
42
The current nautical conditions11 for the port of Tema allow it to receive a very significant
proportion of vessels with a capacity of less than 3,000 TEU, but are relatively restrictive for
vessels with a capacity between 3,000 and 5,099 TEU and above. The quay length is
sufficient for all the active fleet.
11
The current nautical conditions for the port of Tema are a draught limited to 11.5 m and a quay length of 660m.
43
The nautical conditions12 for the port of Lom allow it to receive a large proportion of vessels
with a capacity of between 1,000 and 1,999 TEU, and some vessels with a capacity of less
than 3,000 TEU. The quay length is adequate for the entire active fleet.
12
The current nautical conditions for the port of Lom are a draught limited to 11m and a quay length of 430m.
44
The nautical conditions13 for the port of Cotonou allow it to receive a significant proportion of
the fleet of vessels with a capacity of between 3,000 and 5,099 TEU, and a proportion of
vessels with a capacity below 7,999 TEU. The quay length is sufficient for the entire active
fleet.
13
The current nautical conditions for the port of Cotonou are a draught limited to 13.5m and a quay length of 540m.
45
The nautical conditions14 for the Apapa container terminal in the port of Lagos allow it to
receive a significant proportion of vessels with capacities ranging from 3,000 to 5,099 TEU,
and a limited proportion of vessels with a capacity of between 6,000 and 8,000 TEU. The
quay length is sufficient for all vessels in the active fleet. Like the port of Dakar, the Apapa
container terminal has nautical conditions which are particularly advantageous when
compared to other ports on the West African coast.
14
The current nautical conditions for the Apapa container terminal are a draught limited to 13.5m and a quay length of 500m.
46
The nautical conditions15 for the Tin-Can Island container terminal in the port of Lagos allow it
to receive a significant proportion of the fleet with capacities of between 1,000 and 1,999
TEU, and a limited proportion of vessels with capacities of between 2,000 and 2,999 TEU,
but in terms of draught it remains restrictive for vessels with higher capacities. The quay
length is sufficient for the entire active fleet.
15
The current nautical conditions for the Tin-Can Island container terminal are a draught limited to 11.5m and a quay length
of 770m.
47
The current nautical conditions16 for the port of Douala allow it to receive a very limited
proportion of containerships. In fact, the particularly restrictive draught in this port (7m), limits
access to a significant proportion of Feeder vessels (0 to 999 TEU) and above. However,
the quay length is sufficient for the entire active fleet.
16
The current nautical conditions for the port of Douala are a draught limited to 7m and a quay length of 660m.
48
The current nautical conditions17 for the port of Libreville allow it to host a significant
proportion of vessels with capacities of between 1,000 and 1,999 TEU, and a limited
proportion of vessels with capacities of between 2,000 and 2,999 TEU, but in terms of
draught it remains restrictive for vessels with higher capacities. The quay length is sufficient
for the entire active fleet.
17
The current nautical conditions for the port of Libreville are a draught limited to 11m and a quay length of 475m.
49
The nautical conditions18 for the port of Pointe-Noire allow it to receive a significant
proportion of the fleet of vessels with capacities of between 3,000 and 5,099 TEU, and a
limited share of vessels with capacities of between 6,000 and 7,999 TEU. However, the
draught restricts access for vessels with capacities of more than 8,000 TEU. The quay length
is sufficient for the entire active fleet.
18
The current nautical conditions for the port of Pointe-Noire are a draught limited to 13m and a quay length of 800m.
50
The nautical conditions19 for the port of Luanda allow it to receive a significant proportion of
vessels with capacities of between 1,000 and 1,999 TEU, and a limited proportion of vessels
with capacities of between 2,000 and 2,999 TEU. However, the draught restricts access for
vessels with higher capacities. The quay length is sufficient for the entire active fleet.
19
The current nautical conditions for the port of Luanda are a draught limited to 11m and a quay length of 550m.
51
The advantageous nautical conditions20 for the port of Lobito allow it to receive a significant
proportion of the fleet of vessels with capacities of between 2,000 and 2,999 TEU, and a
limited proportion of ships with capacities of between 3,000 and 5,099 TEU. However, the
draught restricts access for vessels with higher capacities. The quay length is sufficient for
the entire active fleet.
20
The current nautical conditions for the port of Lobito are a draught limited to 12m and a quay length of 550m.
52
The nautical conditions21 for the port of Walvis Bay allow it to receive a significant proportion
of the fleet of vessels with capacities of between 1,000 and 1,999 TEU, and a limited
proportion of ships with capacities of between 2,000 and 2,999 TEU. However, the draught
restricts access for vessels with higher capacities. The quay is sufficient for the entire active
fleet.
21
The current nautical conditions for the port of Walvis Bay are a draught limited to 11.5m and a draught of 550m.
53
The graph above, which shows the width of container vessels in relation to their capacities,
demonstrates quite clearly a fleet divided in two by the criteria for access to the Panama
Canal. Under 32.3m wide, we find ships with capacities ranging between 0 and 1,999 TEU,
and some ships with capacities between 2,000 and 2,999 TEU. The width of these vessels is
mixed. Conversely, beyond the Panamax limits, larger ships have relatively standardised
widths, corresponding to a row containing a specific number of containers (an important
criterion for handling equipment).
We can therefore see that vessels with a capacity of between 1,000 and 1,999 TEU for the
most part have a width suitable for rows of 12 containers (41% of the fleet). These are mainly
vessels with a capacity of around 1,600 TEU. In the other segments, 64% of vessels with
capacities of between 2,000 and 2,999 TEU have a width which accommodates rows of 13
containers (average capacity: 2,500 TEU), while the fleet of Panamax ships (between 3,000
and 5,099 TEU) is composed mainly of vessels which can accommodate rows of 14
containers (average capacity: 3,800 TEU).
54
The evolution of the containership fleet, both in quantitative terms (number of vessels) and
qualitative terms (vessel size) is an important feature of container transport. It is difficult to
predict today whether the growth in the size of ships will continue or if it has reached its
maximum. However, considering the many changes that have taken place over the past two
decades, as well as the arrival of the new CMA-CGM container vessels with a capacity of
16,000 TEU, it would appear that the first option is the most likely.
The worlds containership fleet has experienced particularly strong growth in capacity since
1995, growing at an average annual rate of 11% (while the increase was only 8% per year
between 1985 and 1995). This trend was also accompanied by successive technological
leaps in terms of vessel size and motorisation. However, while capacity has long been
increasing, is has not done so uniformly over time.
Between 1995 and 1999, the world containership fleet grew strongly, in line with
the mass introduction of over-Panamax vessels (more than 4,500 TEU).
2000 to 2001 saw a lull due to a period of consortia reorganisation and mergers.
2000 to 2003 was a period of recovery, notably with the launch of 8,000 TEU
vessels. This was followed by a slight decrease over the next two years even
though the orderbooks were full.
2006 to 2007 was a successful year. Deliveries of vessels continued at a high rate
compared to 2005, particularly for over-Panamax vessels and for ships with
capacities between 300 and 1,500 TEU and 1,500 to 3,000 TEU (+69.3%). Not
only were these deliveries large in number but they also displayed a concentration
at both ends of the size spectrum with the increasing capacity of the larger ships
creating new needs for feeder services, generating traffic that benefitted the hub
ports.
2008 was the first year of the downturn, driven by the financial crisis, and 2009
was a year of crisis management. The brutality of the downturn, following a long
period of euphoria in maritime transport, took owners and operators by surprise,
forcing them to urgently review their development strategies. In addition to the
short-term measures - deferrals of deliveries of chartered vessels and mothballing
of ships - operators had to review their order levels, which in 2008 represented
60% of the fleet and risked creating massive over-tonnage.
2010 was marked by a sharp upturn. The increase in recorded volumes
throughout the year enabled operators to increase the capacity available and
therefore bring many ships back into service.
In 2011, operators adapted their fleets to match the volumes to be transported:
the relative stability of volumes led operators to bring online a capacity roughly
equivalent to that available in 2010 on the major East-West routes, which helped
to ensure a correct level of vessel usage despite many new ships coming into
service.
55
In October 2012, the cellular fleet comprised 5,020 ships with a capacity of approximately
16.2m TEU. For the record, as of 1 January 2000, the fleet consisted of 2,615 vessels with a
capacity of 4.5m TEU. The fleet has therefore doubled in size and more than tripled in
capacity in just over a decade. These impressive figures illustrate the significant
development of containerised transport thanks to the globalisation of trade and the everincreasing role of China in this process.
Because of deferrals, only 163 ships with a total capacity of 1,055,591 TEU (an average of
6,500 TEU per ship) were delivered between January and October 2012 (for comparison, in
the same period in the successful year of 2008, 349 ships had already been delivered).
Shipowners have used all the means at their disposal to negotiate with the shipyards to delay
the deliveries of ships they have ordered. They also tried to negotiate cancellations or the
conversion to bulk carriers or oil tankers of the ships ordered in previous years for delivery in
2013 and 2014 and whose construction was less advanced.
Alongside these quantitative measures, operators have also conducted qualitative reviews of
their fleets, focusing on their larger and more modern ships in the redesign of their East-West
services, in particular on vessels of more than 10,000 TEU which were ordered in large
numbers in 2007 and 2008 (it should also be noted that these vessels can only be used on
routes between Asia and Europe) and transferring smaller vessels onto North-South
services, these moves being designed to streamline and focus services on the principal
routes.
56
Another striking feature is that only 163 ships of less than 5,000 TEU are currently on order
(October 2012), compared to no less than 373 vessels of more than 5,000 TEU. The
significant fact is that this orderbook is very unbalanced in favour of vessels of more than
5,000 TEU, which represent around 75% of capacity (see graph below).
The influx of large vessels has a direct impact on the structure of the market. The rapid
growth in the fleet of vessels of more than 9,000 TEU led to an acceleration of the
concentration of services, in particular on routes from the Far East to northern Europe. These
vessels can achieve economies of scale and reduce the cost per cell, particularly when fuel
prices are high.
57
Between January and October 2012, 128 ships with a total capacity of around 240,000 TEU
were scrapped (within the same period in 2008, only 41,400 TEU of capacity was scrapped).
Therefore, since 2009 a watershed year - the average age of containerships sent for
disposal has been decreasing. Moreover, one of the characteristics of containerships is their
longevity and, demand having been virtually constant since their launch, the level of ships
scrapped is traditionally very low, representing only a small percentage of the arrival of new
vessels.
58
The type of vessel used (speed, consumption, payload, port productivity, ships
gear if necessary);
The size of the vessel, in order to maximise economies of scale. This is limited by
the need to optimise the loading of the ship for the complete rotation. In other
words, the size of the vessel must be adapted to the market share of the operator.
Finally, the container fleet (purchase or rental, maintenance and repair, transport
of empties and rebalancing between areas with surpluses and areas with deficits).
The best kind of containerised transport involves the transhipment of goods. As a result,
networking, in other words the connection of the various regular services of an operator
(with or without partners), makes it possible to capture volumes made larger as increasing
numbers of ports and their hinterlands across the globe are connected. The very concept of
globalisation as we talk about it today would not have been possible without the changes
brought about by the maritime industry in containerisation making trade around the world
faster, cheaper and more efficient.
59
The shipowners and operators met during these interviews account for more than 80%
of the capacity in service between CWA and the other regions of the world.
The interviews were designed to highlight the strategies implemented by shipowners in the
West African market. To this end, the following topics were discussed with the different
representatives of the companies:
60
61
62
63
Port of Dakar
Traffic
64
Nautical conditions
The port is suitably sheltered and well protected from bad weather, which usually comes
from the north/north-west. Tornadoes are very rare and relatively weak.
Port access for merchant shipping is safe and easy, and the docking of ships is rapid. Dakar
is one of the easiest ports on the Atlantic coast of Africa, served by good pilots and an
efficient tug service. Uncertainty about the port of the future project means we cannot
address this issue specifically. However, an eastward extension should give this new port a
situation that is as equally sheltered as the current one.
65
DP World (one of the worlds leading port operators) was awarded the concession for the
port of Dakar in 2008 for a period of 25 years. DP World has a relatively small presence in
Africa (Algiers, Djen-Djen, Sokhna, Maputo, Djibouti, bulk terminals in South Africa etc.).
Before the granting of the concession to DP World, three operators shared handling
operations: Bollor, APMT and Getma. The handover of the terminal was made in a tense
atmosphere which had an impact on operations and volumes during the first six months.
As with previous ports, containers do not stay in the DP World terminal and are processed at
inland terminals for operational reasons (transfer of risk, a safety valve etc.). The ratio of
surface area to length of quay is average at 500m/ml. Inland terminals have relatively limited
surface areas of less than 2ha. Operations in these terminals would need to be standardised
(location of containers, stacking, safety etc.) to improve efficiency but loading and unloading
of containers by road hauliers complicates the organisation.
Road transport is congested around the port of Dakar and the road infrastructure towards
Mali has deteriorated, despite recent work, due to overloaded trucks (>40 tonnes). Rail
transport is inefficient and requires investment from the two countries. Mali is reluctant to
invest in rail because of lobbying from Malian hauliers and the importance of this sector to
the countrys economy. The maintenance and operation of this system should be split.
66
Source: PAD
67
The container terminal in the northern zone has two concrete block wall berths with a draught
of 11.6m (positions 62 and 63) representing a length of 425m. It has three distinct areas: CT
1 is the yard alongside the quayside, CT 2 is found in a second zone and CT 3 is reserved
for empty containers. Work has just been completed on infilling the basin between the CT
and pier 8 (more than eight hectares of reclaimed land and 300m of quay).
DP World has invested heavily to provide the terminal with quality facilities. The terminal
organisation (operations, ISPS, ISO 14002 etc.) nearly meets international standards. The
draught is decent (comparable with the other ports in the region). The facilities are modern
and meet the needs in terms of volumes. The theoretical maximum capacity of the terminal is
estimated at 800,000 TEU.
The distribution of positions for empty containers is made according to the free pool system.
Shipowners believe that the introduction of fixed arrival windows is a significant step forward
and reduces harbour waiting times. Docking times for a ship have fallen from 12 hours to
seven hours in three years. Truck service time is less than 30 minutes.
Productivity is constantly increasing, standing now at 35 containers per vessel per hour (1.5
gantries on average).
68
The port du futur (port of the Future) is a project that was negotiated between the port of
Dakar and DP World during the award of the concession for the port (under the chairmanship
of Mr Wade). It provides for 1,150m of quays with a draught of 15m. Some 90% of its activity
will come from transhipments.
Feasibility studies for the project will be launched once a cap of 412,500 TEU handled is
exceeded.
The objective is to capture transhipment traffic from the lines between Asia and the
Americas. The investment has been calculated at 300 million and the capacity of the new
terminal would be 1.5m TEU. Some shipowners believe the proximity of Dakar to the hubs of
Tangiers and Algeciras is highly disadvantageous for transhipment in Dakar.
69
The DP World terminal is known for its operational qualities and the streamlined way in which
it functions. Land transport still needs to be improved. Currently, the port du futur project
appears to be disproportionate to the needs of the Senegalese economy and the potentiality
for transhipment in the region.
SWOT analysis for the port of Dakar
Strengths
Weaknesses
Opportunities
Threats
70
Port of Abidjan
Traffic
Container traffic in the port of Abidjan was hit hard by the political crisis of 2011 as there was
virtually no activity in the port over a period of three months. The AAP expects traffic in 2012
to rise sharply, returning to pre-crisis levels of more than 600,000 TEU. Approximately
150,000 containers are sent by feeder services to secondary ports. CMA-CGM accounts for
80% of transhipment activities in the port of Abidjan.
Based on fundamental economic and demographic indicators there is strong potential for
economic development and growth in traffic. Political stability will be a significant issue in the
coming years. The target set by the AAP for 2012 is a growth rate of 15% for overall traffic
and 20% for transhipment traffic.
Transit traffic destined for Mali and Burkina Faso has suffered greatly since 2006 and the
port received no traffic for several months in 2011. The ports of Dakar, Lom and Tema, in
particular, took advantage of this situation to serve the landlocked countries. Stakeholders in
the Abidjan port are confident about the ability of the port to recapture this traffic in the
coming months. Nevertheless, problems remain on the routes crossing the north of the
country and could delay the return of volumes destined for the landlocked countries (notably
Mali) from Abidjan.
Market share of shipowners
71
The container terminal operator is SETV, a joint venture between Bollor (60%) and APMT
(40%). The terminal extends over 34 hectares. SETV manages quayside container handling
and then transfers responsibility to stevedoring companies. The access roads require
upgrading, in particular access to the container terminal and to routes serving inland
terminals. The storage of containers on the premises of other companies allows SETV to free
up space and concentrate on port handling activities.
SITARAIL is the rail subsidiary of Bollor and APMT. It connects Abidjan with Burkina Faso.
A project extending the connection to Niger is envisaged. Between two and three trains per
week link Abidjan to Ouagadougou.
72
The average productivity of the gantries is 17 containers per hour, but this varies greatly
between gantries. For example, the P4 gantry has an average productivity of 21.5 containers
per hour and the arrival of two new gantries in 2013 is expected to raise overall productivity
to more than 20 containers per hour.
The current level of productivity is acceptable considering the overall port conditions, but falls
far short of standards in Europe or Asia.
The average gross productivity per ship is 33 containers per hour with a maximum of 43.2
containers/per hour for P4. For SETV, the fact that Maersk vessels are geared complicates
loading and unloading and affects productivity.
73
The port of Abidjan has begun the tendering process for the award of the second container
terminal. Technical bids had to be filed before 19/11/12 for assignment of the terminal in
February 2013.
Four groups responded to this call for tenders:
The PAA attaches great importance to the presence of a shipowner in the group to
guarantee traffic to the new terminal.
Final report MLTC/CATRAM 23/01/13
74
75
Weaknesses
Opportunities
Threats
76
Economic environment
With a population of 23 million people, Ghana is a country which is richer than many of its
West African neighbours. It is the worlds leading cocoa producer and benefits from mineral
wealth (especially gold and, more recently, oil). The rate of GDP growth is remarkably high
and this growth is expected to continue at a high level over the coming years.
Ghana is currently enjoying an economic boom, in part because of the discovery of oil
offshore, but more generally because the country offers a reassuring prospect for foreign
investors because of its democratic maturity and sound business climate, especially when
compared to that of many neighbouring countries. Ghana is attractive to foreign investors as
witnessed by air traffic which has literally exploded, growing by 250% over the course of
three years and attracting 38 airlines to Accra.
Traffic
Traffic in the port of Tema really took off in 2011; a trend confirmed by results in 2012 and
growth looks set to continue in the years to come.
Tema port container traffic in TEU
77
The GPHA is not a landlord because it is either indirectly involved in handling (through local
handlers which it in turn manages) or directly through an ICD (Golden Jubilee).
78
The image above provides a clear view of the container terminal (only the quay facing the
seawall is licensed to the operator MPS) and its storage area, completely separate to the
quay because of the lack of space on the jetty where the containers are unloaded.
Infrastructure
Containerterminal
Operator
Lengthofconcession
Terminalsize(surfacearea)
Inlandterminals
Roadaccess
Railaccess
Lengthofquay
Draught
STS
Mobilecranes
Reachstackers
RTG
Others
Theoreticalcapacity
Productivity
Tema
MeridianPortServices
(Bollor35%,APMT35%,GPHA30%)
20yearsfrom2004
Approx.10ha
3ICDsbeyondtheport
Yes,onlyoneandcongested
No
Berths1and2,575mlinonego
11.50m
3
3
>10
4
500000TEU
35mvt/hship
79
Berths 1 and 2 constitute the quay of the container terminal, measuring 575m in
length and offering a draught of around 11.5m. The concession for this quay was
granted to Meridian Port Services in 2004 for a period of 20 years.
On the other side of the quay, berths 3 and 4 offer lower draughts (10m for berth 3
and 8.8m for berth 4).
On the main quay, berths 6 to 12 offer a draught of 8m, apart from berth 5, which
offers 8.7m.
Berths 1 and 2 are managed under concession by Meridian Port Services (MPS). These are
the only berths in the port to have quayside equipment.
The other berths, numbers 3 to 12, are assigned in turn to local handlers, of which there are
seven or eight. They operate on geared ships, with very low productivity levels.
The operator MPS (30% GPHA, 35% Bollor, 35% APMT) has held a 20-year concession for
the container terminal since 2004.
The equipment available in the container terminal comprises the following:
Three ZPMC quay gantries capable of lifting 40 tonnes with twinlift capacity and
capable of operating across rows of 15 containers.
Three mobile Gottwald cranes with more-or-less the same capacity: twinlift and 15
rows.
Four RTGs for managing the yard, and a number of reach-stackers.
The container terminal is currently saturated, not only on the quays, but also in the yard and
on the access routes.
Berths 1 and 2 are occupied practically 100% of the time22 if we discount the delay required
for one vessel to leave the port and another ship to replace it on the quay, a delay which can
extend to four or five hours (in fact, it is not possible for two ships to pass each other at the
entrance to the port).
However, queuing theory dictates that if the number of equivalent berths is limited to two,
then an occupancy rate of 35% should not be exceeded to maintain waiting times at a level
lower than 10% of the time taken to service ships. Clearly, waiting times here for vessels are
much longer than that. According to converging sources, the average waiting time for access
to the container port is now estimated at about 2.2 days, but in the recent past it has
extended to six days.
Admittedly, ships do not arrive in a completely random manner as berthing windows have
been introduced by MPS. Not all the shipping companies and all services have benefitted
from this introduction, but the most important services do have it at their disposal. However, it
cant solve all the problems. Delayed ships can lose their place in the queue. Above all, the
22
On the increase: according to the Halcrow report, the utilisation rates of berths 1 and 2 were 75% and 73% respectively.
They were then by far the most used berths in the port, the other berths had utilisation rates of 60% for berth 3, around 50%
for berths 4-10, and 20-30% for the last two berths.
80
It cannot be said that the port of Tema has a container terminal as its facilities were designed
for conventional traffic.
Behind berths 1 and 2, there is very little space and this space must also be used for work on
berths 3 and 4 and the removal of the corresponding goods.
The container yard is therefore situated away from the quay and requires extra handling
which then translates into additional costs.
The yard currently operates with a mixture of reach-stackers and RTGs. Its cramped size
makes it essential to change to full RTG operations. The four current RTGs span six rows of
containers plus a truck lane and can pass a container over five.
But even with the densest possible use of the yard, the area available may not be sufficient.
This is why half of the imported containers (full) are invited to leave the port for storage in
one of the three ICDs (Inland Container Depots) established next to the port.
Here again, this transfer generates extra costs compared to short-term storage in the
container terminal.
The facilities at the port of Tema are unsuited to container traffic but, for the moment,
stopgap solutions still allow the port to meet the increase in traffic. However, it is easy to
foresee that these methods will reach their limits in the next few years.
23
Increasing: the Halcrow report noted in 2007 that berths 1 and 2 were operating on 327,000 TEU out of 495,000 TEU,
while berths 3-5 handled 74,000 TEU and berths 6-12 94,000 TEU.
81
Strengths
Weaknesses
Archaic port regulation and control (originally designed for a service port)
Insufficient draught available
Lack of space behind the quays in the container terminal, and a general lack of space
available in the port
Lack of equipment on the conventional quays and poor maintenance of the available
equipment (not including MPS)
Congestion on access roads
Private investment is discouraged by unreliable profitability: the GPHA fixes the rates
of private operators, sometimes in Cedi (which falls in value without any change in
the tariffs)
Procedures are too cumbersome, costing time and money
No rail service
Too many licences granted to operators and freight forwarders, who are too
numerous and incompetent
General lack of resources and a climate which is averse to open competition
Opportunities
Threats
82
3
4
3
2
Opinion
Trafficpotential
Nauticalconditions
Infrastructure
Equipment
Maritimeservices
Roadtransport
Operationalquality
Tariffs
Adaptability/flexibility
Agents
5
2
1
4
3
2
3
2
Portoperators
5
2
0
4
4
3
4
4
1
Public
stakeholders
5
3
2
4
4
4
3
3
3
Projects
For the two scenarios National Gateway (satisfying national needs) and Regional Hub
(additional transhipment streams), the traffic forecasts are as follows:
HALCROW TRAFFIC FORECASTS (IN KTEU)
National Gateway
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
Optimistic
934
1,051
1,177
1,310
1,449
1,592
1,740
1,889
2,038
2,185
2,328
2,465
2,593
2,728
2,870
3,019
3,176
Regional Hub
Neutral Pessimistic
1,177
972
1,319
1,050
1,470
1,129
1,628
1,210
1,796
1,292
1,964
1,373
2,138
1,454
2,314
1,534
2,489
1,611
2,661
1,685
2,829
1,755
2,988
1,820
3,137
1,880
3,294
1,942
3,458
2,006
3,631
2,072
3,812
2,140
83
Regional Hub
1.13
1.10
1.07
1.10
1.12
1.08
1.12
1.09
1.07
1.09
1.11
1.08
1.11
1.09
1.07
1.09
1.11
1.07
1.11
1.08
1.06
1.08
1.10
1.07
1.10
1.08
1.06
1.08
1.09
1.06
1.09
1.07
1.05
1.07
1.09
1.06
1.09
1.07
1.05
1.07
1.08
1.06
1.08
1.06
1.05
1.06
1.08
1.05
1.07
1.06
1.04
1.06
1.07
1.05
1.07
1.05
1.04
1.05
1.06
1.04
1.06
1.05
1.03
1.05
1.06
1.04
1.05
1.04
1.03
1.04
1.05
1.03
1.05
1.04
1.03
1.04
1.05
1.03
1.05
1.04
1.03
1.04
1.05
1.03
1.05
1.04
1.03
1.04
1.05
1.03
1.05
1.04
1.03
1.04
1.05
1.03
The growth rates applied in the long term are particularly high.
The Regional Hub scenario is not a real possibility as the neighbouring port of Lom has set
its sights on this role. It has better natural conditions and a development project already
underway and scheduled for completion in late 2013 or early 2014 which will provide MSC
with the transhipment facilities they want. The port of Abidjan is also in the running with its
proposed second container terminal, but this project is not as advanced.
Furthermore, it appears unlikely that many shipowners would consider mass transhipment in
a port in the Gulf of Guinea when the broad range of the other strategic options available for
serving West Africa is taken into consideration.
Nevertheless, these traffic forecasts have been used as the basis for a very ambitious
expansion project for the port of Tema, which would provide it with a capacity of 4m TEU.
84
85
The image above shows the project in relation to the existing port.
The Halcrow master plan therefore leads to an extremely ambitious expansion of the port,
both in terms of new structures (a new 6km seawall, more than 4km of new quays, 250ha of
land reclaimed from the sea, draughts of 14 to 17m...) and in terms of cost, which has been
estimated at nearly US$3bn!
86
Tema
>4kmofquays,>250halandreclaimedfromthesea
ExpansionoftheportofTema
Concessionsawardedformultipleterminals
Masterplan
US$3billiononlyforinfrastructure
87
The extension outlined in the master plan will not reach fruition, not least because it is too
expensive and will not find funding. Even if the scheme could be achieved in phases, there
are prohibitive costs involved before any quay construction can take place (principally the
building of the new seawall).
The port of Tema, with its rocky seabed and its position enclosed by the city, does not
present any great advantages for expansion when compared to Lom which has more
obvious benefits.
Nevertheless, it is clear that the situation cannot continue for much longer and an emergency
plan will have to be put into action.
MPS plans to do its part by ordering new equipment in order to increase the capacity of its
facilities from 750,000 to one million TEU through improved operational productivity:
Two quay gantries similar to those currently used but with a lifting force of 65 tonnes
(making it possible to conduct twinlifting of full containers)
One additional mobile crane
Eight new RTGs for the container yard, four of which will replace older models
currently in use.
The GPHA plans to build an ore quay near berths 11 and 12 offering several new berths,
which could offer some relief for berths 5 to 10.
But the need is clearly felt for at least one additional berth in the short term for container
traffic. This berth could be located, for example, on the other side of the jetty (berth 3, which
has greater draught). This berth could be assigned to MPS or, alternatively, two berths could
be put out to concession to an operator selected through a competitive bidding process.
More fundamentally, the following needs to be urgently considered:
The possibilities of deepening by at least 1m those berths used for container freight to
see if economically reasonable solutions can be found
It is also necessary to move towards granting concessions on other berths, including
those dedicated to handling conventional and bulk traffic, in order to obtain a sharp
increase in productivity through motivated concessionaires possessing the required
expertise and investing in mobile cranes wherever their use is possible
If it should become obvious that some berths are not suitable for the use of mobile
cranes, ways to make this possible and realistic in terms of investment need to be
studied.
88
In the medium term, it is necessary to think about how to open up the port and the ICDs. A
road (three lanes each way) providing direct port access from the Accra-Tema motorway is
undoubtedly an essential part of achieving this.
The truck park planned for Kpong, some eight to 10km from the port, could also contribute to
improving traffic flow.
It is also essential to conduct a review of port procedures, identify bottlenecks and remedy
them to improve the fluidity of port activities. This will certainly include examining and
introducing a single window system, that is as a Port Community System, but also the
modernisation of customs procedures with a view to conducting random checks based on
risk criteria, thereby reducing the need to pass through the scanner or for physical
inspections.
In the long term long, other ICDs (or more likely one or more logistics platforms offering
diversified services) should be considered. Locating them at a certain distance from the port,
between Accra and Tema, would disperse the flow and reduce the concentration of flows on
a confined site. Ideally, this platform or platforms would be sited along the path of the rail line
linking Tema and Accra, allowing containers to be carried by rail to the platform. Clearly, the
railway, which currently carries a limited number of passengers, would have to be adapted to
carry heavier trains.
Again in the long term, a major port expansion needs to be investigated and built. The only
question that needs to be asked, however, is whether this expansion should adjoin the
existing port, with the risk of greatly increasing congestion on local roads, or whether a more
favourable (and perhaps less expensive to develop on a technical level) site should found, in
accordance with the blueprint for the national road network. Clearly, Accra is an area of great
economic importance, making it unrealistic to locate a future port too far away.
89
Overalltraffic(MT)
2006
2007
2008
2009
2010
2011
Allactivities
5.35
6.18
7.28
7.32
8.00
Containertraffic(TEU)
2006
2007
2008
2009
2010
2011
Total
215,892
237,313
275,277
354,480
339,853
350,000
57,560
55,736
59,653
52,648
55,221
61,300
ImportstoTogo
ExportsfromTogo
81,872
98,873
142,298
166,916
157,476
162,754
137,860
140,476
172,938
172,267
200,850
163,754
Empty
58,488
62,609
78,893
97,537
85,281
59,936
Transit
56,916
59,766
27,394
50,240
73,434
77,090
Transhipment
19,544
22,938
45,932
84,676
53,722
87,872
Full
Container traffic in the port of Lom has steadily increased, reaching approximately 350,000
TEUs in 2011, just as the ports overall traffic has increased too, reaching 8m tonnes in 2010.
Market share of shipowners
90
The nautical conditions are ideal and the port is very rarely affected by the weather (rain,
fog).
Infrastructure
The table below shows the current situation in the Lom container terminal, which has two
berths located on either side of a narrow jetty, as well as container storage situated off the
quay and behind Bollors planned extension, which would add a third quay.
Containerterminal
Operator
Lengthofconcession
Quaydetails
Quayequipment
Terminalsize(surfacearea)
Yardequipment
Inlandterminals
Roadaccess
Railaccess
Lengthofquay
Draught
STS
Mobilecranes
Reachstackers
RTG
Others
Theoreticalcapacity
Productivity
Lom
BollorAfricaLogistics
2010/35years
500mat11m(for230ml):12m(for200ml)
4mobilecranes(Panamax)plus2onorder
12ha
19reachstackers(TOS=Oscar)
No
Yes
No
430mintwosections
230mat11mand200mat12m
0
4+2tocome
20
0
Tractorsandtrailers
350,000TEU
32MVT/h,1000MVTin48hours
Cumulatively, the existing facilities are handicapping operations. Container storage is limited
and situated away from the quay, and the quay itself is divided into two sections which
significantly reduces operational flexibility. The quay limits the length of the vessels which
can be received.
Jetty 2 and its quays are likely to be deepened to 13m, but first of all it will be necessary to
check the stability of the quay walls.
The future third quay will give the whole terminal greater coherence, providing almost double
the length of quays available and providing container storage behind. Storage density can be
increased through the use of RTGs.
91
Customs services are not computerised. This means that customs formalities have to be
done manually, and many steps have to be followed as the papers are transferred between
the different officials.
Port users are waiting for the implementation of the planned single window system. The Web
Cargo software does not work.
A transit time of four to five days is considered efficient. Beyond this, financial penalties in the
form of demurrage may apply.
The detention period is limited to 10 days for the return of containers which contain goods
destined for Togo. Most shipowners have aligned themselves with this figure. For goods
destined for the hinterland, the detention period is at least 21 days and can be negotiated up
to 30 days.
The free demurrage period in the terminal is 25 days for goods for the hinterland and four
days for Togo. The penalties for exceeding these limits are 3,150 FCFA for countries in the
hinterland and 3,717 FCFA for Togo (subject to VAT).
SWOT analysis for the port of Lom
Strengths
The port offers broad expansion possibilities, there is land available for expansion
and possibilities for construction behind the port (car park etc.)
The port can easily achieve the water depths necessary for large container ships
(complementary with the implementation of the two projects mentioned)
A welcoming, stable port offering flexibility in procedures (including transhipment)
when compared to Benin (too much political influence in the port of Cotonou)
The introduction of berthing windows, which have considerably reduced ship
waiting times
Very good productivity : currently close to 35 movements per hour/ship, one of the
best in Africa
No congestion in the port
Free port: ability to import, add value added tax and re-export without paying
customs duties
Weaknesses
The existing container terminal facilities are not rational, the yard is at some
distance which implies additional handling
Less commercial flexibility since Getma is no longer licensed to handle containers
Port roads are in a very poor state
Speed at which imported goods are cleared: four to five days minimum
Inefficient banking system
Opportunities
92
Threats
Projects
Two projects in particular are expected to be completed within the next 18 months:
Quay 3
MSC transhipment dock
The master plan also provides for the lengthening of quay 2 (the container terminal) but for
the moment this has been put on hold.
Extension of the Bollor terminal: quay 3
This comprises an extension of the quay by 450m with a draught of 15m (a big
improvement). This quay will be equipped with four gantries allowing them to operate on
vessels with at least 17 rows of containers. An expansion (30ha) and rationalisation of the
yard located behind the quay is included, with the introduction of 24 RTGs.
Project
Name
Characteristics
Objectives
Managementsystem
Completiondate
Progress
Operator
Conditions
Funding
Lom
Quay3
450mlofquayat15m,4STSandupto24RTG
IncreasethecapacityoftheterminaloperatedbyBollorAfricaLogistics
IncludedintheBollorconcession
Endof2013/beginningof2014
0
BAL
BAL300billionFCFA,457m
24
Oil tankers have been boarded by pirates, towed off the coast of Nigeria and their cargoes transhipped into a pirate oil
tanker!
93
Project
Name
Lom
LCT(LomContainerTerminal)
Shortterm, one quay of 400m (longer term 1050m at 16/17m // surface
Characteristics
area53ha).Secondquaypossiblelater.Capacity>2mTEU
Objectives
TranshipmentfacilityAsia===>CWA/CentralAfrica/EasternLatinAmerica
Managementsystem ConcessionofMSC+ChinaMerchantsInternationalHoldings?
Completiondate
Endof2013/beginningof2014
Progress
Sandtrapconstructed
Operator
MSC/CMHI?
Conditions
Funding
ConsortiumofMSC/BOAD/IFC/Proparco400m
According to its promoters, the LCT will work almost exclusively on transhipment loads. It is
clear that MSC does not have the same strategy as other shipowners, but it is nevertheless
possible to question the strategy implemented, given the following elements:
MSC has a smaller market share in the African ports compared to the market
leaders, Maersk Line and CMA-CGM, and even if its share of the European market
is substantial, its market share in Asia is weak.
With regards to Africa, MSC has numerous ports which could be used for
transhipment: it is a participant in Tangier Med, it is the only user in the port of
Sines, it has a terminal in the port of Valencia, it has a port concession in San
Pedro very close to Lom and, above all, it has a large terminal in Las Palmas
(Canary Islands). But rational and economically sound organisation of
94
The Lom projects would seem to be leading to a significant overcapacity. This could
possibly be welcome as it could temporarily relieve the pressure on the facilities in the port of
Tema, providing imports via Lom for destinations in Ghana.
MSC presents the LCT as a pure transhipment port. Such a port is a cost centre for the
shipowner who uses it and does not generate any direct profits from it: it only makes savings
on the use of the shipowners fleet possible. The entry of CMHI in the project means there
will also be a port activity directly generating profits and therefore the import/export and
transit facilities will compete with those of Bollor.
95
Conakry
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
AenneRickmers
27/01/2010
WEDDEL
DELMASATLANTICCWA
1998
3X45T
2,210
1,750
300
30724
11
195.29
30.2
26,131
10,106
21.3
China
ShipBuilding
CorporationTaiwan
MANBW7S70MC
GL
1,200
9152753
RICKMERSLINIEGMBH&CIE
KG
CMACGM
64875,338
111
DAKAR
BANJUL
CONAKRY
FREETOWN
MONROVIA
ABIDJAN1
ABIDJAN2
SANPEDRO
TAKORADI
TEMA
LOME
COTONOU
TINCAN
LAGOS
PORTHARCOURT
DOUALA
BATA
MALABO
LIBREVILLE
PORTGENTIL
POINTENOIRE
LUANDA
WALVISBAY
Total
Median
Average
Tugfees
Pilotfees
Mooring
fees
2,729
2,822
341
1,005
555
122
7,974
2,779
128
0
0
0
17,987
4,996
600
2,592
4,237
700
2,592
4,237
700
2,592
2,729
910
2,262
889
291
2,262
889
291
2,850
940
183
3,570
1,683
468
0
0
0
0
0
0
0
0
0
2,823
5,538
573
5,076
1,296
1,693
9,911
2,085
183
4,024
7,222
543
4,383
4,856
543
6,313
1,416
0
4,205
1,626
0
1,513
1,549
0
89,650
63,510
12,612
2,592
1,549
291
3,091
2,190
435
Source: Shipowner
Portdues
6,510
22,218
0
20,284
4,336
4,476
2,952
744
2,571
0
0
2,342
27,841
19,963
26,660
9,951
4,741
4,302
16,517
7,231
2,850
7,878
0
321,428
4,406
11,480
Total
12,402
23,900
0
20,284
27,919
12,005
10,480
0
6,012
8,063
27,841
19,963
26,660
18,884
14,231
19,797
28,306
17,012
10,579
13,709
454,973
13,056
16,249
The cost of the tug service for the same vessel varies between 250 (Cape Verde) and
18,000 (Monrovia). Most ports range between 2,000 and 3,000. There is a trend for the
southern ports in this survey to be more expensive than others.
The cost of pilotage varies widely, ranging from the hundreds of Euros (Cape Verde, Banjul,
Bissau, Takoradi, Tema, Lom, Boma and Soyo, i.e. small ports), through to the 1,000 to
2,000 range (Cotonou, Bata, Pointe-Noire and Luanda), the 2,000 to 3,000 range (Dakar,
112
Leaving
Noportduesongoods
Port dues on goods are more homogenous, with two relatively cheap ports (Tema and
Cotonou), two ports situated in the middle (Dakar and Douala), one port 50% more
expensive (Pointe-Noire) and, finally, one very expensive port (Walvis Bay).
113
The table above details the rates (not necessarily the same as the price paid) for 20 and 40
containers entering (E) or leaving (S) the port either full (P) or empty (V). These figures do
not reveal a very great difference between the ports. Douala seems relatively less expensive
than the others, especially for full 40 containers.
Quayside handling
Quaysidehandling
20'
Dakar
EP
EV
40'
SP
SV
EP
EV
SP
SV
Lom
129.59
3.05
53.36
3.05
144.84
6.10
83.85
6.10
Tema
57.56
56.10
50.14
41.00
94.69
83.00
78.84
62.50
114.35
0.00
114.35
0.00
189.05
0.00
189.05
0.00
Lagos
Douala
PointeNoire
RDC
367.50
61.50
526.00
61.50
367.50
123.00
526.00
123.00
Libreville
160.00
20.00
160.00
20.00
240.00
40.00
240.00
40.00
Abidjan
Cotonou
Walvis
The rates for quayside handling show greater differences. The port of Tema appears to be
relatively inexpensive, while ports in the DRC are extremely expensive. The balance
between on-board and quayside handling established by the concessionaire does not
sufficiently explain these differences. However, the local port environment as well as
competitive pressures do.
114
As a general rule, terminals had no quayside equipment until the early 2000s, with
the exception of very large ports that were already equipped with gantries
Most terminals were not, in fact, terminals, but quays used by several handlers
From the early 2000s, we have seen the introduction and then general use of quayside
equipment, mainly mobile cranes. We have also seen the introduction of terminal
concessions, making it possible for operators to increase their investments.
Productivity has therefore increased dramatically, from around 12 movements per hour per
ship up to 30 to 40 movements per hour. As a result, the capacity of facilities has also
increased significantly.
In the early 2000s, the facilities dedicated to containers in the port of Dakar were saturated.
There were containers everywhere in the port as there was no available space left either in
the dedicated facilities or in the two berths. Two handlers shared the facilities at this time,
each with its own yard (managed using reach-stackers) and their own mobile cranes. After
the arrival of DP WORLD and the creation of a third berth, the landscape changed
completely. The terminal is now handled by a single operator, with a unified yard operating
with RTGs, a quay equipped with gantries and mobile cranes and offering more than enough
capacity to meet demand25.
Concessions have progressively become the norm in the main ports, with a recent
acceleration of this trend. The corollary has been the elimination of the secondary operators
offering handling services or their relegation to conventional handling activities: first Progosa
and then Getma have been sidelined from the handling of containers. It is clear that in most
ports there is no room for two terminals.
If it is not possible to exclude an operator, the best option is an alliance to prevent new
operators from seizing the opportunity to enter the market.
Handling companies in West Africa
Two companies dominate container handling in West Africa, and have done so for a long
time: Bollor Africa Logistics and APM Terminals (APMT).
Currently, other companies have only marginal involvement: DP WORLD (Dakar), China
Merchants (Lagos and soon in Lom) and Portek/Mitsui (port authority in Gabon).
Bollor follows a vertical integration model, possessing in West and Central Africa:
25
115
Railways,
Freight forwarders (for example, SDV, SCAC, SAGA etc.),
Handling facilities.
For a time, it was also a shipowner (Delmas-Vieljeux) despite the conflict of interest, but this
interest has been sold to CMA-CGM, with which it maintains close, but not exclusive,
contacts.
Bollor is a company whose international presence is largely confined to Africa in general.
Conversely, APM Terminals has a global footprint: it is present on all continents as are its
major rivals HPH, PSA, DP WORLD and, to a lesser degree, ICTSI.
APMT is a subsidiary of the AP Meller group, which also controls Maersk Line. The
involvement of Maersk/APMT in handling in Africa is longstanding, dating back to the
beginnings of ship ownership in the mid 1980s. However, a major change has occurred since
then: at the time, the African handling parts of the group had just one client - Maersk Line with the objective of ensuring ships in the group enjoyed a good quality service.
Today, APMT is increasingly, in Africa (and elsewhere), a multi-client handling company
seeking to expand its market share and provide a good return for its shareholders.
Handling groups concessions
Ports
Dateof
concession
Operator
Length
Remarks
Dakar
DPWORLD
2008
25
Conakry
Bollor
April2011
25
Freetown
Bollor
February2011
25
Monrovia
APMT
Endof2010
SanPedro
MSC
2011
Abidjan
Bollor(60%),APMT(40%)
2004
30
Takoradi
Tema(MPS)
APMT(35%),Bollor(35%)GPHA(30%)
2007
20
Lom
Bollor
2010
35
LCT(MSC/CMHI)
Cotonou
Bollor(SMTC,including35%GETMA)
2010
APMT(Coman)
SOBEMAP
Nocontainers
LagosApapa
APMT
2006
20
45%ofmarket
LagosTinCan(TICT) Bollor(55%),ChinaMerchants(45%)
June2006
20
35%ofmarket
Onne
WACTAPMT
Douala
Bollor(50%),APMT(50%)
Libreville
25
Oil&gas
Tocome(2014)
Newterminal
2004
15
STCGmajorityBollor+Getma
2008
25
PointeNoire
Bollor(40%),APMT(40%),Socotrans
2009
27
Luanda
Sogester(State50%,APMT50%)
November2007
20
Unicargas(State)
Lobito
State
WalvisBay
State
116
We can see then that the move towards awarding concessions is relatively recent, the oldest
concessions dating back to 2004.
Today, the principal African terminals operate on concessions and the granting of these
concessions, sometimes questionable in form26, has made it possible to change handling
conditions through investments and the putting in place of modern systems of organisation.
APMT and Bollor now dominate the scene with more than 80% of the market without, to
date, suffering any real competition (with the notable exception of Dakar) and have gained
this position due to their incomparable knowledge of the countries involved, their governance
and their economies, which has been gained through their longstanding presence in these
highly specific markets.
To date, the only breakthrough of a global operator has happened in Dakar where the
container terminal is run by Dubai Port World. Equally symptomatic is the fact that the only
global operator engaged in the four consortia bidding for the second container terminal at
Abidjan is PSA in association with Marsa Morocco.
We also note that China Merchants Holdings International (CMHI) is present in Nigeria (TinCan) replacing ZIM as Bollors partner and now also has a 50% stake in the LCT project in
Lom. CMHI says it will continue to invest in developing countries with high growth rates.
Africa is, in fact, a continent experiencing growth in a world where growth has sharply
declined. Other handling operators may well show an interest in this market in the future
despite the manifest difficulties in gaining entry.
Opportunities still exist in the south of the covered region (terminals mainly or wholly
managed by public entities in Angola and Namibia) and others may also appear in the form
of new greenfield ports or terminals such as the future terminal in Lekki, Nigeria, promoted by
Singapores Tolaram group, which already has a presence in Africa, but not as an investor in
ports and handling facilities.
Shipowners may wish to enter the handling market too, but probably only in cases where the
stakes for transhipment are high, as evidenced by the MSC projects in Lom, the second
container terminal in Abidjan, and the CMA-CGM project in Equatorial Guinea, even though
the latter may not happen.
26
Some operations were acquired as much by pressure at the highest level as by the technical and financial excellence of the
bids.
117
N.B.: In the following pages, the abbreviation AAGR is used for average annual growth rate.
118
The hypotheses on GDP growth are drawn from the Dynamar study, which itself is based on
forecasts from the IMF and WTO. Historical changes in GDP make it possible to produce an
elasticity coefficient for container traffic. GDP projections concern the period 2011-2015,
which we have extended until 2020. Given global economic instability and the geopolitical
risk inherent in the African continent, it seems unlikely that data on a timescale longer than
this would be reliable.
It is important to note that these growth rates are high when compared to world growth rates.
They range from 3% for Chad to 11% for Sierra Leone. Our calculations took into account
the AAGR for the period and not the gross annual figures in order to reduce cyclical effects.
119
The population data is based on a study by the United Nations, and a 2005 study entitled
The Demography of Sub-Saharan Africa from the 1950s to the 2000s. It is interesting to see
that in general the projected rates of population growth over the period 2010-2020 are lower
than the period 2005-2010, which will affect the domestic consumption of the countries being
studied.
120
As described earlier, the objective of this section is to determine how container traffic evolves
as a function of GDP and population in order to then be able to use projections for GDP and
population as a basis for predicting traffic trajectories.
The growth rates for container traffic are consistent with the rates observed over the period
2006-2010. PIDA (Programme for Infrastructure Development in Africa) predicts an increase
in trade of 6.7% per year to 2020.
However, we were faced with two problems:
The volumes taken into account include both domestic traffic and transhipment traffic,
which distorts the analysis, but the available data was not precise enough to
distinguish between the two types of traffic.
Some evolutions were overestimated due to specific cyclical factors or due to the
entry into service of new port capacity which boosted traffic. We have therefore built
in a weighting coefficient to avoid extreme values and to put cyclical effects into
perspective.
121
122
Designation
Phase 1 extension
500m
500,000 TEU
2020
Final extension
500m
500,000 TEU
2025
Quay length
660m
Surface
area
18ha
Capacity
Year
600,000 TEU
The Dakar container terminal is far from being saturated, with a fairly slow growth in traffic. In
principle, the concessionaire is committed to investing in an external extension programme
beyond the current port, which will require protection works. It should be noted, however, that
there are alternatives which would allow container capacity to be developed inside the
current port, making it possible to put back the introduction of the Port du Futur27
infrastructure. In any event, the port of Dakar should be able to meet the demand for
increases in the medium term without requiring more infrastructure resources.
Conakry
2011 traffic=160,000 TEU
Current terminal
270m
Surface
area
8ha
Phase 1 extension
338m
12ha
300,000 TEU
2013
Final extension
300m
300,000 TEU
2025?
Designation
Quay length
Capacity
160,000 TEU
Year
Long term
The concession for the Conakry terminal was recently (2011) taken over from Getma by
Bollor. The concessionaire is committed to making significant investments to increase the
capacity of the terminal. This effort is underway with the extension of the quay (+338m) and
an increase in yard area. Eventually, the quay will be increased to 900m in length.
Freetown
2011 traffic=55,000 TEU
Concession BAL ==> 2030
Designation
Current terminal
Quay length
722m
Surface
area
Capacity
Year
>300,000 TEU*
Extension
* depending on reinforcements in equipment
27
The latter has the major disadvantage of requiring costly protection works before the first metre of quay can come into
service.
123
Quay length
Current terminal
Surface
area
600m
Capacity
Year
75,000 TEU*
Phase 1 extension
Final extension
Long term
Quay length
Current terminal
210m
New terminal
700m
Surface
area
Capacity
20ha
500,000 TEU
Year
120,000 TEU
2017+
MSC was awarded the concession for the container terminal in 2010 in order to cater for
transhipment traffic. This occupies almost half of the only quay in the port, which is now
saturated not only because of the many halts by MSC ships, but also by those of other
shipping lines (Maersk, CMA-CGM etc.) and conventional vessels on long stopovers.
Depending on the season (for example, conventional rice imports during the cocoa season),
this can result in long delays for some vessels.
There is a project to construct a new container terminal with a capacity of 500,000 TEU, but
this will not be available before 2017-2018.
Abidjan
2011 traffic=546,000 TEU
Current terminal
Quay
length
1000m
Extension
Second terminal
1500m
Designation
Surface
area
31ha
1,100,000 TEU*
35ha
1,500,000 TEU
Capacity
Year
2018+
The Abidjan container terminal has changed profoundly over recent years through major
investments in equipment (renewal of quayside gantries and the transformation of yard
management from using reach-stackers to a management system which is now almost fully
124
Quay
length
660m
Surface
area
10ha
Capacity
Year
600,000 TEU*
Unrealistic projects
2020+
Final extension
Long term
The current terminal in Tema, comprising only two berths, deals with 80% of the ports
container traffic. It is saturated as is the entire system, including the three ICDs.
The capacity of the system could be increased marginally by adding to the equipment
available and increasing the space available at the ICDs, through improving shared computer
systems and strengthening scanning equipment in order to streamline the processing of
containers. It is also possible to relieve the pressure on the terminal quays by adding a berth
and equipping the other quays with mobile cranes with a view to increasing productivity for
the treatment of goods other than container traffic.
But currently there is no viable solution for the medium and long term. The master plan for
the port has resulted in an unrealistic project for a new port constructed outside and backing
onto the current port. The cost for this has been estimated at $3bn and it would have the
effect of concentrating flows and substantially increasing the level of congestion, which is
already at a critical level.
Lom
2011 traffic=350,000 TEU
Designation
Current terminal
Quay
length
430m
Surface
area
Capacity
Year
350,000 TEU
Phase 1 extension
Third quay
450m
500,000 TEU
2013-2014
Phase 2 extension
LCT phase 1
400m
500,000 TEU
2013-2014
Phase 2 extension
600m
750,000 TEU
2020?
Long term
1000m
1,250,000 TEU
2030
The current terminal, under concession to Bollor Africa Logistics, has two berths either side
of a jetty with extremely limited capacity. The space available behind the quay for the
container yard is thoroughly inadequate to cope with the storage needs, so many containers
125
Benin Terminal
Quay
length
600m
Surface
area
540m
20ha
Capacity
Year
250,000 TEU
540,000 TEU
2013
2025
The Benin Terminal is expected to come into service in the port of Cotonou in early 2013,
offering 540m of quay with a draught of 13m, while the channel should be deepened to 15m
over the next two years.
Beyond this, the port cannot be extended (because of its proximity to the city, to the French
Embassy and the Presidential residence) and beyond the commissioning of the new
container terminal south of the dock, further port development will require a new site.
In the long term, we know of the proposed second port in Benin, located at Seme-Kpodji,
20km from Cotonou in the direction of Nigeria.
Lagos
Nigeria's ports are expecting to have to deal with 10m TEU in 30 years time and 2m TEU by
2018, compared to 1.2m TEU today. Faced with such a prospect, ambitious greenfield ports
will need to be envisaged. Most of the demand will continue to be concentrated in the region
of Lagos.
2011 traffic=1,100,000 TEU
Apapa terminal
Quay
length
1050m
Surface
area
55ha
850,000 TEU
Tin-Can terminal
770m
24ha
400,000 TEU
Designation
Capacity
Year
Badagry (Phase 1)
3,000,000 TEU
2016+
Lekki (Phase 1)
2,000,000 TEU
2016+
This justifies the two projects planned, one at Lekki and a second, more recent, project at
Badagry.
126
Multipurpose quay
Quay
length
700m
Surface
area
Capacity
Year
500,000 TEU
700m
400,000 TEU
2015?
The port of Douala is handicapped by its access channel and the difficulty of keeping it
dredged. Use of the port is prohibited to vessels with a medium and large draught.
There are no extension projects planned for this site.
In contrast, the first step in the construction of a greenfield port at Kribi is well advanced. At
its launch, it was a very ambitious project with many specialised terminals to be put out to
concessions. Today, the first step is underway with the Chinese company CHEC entrusted
with building the general port, including a multipurpose terminal offering 600m of quay.
Libreville/Owendo
2011 traffic=81,000 TEU
Current terminal
Quay
length
475m
Phase 1 extension
150m
Designation
Surface
area
15ha
Capacity
Year
120,000 TEU
2014?
Long term
The port is congested with an average wait of four days per ship. A large part of the problem
is down to very slow handling, which is performed exclusively with on-board equipment. The
first improvement will come with the arrival of two mobile cranes, a process which is
underway. The port authority also plans to increase the length of quay available in the
container terminal, with the addition of one berth.
Pointe-Noire
2011 traffic=443,000 TEU
Current terminal
Congo Terminal
Quay
length
800m
Phase 1 extension
Congo Terminal
700m
Designation
Surface
area
31ha
450,000 TEU
36ha
750,000 TEU
Capacity
Year
2030+
Long term
127
Current terminal
Sogester
Quay
length
542m
Multipurpose terminal
Unicargas
536m
Barra do Dande
800m
Designation
Surface
area
14ha
330,000 TEU
18ha
200,000 TEU
Capacity
Year
Extension?
Long term
800,000 TEU
The port of Luanda has two main facilities for dealing with container traffic: the Sogester
terminal (a joint venture between APMT and a local operator) and the multipurpose
Unicargas terminal.
Following the boom in traffic in recent years, these facilities are now saturated. There is a
greenfield project 50km north of Luanda at Barra do Dande, but we know nothing concrete
about the progress of this project.
Walvis Bay
2011 traffic=230,000 TEU
Designation
Quay
length
Surface
area
Current terminal
Capacity
Year
300,000 TEU
Phase 1 extension
480m
24ha
350,000 TEU
Final extension
2,400m
120ha
1,750,000 TEU
2015
2025?
Long term
The infrastructure of the port of Walvis Bay is still quite underdeveloped and lacks
specialised facilities.
There are long-term plans for extension, which could be achieved in phases. Specifically this
concerns a jetty, reclaimed from the sea, of some 2.4km in length and with a depth of 500m.
128
129
130
131
132
133